PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS

Similar documents
Lightning Overvoltage Performance of 110 kv Air-Insulated Substation

Lightning Flashover Rate of an Overhead Transmission Line Protected by Surge Arresters

Analysis of lightning performance of 132KV transmission line by application of surge arresters

Lightning overvoltage and protection of power substations

Lightning performance of a HV/MV substation

Effective Elimination Factors to the Generated Lightning Flashover in High Voltage Transmission Network

INSTALLATION OF LSA ON A 400 KV DOUBLE-CIRCUIT LINE IN RUSSIA

ABSTRACTS of SESSION 6

Session Four: Practical Insulation Co-ordination for Lightning Induced Overvoltages

Analysis of MOV Surge Arrester Models by using Alternative Transient Program ATP/EMTP

2000 Mathematics Subject Classification: 68Uxx/Subject Classification for Computer Science. 281, 242.2

University of Zagreb Faculty of Electrical Engineering and Computing

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION

Modeling insulation in high-voltage substations

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS

Parameters Affecting the Back Flashover across the Overhead Transmission Line Insulator Caused by Lightning

Statistical Lightning Simulations for a HV "Mixed" Overhead-Cable Line: Preliminary Studies

Lightning current field measurement on a transmission line, comparison with electromagnetic transient calculations

Maximum Lightning Overvoltage along a Cable due to Shielding Failure

Estimating BFOR on HV Transmission Lines Using EMTP and Curve of Limiting Parameters

The line-lightning performance and mitigation studies of shielded steelstructure

Including Surge Arresters in the Lightning Performance Analysis of 132kV Transmission Line

Tab 2 Voltage Stresses Switching Transients

Lightning Protection of Distribution Substations by Using Metal Oxide Gapless Surge Arresters Connected in Parallel

Utility System Lightning Protection

High voltage engineering

MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT

TECHNICAL NOTE 2.0. Overvoltages origin and magnitudes Overvoltage protection

Simulation of Lightning Transients on 110 kv overhead-cable transmission line using ATP-EMTP

Substation Insulation Coordination Study

Electric Stresses on Surge Arrester Insulation under Standard and

Simplified Approach to Calculate the Back Flashover Voltage of Shielded H.V. Transmission Line Towers

Computation of Lightning Impulse Backflashover Outages Rates on High Voltage Transmission Lines

Modeling of overhead transmission lines with line surge arresters for lightning overvoltages. Poland

X International Symposium on Lightning Protection

Earthing of Electrical Devices and Safety

EE 1402 HIGH VOLTAGE ENGINEERING

Lightning Performance Improvement of 115 kv and 24 kv Circuits by External Ground in MEA s Distribution System

Simulation and Analysis of Lightning on 345-kV Arrester Platform Ground-Leading Line Models

The Many Uses of Transmission Line Arresters

G. KOEPPL Koeppl Power Experts Switzerland

B2-301 IMPROVING DOUBLE CIRCUIT TRANSMISSION LINE RELIABILITY THROUGH LIGHTNING DESIGN

GIS Disconnector Switching Operation VFTO Study

Analysis of Electromagnetic Transients in Secondary Circuits due to Disconnector Switching in 400 kv Air-Insulated Substation

Research on Lightning Over-voltage and Lightning Protection of 500kV. HGIS Substation

Disclosure to Promote the Right To Information

Study of Tower Grounding Resistance Effected Back Flashover to 500 kv Transmission Line in Thailand by using ATP/EMTP

CHOICE OF MV FEEDER BIL TO MAXIMIZE QOS AND MINIMIZE EQUIPMENT FAILURE

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

Appendix B to Working on Exposed Energized Parts

APPLICATION OF LONG FLASHOVER ARRESTERS FOR IMPROVEMENT OF LIGHTNING PROTECTION AND OPERATING VOLTAGE RELIABILITY OF DISTRIBUTION LINES

A Case Study on Selection and Application of Lightning Arrester and Designing its Suitable Grounding Grid

Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning

The relationship between operating maintenance and lightning overvoltage in distribution networks based on PSCAD/EMTDC

Comparison between Different InstallationLocations of Surge Arresters at Transmission Line Using EMTP-RV

OVERVOLTAGE PROTECTION OF POLE MOUNTED DISTRIBUTION TRANSFORMERS

Insulation Co-ordination For HVDC Station

Chapter 1. Overvoltage Surges and their Effects

Software Development for Direct Lightning Stroke Shielding of Substations

Metal-Oxide Surge Arresters Integrated in High-Voltage AIS Disconnectors An Economical Solution for Overvoltage Protection in Substations

Lightning transient analysis in wind turbine blades

SCIENCE & TECHNOLOGY

Limitation of Transmission Line Switching Overvoltages using Switchsync Relays

Effect of Surge Arrester on Overhead Transmission Lines as Shield against Over Voltage

Electrical Power and Energy Systems

ABSTRACT 1 INTRODUCTION

EXPERIMENTAL ISSUES OF OVERVOLTAGE COORDINATION

Insulation Coordination Fundamentals Where Arrester and Insulator Characteristics Meet

SUPPRESSION METHODS FOR VERY FAST TRANSIENT OVER- VOLTAGES ON EQUIPMENT OF GIS

Towards an Accurate Modeling of Frequency-dependent Wind Farm Components under Transient Conditions

DEPARTMENT OF EEE QUESTION BANK

Investigation into Transient SFO, FFO, VFTO Overvoltage Characteristics for Typical Gas Insulated Substations

WORLD MEETING ON LIGHTNING Lightning Performance Research on Mexican High Voltage Transmission Lines

Electrical Transient Interaction between Transformers and Power System. Brazilian Experience

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS

Mitigation Methods to Improve the Lightning Performance of Hybrid Transmission Line

The Analysis Results of Lightning Overvoltages by EMTP for Lightning Protection Design of 500 kv Substation

Protection against unacceptable voltages in railway systems

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow

A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009

CHAPTER 2. v-t CHARACTERISTICS FOR STANDARD IMPULSE VOLTAGES

The Influence of Atmospheric Overvoltages on High-Voltage SF 6. Substations

Insulation Coordination Study of 275kV AIS Substation in Malaysia

TECHNICAL REPORT. Insulation co-ordination

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT CODE & NAME : EE 1402 HIGH VOLTAGE ENGINEERING UNIT I

ROEVER ENGINEERING COLLEGE ELAMBALUR, PERAMBALUR DEPARTMENT OF ELECTRICAL & ELECTRONICS ENGINEERING

Computer Based Model for Design Selection of Lightning Arrester for 132/33kV Substation

Effect of Shielded Distribution Cables on Lightning-Induced Overvoltages in a Distribution System

Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers

A Study on Lightning Overvoltage Characteristics of Grounding Systems in Underground Distribution Power Cables

ScienceDirect. Simulation Models for Various Neutral Earthing Methods in Medium Voltage Systems

ABSTRACT 1.0 INTRODUCTION LIST OF SYMBOLS

A Simple Simulation Model for Analyzing Very Fast Transient Overvoltage in Gas Insulated Switchgear

Lightning Overvoltage performance of 132kV GIS Substation in Malaysia

Transmission of Electrical Energy

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

In order to minimise distribution (11 and 22 kv) feeder breaker

Lightning phenomena and its effect on transmission line

Statistical analysis of overvoltages due to the energisation of a 132 kv underground cable

Transcription:

