optimisation of pre-cast support beams

Similar documents
Design of structural connections for precast concrete buildings

Finite Element Study of Using Concrete Tie Beams to Reduce Differential Settlement Between Footings

Glulam Connection Details

Shinde Suyog Sudhakar, Galatage Abhijeet.A, Kulkarni Sumant.K, International Journal of Advance Research, Ideas and Innovations in Technology.

INFLUENCE OF PILES ON LOAD- SETTLEMENT BEHAVIOUR OF RAFT FOUNDATION

Seismic Performance of Brick Infill in RCC Structure

K L Rakshith, Smitha, International Journal of Advance Research, Ideas and Innovations in Technology.

EFFECT OF SETBACK RATIO ON SEISMIC PERFORMANCE OF RC STRUCTURES

Effect of Infill Walls on RC Framed Structure

ROOM smooth cement f.f FLOOR LAYOUT

NALYSIS OF STABILIZING SLOPES USING VERTICAL PILES

Finite Element Analysis per ASME B31.3

Flanged Dowel Box. Load Transfer System INDUSTRIAL SLAB ON GROUND

Prying of a Large Span Base Plate Undergoing a Moment Load Applied by a Round Pier

Effect of Masonry Infills on Seismic Performance of RC Frame Buildings

ProConcrete. Gernot Jeromin Product Manager Bentley Systems, Incorporated

shawprecastsolutions.com BEBO Arch Systems PRODUCT GUIDE & TECHNICAL REFERENCE MANUAL Providing the right solutions.

Dynamic Analysis of Infills on R.C Framed Structures

Module 10 : Improvement of rock mass responses. Content

F I X I N G B R O C H U R E

TEST SERIES TO EVALUATE THE STRUCTURAL BEHAVIOUR OF ISOBOARD OVER RAFTER SYSTEM

ANALYSIS OF LATERAL STIFFNESS FOR INFILLED FRAME WITH OPENING

IBS IS A SYSTEM NOT A MACHINE significantly difference from traditional cast in-situ construction which relies heavily on customized site work

Acceptable Standards of Domestic Construction

Expanding the Frontiers of Geotechnical Engineering

3.1 General Provisions

General Layout. Eng. Maha Moddather

Suggested Reinforcement Detailing Practices Based on comments from R&D and ES ESS Committees

Structural Strength of Lapped Cold-Formed Steel Z-Shaped Purlin Connections with Vertical Slotted Holes

Double Storey HC Precast System Drawing - 3D

Experimental Study on the Seismic Behavior of Retrofitted Concrete Infill

TECHNICAL MANUAL. TERADOWEL and ULTRADOWEL. Reliable Dowel System for Floor Joints

Experimental Study on Pile Groups Settlement and Efficiency in Cohesionless Soil

PRECAST CONCRETE STRUCTURES

This specification describes the minimum requirements for structural steel drawings.

Nailed Structural-Use Panel and Lumber Beams

Reinforced Concrete Structures

EFFECT OF YARN CROSS-SECTIONAL SHAPES AND CRIMP ON THE MECHANICAL PROPERTIES OF 3D WOVEN COMPOSITES

Diamond Dowel. Load Transfer System INDUSTRIAL SLAB ON GROUND

PRACTICE NOTE NO: 13 Version 1 Amended March 2001 Page 1 of 6 PRECAST CONCRETE ELEMENT DESIGN RESPONSIBILITIES AND CONTRACTUAL ARRANGEMENTS

WHY YOU SHOULD USE TUFFLOOR. components

BRIDGE TYPE CONCEPT EVALUATION

Introduction. Figure 1. Bender Machine Bend Heads

CIVIL TECHNOLOGY. 9. For the purpose of this paper, the size of a brick should be taken as 220 mm 110 mm 75 mm.

