University of Central Florida Main Campus. Electric. Service and Meter Installations Requirements. Issued January 26 th, 2017.

Similar documents
Quality Control Checklist - Design Drawings

1. All electrical switches and outlets used shall be equal to Hubbell heavy duty, specification grade or equivalent quality.

CONTINUING EDUC ATION

Customer Connection Guide Updates Effective May 2017

INTELLIMETER REGISTER

SECTION LOW-VOLTAGE ELECT. DIST. DESIGN AND CONSTRUCTION STANDARDS _ February 2015 PART I: GENERAL

PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION!

Page Electric Utility Service Specifications

SaskPower Electric Service Requirements Revision 0 November 24, Electric Service Requirements

SECTION 5 TRANSFORMERS

Article 225: Outside Branch Circuits And Feeders

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer

Primary Metering. What is Primary Metering?

Article 250 Grounding & Bonding

METER - INSTALLATION Pad Mount Transformer

Electric Service Guide. Residential Subdivision

9. Pay for the power consumed until the project has been accepted as substantially complete.

PLOT PLAN INSTRUCTIONS ROOF MOUNT SOLAR AN ACCURATE PLOT PLAN IS NECESSARY TO PROCESS YOUR PERMIT

Wisconsin Contractors Institute Continuing Education

American Electrical Institute

Education & Training

3.1 Overview of ATCO Electric s URD System Design

SAFETY AND HEALTH STANDARD ELECTRICAL GROUNDING Effective Date: 07/17/10 Standard: Document Number: KUCSH0039 Rev: 4

Grounding and Bonding of Service Equipment

Bid No. B14-02 Building 100 HVAC Improvements

FINAL - ER 70 Electrician Regulations Answer Schedule. Question 1 Marks Reference Marking notes

WESTERN UNDERGROUND COMMITTEE GUIDE 2.6 (2.6/00/0868)

Planning Guidelines. Lightcloud. Best Practices for Installing Lightcloud

ENGINEERING STANDARD FOR INSTRUMENTS ELECTRICAL POWER SUPPLY AND DISTRIBUTION SYSTEMS FIRST EDITION MAY 2013

Section 16621A - AUTOMATIC TRANSFER SWITCH. Part 1 General

Customer Requirements RF Antenna Installations

MERALCO Standards: Electrical Design. Engr. Eduard Mercado Electrical Design Team

First Draft Language

How to maximize reliability using an alternative distribution system for critical loads

WAVEFORM CORRECTOR (WAVEFORM CORRECTORS) REPLACES SURGE PROTECTION DEVICES (SPD) PREVIOUSLY KNOWN AS (TVSS)

Table of Contents. Introduction... 1

2014 NEC Changes Part 1

POWER SERVICE DETAILS

Greenlining and Bluelining of Ergon Energy Substation Drawings

NOTICE OF RULE MAKING PROCEEDINGS AND PUBLIC HEARING

Installation Manual DOC R1 Date: 05/27/99. Plug-in Meter Installation Manual

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 2/9/11 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

Grounding Recommendations for On Site Power Systems

Busbar and Modular Wiring Systems

SECTION EMERGENCY RESPONDER RADIO COVERAGE SYSTEMS

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.

TABLE OF CONTENT

POWER DELEGATOR SERIES 7200A POWER DISTRIBUTION UNIT WITH POWER CONDITIONING GENERAL SPECIFICATIONS

Michigan State University Construction Standards SWITCHBOARDS, PANELBOARDS, AND CONTROL CENTERS PAGE

REDKOH INDUSTRIES SWITCH MODE POWER SUPPLY DEMO UNIT

Chapter 1. Applied Grounding and Bonding. Applied Grounding and Bonding 9/18/2011. Introduction. Introduction. Paul Dobrowsky Member NEC Panel 5

2/15/2015. Current will always try to return to its source. In order for there to be current, there must be a complete circuit

Back to the Basics Current Transformer (CT) Testing

Adaptive Autoreclosure to Increase System Stability and Reduce Stress to Circuit Breakers