29 th International Conference on Lightning Protection 23 rd 26 th June 2008 Uppsala, Sweden PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS Ivo Uglešić Viktor Milardić Božidar Filipović-Grčić Amir Tokić ivo.uglesic@fer.hr viktor.milardic@fer.hr bozidar.filipovic-grcic@fer.hr amir.tokic@untz.ba University of Zagreb Faculty of Electrical Engineering and Computing Unska 3, Zagreb, Croatia University of Tuzla, Faculty of Electrical Engineering, Franjevacka 2, Tuzla, Bosnia and Herzegovina Abstract - The paper describes a simulation procedure which can be applied in order to analyse the prevention of flashover near a substation by installing line surge arresters (LSAs). The demonstrated procedure includes the application of a three-dimensional electro-geometric model, description of modelling process, EMTP simulations and estimating the lightning performance of a high voltage substation. This is shown in the case study on the double-circuit line of 220 kv with one shield wire entering the substation. By locating LSA on a tower near a substation, the risk of backflashovers near the station is significantly reduced and the steepness and amplitude of incoming travelling waves are lowered, thus improving the protection performance of station arresters. 1 INTRODUCTION Short circuits on transmission lines need to be avoided, not only to ensure continuous electricity supply for consumers but also to prevent stresses and damage they can cause to power system elements. Insulation faults on a transmission line in front of substations can provoke short circuit currents with high magnitudes. The consequence of insulator flashover is the forming of a surge with a very steep front that enters the substation and causes insulation stress especially on winding elements (transformer). Interruptions provoked by lightning are usually the most frequent cause of transmission line outages. While most lightning outages can be successfully eliminated by circuit breaker reclosing, the momentary loss of supply or load is not tolerated well by electronic equipment. One way for improving the lightning performance of substations is LSA installation on the first towers of the line entering the substation. LSAs are already employed by numerous electrical utilities around the world. 2 IMPROVEMENT OF LIGHTNING PERFORMANCE OF DOUBLE-CIRCUIT TRANSMISSION LINE The transmission line faults caused by lightning can be classified into backflashover and shielding failure. The backflashovers on the insulator string may involve one or more phases and one or more circuits of a double-circuit line. To avoid backflashover due to a lightning stroke to tower or overhead ground wire, the tower footing resistance should be as low as possible. In some areas where the soil resistance is high, this method is not practical because it may be too costly. Another solution, especially for suppression of a double-circuit simultaneous fault, is the installation of the unbalanced insulation of the double-circuit line [1]. This means the increase of the insulation level of one circuit, which should be higher than that of the other circuit. This increase is limited on the existing tower configuration due to the lack of space to increase the insulation length. Therefore usually an increase of insulator string length has to be combined with the improvement of the tower footing resistance. The installation of a new, or an additional overhead ground wire on top of the tower, or at portions of the line where they are missing, has been also applied to suppress the rise of potential that can lead to the flashover. This measure can demand significant modifications of tower construction due to changes of mechanical forces. The traditional countermeasures are often not effective enough to prevent simultaneous faults and the installation of LSA can be helpful in such cases in order to prevent double-circuit outages. In this way power supply continuity will be secured and the flashover rate of the double-circuit line significantly improved. Experience shows that the use of LSA is more efficient than conventional methods, especially in cases of double-circuit faults of transmission lines, which can be eliminated almost completely [2]. ICLP2008 Local Organisation Committee 6b-12-1