HOLLOW CORE PRODUCTS GROUNDED IN STRENGTH

PRECAST CONCRETE BRIDGE SUBSTRUCTURE COMPONENTS. Presented by: Matthew Youngblood, PE, SE Scott Noyer, PE Janssen & Spaans Engineering

Seismic Response of Cellwise Braced Multistoried Frames

HC Precast System ( 100 % Malaysia Technology With 6 IPs )

BRACING BRACING SECTION 7 SECTION 7

Cyclic Response of Dowel Connections in Precast Structures

International Journal of Science, Engineering and Technology Research (IJSETR), Volume 4, Issue 11, November 2015

Moment Resisting Connections for Load Bearing Walls

Connectors for Cold-Formed Steel Curtain-Wall Construction

Innovative composite dowel for steel concrete composite bridges. Neil Westmacott, Wolfram Schwarz

The predictive model for strength of inclined screws as shear connection in timber-concrete composite floor

VERSA-LAM. An Introduction to VERSA-LAM Products

ARCHITECTURE CADD Course Syllabus

3D Non-Linear FEA to Determine Burst and Collapse Capacity of Eccentrically Worn Casing

Corporate Subscription. NAFEMS reference library at the click of a button

Nonlinear behavior of Reinforced Concrete Infilled Frames using ATENA 2D

Technical Data Sheet. T E C H N I C A L D A T A S H E E T Superprop. Mass 25 Mass 50 M AT 125 Superprop. MU Bridging

Experimental Investigation of Crack Detection in Cantilever Beam Using Natural Frequency as Basic Criterion

Hanger bolts and solar fasteners in sandwich panels

Composite Sections. Introduction BETON PRATEGANG TKS Session 10: 2015/4/27

The Behaviour Of Round Timber Sections Notched Over The Support On The Tension Face. Justin Dewey

CONNECTIONS FOR CONTINUOUS FRAMING IN PRECAST CONCRETE STRUCTURES

Sprocket and Hub Bolt Analysis for Slip-Critical Bolted Applications in Mining and Mineral Processing Equipment

Theory of Structures-I (CE-206)

Experimental investigation of the behaviour of pinned beam to column connections to pure shear monotonic and cyclic excitation

Experimental investigation of crack in aluminum cantilever beam using vibration monitoring technique

Free-Spanning Pipelines in the Digital Age Nicholas Nielsen & Olivier Royet

GROUND FLOOR PLAN S.F. 2 Bedroom - 1Bath 2 Storey (First Floor Only) FIRST FLOOR PLAN S.F. 2 Bedroom - 1Bath 2 Storey (First Floor Only)

Dowel connections in laminated strand lumber

TYPICAL PATIO COVERS. OWNER: ADDRESS: PHONE:

Seismic Response of Cellwise Braced Reinforced Concrete Frames

UPPER FLOORS TIMBER AND CONCRETE

Numerical Analysis of Piled Raft Foundation using Fem with Interaction Effects

Modelling of Rebar and Cable Bolt Behaviour in Tension/Shear

SUMMARY SHEETS OF BAR COUPLER CONNECTIONS

Hydraulic Tensioner Assembly: Load Loss Factors and Target Stress Limits

Lawrence A. Soltis, M. and Robert J. Ross, M. 1

ASSESSMENT OF BASIC STEEL I-SECTION BEAM BRACING REQUIREMENTS BY TEST SIMULATION

CURVED ROOF ASSEMBLY INSTRUCTIONS ATTACHED VERANDAH. Your supplementary guide to building an ATTACHED CURVED ROOF VERANDAH or PATIO BEFORE YOU START

Dowels for the 21st Century

PAST EXAM PAPER & MEMO N3 ABOUT THE QUESTION PAPERS:

Mechanical behavior of fiberglass reinforced timber joints

Engineering Research into Traditional Timber Joints

Posi-Joist Installation Guide. A guide for storage, handling and installation of the MiTek Posi-Joist floor system

Table 5G-2.01: Transverse Joint Requirements. Transverse Joint Type 6 C 12 7 C 15 8 CD CD CD 1 20

R&T UPDATE. An Alternative to Traditional Round Dowel Bars Plate Dowel Innovations Driven by Industrial Concrete Paving

VIBRATIONAL TESTING OF A FULL-SCALE PILE GROUP IN SOFT CLAY

DOLPHIN TITAN CHANGING UNIT. Carrying capacity of more than 400kg

24" max from each end of the ledger. See detail 6A & 6B, typ. both ends IRC R Ledger R507.2

