NSP/007/019 - Guidance on Substation Design: EHV Substation Drawing Policy

Similar documents
NSP/007/028 Guidance On Substation Design: Drawing Submission Requirement

NSP/ 007 / 006 Guidance on Substation Design: Transformer Transport, Delivery and Installation

Click to edit Master title style. Click to edit Master title style. Northern Powergrid Asset Recording Guidance

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

Introduction to Substation Design TADP 542

IMP/007/011 - Code of Practice for the Application of Lightning Protection

EDS GRID AND PRIMARY SUBSTATION CIVIL DESIGN STANDARDS

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer

EDS LV ELECTRICAL SERVICE DRAWINGS

ECP DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE

PROCEDURE FOR INSPECTION OF ELECTRICAL INSTALLATIONS ABOVE 250KVA

ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE

EDS FAULT LEVELS

MESP TECHNICAL SPECIFICATION FOR AN ESSENTIAL SERVICES SUPPLY STEP UP TRANSFORMER

SUBJECT HEADING: Switching Programmes ISSUE: 18

ECP HV INSULATION TESTING

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

VI 3 - i TABLE OF CONTENTS

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-I) UNDERGROUND NETWORK GROUNDING. Rev. 01

NEO TELE-TRONIX PVT. LTD. 6/7 Bijoygarh, Kolkata , Tel : ; Fax :

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-II) OVERHEAD NETWORK GROUNDING. Rev. 01

This specification describes the general requirements for Engineering Services provided to Vale.

Company Directive STANDARD TECHNIQUE: TP21D/2. 11kV, 6.6kV and LV Earthing

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

Functional Specification Revision History

INTERNATIONAL STANDARD

Distribution transformers Part 2 Ground mounted transformers not closecoupled

ECP HV INSULATION TESTING

Greenlining and Bluelining of Ergon Energy Substation Drawings

UNIFIED FACILITIES GUIDE SPECIFICATIONS

4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118

SECTION ELECTRICAL IDENTIFICATION

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER

SYNCHRONISING AND VOLTAGE SELECTION

ACCESS TO HIGH VOLTAGE APPARATUS

EI HIGH VOLTAGE INSULATION TESTING POLICY

APPLICATION FORM FOR INFRASTRUCTURE NOC

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

KENYA ELECTRICITY GENERATING COMPANY LTD

IMP/010/011 Code of Practice for Earthing LV Networks and HV Distribution Substations

Earthing Guidance Notes

Table of Contents. Introduction... 1

ELECTRICAL GENERAL DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL Electrical/Telecommunications Design

2. Electrical rooms shall be centrally located and stacked so that feeder conduits and bus duct are run as straight and short as possible.

ECP HV METERING EQUIPMENT COMMISSIONING PROCEDURE

FACILITY RATINGS METHOD TABLE OF CONTENTS

ELECTRIC NETWORK DESIGN APPROVAL APPLICATION

11.0 INSTRUMENTATION LOOP DIAGRAMS

GENERAL TECHNICAL SPECIFICATION (Turnkey Work)

ENGINEERING STANDARD FOR INSTRUMENTS ELECTRICAL POWER SUPPLY AND DISTRIBUTION SYSTEMS FIRST EDITION MAY 2013

DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW)

Manual: Distribution Substation Manual (DSM) Section D: Substation Drawing Revision List

Guideline for Creating Disconnection Points and Establishing a Not Electrically Connected Area

Cymap Electrical. Reference: CYELEC_1117_v1. Page 1 of 15. Cymap Electrical

Company Directive STANDARD TECHNIQUE: SD5F. Relating to connecting multiple small low voltage connections with limited network analysis

THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE. Contents

Customer Connection Guide Updates Effective May 2017

3. DESIGN SPECIFICATIONS

ECP GROUND-MOUNTED SWITCHGEAR COMMISSIONING PROCEDURE

Embedded Generation Connection Application Form

Iec Schematic Symbols For Autocad Electrical

Embedded Generation Connection Application Form

138kV / 13.8kV Substation Protection and Control Design Project

Australian Standard. Switchgear assemblies and ancillary equipment for alternating voltages above 1 kv AS

SECTION - II BID DATA SHEET

Guidelines for the Preparation of Traffic Signal & Intelligent Transportation System Plans on Design-Build Projects August 2007

Section XV - PER, Design, and Construction Submittal Requirements

University of Central Florida Main Campus. Electric. Service and Meter Installations Requirements. Issued January 26 th, 2017.