Distribution/Substation Transformer

Single Line Diagram of Substations

SUPPORT ROADS ALL AIRPORT SERVICES BUILDINGS. ONLY CARGO BUILDINGS (Tenants) Sign Types Summary SIGN TYPES - A.SERVICES

SECTION TRANSFORMERS

SECTION COMMUNICATIONS ELECTRICAL POWER DISTRIBUTION

SECTION DISTRIBUTION SWITCHBOARDS

Variable Transformers Product Design & Engineering Data

PROCEDURE FOR INSPECTION OF ELECTRICAL INSTALLATIONS ABOVE 250KVA

DESIGN CHECKLIST INTRODUCTION

SECTION PANELBOARDS

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 9/8/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

TECHNICAL DESCRIPTION TD-77A/3 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES

Stanford University-Facilities Design Guideline SECTION Plans Review Submission Guidelines

Metering Project Guide

State College Area School District

CONSULTANT PROCEDURES & DESIGN GUIDELINES Liquid-Filled Utility Transformers UNIVERSITY OF MISSOURI

NEO TELE-TRONIX PVT. LTD. 6/7 Bijoygarh, Kolkata , Tel : ; Fax :

6B.6 Substation Grounding

3Ø Short-Circuit Calculations

SOLAR PV MICROINVERTER/ACM STANDARD PLAN - COMPREHENSIVE Microinverter and ACM Systems for One- and Two- Family Dwellings

Brown University Revised 2/1/2006 Facilities Design & Construction Requirements SECTION 16461C - DRY TYPE TRANSFORMERS

MODEL 421 Over/Under Motor Load Monitor

120 / 240 VAC SINGLE SPLIT PHASE & MULTI-WIRE BRANCH CIRCUITS. Excerpt from G4 InverCharge Series Manual BY: VIJAY SHARMA ENGINEER

CHAPTER 29 PROJECT COMPLETION DOCUMENTS

GROUNDED ELECTRICAL POWER DISTRIBUTION. Excerpt from Inverter Charger Series Manual BY: VIJAY SHARMA ENGINEER

TABLE OF CONTENTS. References

AN EXAMPLE OF A STANDARD ARC FLASH PPE LABELING STRATEGY

Capstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:

Unit 2. Single Line Diagram of Substations

NEC 2014 Code Changes

September 21, Mannik Smith Group 1771 North Dixie Highway Monroe, Michigan RE: LA Fitness City File No.: CVLP

FORM NWC-705. Section 1: General Information. Section 2: Collocation Information. Collocation Location:

CITY OF PINE CITY SMALL WIRELESS FACILITY DESIGN GUIDELINES

2018 Consultant s Handbook Division 26 Electrical ARC Flash Hazard Analysis

Vanderbilt University Standard Specification Revised 2/6/08

Notes 1: Introduction to Distribution Systems

Description & Applications Questions & Answers Selection Charts Single Phase Selection Charts Three Phase...

ADDENDUM NO. TWO. To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS

MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE

ULTRA-K Series 600K - he

B. Manufacturers: Square-D, G.E. or Westinghosue.

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

Electrical IP Red Seal Practice Exam

Short Circuit Current Calculations

Transcription:

University of Central Florida Main Campus Electric Service and Meter Installations Requirements Issued January 26 th, 2017 1 P a g e