29th International Conference on Lightning Protection 3 SIMULATION OF LIGHTNING STROKE IMPACTING THE TRANSMISSION LINE The procedure for preventing flashover near a substation includes the application of a three dimensional electrogeometrical model, transient simulation and the evaluation of the lightning performance of HV substation. Lightning strokes impacting the HV transmission line are observed in order to determine the density of lightning strokes, which quantifies the threat of lightning strokes per unit length of a line during a one year period. The average lighting stroke density for a given area is defined as the number of strokes per area unit during the one year period. The goal of the simulation is to determine the distribution of lightning current amplitudes which strike high voltage transmission line or the phase conductor directly. Furthermore, characteristic values, such as minimal, maximal and critical current amplitude will be determined. The Monte Carlo method is used for simulation. This method is suitable for a calculation in case when all input parameters are not exactly known, but parameter distribution functions are known. It is supposed in this calculation, that the distribution of lighting current is known, but the current amplitudes are unknown. By a large number of simulations it is possible to calculate relevant values which are statistically arranged and are later used in lightning overvoltage calculation. The basic parameter needed for simulation is lightning current amplitude, for which the statistical distribution is known. The log-normal distribution, which is mostly used [3], can be approximated as following: 1 P = (1) 2.8 I 1+ 31 P - probability of occurrence of lightning current amplitude higher than I, I - lightning current amplitude, The general expression for the striking distance is represented by the equation: R - striking distance, I - lightning current amplitude, a - constant [3.3 10.6], b - constant [0.5 0.85]. R b = a I (2) The striking distance can vary significantly and therefore different values of constants and modifications of the above equation are proposed by various investigators [3]. Expression for the striking distance with constants a=7.2, b=0.65 is used in simulations. The tower of a double-circuit 220 kv line and part of a transmission line is depicted in Fig. 1. Shield wire at six spans; portal and six towers with their arms are modelled as straight lines. All three phase conductors of both circuits are modelled although all phase conductors are not exposed equally to lightning strikes. In order to collect enough data for statistical calculation, the simulation is conducted for a large number of generated lightning current amplitudes. The random nature of lightning phenomena can be quantified with a large number of samples that make more credible results of statistical calculation. Hence, simulations with large number of strikes are made first in order to get a better view of the numerical relations between ground strikes, strikes on shielding wires and towers and phase conductor strikes. 6b-12-2

ICLP 2008, June 23-26, Uppsala, Sweden Fig. 1-220 kv tower and 3D scheme of the modelled system's six spans Simulations were carried out until 500 simulations finished with phase conductor strike. There were a total of 24811 simulations made, of which 17014 finished with ground strikes, 7297 with shielding wire and tower strike. According to statistical calculation, the following phase conductor strike currents values are calculated: - average value: 12.99 ka, - variance: 63.50 ka, - standard deviation: 7.97 ka, - maximal phase conductor strike current: 33.10 ka, - critical current: 34,94 ka. Critical current is calculated for the highest tower of the observed part of a transmission line. According to the simulation results 6.85 % of total lightning strokes finished as shielding failure - distribution is shown in Fig. 2. Fig. 2 - Distribution of lightning currents which strike phase conductors Distribution of lightning strokes per phases (Fig. 3), shows that 66.18 % of strokes, which strike phase conductors finished in the upper phase. About 32.35 % of lightning strokes finished in middle phase and about 1.47 % of lightning currents which strike the lower phase cannot provoke the flashover (e.g. 2.56 ka, 3.06 ka). 6b-12-3

29th International Conference on Lightning Protection 0.7 0.6 Probability 0.5 0.4 0.3 0.2 0.1 0 Upper phase Middle phase Lower phase Fig. 3 - Distribution of lightning striking phase conductors per phases 4 MODELING PROCEDURE FOR CALCULATING LIGHTNING OVERVOLTAGES In the case study 220 kv double-circuit line with one shield wire entering the substation is modelled. For the operating condition (shown by dashed line in figure 4 - LINE 2 and autotransformer AT2 in service) lightning overvoltage calculations were carried out by EMTP-ATP in case when lightning strike the transmission line. 220/115/10.5 Yy0d5 220/115/10.5 Yy0d5 220/115/10.5 Yy0d5 Fig. 4 Single-line diagram of the 220 kv substation placement of station surge arresters The power transformer is modelled as a lumped capacitance of 6000 pf and capacitor voltage instrument transformer with lumped capacitance which has value of 4400 pf. The substation buses are represented by line sections. The lightning stroke hitting a tower or a phase conductor can be replaced by a surge current generator and a resistor (Norton generator). The peak current magnitude and the tail time are important when observing the line arrester energy stresses, while the influence of the rise time is hardly noticeable in such a case. In contrast the current wave front is an important parameter with regard to insulator flashover. The so-called Heidler model can approximate well the concave form of the lightning current front. The transmission line, conductors and earth wire is represented by several multi-phase untransposed distributed parameter line spans at both sides of the point of the lightning stroke impact. Two or three line spans at both sides of the point of impact should be modelled when observing the flashovers of the insulators. Many more spans are needed for the evaluation of the line arrester energy stresses when arresters are installed in the neighbouring spans. Figure 5. depicts the model used for simulation of lightning striking a double-circuit 220 kv line. 6b-12-4