CUSTOMER SUPPLIED HIGH VOLTAGE METERING UNIT SPECIFICATION FOR 11, 22 & 33 kv

Mechanical Design. Brian Brinson Mechanical Design Manager.

Standard Prices for Generators 2010

Drawing Management Standard

Quality Control Checklist - Design Drawings

NSP/004/107 (OHI 7) Guidance on the selection of conductor jumpers and non-tension connections

Fatima Michael college of Engineering and Technology

QUESTIONNAIRE for Wind Farm Power Stations only

RELEVANT ELECTRICAL STANDARDS

GENERAL TECHNICAL SPECIFICATION

1. All electrical switches and outlets used shall be equal to Hubbell heavy duty, specification grade or equivalent quality.

MESP TECHNICAL SPECIFICATION FOR AN AUXILIARY OR ESSENTIAL SERVICES AND AUXILIARY TRANSFORMER FOR USE IN A RAILWAY SUBSTATION

Licensed Electricians Practical Assessment (LEP)

Checklist for Minor Plan Modification

Spec Section: , Complete Elec, Comm, and Fire Alarm , Complete Elec, Comm, and Fire Alarm Data Sheets RAN/GCAN

Lodgement checklist: water heater (solar or heat pump)

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

RELEVANT ELECTRICAL STANDARDS

TS RES - OUTSTANDING ISSUES

03/7/12 Issuance UTD Section Page 1 of 5 Electrical General

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

Form-IV. Form of Inspection/Test Report. (Under Regulation 43)

SECTION LOW-VOLTAGE ELECT. DIST. DESIGN AND CONSTRUCTION STANDARDS _ February 2015 PART I: GENERAL

Section 4: Ontario Realty Corporation CAD Standards and Guidelines

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Chapter 25. Lighting Plans

PSSI 27 Work or Testing On or Near to High Voltage Direct Current (HVDC) Plant and Apparatus

NPS/002/003 Technical Specification for Protection Tile, Protection Tape, Cable Ducting and Route Markers

2V68-S User Guide. CT Supervision And Shorting Relay. User Guide

SECTION VI SCOPE OF WORK

AVEVA PDMS. Business Benefits. Accurate and clash-free 3D plant design

Transcription:

Version:- 1.1 Date of Issue:- Feb 2015 Page 1 of 13 NSP/007/019 - Guidance on Substation Design: EHV Substation Drawing Policy 1. Purpose The purpose of this document is to outline the Northern Powergrid requirements for new drawings for primary and supply point substations. The guide details the numbering system to be used, drawing title requirements and gives details of the drawings required for a Northern Powergrid substation. 2. Scope This design guide shall be applied to all primary and supply point substations on the Northern Powergrid network. 2.1 Contents Clause Description Page No. 1.0 Purpose 1 2.0 Scope 1 2.1 Contents 1 3.0 Northern Powergrid substation Drawings 2 3.1 General 2 3.2 Title 2 3.3 Drawing Reference Number 3 3.3.1 General 3 3.3.2 Meridian Database Levels 3 3.3.3 Level 3 & 4 Sub Sections 4 3.4 Historical Drawing Number 5 3.4.1 General 5 3.4.2 Historical Drawing Number Details 5 3.4.3 Section and Sub Section Numbers 7 3.5 Drawing Revision Policy 8 3.6 Drawing Offices 8 3.7 Substation Drawings Required 8 3.7.1 Substation Layout Drawings 8 3.7.2 Civil Drawings 9 3.7.3 Transformer Drawings 9 3.7.4 Switchgear Drawings 9 3.7.5 Relay Panel Drawings 9 3.7.6 Earthing Drawings 9 3.7.7 Heating & Lighting and Fire Mitigation Drawings 10 3.7.8 Cable Route Drawings 10 3.7.9 Multicore Cable Layout Drawings and Schedules 10 3.7.10 Single Line Diagrams 10 3.7.11 Telecontrol Schedules 10 3.7.12 Circuit and Wiring Diagrams 11