Table of Contents 1. GENERAL INFORMATION... 3 2. DEFINITIONS... 3 3. TYPE AND CHARACTER OF SERVICE... 4 4. Typical Requirements... 5 5. Meter Location... 6 6. Current Transformer Installations... 6 7. Plan Review and Coordination with UCF UES... 7 ELEC FIGURE 00: GENERAL NOTES RELATED TO ELECTRIC SERVICE ELEC FIGURE 01: ELECTRIC SERVICE RESPONSIBILITY TABLE ELEC FIGURE 02: UNDERGROUND CONDUIT ENCASEMENT ELEC FIGURE 03A: POST-MOUNTED METER DETAIL W/ CTS IN XFMR ELEC FIGURE 03B: BUILDING-MOUNTED METER, SELF-CONTAINED METER OR METER W/ CTS IN BLDG ELEC FIGURE 03C: BUILDING-MOUNTED METER W/ CT CABINET ELEC FIGURE 04A: METER BASE FORM 1S WIRING DIAGRAM ELEC FIGURE 04B: METER BASE FORM 2S WIRING DIAGRAM ELEC FIGURE 04C: METER BASE FORM 9S WIRING DIAGRAM ELEC FIGURE 04D: METER BASE FORM 16S WIRING DIAGRAM ELEC FIGURE 05: SELF-CONTAINED METER BASE LINE & LOAD WIRING CONFIGURATIONS (FORM 1S, 2S, 9S, 16S)" ELEC FIGURE 06: CT WIRING AND CONDUIT SIZING TABLE ELEC FIGURE 07: CT CABINET SIZING CHART ELEC FIGURE 08: CT CABINET WIRING AND MOUNTING DIAGRAM ELEC FIGURE 09: CURRENT TRANSFORMER (CT) REQUIREMENTS ELEC FIGURE 10: METERING EQUIPMENT LABELING REQUIREMENTS 2 P a g e

1. GENERAL INFORMATION 1.1. Duke Energy maintains the Main Campus Primary Loop and associated step down transformers; therefore, Duke Energy s standards and requirements shall be considered the minimum standard for all new and existing service modifications. These UCF Construction Standards are intended to identify any items that must exceed Duke s minimum requirements, as well as any minimum Code requirements. 1.2. Electric meters and sub-meters are utilized for utility billing, savings calculations, demand profiling, and performance monitoring. Essential to these functions are an accurate, properly selected and installed system. The following information pertains mainly to low voltage services at 600V and under, unless otherwise specified. 1.3. For services greater than 600V, please contact UCF Utilities & Energy Services directly for specific requirements. 1.4. Electric utility requirements such as conduit for primary conductors and concrete requirements for pad-mounted transformers will still be dictated by Duke Energy s minimum standards; however, UCF has provided a few additional items through the included details 1.5. For ease of use, this section of the construction standards refers to multiple 8.5 x11 details or Figures. These details are used to convey critical information to the designer, track the designers progress and verify the contractor s installation. These details or Figures will be referenced below and are intended to be incorporated into the construction documents, by the designer, after a detailed review for Code and design intent requirements. 2. DEFINITIONS 2.1. Low Voltage up to 600V (AC) 2.2. Medium Voltage 1kV 35kV (AC) 2.3. High Voltage greater than 35kV (AC) 2.4. Main Distribution Panel Meter: Switchgear/Panel mounted meter covering complete main service to the entire facility 2.5. Billing Electric Meter: Main exterior mount revenue/billing meter for each main service to a facility 2.6. Billing Electric Sub-Meter: Meter installed on a portion of the main facilities electrical distribution, downstream of the main facility meter; primarily used to measure electric consumption for billing purposes. 2.7. BAS Electric Meter: Meter installed main service or on a portion of the main facilities electrical distribution, downstream of the main facility meter; primarily monitored through BAS for specific loads related to lighting, chilled water equipment and plug-load circuits. 2.8. MCC (Motor Control Center): Assembly of one or more enclosed sections having a common power bus and containing motor control units. 2.9. Switch Gear: Combination of electrical disconnect switches, fuses or circuit breakers used to control, protect and isolate electrical equipment 2.10. Utility Transformer: Any pole-mount or pad-mount distribution transformers providing the final voltage transformation in the electric power distribution system, stepping down the voltage used in the distribution lines to the level used by the customer. 3 P a g e