ICLP 2008, June 23-26, Uppsala, Sweden 140 m Z=122.8 Ω 213 m Z=121.4 Ω 354 m Z=157.0 Ω 384 m Z=153.5 Ω 367 m Z=157.0 Ω 358 m Z=125.2 Ω 2000 m Matching resistance Fig. 5 Model of 220 kv double-circuit line entering HV substation Tower surge impedances [4] are calculated using equation (3). Each tower is divided in four parts. First part is from tower top to upper arm, second one from upper arm to middle arm, third part from middle arm to lower arm and the last part from lower arm to ground. On this way it is possible to calculate transient voltages of tower arms. H Z = 60 ln 1 ( R << H ) (3) R Phase voltages at the instant at which a lightning stroke impacts the line must be included. The largest voltage difference across insulator/arrester terminals occurs during the peak value of phase voltage, which has the opposite polarity of the lightning surge. For statistical calculations, phase voltages can be deduced by randomly determining the phase voltage reference angle and considering a uniform distribution between 0 0 and 360 0. To avoid reflection of travelling wave, line is terminated with multiphase matching resistance on one end. Insulators themselves represent capacitances with only very moderate influence on the occurrence of overvoltage. The decisive parameter for the behaviour of overhead line insulation subjected to the lightning overvoltages is its corresponding flashover voltage, which depends on the voltage level due to different insulation clearances. The flashover volt-time characteristic of an 220 kv insulator string [5] is given by the following equation: K 1 = 0.4 L [m]; K 2 = 0.7 L [m]; L - flashover distance [m]; T front - front duration in [μs]. K U ( t) = K + (4) 1 2 0.75 T front Flashover characteristic it is modelled using Model and TACS-controlled switch in an EMTP calculation. Tower footing resistances are modelled taking into account ionization [5]. The ionization model according to equation (5) takes into account the soil ionization that is caused by the lightning currents. In the EMTP calculation the tower grounding is represented as non-linear resistors using Model and TACS-controlled time-dependent resistor: R i = R o 1+ I I g (5) 6b-12-5

29th International Conference on Lightning Protection R o - footing resistance at low current and low frequency, i.e. 50 or 60 Hz [Ω], I - stroke current through the resistance [ka], I g - limiting current to initiate sufficient soil ionization [ka]. The tower footing resistance remains R i =R o if I < I g and varies according to the given equation if I > I g. The limiting current is given by: I g = ρ E 0 2 2 π Ro ρ - soil resistivity [Ωm]; E 0 soil ionization gradient, recommended value: 400 [kv/m]. (6) The model of gapless type line arrester includes non-linear and dynamic behaviour of the arrester. The non-linear behaviour is represented by the U-I characteristic depicted in Fig. 6. while the frequency-dependent arrester model takes into account its dynamic behaviour. 650 600 550 Voltage (kv) 500 450 400 350 300 0,1 1 10 100 Current (ka) Fig. 6 - U-I characteristic of surge arrester for 220 kv line (U r =192 kv) A frequency-dependent arrester model is depicted in Fig. 7. Model parameters are identified using a formula that does not require any iterative correction and that makes use only of the data reported on manufacturers datasheets [6]. L 0 L 1 R A 0 A 1 Fig. 7. Frequency-dependent arrester model 5 OVERVOLTAGE PROTECTION OF 220 KV SUBSTATION SIMULATION RESULTS Simulations of lightning overvoltages are conducted for direct strokes to the phase conductor near the substation, because that is one of the most severe cases for substation equipment. Lightning overvoltages are calculated for the operational condition shown in Fig. 8. (one transmission line and transformer in service) in case of lightning impacting the line. 6b-12-6