Version:- 1.1 Date of Issue:- Feb 2015 Page 2 of 13 3.7.13 Auxiliary Equipment Drawings 11 3.7.14 Temporary Drawings 11 3.7.15 Contractors Drawings 11 4.0 References 12 4.1 External Documentation 12 4.2 Internal Documentation 12 5.0 Definitions 12 6.0 Authority For Issue 13 3 Northern Powergrid Substation Drawings 3.1 General On all Northern Powergrid produced drawings, in the bottom right hand corner of the drawing there shall be a title block containing the following details: Northern Powergrid name, registered address and logo Drawing Title Document Details Drawing Reference Number Historical Drawing Number Revision Details Scale Drawn and checked names and dates. On all externally produced drawings, the title block shall contain the following details: Company name and logo Client - Northern Powergrid Drawing Title Company Drawing Number Northern Powergrid Drawing Reference Number Northern Powergrid Historical Drawing Number Revision Details Scale Drawn and checked names and dates. 3.2 Title The title block should contain no more than 4 lines. If one of the lines is not required then the following lines will move up as appropriate. Line 1: Substation Name and Voltage. Line 2: Circuit number and voltage as per (a) and (b) below. Line 3: Purpose of drawing as per (c) below. Line 4: Other information as per (d) below. (a) The circuit(s) reference number(s) for 11kV, 20kV, 33kV and 66kV circuits will be the circuit number on the Diagram of Main Connections and Protection (eg 301, 503, 607) which corresponds with the circuit breaker reference in the plant record system. For 132kV circuits the reference number will be the circuit breaker number which is shown on the Diagram of Main Connections and Protection (eg 305, 805). Where there is no 132kV circuit breaker, as at most transformer end sites, the reference number will be the associated 132kV disconnector reference (eg 113, 213).

Version:- 1.1 Date of Issue:- Feb 2015 Page 3 of 13 (b) (c) panel. (d) The circuit voltage. The purpose of the drawing (eg control, alarms and indications) or the type of plant (eg control Other information (eg layout or schedule). Wherever possible a drawing should be associated with an individual circuit or circuits eg 302,304,314 11kV feeder IDMT/SEF circuit breaker. 3.3 Drawing Reference Number 3.3.1 General The drawing reference number is generated automatically at the time of entry into Meridian (Northern Powergrid s drawing management database). The drawing reference number is a chronologically issued number starting with the letter C. Whilst being unique to the drawing, the drawing reference number has no intelligent base to identify the properties of the drawing. These numbers can be allocated prior to the production of the drawings by creating a blank entry in Meridian which would be populated with the drawing file by the appropriate drawing office representative once completed. The Meridian database is segregated into levels as described below. The appropriate database level 3 and 4 names should appear in the Document Details section of the title block. 3.3.2 Meridian Database Levels Drawings filed in the Meridian drawing management database require to be filed within set vaults or levels. There are four levels as follows: Level 1 Top Level This level contains only one section which is for all Northern Powergrid drawings. Level 2 Document Type This level contains five sections as follows: ( C ) CAD This section contains all drawings covered by this document and provides the C prefix for the drawing reference number. It is divided into further levels as indicated in Section 3.3.3 below. ( D ) Development documents. ( L ) Library Documents. ( M ) Maps. ( W ) Wayleave documents.