Journal of American Science 2015;11(8) Soil Nailing For Radial Reinforcement of NATM Tunnels

Beam & Header Technical Guide. LP SolidStart LVL. 2900F b -2.0E. U.S. Technical Guide U.S. TECHNICAL GUIDE

TECHNICAL MANUAL. OPTIMAJOINT Free Movement Joint. Free Movement Joint System for Heavy Traffic

RADAR INSPECTION OF CONCRETE, BRICK AND MASONRY STRUCTURES

Quality Control and Quality Assurance Guide

Please direct powder-actuated and screw fastening technical inquiries to your local Hilti Field Engineer or Technical Support at

Model Correlation of Dynamic Non-linear Bearing Behavior in a Generator

Transcription:

optimisation of pre-cast support beams Design Optimisation of Pre-cast Support Beams Investigation into pile and beam systems for a client in the civil engineering industry with the following objectives: To reduce the reinforcement in the beams to eliminate the over-design previously identified. To demonstrate that piles supporting a masonry structure do not need to be restrained in two directions by beams even when placed out of position, and therefore to eliminate unnecessary tie beams. T: +44 (0) 161 4747479 E: info@wildefea.co.uk Wilde FEA Ltd. 1998

Case Study: Design Optimization of Pre-Cast Support Beams Tim Morris - Wilde & Partners

Problem Description Background Work performed on behalf of Roger Bullivant Limited Existing design for pre-cast pile and beam foundation system for housing Introduced in early 1990 s Used in poor to marginal ground conditions Proved successful, currently 50 houses per week Existing design not cost-effective for good ground conditions

Background System Components

Known Conservatisms Existing design known to be unduly conservative Design calculations based on assumption of simply supported beams Full load of walls, floor and roof imposed as a UDL Bending moment = WL 2 /8 Background Shear Force = WL/2 Work by Building Research Station in 1950 s identified this approach as conservative as no account is taken of stiffness of masonry Conservatisms therefore relate to load paths and the interaction between the masonry superstructure and the supporting sub-structure of support beams and pile caps

Background Load is attracted to piles due to: Arching effect of masonry Greater stiffness of support points Hence load is less than UDL at centre span Some moment restraint is offered at beam supports Extent of these effects difficult to quantify

Project Objectives To reduce the reinforcement in the beams to eliminate the overdesign previously identified. Background To demonstrate that piles supporting a masonry structure do not need to be restrained in two directions by beams even when placed out of position, and therefore to eliminate unnecessary tie beams.

Background Pile caps Beams directly under walls Tie beams for additional stability (no wall above)

Project Objectives To reduce the reinforcement in the beams to eliminate the overdesign previously identified. Background To demonstrate that piles supporting a masonry structure do not need to be restrained in two directions by beams even when placed out of position, and therefore to eliminate unnecessary tie beams. To eliminate reinforcement cast into the ends of the beams to form the connections.

Front Elevation Background Plan View

Project Objectives To reduce the reinforcement in the beams to eliminate the overdesign previously identified. Background To demonstrate that piles supporting a masonry structure do not need to be restrained in two directions by beams even when placed out of position, and therefore to eliminate unnecessary tie beams. To eliminate reinforcement cast into the ends of the beams to form the connections. To investigate different bearing lengths between cap and beams to allow the beam to be cast in incremental stock lengths.

Project Stages Construction of Test House Evaluation of Behaviour FEA and Comparison with Test Initial Test House Background Derivation of New Layout FEA of New Layout Design Optimization Construction and Monitoring of Test House Submission to BBA for Approval Second Test House

Initial Test House Initial Test House KEY DESIGN ASPECTS Constructed prior to use of FEA Spans of up to 5m Substantial reduction in levels of reinforcement Maximum design loads applied Removal of steel at joints RESULTS Separation at Damp Proof Course level Cracking of brick and blockwork

Benefits of FEA A more accurate prediction of the true load paths. Initial Test House A reduction in the number of conservative approximations needed in design calculations. An examination of the effects of different designs, boundary conditions and loading situations with (comparative) ease. An ability to investigate the robustness of the design to potential hazards (for example, the unforeseen catastrophic failure of a supporting pile).