ICLP 2008, June 23-26, Uppsala, Sweden Figure 8. Substation elements analyzed in overvoltage calculation Table 1 gives peak values of overvoltages on the following substation elements: (Fig. 8): 1 voltage instrument transformer in line bay; 2 circuit breaker in line bay; 3 circuit breaker in autotransformer AT2 bay; 4 - autotransformer AT2. For different lightning current parameters the stroke to the upper phase conductor at first tower is simulated. Surge arresters in the autotransformer bay are included in all simulations. Calculation results are shown in table 1. Lightning current parameters Table 1: Overvoltage calculation results on substation elements for different lightning current parameters Insulator flashover in upper phase Surge arrester in line bay LSA in upper phase at first tower Voltage on voltage instrument transformer in line bay (1) Voltage on circuit breaker in line bay (2) Voltage on circuit breaker in autotransformer bay (3) Voltage on autotransformer AT2 (4) 4.02 ka, 0.33/50 μs No No No 727 kv 693 kv 523 kv 512 kv 9.45 ka, 0.53/50 μs Yes No No 993 kv 975 kv 689 kv 538 kv 9.45 ka, 0.53/50 μs Yes Yes No 705 kv 687 kv 612 kv 438 kv 9.45 ka, 0.53/50 μs No Yes Yes 449 kv 472 kv 461 kv 459 kv Calculation results show that surge arresters in the line bay protect substation elements (voltage instrument transformer and circuit breaker) that are not effectively protected with surge arresters in the autotransformer bay. Surge arresters in the line bay also reduce overvoltage values on the autotransformer (Table 1.) and takes a part of the overvoltage energy. Furthermore, in operating conditions when the circuit breaker or disconnector in the line bay is opened, all substation equipment from the circuit breaker (disconnector) towards the transmission line remains completely unprotected from overvoltages. The modern concept of overvoltage protection is the placement of surge arresters close to power transformers and in the line bay in front of voltage instrument transformers. Lightning currents of smaller amplitudes often originate from multiple strokes with higher steepness. Almost all lightning currents hitting the phase conductor (except the smallest) can cause insulator flashover, although insulator flashover voltage is high. For maximum operating voltage of 245 kv circuit breaker and voltage instrument transformer have standard lightning insulation level of 1050 kv / 460 kv. Coordination lightning impulse withstand voltage of 913 kv was determined for safety factor K s =1.15. Although insulator flashover results in voltage unloading, if no surge arresters are installed in the line bay, the voltages on the circuit breaker and voltage instrument transformer exceed a value of 913 kv. Power transformer has a nonstandard reduced insulation level of 900 kv / 395 kv. Coordination lightning impulse withstand voltage of 720 kv was determined as 80% of transformer s standard lightning impulse withstand voltage (900 kv). Overvoltages on power transformer AT2 in all simulations were below the coordination lightning impulse withstand impulse voltage of 720 kv. Lightning activity can cause momentary outages of certain transmission lines when the circuit breaker switches off the line. In that case substation elements behind the circuit breaker remain completely unprotected and exposed to lightning overvoltages. Examples of overvoltages on the voltage instrument transformer and circuit breaker in the line bay are shown in Fig 9. for three cases of surge arrester placement: a) surge arrester installed in autotransformer bay b) surge arrester installed in autotransformer bay and line bay c) surge arrester installed in autotransformer bay and line bay + LSA at first tower (in the upper phase) 6b-12-7