Version:- 1.1 Date of Issue:- Feb 2015 Page 4 of 13 Level 3 - Document Class Level 4 - Document Subclass 3.3.3 Levels 3 & 4 Sub Sections LEVEL 3 DOCUMENT CLASS Construction Legacy Legal Drawings Overhead Planning Protection and Control Safety Scheme Drawings Substation Operational Diagrams ESI Switchgear System Diagrams Telecoms Transformers LEVEL 4 DOCUMENT SUBCLASS Layouts Buildings Compound Site Sites Photographs Other Plans Agreements Consents Other Towers Poles Lines System Other Technical Documents C & P and Logic Drawings Equipment Notices Turnkey Major Projects Capital Temporary Northern Powergrid (Northern) Northern Powergrid (Yorkshire) OI10 Drawings ESI Arrangements Details General HV Northern Powergrid (Northern) Protection Data & Radio Telecontrol Security Distribution Primary Supply Point Other

Version:- 1.1 Date of Issue:- Feb 2015 Page 5 of 13 Underground Plant Diagrams Other Plant Jointing Cables Wiring Circuit General Relay Panel General Arrangements Metering Earthing Auxiliary Cables Auxiliary Equipment 3.4 Historical Drawing Number 3.4.1 General The historic drawing number should be constructed in accordance with section 3.4.2 below. The construction of this number is such that it is easy to identify the substation and the type of information shown on the drawing from the number. For details of historic numbering practices employed within the former NEDL area prior to the introduction of Meridian in 2006 please refer to the Northern Powergrid (Northeast) drawing office in Shiremoor. The historic drawing number can be created prior to the production of the drawing. A database is maintained within Primary Engineering Projects, Northern Powergrid (Yorkshire) at Castleford which stores details of historic drawing numbers and should be used to determine the next available historic drawing number. Contractors wishing to allocate historical drawing numbers should submit a request to QC Data (see Section 3.6). Requests should be submitted using the attached drawing template excel spreadsheet. The format of this spreadsheet is such that the database can be auto populated directly from the spreadsheet without the need to enter drawings individually in to the database. 3.4.2 Historical Drawing Number Details The historic drawing number is made up of six parts: (i) Prefix Letter The prefix letter indicates the licence operator. Numbers beginning with Y are for drawings in the Northern Powergrid (Yorkshire) area. Numbers beginning with N are for drawings in the Northern Powergrid (Northeast) area. (ii) Reference Number After the prefix letter is the three digit reference number. These three digits are dependent on the drawing group. For a substation drawing, the reference number is a unique number allocated to an individual substation. These numbers are allocated by the Substation Design Engineer within Primary Engineering Projects at Castleford. The drawing reference number does not have any connection with the operational substation number which is found on the mains records or on the substation door. This substation number is issued by control and care should be taken not to confuse the two. For standard drawings, the reference number relates to a particular group of standard drawings. Most of these are no longer in use.

Version:- 1.1 Date of Issue:- Feb 2015 Page 6 of 13 (iii) Group Letter After the reference number is the group reference. A Operational Project Drawings. This group is for substation drawings. Several other group letters have been used in the past but these are no longer in use. (iv) Section Number After the group letter is the section number. This is a single digit ranging from 0 to 9.See below for details. (v) Subsection Number After the section number is the sub section number. This is a single digit ranging from 0 to 9. See below for details. (vi) Serial Number (Individual Drawing Number). The final two digits are a unique number allocated to the specific drawing. These are issued chronologically starting from 01. On rare occasions for large sites where there are a large number of drawings of a particular type it may be necessary to use 3 digits in this section. For example, a typical historic drawing number would be constructed as follows: Prefix Reference Group Section Subsection Serial Letter Number Letter Number Number Number Y 087 A 4 2 40 Drawing number is Y087A4240 The title is - Queens Road 33/11kV S/S 302,304,314 11kV feeders IDMT/SEF circuit breakers Circuit Diagram