Initial Test House FE Model

Initial Test House FE Model

Modelling Methods Wall Ties Beam Elements Initial Test House Blockwork Brickwork T Beam Floor Reinforcement Schematic Layout Shell Elements Shell Elements Gap Elements Beam Elements FE Representation

Modelling Methods Initial Test House Double layers of shell elements for walls Wall ties using beam elements Support beams modelled with beam elements, with cross-section defined explicitly Embedded reinforcements in beam elements Multiple fixed crack model for concrete DPC represented with interface gap elements

Results Initial Test House Prediction of cracks at DPC level with size and disposition showing good agreement with test Areas where stresses in masonry exceeded likely tensile strength showed good agreement with size and location of observed cracks Cracks predicted to occur on beams in locations and of an extent that corresponded well with cracks observed on test beams

Decision For Further Actions Initial Test House Use FEA to investigate further the effects of various possible design modifications Derive a new test house layout Analyse the new test house layout, with various sensitivity studies Construct a new test house, and monitor it fully during a comprehensive loading sequence.

Layout Features Second Test House Large garage Typical door and window layout from detached and semi-detached houses Large party wall Large patio door Opening included post-construction Modified beam connections Omission of tie beams Reduction in maximum beam span

Second Test House Layout

Second Test House FE Model

Sensitivity Studies Second Test House Zero lateral restraint at pile locations, compared with full lateral restraint. Variations in material properties. The inclusion of future openings. Piles being placed away from their intended position. The connections between the beams being unable to develop sufficient hogging capacity, allowing a plastic hinge to be formed.

Analysis Results Second Test House Beam forces and moments for design purposes Displacements Minimal cracking of beams No more than hairline cracks at DPC level Low probability of significant cracking in masonry

Bending Moments FEMGV 4.2-01 Wilde & Partners 24 JUN 1998 Model: NBM2 LC1: Load case 1 Step: 1 LOAD: 1 Element EL.MX..L MY Max/Min on model set: Max =.115E8 Min = -.208E8 Second Test House Y Z X

Second Test House

Beam Displacements Second Test House FEMGV 4.2-01 Wilde & Partners 17 SEP 1998 Model: NBM LC1: Load case Step: 1 LOAD: 1 Nodal TDTX...G RESTDT Max/Min on model set: Max = 3.3 Min = 0 Factor = 238 Y Z X

Second Test House

Second Test House

Comparison With Strip Footing Second Test House Simplified analysis for comparison Same house superstructure supported on Winkler spring representation Likelihood of masonry cracking predicted to be at least as great as that from kit T-beam foundation system

Second Test House

Second Test House

Design Methods Second Test House Design calculations as per BS8110: Part 1: 1997 Design of suitable beam cross-sections arrived at through iterative process Final forces and moments ~40% of those based on UDL Hogging moment capability at joints by use of top steel

Second Test House Beam Cross-Sections

Testing / Monitoring Second Test House Full scale test house constructed Loaded with full design load Load applied in phases to investigate all potential load imbalances etc. Behaviour of structure fully monitored by CERAM Building Technology Displacements monitored and crack surveys carried regularly during entire loading process and subsequently as structure left at full load Strain gauges used at potential crack locations Precision levelling

Second Test House Testing / Monitoring

Second Test House Testing / Monitoring

Second Test House Testing / Monitoring

Comparison of Test & Analysis Second Test House No significant cracks or displacements observed during testing Displacements of similar order to predictions but too small to make accurate comparisons possible No distress to structure despite significant loading

Conclusions FEA used in combination with test programme FEA substantially reduced amount of testing required FEA allowed design to be optimized resulting in significant cost savings Environmental benefits from reduced use of materials Unnecessary conservatisms substantially reduced Final design proven by testing BBA approval granted for revised system Design optimization of pre-cast components is an ideal application for advanced FE methods