Early-on HAZOP (PHAZOP) Advocacy: Best Practices

Similar documents
Subsea Integrity Practices in GoM A Case Study

Learn more at

DRIVING PSM PERFORMANCE BEYOND KPI METRICS

Effective Implementation of Subsea Integrity Management

Subsea Pipeline IMR. PT Hallin Marine June 18 th, 2014!

Life Extension of Subsea Umbilical Systems Assessment Process Marian Copilet Technical Solutions Manager - APAC November 2016

Tony Owen, Subsea and Pipelines Decommissioning Delivery Manager AOG February 2017

Keeping Your House in order?

Integrity Management of Offshore Assets

Integrity Monitoring? New thinking in the approach to Subsea IMMR. Dr Karl Woods, Snr Subsea Reliability Engineer 22/2/2017

Asset Integrity Management for Purpose-Built FPSO s and Subsea System Facilities

Slug Flow Loadings on Offshore Pipelines Integrity

Implementing FPSO Digital Twins in the Field. David Hartell Premier Oil

Offshore Construction Management Services. Capability & Experience

Pipeline Design & Installation Systems

7 Briefing. Responsible investor

Riser Lifecycle Monitoring System (RLMS) for Integrity Management

CAN WE IDENTIFY POTENTIAL MAJOR HAZARDS?

Predictive Subsea Integrity Management: Effective Tools and Techniques

4 Briefing. Responsible investor

SUBSEA CONTROLS & COMMUNICATIONS SOLUTIONS

IMR Best Practice - Practical Lessons from a Decade of Subsea IM. John MacDonald & Dharmik Vadel 11 March 2015

marine, construction, drilling, floating production, decommissioning and renewables industries.

MU064: Mechanical Integrity & Reliability in Refineries, Petrochemical & Process Plant

Challenging Inspections of Offshore Pipelines by Intelligent Pig

VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application

SUBSEA 7 AND GRANHERNE ALLIANCE. Engaging Early to Deliver Value

RISK MANAGEMENT IN THE OPERATIONS OF A SUBSEA PIPELINE

Innovative Subsea Engineering

The use of Mechanical Connectors throughout Life of Field

BSOL: Key Standards for the Oil & Gas Industry. bsigroup.com/bsol

Using Critical Zone Inspection and Response Monitoring To Prove Riser Condition. M Cerkovnik -2H Offshore

DNV GL s 16 th Technology Week

ESSENTIAL PROCESS SAFETY MANAGEMENT FOR MANAGING MULTIPLE OIL AND GAS ASSETS

Macondo Blowout Lessons Learned for Prevention and Mitigation

Lessons Learned from the US Chemical Safety and Hazard Investigations Board. presented at

Flexible solutions for your oil and gas needs

Subsea Asset Integrity. Matthew Kennedy

The Deepwater Horizon

FPSO Operation and Maintenance

Ring Pair Corrosion Monitor : RPCM

Masao Mukaidono Emeritus Professor, Meiji University

Asset Integrity For Floaters

INVESTIGATION OF SLUG FLOW IN DEEPWATER ARCHITECTURES. Y. OLANIYAN TOTAL S.A. France

Looking Ahead: Management in the GoM. June 2011

Subsea and Export Systems. The world s leading independent provider of subsea and export systems, engineering and technology solutions.

THE USE OF A SAFETY CASE APPROACH TO SUPPORT DECISION MAKING IN DESIGN

ENGINEERING SERVICES CONSULTANCY

Brae Area Pre Decommissioning MARATHON BRAE. Brae Area Decommissioning Programme. June Revision 1.0

ISO INTERNATIONAL STANDARD. Petroleum and natural gas industries Offshore production installations Basic surface process safety systems

Learn more at

Employability Enhancement Program for Engineers. Transformation of an engineering degree holder to a real Engineer, who can do more at work.

Technological and Logistical Challenges during Construction & Installation of Deepwater Mega Subsea Development in West Africa

DNVGL-SI-0167 Edition July 2015

High Reliability Organizing Conference. Deepwater Horizon Incident Investigation

Reliance Industries Limited. Notice Inviting Expression of Interest

Optimizing wind farms

Emergency Pipeline Repair Systems; A Global Overview of Best Practice

Learning from the Causes of Failures of Offshore Riser Emergency Shutdown Valves

Challenging Inspections of Offshore Pipelines by Intelligent Pig

RELIANCE INDUSTRIES LIMITED

Extending the Service Life Span of Ageing Oil and Gas Offshore Production Facilities

