Survey of Operational Events

Similar documents
Fixed Series Compensation

1

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

CONTENTS. 1. Introduction Generating Stations 9 40

Contents. 1 Introduction Assessment criteria Assessment Recommendations References... 8

A New Subsynchronous Oscillation (SSO) Relay for Renewable Generation and Series Compensated Transmission Systems

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

Generation Interconnection Requirements at Voltages 34.5 kv and Below

Transmission System Phase Backup Protection

Technical Interconnection Requirements For Transmission Voltage Customers for Service at 60,000 to 287,000 Volts R XX

EDS FAULT LEVELS

System Protection and Control Subcommittee

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

Transformer energisation after network blackout

Arc Flash Analysis Training

EH2741 Communication and Control in Electric Power Systems Lecture 2

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS

FREQUENCY and VOLTAGE, ranges and durations

Power Plant and Transmission System Protection Coordination Fundamentals

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

ANALYSIS OF A FLASHOVER OPERATION ON TWO 138KV TRANSMISSION LINES

Wind Power Facility Technical Requirements CHANGE HISTORY

Connection of Embedded Generating Plant up to 5MW

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks

Busbars and lines are important elements

GIS Instrument Transformers: EMC Conformity Tests for a Reliable Operation in an Upgraded Substation

TS RES - OUTSTANDING ISSUES

Research on State Estimation and Information Processing Method for Intelligent Substation

COMPARATIVE PERFORMANCE OF SMART WIRES SMARTVALVE WITH EHV SERIES CAPACITOR: IMPLICATIONS FOR SUB-SYNCHRONOUS RESONANCE (SSR)

EE171. H.H. Sheikh Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

Design of Low Cost Embedded Power Plant Relay Testing Unit

Greenlining and Bluelining of Ergon Energy Substation Drawings

Hamdy Faramawy Senior Application Specialist ABB Sweden

PQ for Industrial Benchmarking with various methods to improve. Tushar Mogre.

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

60 kv to 500 kv Technical Interconnection Requirements For Power Generators

Impact of transient saturation of Current Transformer during cyclic operations Analysis and Diagnosis

System Protection Schemes in Power Network based on New Principles

A New Use for Fault Indicators SEL Revolutionizes Distribution System Protection. Steve T. Watt, Shankar V. Achanta, and Peter Selejan

Evaluating the Response of Surge Arresters

ACS 1000 Transformer Failure Investigation. Nathan Schachter, Peng

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin

I WP Asset # I ~:2 3. I Review Annual. ~c~~ Date: 'l/j(j/! ZL>IJ,...

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Immunity Testing for the CE Mark

ESB National Grid Transmission Planning Criteria

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code)

A New Fault Detection Tool for Single Phasing of a Three Phase Induction Motor. S.H.Haggag, Ali M. El-Rifaie,and Hala M.

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

Voltage Sags Evaluating Methods, Power Quality and Voltage Sags Assessment regarding Voltage Dip Immunity of Equipment

69 kv to 500 kv INTERCONNECTION REQUIREMENTS FOR TRANSMISSION FACILITIES

Conventional Paper-II-2011 Part-1A

Electrical Power Systems

New Redundant Automatic Voltage Regulator (AVR) Solution

Should we transform our lines to HVDC?

Massive Transient Stability Based Cascading Analysis and On-line Identification of Critical Cascades

ARC FLASH HAZARD ANALYSIS AND MITIGATION

OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES

Anti-IslandingStrategyforaPVPowerPlant

Transmission Interconnection Requirements for Inverter-Based Generation

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in

TABLE OF CONTENT

Power Plant and Transmission System Protection Coordination

NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Utility System Lightning Protection

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions

P2 Power Solutions Pvt. Ltd. P2 Power Magnetics. Quality Power within your Reach. An ISO 9001:2008 Company

Canadian Technology Accreditation Criteria (CTAC) POWER SYSTEMS ENGINEERING TECHNOLOGY - TECHNICIAN Technology Accreditation Canada (TAC)

DRAFT. City of Lethbridge Electric ENGINEERING STANDARDS GUIDELINE FOR GENERATOR INTERCONNECTION THE CITY OF LETHBRIDGE ELECTRIC DISTRIBUTION SYSTEM

Inverter-Based Resource Disturbance Analysis

SELECTING NATIONAL MW BOUNDARIES

Ferroresonance in MV Voltage Transformers: Pragmatic experimental approach towards investigation of risk and mitigating strategy

Harmonic Distortion Levels Measured at The Enmax Substations

A NEW METHOD FOR ISLANDING DETECTION IN DISTRIBUTED GENERATION

Microgrid Protection

BED INTERCONNECTION TECHNICAL REQUIREMENTS

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

Power System Protection Manual

High-set undervoltage stage with definitetime. or inverse definite minimum time (IDMT) characteristic. Low-set undervoltage stage with definitetime

Common Mode Susceptibility of Computers

Capstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:

Appendix D Fault Levels

PROTECTION of electricity distribution networks

Transcription:

Survey of Operational Events Final presentation,, Stockholm Mikael Wämundson 1

Content Background to the study Conclusions from literature survey Notable events at Nordic NPPs Mitigating actions taken at the Nordic NPPs Toolbox for future mitigating actions Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept Conclusions 2

Background to the Study In the Energiforsk report Grid interference on operations, Mapping of R&D needs a number of topics for future work were identified Survey of operational events from the offsite power system with focus on retrofit of mitigating actions Sub synchronous resonance phenomenon and modelling combined with hybrid simulations Survey on new electrical devices with different technology compared to existing electrical devices Survey of methodologies to verify that the outer grounding line network in the nuclear power plants is intact Generic lightning model of the Nordic nuclear power plants to study lightning incidents due to conducting 3

Content Background to the study Conclusions from literature survey Notable events at Nordic NPPs Mitigating actions taken at the Nordic NPPs Toolbox for future mitigating actions Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept Conclusions 4

Conclusions from Literature Survey The reliability of critical on site equipment must be ensured Training of personnel to handle situations of loss of off site power is important Perform testing to ensure proper function of equipment and procedures Assess (by simulations and experienced events) the immunity of the plant towards events in the off site power system 5

Conclusions from Literature Survey Susceptibility of Nuclear Stations to External Faults, NUREG 7175 Many of the LOOPs and plant trips [ ] would otherwise have been avoided if the existing properly designed protection systems had operated as originally intended. In some cases it may be possible to reduce the time delays for backup protection or breaker failure schemes to reduce or mitigate the effects of electrical transient events. Increasing the reliability in critical parts of the system Increasing the redundancy in the protection system Identify crucial and significant components Inspection, testing and maintenance of protection system and equipment 6

Content Background to the study Conclusions from literature survey Notable events at Nordic NPPs Mitigating actions taken at the Nordic NPPs Toolbox for future mitigating actions Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept Conclusions 7

Notable Events at Nordic NPPs Forsmark On June 25, 2006, June 13, 2008 and July 13, 2012 events occurred that stressed the power electronics (rectifiers and inverters) due to fast voltage transients and jeopardized the battery secured system On May 30, 2013 at least one non functioning circuit breaker pole in the unit circuit breaker caused an unbalanced supply voltage for the on site power system. This could have led to severe damage to asynchronous motors Oskarshamn A number of events in the off site power system close to Oskarshamn, due to the protection system, have led to disconnection of the units from the grid inadvertent operations 8

KD3 Notable Events at Nordic NPPs Olkiluoto On May 30, 2008 the generator excitation system of OL1 caused high excitation current, and the generator output voltage rose to 125%. The unit circuit breaker disconnected the unit leading to a further increase of the generator voltage. Differential protection tripped the generator and turbine and led to a reactor trip 9

Bild 9 KD3 - Känns ju lite knepigt att genertor-diffskyddet löste... det antyder shuntfel snarare än överspänning... - Men jag gör ingen stor affär av det... Karlsson, Daniel; 2016-06-12

Content Background to the study Conclusions from literature survey Notable events at Nordic NPPs Mitigating actions taken at the Nordic NPPs Toolbox for future mitigating actions Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept Conclusions 10

Mitigating Actions Taken Improvement of the fault clearing system in the off site power system to minimize fault clearing times and improve reliability Improvement of the relay protection system for main generators, transformers, etc. Extensive studies of the units ability to withstand disturbances in the off site power system Improved communication between the NPP and the network operator to ensure a reliable supply during revisions and maintenance work in the power system Verification, by test, of transfer to house load operation Special attention given to selectivity of protection for rectifiers/inverters for battery secured systems 11

Content Background to the study Conclusions from literature survey Notable events at Nordic NPPs Mitigating actions taken at the Nordic NPPs Toolbox for future mitigating actions Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept Conclusions 12

Toolbox of Mitigating Actions The outcome of the survey of events and experiences and the actions taken at the NPPs has led us to four tools that could be further investigated and applied to minimize the impact of future incidents and events related to loss of off site power Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept 13

Detection of Loss of Phase (Patent Pending, SE 1400207 5) Current based calculation To be implemented on the infeed to the step up transformer and start up transformer, in existing IEDs. Not to function for three phase interruption. A threshold value in at least one phase must be exceeded. This is a start criterion S for function. Six test values, based on the value of the phase currents, are defined, D a,, D ab, Small values implicate function, large values does not. a 2 a b c ab a b 2 c 14 ε is a small value to prevent division by zero

Detection of Loss of Phase (Patent Pending, SE 1400207 5) The test values are compared to threshold values (T 0 and T 1 ) to detect loss of phase. The threshold values shall fulfill the conditions, 0 < T 0 < 1 and 1 < T 1 < M, where M is a large number. For function it is required that S, C 1, C 2 and C 3 are all fulfilled. State Criteria C 1 C 2 C 3 Loss of phase a D a < T 0 D b > T 1 D c > T 1 Loss of phase a and b D ab < T 0 D bc > T 1 D ca > T 1 15