Version:- 1.1 Date of Issue:- Feb 2015 Page 7 of 13 3.4.3 Section and Subsection Numbers The Section and Subsection numbers for substation drawings in the A group are listed below. Section Subsection 1. Construction Drawings 0. Site and External Works 1. Equipment Layouts 2. Building Details 3. Building Foundations 4. Compound - Arrangements 5. Compound Supports and Foundations 6. Compound Other Details 2. Plant Drawings 0. Transformers & Associated Equipment 1. Switchgear Arrangements (Including LVAC) 2. Switchgear Details (Including LVAC) 3. Control & Relay Panels 4. Auxiliary Equipment &Earthing 5. Telecommunication / Telecontrol 3. Mains & Multicore Cables 0. Easement Plans 1. Underground Cables and Associated Equipment 2. Overhead Lines and Associated Equipment 3. Multicore Cables, Block Diagrams & Schedules. 4. Diagrams 0. Connections, Main Protection, Phasing (circuit diagrams and wiring Operation, Interlocking Key Diagrams diagrams/schedules except 1. Telecommunication / Telecontrol multicores) 2. 66, 33, 20, 11kV Plant Circuit & Schematic Diagrams, Mag Curves, Logic Diagrams 3. 66, 33, 20, 11kV Plant Wiring Diagrams, Diagram of Connections, Wiring Schedules 4. Auxiliary Equipment Battery Circuit & Wiring, General Arrangements, Wiring Diagrams, LVAC Circuits 5. 132kV Plant Wiring Diagrams 5. Drawings in Transit Temporary Drawings 6. 132kV Plant Circuit Diagrams 0. Diagrams 1. Site Drawings 2. Other Drawings Schedules, Structure Drawings 3. Redundant Power Stations 4. Explosion (Investigation Drawings) 6. Other Drawings 0. Incident Investigations 1. Reports & Manuals 2. Photographs

Version:- 1.1 Date of Issue:- Feb 2015 Page 8 of 13 3.5 Drawing Revision Policy When a drawing is revised, the drawing should retain the existing drawing number(s) and the revision should be advanced alphabetically. The first revision of a drawing should be set at 00. Further revisions should continue from A to Z then AA to ZZ as required. The drawing management software is configured so that previous revisions are archived and available for future reference. 3.6 Drawing Offices Drawing numbers for sites within Northern Powergrid (Yorkshire) will be issued by QC Data, (the Northern Powergrid (Yorkshire) drawing office contractors) at the following address: QC Data, Northern Powergrid (Yorkshire), 98 Aketon Road, Castleford, West Yorkshire, WF10 9DS. Telephone: 01977 60(760) 5626. Email: QCData@Northernpowergrid.com Drawing numbers for sites within Northern Powergrid (Northeast) will be issued by the Northern Powergrid (Northeast) drawing office at the following address: Northern Powergrid (Northeast) Drawing Office, New York Road, Shiremoor, Newcastle Upon Tyne, NE27 0LP. Telephone: 0191 229 4(781 5) 287. Email: safediggingplans@northernpowergrid.com 3.7 Substation Drawings Required 3.7.1 Substation Layout Drawings A site plan should be filed in Section 1, Subsection 0. These drawings should normally be at a scale of 1:100 or 1:200 and contain a location plan to a scale of 1:2500 or 1:1250. The drawing should show the overall site layout with dimensions and circuit centre lines. A substation layout drawings should be filed in Section 1, Subsection 1, 2 or 4. These drawings should show an overview of the equipment layouts in buildings and compounds and would normally be at a scale of 1:100. The drawing will dimension the key items of plant in relation to the layout of the site boundaries. For smaller sites, building, transformer and compound details can be detailed on the substation layout drawing. For more complicated sites, this drawing can be simplified to show more of an overview of the site, and the building, transformer and compound can be shown in more detail on specific drawings. Building layouts should give the dimensions of the building in more detail. These would show the position of switchgear, relay panels etc. Separate plan views would be used to detail electrical requirements, equipment layouts, and conduit layout. The drawing would normally be to a scale of 1:50. A separate drawing may be required to show elevations. Transformer layouts should give the dimensions of the transformer bund and enclosure where appropriate in more detail. Separate plan views would be used to detail electrical requirements, equipment layouts, and conduit layout. The drawing would normally be to a scale of 1:50. A separate drawing may be required to show elevations. Oil containment calculations for the transformer bunds should be filed in Section 2, Subsection 0.