MOE125 Offshore Well Construction

Flow Assurance. Capability & Experience

TECHNOLOGY QUALIFICATION MANAGEMENT

In detailed design the station is prepared for operation

Managing Ageing Infrastructure

Oil and gas services. Systems and Engineering Technology

Introduction to Bowtie Methodology for a Laboratory Setting

Top 10 Questions About Aspen HYSYS Dynamics FAQ

Defining the New Normal for Offshore Drilling Copenhagen 16 June Alan Spackman Vice President, Offshore Regulatory & Technical Affairs

New concepts are emerging frequently in various fields such as: microprocessor sensors,

Control and Monitoring of Subsea Power Grid

Emergency Pipeline Repair Solutions and Future Contingency Planning

DEVELOPMENT OF MACHINERY AND ROTATING EQUIPMENT INTEGRITY SAFETY INSPECTION GUIDANCE NOTES

Safety and Environment considerations override all other items and should be considered in all design aspects.

OFFSHORE CATHODIC PROTECTION AND INTEGRITY

Real Time Monitoring (RTM) Workshop Production Panel Representative Marathon Oil Company

ENGINEERING INNOVATION

2017 Award Nomination Title of Innovation: Wells Materials Design & Performance enhancement

FEDP. About FEDP. FESP-001: 4 ½ Days Fundamentals of Process Risk Assessment, HAZID & HAZOP

Summary of Changes and Current Document Status

Tidal Energy. Transmission & Distribution Network. Wind Energy. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Risk Based; Approach in UK:

Cathodic Protection & Monitoring

Introducing Subsea Connect. Neil Saunders President & CEO, Oilfield Equipment, BHGE

Offshore critical barrier identification; management of their continuing suitability and their verification

Send your directly to

Wave & Tidal Safety & Construction Guidelines

FEDP. About FEDP. FESP-001: 4 ½ Days Fundamentals of Process Risk Assessment, HAZID & HAZOP

Virtual Reality Immersion: A Tool for Early Human Factors Intervention

Location. Established in 2015 Office location: Klepp Næringspark, Norway.

STRETCH IN TECHNOLOGY AND KEEPING THE FOCUS ON PROCESS SAFETY FOR EXPLORATION AND PRODUCTION IN THE 21st CENTURY

Mooring Capabilities. Angola Brazil Egypt Equatorial Guinea Malaysia Mexico Norway Singapore United Kingdom United States

Angola Brazil Mooring Egypt Equatorial Guinea Capabilities Malaysia Mexico Norway Singapore United Kingdom United States

Mooring Capabilities. Angola Brazil Egypt Equatorial Guinea Malaysia Mexico Norway Singapore United Kingdom United States

FLANGE INTEGRITY MANAGEMENT

Presentation. Professor II Jan Erik Vinnem University of Stavanger.

Industry & Govt Changes Post Macondo. Charlie Williams Chief Scientist Shell Executive Director - Center for Offshore Safety

The Essentials of Pipeline Integrity Management

Transcription:

Mary Kay O Connor Process Safety Center International Symposium Early-on HAZOP (PHAZOP) Advocacy: Best Practices Building from the past to the future in integrity management Bob Wittkower, Adriana Botto, Dr. Binder Singh, Meghan Hull, Dr. Paul Jukes October 26th - 28th, 2010 rev 0

Agenda 1. Introduction 2. Risk Identification and Gaps 3. PHAZOP as a Tool 4. Hazard Discussion 5. Challenges and Interface Issues 6. Impacts 7. Review of HSE, Rules and Regulations 8. Conclusion, Acknowledgements 1

1. Introduction HAZOP origin and use discussed by Trevor Kletz at MKOPSC 2009 Structured process to review designs If had to do over again would have the HAZOP earlier in the process More lead time to influence the design Earlier recognition of issues Detect issues sooner more time to develop options Longer time to consider the gap exposed and implications for more gaps We can never know how much we don t know. Issues studied identify more areas we didn t know about Risk mitigations may create more problems not expected 2

1. Introduction Events Define Change; Change expands thought, discipline Piper Alpha Bhopal Chernobyl 3 mile island Flixborough Texas City Deepwater Horizon Events Mark Points-in-time Piper Alpha 9/11 London 7/7 Kennedy Assassination 3

1. Introduction The Trevor Kletz statement comes into view: Find the hazards as early as possible in the design process. When can the PHAZOP be effective as a process? What kinds of design products are available at an early stage? Are PHAZOP goals clear and evident to the participants? Do we have genuine buy-in and commitment to the process? Both experiences and less-experienced can contribute Experience draws on lessons learned and workable designs Less-experienced bring a fresh set of eyes to critically review 4