2.11. CT (Current Transformer): Also known as instrument transformer, are used to reduce the primary current accurately proportional to the current in the circuit, allowing for convenient connections to measuring and sensing equipment. 2.12. PT (Potential Transformer): Voltage transformers (VT) (also called potential transformers (PT)) are a type of instrument transformer, used for metering and protection in high-voltage circuits or phasor phase shift isolation. They are designed to present negligible load to the supply being measured and to have an accurate voltage ratio to enable accurate metering. 3. TYPE AND CHARACTER OF SERVICE 3.1. Services shall be underground. Overhead services are not permitted. 3.2. Standard voltages shall be 120/240, 120/208 and 277/480. 3.3. All new services shall be 277/480V 3-Phase 4-Wire, with the following exceptions: 3.3.1. 120/208V 3-Phase is acceptable if service is 400A or less at specified voltage. 3.3.2. 120/240V 1-Phase is acceptable for temporary services, unoccupied structures and auxiliary equipment if service is 400A or less at specified voltage. e.g. Construction trailer, Illuminated signs or irrigation controllers. 3.4. Use the table below to locate the service type being provided. Then refer to the Figures indicated. These Figures are intended to be incorporated into the construction documents, as referenced in the section above. Circuit 2-wire, 1- phase 3-wire, 1- phase 3-wire network 4-wire wye Voltage Service Size (Amps) Current Connections 120 Up to 400A Self-contained 120/240 Up to 400A Self-contained Over 400A With CTs Figures to Include Figure #00, 01, 02, 03B, 04A, 05, 10 Figure #00, 01, 02, 03B, 04B, 05, 10 Figure #00, 01, 02, 03A or 03B or 03C, 04C, 06, 07, 08, 09, 10 120/208 Up to 400A Self-contained Figure #00, 01, 02, 03B, 05, 10 120/208 OR 277/480 Over 400A Up to 400A Over 400A With CTs Self-contained With CTs Figure #00, 01, 02, 03A or 03B or 03C, 04C, 06, 07, 08, 09, 10 Figure #00, 01, 02, 03B, 04D, 05, 10 Figure #00, 01, 02, 03A or 03B or 03C, 04C, 06, 07, 08, 09, 10 Coordinate directly w/ UCF UES Over 600V & Duke *For services over 200A, a meter with CTs may be used in lieu of a self-contained meter. 4 P a g e

3.5. Temporary Service 3.5.1. This is a service that will be temporarily installed and energized for short term use involving project/contracted work services until project completion. Service is not utilized in any way as a permanent facility service and will be coordinated for disconnection and removal at the completion of the project. (Example: Temporary construction trailer or site power for project work) 3.5.2. Temporary services to construction trailers or site power for projects that are building expansions must not be serviced off an existing facilities circuit(s). All temporary connections must be direct from the utility company transformer for site power or construction trailers. If this is not feasible, a generator must be utilized for temporary power during construction. 3.5.3. Facilities under construction, that are connected to any existing facility as an expansion or added space, must have all construction related circuits separately sub-metered for billing purposes. Sub-metered use will be subtracted from the original building s main service meter. It is the responsibility of the project/contractor to fund any power consumption directly related to the project, even in existing building expansions. 3.5.4. Temporary services shall follow the same requirements outlined in these construction standards. 3.6. Permanent Service 3.6.1. Permanent service conductors installed for purpose of supplying main power feed to newly renovated or constructed facility, site, or structure. 3.6.2. Permanent service, upon final approval for Certificate of Occupancy, will transfer responsibility of service from the project or contractor to the final end customer. 3.6.3. Separate physical structures must have separate utility services (distributions) originating from the Utility Company transformer. At no point should any facility be fed from an individual circuit downstream of a main service on another facility, causing a condition for sub-metered loads and split billing. 4. TYPICAL REQUIREMENTS 4.1. Electrical rooms must be located along an exterior main wall with the electric meter installed on the exterior of the building. 4.2. If the electrical room, by design, cannot be located along an exterior wall, and distance is greater than 50 linear feet from meter enclosure to current transformers, then the meter must be installed in one of two ways: 4.2.1. Exterior Wall Mount (Meter & CT Enclosure) 4.2.1.1. Primary conductors from utility transformer to site must be routed through a wall-mounted CT Cabinet. 4.2.1.2. A primary disconnect must follow the CT cabinet before entering main electrical room. 4.2.2. Exterior Concrete Post Mount (Meter & CT Enclosure) 5 P a g e