Version:- 1.1 Date of Issue:- Feb 2015 Page 9 of 13 Compound layouts should show circuit names, centre lines and detailed equipment layouts, including location marks, mech box positions, structure references, and clearances. Dimensions of equipment in the compound should be shown. These drawings would normally be to a scale of 1:100 or 1:50. A separate drawing may be required to show elevations. On larger sites where the substation layout drawing has become over crowded, separate drawings usually at a scale of 1:100 or 1:50 can also be used to detail proposed conduit layouts, cable routes etc. Structure drawings should be filed in Section 1, Subsection 5. These drawings should show an outline of the proposed structures for use by the structure designer/fabricator. They are intended to indicate Northern Powergrid requirements for the structure and should show phase centres, structure heights, mech box positions and heights, cross sectional area for wind loading, equipment weights, earthing requirements, structure references etc. 3.7.2 Civil Drawings Drawings produced by the civil contractor(s) should be filed in Section 1, Subsections 2, 3, 5, or 6 as appropriate. These should detail the civil requirements associated with the site nominally at a scale of 1:50 or 1:100 as appropriate. 3.7.3 Transformer Drawings General arrangement, diagram plate, rating plate, valve location plate and marshalling kiosk arrangement drawings should be filed in Section 2, Subsection 0. Circuit and wiring diagrams should be filed in Section 4, Subsections 2, 3, 5 or 6 as appropriate. Drawings provided by transformer manufacturers should show detailed information relating to the arrangement of the transformer. Key dimensions should be shown such as phase centres, cable termination positions, tank dimensions and mounting footprint, oil capacities and weights. 3.7.4 Switchgear Drawings General arrangement drawings and switchgear detail drawings should be filed in Section 2, Subsections 1 or 2 as appropriate Circuit and wiring diagrams should be filed in Section 4, Subsections 2, 3, 5 or 6 as appropriate. Drawings provided by switchgear manufacturers should show detailed information relating to the arrangement of the switchgear. Key dimensions should be shown such as panel sizes, cable box positions and sizes, transportation and installation requirements etc. 3.7.5 Relay Panel Drawings General arrangement drawings of relay and control panels should be filed in Section 2, Subsection 3. Circuit and wiring diagrams should be filed in Section 4, Subsections 2, 3, 5 or 6 as appropriate. Drawings provided by relay panel manufacturers should show detailed information relating to the arrangement of the panels. Key dimensions should be shown such as panel sizes, heights, transportation and installation requirements etc. 3.7.6 Earthing Drawings Earthing layout drawings should be filed in Section 2, Subsection 4.