1. Introduction The process then is a Design Challenge and Execution Challenge: Provide thought provoking direction. Use of a guideword process to initiate response and call to action to participate. Guidewords, experience and fresh thought open the design to discussion of risks by challenges Execution risks and aspects appear early-on. Develop KPI s (Key Performance Indicators) 5

2. Risk Identification and Gaps Early-on HAZOP or Preliminary HAZOP (PHAZOP) Do we know all that can be known? Do we have a full list of hazards and the risk? Can we know how much we don t know about a design and its hazards? What is completeness of the process? When we consider our process complete is it actually incomplete at the very moment? Are identified hazards fully mitigated or is the system now with a new hazard and the same or worse than the original? Supposing the contrary, do we think we have discovered all gaps and learned everything in every study? 6

2. Risk Identification and Gaps Early-on HAZOP or Preliminary HAZOP (PHAZOP) IM approach - Guidewords to support discussions - link experience and knowledge of SMEs to the process to reduce the unknown risk PHAZOP Benefits: ensure hazard detectability and thus consideration of the mitigations which can be brought to bear on the design in its early stages before decisions that exclude options are made. 7

3. PHAZOP as a Tool Experiences Many clients use the PHAZOP as an early tool and include it in the process, but not all. A subsea deepwater tie-back used a PHAZOP in FEED. Recent corrosion lessons learned were incorporated and an additional corrosion protection issue was identified. 30 items were detected. PHAZOP was held just 3 months into the project as soon as first rev P&ID s were available. A subsea deepwater tie-back used a PHAZOP and corrosion, and compatibility and materials studies were identified. 8

3. PHAZOP as a Tool Experiences An offshore drilling platform with well-testing facilities and accommodations held a PHAZOP with early identification of critical design, life safety and environmental issues. A subsea deepwater tie-back was in select stage and with numerous options with P&IDs developed. End of stage comments were that a PHAZOP would have been a more valuable process. This is a possible example of the point Trevor Kletz made. A subsea pipeline system with multiple wells and platforms in FEED was scheduled with the HAZOP at 90% design point. This is a possible example of the point Trevor Kletz made. 9

3. PHAZOP as a Tool Experiences A refinery upgrade PHAZOP identified items for system design which included a cold vent for which a recommendation early-on was a new line to the flare header to run to flare. A refinery debottlenecking PHAZOP showed the need for an additional relief valve and resulted in the direction of a new heat load study. A refinery PHAZOP identified over 100 items for review. We find that experiences define major problem areas e.g. Corrosion under insulation. 10

3. PHAZOP as a Tool Risk Identification Progression 11

4. Hazard Discussions Key Aspects Internal corrosion External corrosion Material degradation Flow Assurance 12

4. Hazard Discussions Barriers & Mitigations (Corrosion Examples) Swiss Cheese Model: Macro and Micro elements Localized Pitting 1 Erosion, Cavitation, wear 2 New Mechanism(s) LME, CUI, 8,10,12 etc 3 4 etc P.T.W. Hazards Losses Management Snafu, Adverse Project Decision, General Corrosion, Poor Inspection data, etc Materials Performance, Fracture, Embrittlement, SCC, etc, Structural Integrity, Mechanical Strength, Loss of Properties, Weld defects, etc Operations, Steady State, Out of Envelope, Excursions, Transients, Ergonomics, Human Error, etc 13

5. Challenges and Interface Issues Knowledge Management Validation of new applications and step-outs in technology; Increased confidence in design inputs for new developments; Increased integrity assurance and early warning of potential issues for existing developments; Identification of evolving industry practices; Improved tracking and application of lessons learned Brownfield/Greenfield Possibility to base Greenfield design requirements on Brownfield available operational parameters - ensure more accurate design and less conservative assumptions 14

5. Challenges and Interface Issues Design Variation / Change Management If changes are not properly assessed, catastrophic events may occur: Accelerated degradation of materials can take place if the correct material compatibility assessment has not been undertaken Specification of design limits and identification of suitable materials Insufficient Structural Integrity of hosting facility due to additional hanging off loads from new risers on one side of a facility Detailed review topsides operations and hardware Detailed review of extreme dynamic response & the fatigue life of the risers Brownfield/Greenfield Compilation of histogram of historic operating data from Brownfield to most accurately define the service conditions 15