Content Background to the study Conclusions from literature survey Notable events at Nordic NPPs Mitigating actions taken at the Nordic NPPs Toolbox for future mitigating actions Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept Conclusions 16

Double Circuit breakers in Series In some cases it may be possible to reduce the time delays for backup protection or breaker failure schemes to reduce or mitigate the effects of electrical transient events. Susceptibility of Nuclear Stations to External Faults, NUREG 7175 The only relevant reason for long fault clearing times, in a protection system with duplicated protections, is a nonfunctioning circuit breaker Reliability is ensured by duplicating the components of the faultclearing system, i.e. protection functions, relay protection, current transformer cores, trip coils, etc. However, it has not been practice by many network owners to duplicate the circuitbreakers 17

Double Circuit breakers in Series A non operating circuit breaker (or one or more of the poles) in a series arrangement will not lead to a prolonged fault clearing time since the adjacent circuit breaker will operate There might be a possibility to retrofit existing double breaker substations with a third line circuit breaker, according to the arrangement to the right 18

Content Background to the study Conclusions from literature survey Notable events at Nordic NPPs Mitigating actions taken at the Nordic NPPs Toolbox for future mitigating actions Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept Conclusions 19

Duplicated Analyses Reliability is ensured by duplicating the components of the faultclearing system, i.e. protection functions, relay protection, current transformer cores, trip coils, etc. From practical and economic reasons technical analyses of protection relay settings etc. are often performed By the same person that has performed previous analyses By different person, but using data from previously performed analyses By only one person (even if several persons review the work) Results/settings from analyses are often inherited by other units in the same station or even by other nuclear power stations 20

Duplicated Analyses A possible way to improve the reliability of analyses, relay protection schemes and settings could be Let two engineers perform the same analysis independently It could be that technical analyses (e.g. calculation of physical or electrical properties or relay protection settings) are performed by the contractor as part of a purchase agreement. This could open for the possibility of the NPP s engineers to independently perform the same analyses. Do not use existing reports or analysis as basis for the renewed analysis By reading a previous analysis report the engineer most certainly will be biased. 21

Duplicated Analyses Diversify by using different entrepreneurs When purchasing and installing apparatuses and systems a way to avoid common cause errors is to use different brands, manufacturers and/or models of the equipment, e.g. for SUB1 and SUB2 relay protection. The idea is that a latent fault in one model does most probably not exist in a model of another brand or manufacturer. The same thinking can be used in the analysis phase. 22

Content Background to the study Conclusions from literature survey Notable events at Nordic NPPs Mitigating actions taken at the Nordic NPPs Toolbox for future mitigating actions Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept Conclusions 23

Withstand or Isolate Concept This concept is formed around the idea of what the critical equipment can endure or withstand its immunity towards disturbances in the electrical environment This is in contrast to the method were a limited number of external events or scenarios are postulated and the response from the equipment is evaluated Experienced disturbances reveal the difficulty to predict what could happen and this holds also for the future 24

Withstand or Isolate Concept Withstand The method of obtaining the immunity levels may include Relying on manufacturer data For less critical equipment this may be sufficient. The equipment can be manufactured according to specific standards on EMC. Performing theoretical analyses or simulations As a complement to available manufacture data it may be necessary to perform analyses of how the equipment will behave under certain conditions. To obtain information of how different components behave together this may also be necessary. 25

Withstand or Isolate Concept Withstand Estimating the immunity from registrations of earlier events Information of the immunity can be concluded from registered events where the equipment both have succeeded and failed to operate as intended. Having a sufficient amount of such registrations can serve as a basis for such estimation. Performing tests on equipment Sometimes the only (but always the best!) way to get information on the immunity of a component or equipment is to perform testing to see under what conditions it will operate as intended. 26

Withstand or Isolate Concept or The decision between withstand and isolate is performed by protective relaying and automatic sequences The protective system must be set to function when the equipment cannot withstand The protective system must be reliable (redundance) The protective system must be fast enough not to jeopardize the function of the equipment 27

Withstand or Isolate Concept Isolate Given that the on site power system is isolated from the offsite power system it is important that the level of isolation is sufficient Circuit breakers that have tripped form a galvanic barrier between the two systems Keep the system isolated also with respect to inductive and capacitive phenomena Should the critical equipment form several sub systems, isolated from each other? What about disturbances from within the on site power system? 28

Withstand or Isolate Concept 29

Content Background to the study Conclusions from literature survey Notable events at Nordic NPPs Mitigating actions taken at the Nordic NPPs Toolbox for future mitigating actions Detection of loss of phase Double circuit breakers in series Duplicated analyses Implementing withstand or isolate concept Conclusions 30

Conclusions A survey has been performed in available literature on events at NPPs around the world that has been triggered from the off site power system Events related to loss of off site power have led to mitigating actions at the Nordic NPPs Four possible tools are presented that could be further investigated and applied to minimize future incidents and events related to loss of off site power Detection of loss of phase Double circuit breakers in series Implementing withstand or isolate concept Duplicated analyses 31

Thank You for Your Attention! 32