SUBSEA TREES INSTALATION IN DRAGON FIELD MARISCAL SUCRE PROJECT, PHASE I

Similar documents
Vincent/Enfield Conductor and Flowbase Installation Review. Roy Grant, TSMarine

MARS. Multiple application reinjection system

The Next Generation of Reeled Pipe Lay Vessels: for Ultra Deep Water Field Developments in Remote Locations

MAERSK SUPPLY SERVICE. Actively taking part in solving the energy challenges of tomorrow

HELIX ENERGY SOLUTIONS

Marginal Project Development

Marine Well Containment Company Outer Continental Shelf Summer Seminar

VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application

Subsea Pipeline IMR. PT Hallin Marine June 18 th, 2014!

Offshore Drilling Rigs

June 24, 2010 RPSEA Project 1502 Thomas E. Williams int.com

Nomarna Construcciones e Ingeniería develops a high knowledge in solutions of design, consulting, training, supervision, manufacturing and management

Dagang Zhang China-America Frontiers of Engineering Symposium San Diego, USA

Emerging Subsea Networks

INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE

A marginal field (re-)development using several alternative methodologies 1

Topaz Tangaroa Multipurpose Field and ROV Support Vessel. Vessel Specifications

NORWAY. Norwegian Industrial Property Office (12) APPLICATION (19) NO (21) (13) A1. (51) Int Cl.

Eelume: A Resident Subsea IMR Vehicle. Peter Bennett Business Manager Subsea Kongsberg Maritime

DEA Technology Forum 17 Nov. 2011

Deepwater Precommissioning Services

9/21/2017 DeepOcean Group 1

Che Keong Lee Sales Subsea Manager Kongsberg Maritime AS. Eelume: A Resident Subsea IMR Vehicle

RENEWABLE ENERGY SOLUTIONS. oceaneering.com

Capital Marked Presentation. Dof Subsea Atlantic Region

INTEGRATED SUBSEA PRODUCTION SYSTEMS Efficient Execution and Cost-Effective Technologies Deliver Project Success. Deepsea technologies

Speaker at the Americas: Decommissioning and Well Abandonment. September 23, 2015

Pressurised Subsea Pipeline Repair Recent Case Studies

PIPELINE THROUGH-WALL COMMUNICATION CAPABILITIES By Gary Anderson, Offshore Market Development Director, T.D. Williamson, Inc.

MSV Seawell. The vessel that pioneered subsea light well intervention

Company Update. Spill Containment Fast Response to GOM Subsea Oil Spills. Changing the way you succeed.

Richard Rickett, General Manager Engineering and Procurement - March Case Study

Subsea Production Market and Industry Teaming. Presented by: Bruce Crager Executive Vice President: Expert Advisory Group Endeavor Management

Send your directly to

Jim Britton Deepwater Corrosion Services Inc. Houston, TX. UTC 2008 Bergen

Intervention/Decommissioning

i-tech SERVICES DELIVERING INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE

Well Intervention Vessels Used in the G.O.M. Macondo Incident Response. Helix - Well Ops June 2011

Innovative Subsea Engineering

Emerging Subsea Networks

Ecosse Subsea Systems. Subsea Springboard 2017 David Hunt

Onshore & Offshore Engineering and Management of Subsea Cables and Pipelines

COMPREHENSIVE SOLUTIONS

Eelume: The Next Evolution in Underwater Robotics. Richard Mills Director of Sales Marine Robotics Kongsberg Maritime AS

SWIMMER: Hybrid AUV/ROV concept. Alain FIDANI Innovative Projects and R&D Manager Oil&Gas Division CYBERNETIX SA, France

FIELD CASE STUDIES: CATHODIC PROTECTION SYSTEMS

Volve Subsea Removal. Trond Hofseth Subsea Operations Conference. Haugesund

Driving down the costs of decommissioning through technology. Malcolm Banks & Susi Wiseman Offshore Decommissioning Conference, November 2017

ISO INTERNATIONAL STANDARD

A Perspective on Digitalisation in the Oil and Gas Industry

Subsea Structural Engineering Services. Capability & Experience

NORMAND MERMAID - LIGHT OFFSHORE CONSTRUCTION VESSEL RELIABLE COMPETENT DEMANDING COLLABORATIVE

Engineering and Procurement We are designing and purchasing everything we can firmly identify

AADE Houston Chapter. Group. 26 January 2011

Latest developments in Asset Management - Oil and Gas production via Internet?