6. Impact to Hazard Discussions Fatigue Challenge Knowledge Management Change Management Preliminary Design Specification Benefit Validation of numerical assumptions Accurate modeling of drag properties Changes in topsides pipework that may be impacted by FIV Base fatigue design based on measured conditions 16

6. Impact to Hazard Discussions Internal Corrosion Challenge Knowledge Management Change Management Preliminary Design Specification Benefit Calibration of corrosion models with monitored Brownfield data Fluid composition changes that may impact internal corrosion Driven by Knowledge Management (No definite industry codes of practice) 17

6. Impact to Hazard Discussions External Corrosion Challenge Knowledge Management Change Management Preliminary Design Specification Benefit Identify best practice from latest DNV, ISO, or NACE standards Capture changes that may require modification to CP system or coatings Better understanding of local environment = better assessment of marine growth 18

6. Impact to Hazard Discussions Material Degradation Challenge Knowledge Management Change Management Benefit Most recent polymer degradation curves Material or global CP compatibility concerns Preliminary Design Specification Better design basis = Less design iteration 19

6. Impact to Hazard Discussions Flow Assurance/Operability Challenge Knowledge Management Change Management Preliminary Design Specification Benefit Identify operating regimes and quantify slug loads on system Accurate modeling of riser stresses and future slug loads Better definition of riser behavior during slug events, with potential to revise fatigue life (+ or -) 20

6. Impact to Integrity Management Plan IM Performance Standards Lessons Learned System Data HAZID / HAZOP Risk & Reliability Assessment Recommendations Knowledge Management Risk & Reliability Analysis Changes to System? Yes Yes No No Update risk? Schedule / Implementation Trigger Anomaly Limits / KPIs Spares Strategy IM Plan Specification IM Plan Implementation No Regulatory Compliance Plan Execution Fitness for Purpose Periodic Review & Fitness Assessment Action required? Yes 21

6. Impact to Integrity Management Plan Whole Life Cycle Approach Prevention of all failure modes in terms of: Functionality the system must safely contain fluids in accordance with the service requirements; Reliability the system must maintain the integrity during normal production & operational conditions, and during non-routine operations. Survivability the systems must maintain the integrity during foreseeable environment conditions; Dependency/interactions the system must maintain control process to prevent loss of containment and failures by implementing procedures and instrumented protective functions. 22

Probability Index, P 6. Impact to Integrity Management Plan Risk Analysis & Reduction - ALARP ALARP RISK TRIANGLE As applied to Corrosion Assessment 5 Detective Detective Detective Predictive Predictive INSIGNIFICANT RISK- Corrosion Events Negligible 4 Basic Detective Detective Detective Predictive 3 Basic 2 None Basic Detective Detective Detective Basic Basic Detective Detective TOLERABLE RISK REGION Corrosion Manageable Risk reduction benefits practicable Consequences acceptable 1 None None Basic Basic Detective 1 2 3 4 5 Consequence Index, C UNACCEPTABLE RISK CONSEQUENCES TOO BAD Material/Corrosion failures not Acceptable Justifiable only in very exceptional cases 23

7. Review of HSE, Rules and Regulations Incidents 2002 During a scheduled platform shutdown a gas release occurred from a flange as flange bolts were removed. Gas alarms sounded and activated the platform deluge system along with the GPA, general platform alarm, and personnel assembled at the muster stations. The gas dispersed by natural ventilation. 2005 Failure to isolate energy source during maintenance allowed gas to migrate through sales gas line back through production equipment and escape. Later activities caused further issues and the evacuation of the platform. The platform was later reboarded when safe and valves closed to stabilize the incident. 24

7. Review of HSE, Rules and Regulations Regulatory Environment The regulatory environment was changing prior to the April 20, 2010 Deepwater Incident and more so afterward. Risk assessment will continue to be a key element in incident prevention with the HAZID, PHAZOP and HAZOP as important tools. Inherently safer design will move to the forefront. The involvement of the IM disciplines with knowledge, experience and techniques in corrosion prevention, material degradation and risk based solutions is a key asset. 25

8. Conclusions PHAZOP is a valuable early-on risk assessment tool which allows time to influence the design. Use PHAZOP as part of a risk assessment progression of several studies across many stages since our knowledge is not complete but an ongoing task. Risk assessment strives to decrease the unknown while not introducing new hazards. Hazard identification and detection is part of the Integrity Management process which uses subject mater experts from many areas. Experience has demonstrated the value of the PHAZOP. Get in EARLY. Focus on Integrity from the EARLY project stages and utilize the process to define/discuss/develop KPI s. 26

Thank you Any questions?