4.2.2.1. If a pad mounted transformer is serving only the single facility, the metering can be performed by using CT s installed on the secondary bushing of the transformer. If this metering configuration is used, the meter must be mounted on a concrete post adjacent to the transformer. 4.3. Any electrical equipment or enclosures on an exterior wall or post mount structure must be obstructed from view; however, all clearances for equipment routine maintenance and servicing must be provided. Proposals for either landscaping shrubbery or material structures used to block the sight of such equipment must be submitted to and pass the approval of the University Master Planning Committee (UMPC). Such requests must be routed through the project manager. Any proposed landscaping must consider the requested equipment clearances when plants are mature. 5. METER LOCATION 5.1. The location of meters is an important consideration to both the UCF UES and the Project. UCF UES shall always be consulted and shall endeavor to select a location that shall be the most suitable to both parties. 5.2. Metering shall normally be installed outdoors. Exceptions to this must be approved by UCF UES prior to installation. 5.3. Meter, CT cabinet (if applicable), CT location, utility transformer, primary conductors, secondary conductors and conduit from CTs to meter shall be shown on civil and electrical site plan for coordination purposes. 5.4. Any equipment in or mounted on the building shall be shown on electrical building floor plans. 5.5. All site lighting and equipment outside of a building shall be on a separate electric service and meter. 6. CURRENT TRANSFORMER INSTALLATIONS 6.1. The size and type of each current transformer shall be reviewed with and approved by UCF UES. 6.2. Current transformer installations are usually made by one of three means, each of which requires coordination between the Contractor and UCF UES. 6.2.1. Self-Contained meters where service conductors are fed directly through meter socket 6.2.2. Outdoor current transformer cabinets where a self-contained meter cannot be used and pad-mounted CTs cannot be used.. 6.2.3. Current transformers shall be located in pad mounted transformers where a service is too large for a self-contained meter or CT cabinet and the transformer only services once building. 6 P a g e

7. PLAN REVIEW AND COORDINATION WITH UCF UES 7.1. Coordination of service and metering requirements with UCF UES is important for the success of the project. UCF UES will arrange joint meetings with UCF UES and Duke Energy at each phase of project. 7.2. At the 50% Construction Document Phase the following shall be shown on plans and reviewed with UCF UES: 7.2.1. Proposed location of pad-mounted transformer 7.2.2. Proposed routing of primary conduit and conductors to new transformer. 7.2.3. Proposed routing of service entrance conduits/conductors. 7.2.4. Proposed location of meter. 7.2.5. Proposed metering arrangement. 7.2.6. Designer shall submit all included Figures identified by UCF for the service type. Designer shall identify any aspects of the Figure that cannot or will not be provided. 7.3. At the 100% Construction Document Phase the following shall be shown on plans and reviewed with UCF UES: 7.3.1. Location of pad mounted transformer. 7.3.1.1. Transformer pad details coordinated with Duke Energy 7.3.2. Routing of primary to new transformer. 7.3.2.1. Primary Conduit Sizing. 7.3.2.2. Primary Conduit Installation Details. 7.3.3. Routing of service entrance conduits/conductors. 7.3.3.1. Sizes of conductors and conduits. 7.3.3.2. Load sizing calculations 7.3.4. Location of meter enclosure. 7.3.4.1. Metering arrangement including: 7.3.4.2. Specific models and specifications of CT s to be utilized if applicable. 7.3.4.3. Mounting method for CT s as applicable. 7.3.4.4. Size and specifications for CT cabinet as applicable. 7.3.4.5. Routing and size of conduits and wiring interconnecting CT s with meter enclosure. 7.3.4.6. Specific models and specification of meter enclosure. 7.3.5. Designer shall submit all included Figures identified by UCF for the service type. Designer shall identify any aspects of the Figure that cannot or will not be provided. All requested Figures shall be submitted to UCF UES, through UCF s project manager, at the 50% and 100% construction document submission. 7 P a g e