Version:- 1.1 Date of Issue:- Feb 2015 Page 10 of 13 Separate drawings may be required to show building, compound, site and transformer enclosure earthing designs. The drawings would normally be to the same scale as the equivalent layout drawings. Drawings should detail the earthing design, along with supporting detail such as earth tape size, tape lengths, mech box earthing positions, stance earth positions, structure earth positions, earth rod and fence earth rod positions etc. Any specific earthing requirements such as insulated fence panels will be shown. Dimensions will only be required where specifically required ie distance of tape from fence or building. Drawings will cross reference other related drawings and shall show a key to the main requirements of the earthing design. 3.7.7 Heating and Lighting and Fire Mitigation Drawings Heating, lighting and power point layout drawings and calculations should be filed in Section 2, Subsection 4. The drawings would normally be to the same scale as the equivalent layout drawings. Drawings should detail the electrical requirements associated with the low voltage heating and lighting circuits and fire mitigation requirements. They are intended to show a representation of the physical position of the equipment, switch positions, heater positions etc for the install contractor to use as an indication of our requirements. They are not intended to be used to provide a detailed wiring diagram of the substation installation. Drawings should show a key to the symbols used and a layout of the LVAC board circuitry showing the key equipment fed from each way. 3.7.8 Cable Route Drawings Proposed cable route drawings should be filed in Section 3, Subsection 1. The drawings would normally be to the same scale as the substation layout drawing. Drawings should detail the feeder and transformer cable route proposals for planning purposes. These drawings are not intended to replace the statutory mains record drawings which should always be the first choice drawing for cable positions. 3.7.9 Multicore Cable Layouts and Schedules Multicore cable layout drawings and multicore cable schedules should be filed in Section 3, Subsection 3. The drawings would normally be to the same scale as the substation layout drawing. Drawings should detail the multicore cable route proposals for planning purposes. These drawings are not intended to replace the statutory mains record drawings which should always be the first choice drawing for cable positions. 3.7.10 Single Line Diagrams Drawings showing Main Connections & Protection, Logic Diagrams, Phasing Diagrams, Interlocking arrangements should be filed in Section 4, Subsection 0 3.7.11 Telecontrol Schedules Telecontrol schedulesshould be filed in Section 4, Subsection 1.

Version:- 1.1 Date of Issue:- Feb 2015 Page 11 of 13 3.7.12 Circuit Diagrams and Wiring Diagrams Circuit diagrams for equipment from 11kV up to 66kV should be filed in Section 4, Subsection 2. Wiring diagrams for equipment from 11kV up to 66kV should be filed in Section 4, Subsection 3. Circuit diagrams for equipment at 132kV should be filed in Section 4, Subsection 6. Wiring diagrams for equipment at 132kV should be filed in Section 4, Subsection 5. 3.7.13 Auxiliary Equipment Drawings General arrangement drawings, circuit diagrams and wiring diagrams for batteries, LVAC Boards etc should be filed in Section 4, Subsection 4. 3.7.14 Temporary Drawings Drawings showing temporary arrangements or proposals should be filed in Section 5. 3.7.15 Contractors Drawings All drawings provided by contractors should be clear and concise, and conform to a similar standard of detail as provided by the Northern Powergrid electrical layout drawings. All drawings should be provided electronically in an industry standard CAD format AutoCAD (.dwg or.dxf) or microstation (.dgn).

Version:- 1.1 Date of Issue:- Feb 2015 Page 12 of 13 4 References 4.1 External Documentation Reference Title 4.2 Internal documentation Reference Title 5 Definitions Reference Title

Version:- 1.1 Date of Issue:- Feb 2015 Page 13 of 13 6 Authority for Issue 6.1 CDS Assurance I sign to confirm that I have completed and checked this document and I am satisfied with its content and submit it for approval and authorisation. Sign Date Lynn Donald CDS Administrator Lynn Donald 01/07/13 6.2 Author I sign to confirm that I have completed and checked this document and I am satisfied with its content and submit it for approval and authorisation. Sign Date Mick Rowley PEP Design Engineer Mick Rowley 02/07/13 Standard CDS review of 3 years Non Standard Review Period & Reason Yes Period: Reason: 6.3 Technical Assurance I sign to confirm that I am satisfied with all aspects of the content and preparation of this document and submit it for approval and authorisation. Sign Date Steve Wilkinson PEP Engineering & Design Manager Steve Wilkinson 29/07/13 6.4 Approval Approval is given for the content of this document Sign Date Dave Sillito PEP Manager Dave Sillito 12/08/13 6.5 Authorisation Authorisation is granted for publication of this document. Sign Date Sean Caskey Head of Programme Delivery Sean Caskey 27/08/13