29th International Conference on Lightning Protection 1.0 [MV] 0.8 OVERVOLTAGES ON VOLTAGE INSTRUMENT TRANSFORMER IN LINE BAY 1.00 [MV] 0.75 OVERVOLTAGES ON CIRCUIT BREAKER IN LINE BAY 0.6 0.4 0.50 0.2 0.25 0.0 0.00-0.2-0.4-0.25-0.6 800 [kv] 580-0.50 700 [kv] 480 360 260 140 40-80 -180-300 470 [kv] 430 390 350 310 270 230 190-400 500 [kv] 450 400 350 300 250 200 150 150 Figure 9. Overvoltages on voltage transformer and circuit breaker Overvoltage protection is improved by installing additional surge arresters in the line bay. Calculation results show that complete protection is achieved by installing surge arresters close to the voltage instrument transformer in the line bay and in front of the power transformer. Thereby all substation elements are completely protected from overvoltages Overvoltage protection decreases the dielectric stresses of the power transformer insulation and all substation elements. When an additional LSA is installed, overvoltage protection of the substation is improved and ''the first line'' of protection is displaced to the transmission line entering the substation. Besides direct lightning strokes to phase conductors, another dangerous event for substation elements is the occurrence of backflashover near a substation, which results in short circuit currents of high magnitudes. A lightning stroke (100 ka, 1/50 μs) to a fourth tower with the highest footing resistance (70 Ω) is analyzed. The appearance of backflashover strongly depends on the tower footing resistance and the voltage phase angle. In order to prevent backflashover occurrence the LSA was installed in the upper phase of one system. 6b-12-8

ICLP 2008, June 23-26, Uppsala, Sweden Figure 10. Voltages in phases of one circuit (without LSA) Figure 11. Voltages in phases of one circuit (LSA installed in the upper phase) Backflashover occurs in the upper phases of both circuits if surge arresters are not installed (Fig. 10). If a surge arrester is installed in the upper phase of one circuit, the backflashover is in this case prevented in both circuits (Fig. 11). The arrester in the upper phase also reduces voltages in the other phases (better coupling factor, tower voltage reduction). 6 CONCLUSIONS In cases when insulator flashover occurs near a substation, short circuit currents can have high magnitudes and a very steep front of wave is formed that enters the substation and causes insulation stresses, especially on winding elements such as the transformer. Backflashover near a substation can be avoided by installing LSAs and the overvoltage protection of the substation can be improved. The installation of LSAs can also minimize operation of the circuit breakers with a possible system outage resulting from backflashover on the transmission line. This eliminates interruption of power supply and results in better power quality. The analysis performed are conducted with the application of a three-dimensional electro-geometric model and EMTP simulations. Results show that the installation of LSA in front of the HV substation significantly prevents backflashover and improves the overvoltage protection of the entire substation. 7 REFERENCES [1] Wei-Gang H., Lightning performance of 500 kv double-circuit line schemes for the Three-Gorge project, IEEE Transactions on Power Delivery, vol. 21, no. 2, pp. 736-743, Apr. 2006. [2] Shigeno T., Experience and effectiveness of transmission line arresters, Transmission and Distribution Conference and Exhibition 2002: Asia Pacific. IEEE/PES, vol.1, 636 639, Oct. 2002. [3] Hileman R. A., Insulation coordination for power systems, Power Engineering Book, Marcel Dekker, Inc., 1999. [4] IEC 60071-4: Insulation co-ordination Part 4: Computational guide to insulation co-ordination and modelling of electrical networks, 2004. [5] IEEE Working Group: A Simplified method for estimating lightning performance of transmission Lines, IEEE Transactions on Power Apparatus and Systems, vol: PAS 104, no. 4, July 1985. [6] Martinez J. A. and Castro-Aranda F., Modeling Overhead Transmission Lines for Line Arrester Studies, IEEE Power Engineering Society General Meeting, vol. 1, pp. 1125-1130, June 2004. [7] P. Pinceti and M. Giannettoni, A simplified model for zinc oxide surge arrester, IEEE Transactions on Power Delivery, vol. 14, no. 2, pp. 545 550, April 1999. 6b-12-9