OBSERVATORY SERVICING AND MAINTENANCE

SUBSEA 101. Find more Subsea 101 case studies online

Sponsored by. Created and produced by

Subsea UK Neil Gordon Chief Executive Officer Championing the UK Subsea Sector Across the World

Advancing Global Deepwater Capabilities

Deep. Navigating the. High Accuracy Positioning Support for Deep Water Construction. Copyright Journal of Ocean Technology 2017

Latest Evolution of Vessel Lay Equipment, to Meet the Challenges of Deepwater Installations. SUT Perth, 14 th February 2018

BT-4000 LIGHT WORKOVER UNIT

ETSU V/06/00187//REP; DTI Pub/URN 01/799 (for Ove Arup reference:

Reducing Risk and Improving Weather Window in Offshore Lifting Operation

Offshore Cable Installation. November 2010 John Davies Global Marine Systems Limited

SUBSEA LIFETIME EXTENSION OF A WELLHEAD PLATFORM

ENGINEERING SOLUTIONS FOR THE OIL & GAS INDUSTRY

Increased Safety & Efficiency from a Dedicated Light Well Intervention Vessel on Deepwater Subsea Wells

New Developments in Regulation of U.S. Offshore Oil and Gas Operations

SUBSEA WELL CONTAINMENT. Global Basis. Deepwater & Emerging Technologies Group (DETG) AADE Houston Chapter 25 January 2012

Offshore Support Vessels Located in the US Gulf of Mexico in March 2018

SIMON HINDLEY MENG, AMRINA MANAGING DIRECTOR, NAVAL ARCHITECT

Subsea Tooling Services UK Ltd Engineered Subsea Solutions

European Wind Energy Technology Roadmap

Morgan Stanley Houston Energy Summit

Engineering. Drafting & Design. Regulatory Interface. Project & Construction Management. Marine Operations Services

The Norwegian Context PTIL/PSA 1

Evolution of Deepwater Subsea / Offshore Market

Dry trees for cost effective solution with the Wellhead Barge: WHB

Reliance Industries Limited. Notice Inviting Expression of Interest

SUBSEA INSTALLATION WITHOUT A HEAVY LIFT VESSEL A STEP CHANGE IN SUBSEA INSTALLATION

Pipeline Inspection and Environmental Monitoring Using AUVs

Offshore Construction Management Services. Capability & Experience

Umbilical Manufacturer s Perspective on the Challenges of Deep Water Operations. Presented by: James Young, JDR Engineering Director

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015

Offshore Wind Risks - Issues and Mitigations

Pumps and Subsea Processing Systems. Increasing efficiencies of subsea developments

INDUSTRIAL PROCESS CLEANING SPECIALISTS SEPTEMBER 2017

Implementing a Deepwater- Pipeline-Management System

Guide for Participants in the BC Booth (1917) Offshore Technology Conference April 30 - May 3, 2007

Offshore Development Concepts: Capabilities and Limitations. Kenneth E. (Ken) Arnold Sigma Explorations Holdings LTD April, 2013

Subsea Asia Subsea Processing. June 2008 Dennis Lim Senior Field Development Engineer

For personal use only

By: Derek Watson and Lee Robins, Tracerco, UK

Subsea Boosting. November 2015 John Friedemann

Kinsale Area Gas Fields Decommissioning Project Information Leaflet

from ocean to cloud DUAL-CONDUCTOR CAPABILITIES IN WET PLANT DESIGN QUALIFICATION SEATRIALS

Teledyne Marine Oil and Gas.

OneSubsea Pumps and Subsea Processing Systems

Transcription:

International Gas Union Research Conference 2014 September 17-19 in Copenhagen SUBSEA TREES INSTALATION IN DRAGON FIELD MARISCAL SUCRE PROJECT, PHASE I Abstract N 658 Luis Peraza - Luz Velazco PDVSA Producción División Costa Afuera Oriental- Major Projects Management e- mail: perazaln@pdvsa.com, velazcolb@pdvsa.com ABSTRACT PDVSA Offshore Division develops The Mariscal Sucre Project with the exploitation of the gas fields Dragon, Patao, Mejillones and Rio Caribe located north of the Paria Peninsula, in Sucre State, Venezuela. For the Phase I of the Project two field production stages were planned. The first one includes the Dragon field's production by an accelerated production system and after that the inclusion of the Dragon and Patao field production through a platform. This work describes the installation campaign of the first four subsea tress in Venezuela corresponding to the subsea infrastructure of the Dragon Field s Accelerated Production System. This was a milestone that marked the history of the offshore industry in the nation. These trees are horizontal type and they are set for ten thousand pounds design pressure and a configuration that allow performing well interventions without removing the tree. The subsea trees installation was held with the support of a multipurpose vessel, two working class ROVs, tree handling tools, connection equipment, etc. The produced gas of the Dragon field during the Accelerated Production System will be collect by a 16 inch and 19 kilometer length pipeline the transported to shore through a 36 inch export pipeline for distribution in the internal market. The subsea system control will be manage by a control vessel and the gas dehydration will be handle for temporary skids located in the Conditioning Plant for the Internal Market (PAGMI) in the CIGMA complex. The Dragon field subsea production system will permit the delivery of 300 MMCFD of dry gas to the internal market achieving a social commitment with the gasification of the north east side of the country substituting liquid fuels which have a high value in the export market. This substitution will facilitate the production of the electric generation plants in that region. Keywords: gas fields, subsea system, Dragon field, Mariscal Sucre Project, Accelerated Production System. ABREVIATIONS a APS: Acelerated Production System b ROVs: Remote Operated Vehicules c Km : Kilometers d mts: Meters e Ton: Tons e CIGMA : Complejo Industrial Gran Mariscal de Ayacucho. f MMSCFD: Million Standar Cubil Feet per Day g THT:Tree Handling Tool h PETU: Portable Electric Test Unit INTRODUCTION The main objective of this paper is to describe the subsea tree installation procedures for the Dragon field. The installation activities described were performed by a multipurpose vessel. The subsea tree installation procedure for the Dragon field was elaborated by a Contractor and revised with PDVSA to serve as a trust foundation reference for supplementary information during the trees installation operations with safety and efficiency. Next is a description of a summary of the methodology used for the trees installations. The main activities are highlighted as follows:

A. Preparation of the tree B. Lifting of the tree from the compensation system multipurpose vessel C. Lowering of the tree 20 meters above the wellhead D. Mobilization of the vessel from the deployment area to the installation location E. Landing and positioning of the tree inside the wellhead F. Disconnection and recovery of the tree handling tool G. Test to the VX of the tree H. Tree landing study DESCRIPTION OF THE SUBSEA TREE It consists in a valve arrangement, connectors, metering, flow and pressure instruments and coupling accessories to the production elements. Its main function is to control the gas volume produced in the well for a safe and reliable operation adjusted to the production requirements. The subsea production trees of the Dragon field are designed for a 10 thousand pounds pressure. They are horizontal type and have a configuration that allows well interventions without removing it. Table 1. Subsea tree dimensions Property Units Feet Meters Length 17,8 5,43 Dimensions Wide 14,8 4,53 Height 12,8 3,91 In the air (Tons) 50 Center of gravity In the water (Tons) 43,5 X (mts) Y (mts) Z (mts) 0 0 2,345 PROCEDURES The subsea tree installation was performed using high power remote operated vehicules (ROVs) which monitored the operation and actuated the valves and the 400 tons crane which has a compensation system necessary to maintain the tree stability during lowering it to the seabed, likewise it was necessary the use of wellhead cleaning tool and communications tests. Rov Rov Figure 1. Tree lowering technique Rotation of the tree Weelhead 400 Ton crane Tree Figure 2. Detail of the tree installation to the wellhead The next description compiles the procedures for the subsea trees installation [1]: 1.- Checking prior deployment of the first subsea tree: this consist in a visual inspection of the tree, oil levels verification, tree handling tool (THT) verification and plot of the route for the deployment area to the wellhead.

Figure 5. Beginning of the tree lowering Figure 3. Preparation of the subsea tree in the vessel deck 2.- Pre-deployment of the tree from the vessel to the inspection base: revision of the personnel involved and safety talk, communication checking and positioning of the crane, tree lifting and cleaning of the area. 5.- Tree orientation: with the ROV and the THT support which will be attached to the suspended wireline of the vessel main crane. 3.- Lifting of the tree using the main 400 Tons crane: elevate the tree by starboard for a period of 50 seconds before the horizontal immersing into the water. Figure 6. Subsea tree orientation with ROV 6.- Tree location above the wellhead: in the predetermined position. Figure 4. Lifting of the subsea tree 4.- Beginning of the tree lowering: up to a 20 meters distance to the seabed. Figure 7. Tree location above the wellhead

7.- Verification of the tree to the wellhead adjustment and installation of the debris cap over the tree: to avoid drop objects to the interior of the tree. 1.- Multipurpose vessel for installation: Dynamic Positioning (DP2) vessel equipped with two cranes (400 Tons and 120 Tons capacity each) 2.- Work class remote operated vehicles (WROVs) 3.- Tree Handling Tool (THT). 4.- ROV operated wellhead cleaning tool 5.- Tree inspection support. 6.- Portable Electric Test Unit (PETU) and other connection equipment. 7.- Support vessels. Figure 8. Installation of the debris cap RESULTS Y ANALYSIS The operation of the subsea trees installation takes about 8 hours, but this depends on the weather conditions of the area. In Dragon field the weather conditions made the operations, in some cases, to take longer than expected. These are the major conditions registered during the operations in Dragon field: Table 2. Weather conditions in Dragon field Major conditions registered during the installation Wind (knots) Waves (mts) Marine currents (m/seg) 15-18 2,5 03-05 Due the adverse weather conditions in the Dragon field during the operations of the subsea trees installations it was necessary the use of high power ROVs. The required equipment for the subsea trees installation in the Dragon field was: For the subsea trees installation it was indispensable the use of the 400 tons crane which has a compensation system necessary to maintain the tree stability during the lowering to the seabed CONCLUSIONS 1.- Using the multipurpose vessel the installation of the first four subsea production trees for the Dragon field subsea production system was performed successfully. 2.- The subsea production trees installation for the Dragon field was an immense challenge for Petróleos de Venezuela S.A. (PDVSA) because it was the first time that this kind of operations took place in the tropical waters of the country. 3.- The operation for the Dragon field subsea production trees installation required high power ROVs due to the adverse weather condition in the area. 4.- The subsea production system for the Dragon field will allow the delivery for the internal market of 300 MMSCFD of gas. This is the first offshore development of gas production in Venezuela.

REFERENCES [1] Technip. Tree Installation Procedure, document N. TF027337-000-CP-3865-0813, 2012.