Linear Scheduling 101. How to create your most-valuable project management tool on a single page.

Similar documents
Phase 2 Silver Line Update

Massport Capital Programs Enterprise Schedule Management. Primavera Schedule Toolkit Design. January 2018 Version 1.0

University of Bristol - Explore Bristol Research. Peer reviewed version. Link to published version (if available): /geng.13.

Using Graphing Skills

Overview of Precast ABC Projects in the Pacific Northwest. Chuck Prussack, P.E., Oldcastle Precast, Inc - Spokane

The Big Train Project Status Report (Part 94)

Segmental Bridge Technology Established and Evolving. W. Jay Rohleder, Jr, P.E., S.E. Senior Vice President / Project Development FIGG

Louisville-Southern Indiana Ohio River Bridges Project

School Based Projects

- go over homework #2 on applications - Finish Applications Day #3 - more applications... tide problems, start project

How to Make the Right Dreams Come to Life in 2018 #LessHustleMoreGrace

Using Graphing Skills

About Hensel Phelps - Thai Nguyen About the project Rob Muellner BIM on the project Rob Muellner 3D Lift Drawing Production Rob Muellner MEP

Setting.

Innovative Approaches in Collaborative Planning

Recreation Facility Hours

DRAWING MANAGEMENT MISTAKES

FUTURE FILE HOW TO KEEP YOUR DESK CLEAR WITH THE A SNOOZE BUTTON SYSTEM FOR PAPER

CMC Rescue is an employee-owned company focused on the needs of our customers and committed to doing the right thing.

Wamba.com Proposal of White Label Solution for Dating Service

Sinusoidal Applications

Description: PUP Math World Series Location: David Brearley High School Kenilworth, NJ Researcher: Professor Carolyn Maher

Ready? Turn over to get started and let s do this!

Implementing BIM for infrastructure: a guide to the essential steps

FUTURE FILE HOW TO KEEP YOUR DESK CLEAR WITH THE A SNOOZE BUTTON SYSTEM FOR PAPER

How to Start a Blog & Use It To Squash Writer s Block

Today s Session. Presenting for audience with varying levels of experience, skills. The Basics. The Marketing Mix. Creating a Marketing Plan.

UDW Technology Conference Dan McLeod / John Jacobson Lockheed Martin MS2 July 27, Secure Energy for America

Deepwater riserless (RLWI) enablers for increased oil recovery. Bringing shallow water experience to deepwater.

Accelerated Bridge Construction (ABC) and the Utah Experience

MR. DAVID DALE, PE, PMP, SES DIRECTOR, Programs Great Lakes & Ohio River Division. 14 May Braddock Dam

2005 First Quarter Presentation

5 Drawing Management Mistakes You re Making. And How to Avoid Them

KEY FACTS PASSIONATE GARDENERS... Circulation 30,060 Subscriptions 9,522 Source Jan - Dec 2015 ABC (print & digital)

APPENDIX C: MAIN RIVER BRIDGE PLANS. The graphics in this appendix depict the Practical Alternatives.

SCULPTURE WALK - HARBORPARK

BusinessHaldimand.ca. Haldimand County 2018 Community Profile

Using Graphing Skills

Welcome to Introduction to Probability and Statistics Spring

Wisconsin Technical College System. Curriculum Standards & Program Design Summary CARPENTRY APPRENTICE (ABC)

Thank you, Honorable Chairperson- Being a good team member

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

Chris and Wes are calm professional trades people with good problem solving skills

Webinar Module Eight: Companion Guide Putting Referrals Into Action

No limitations to precast

BIM 360 with AutoCAD Civil 3D, Autodesk Vault Collaboration AEC, and Autodesk Buzzsaw

TS79L00 Series 3-Terminal 100mA Negative Voltage Regulator

Data Acquisition in TBM tunnelling. Tim and Lars Babendererde, Frank Stahl, Philipp Elsner

Seaman Risk List. Seaman Risk Mitigation. Miles Von Schriltz. Risk # 2: We may not be able to get the game to recognize voice commands accurately.

Wireless Telecommunications Facilities Meeting. Neighborhood Leaders Meeting May 8, 2014

Skylands Learning is your trusted learning advisor. That is our promise your trusted learning advisor. Four simple words.

Legislative Joint Transportation Committee Meeting. Arkansas Convention Center Texarkana Thursday, November 21, 2013

TABLE OF CONTENTS 1200 PLAN PREPARATION

Active Cable TV Connections. Active Residential Cable Modem Customers. Page FIRST QUARTER REPORT

The use of an integrated contract model (iepci) for Subsea developments

OpenBridge Modeler: What is it and how can I use it today?

Housing Market Outlook

Featured Expert: Natasha Vorompiova // SystemsRock.com

IMAGERY USES STOCK. An insight into image buyers in the creative industries

Are you new to the real estate industry? Did you recently relocate your business?

Subtracting Rational Numbers

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges

The Second Health Information Technology Summit

CONSULTANT ACCREDITATION SCHEME SEWER DESIGN

THE PROCESS. Steps to Finding and Using the Right Information. Anytime. Anywhere.

THE. design STAGES THE GENERAL STAGES AND TIME FRAMES FROM START TO FINISH

1

INSTALLATION MANUAL. 2. Check with local utility companies for locations of underground cables or pipe lines.

English as a Second Language Podcast ESL Podcast 200 Meeting a Deadline

and Key Points for Pretty Houses

3108 Luli Rd Mogadore, OH (330) rocksolidpaintingco.com

ABC and Innovative Bridge Construction for Minnesota Local Roads

Deep Creek Canyon US Highway 12

Precast Bridge. in only Eight Days. profile. Minimizing construction-related traffic delays and improving workzone

How to choose a marketing agency

James Luebke, PE Structural Development Engineer WisDOT Bureau of Structures

AKBAR BASHA Mobile: , Doha Qatar.

INSTALLATION MANUAL. 2. Check with local utility companies for locations of underground cables or pipe lines.

BusinessHaldimand.ca. Haldimand County 2019 Community Profile

Persuasive. Software Development. Proposals. How to Write Persuasive. Proposals

LESSON INTRODUCTION. Reading Comprehension Modules Page 1. Joanne Durham, Interviewer (I); Apryl Whitman, Teacher (T)

The Ultimate. Content Creation. Guide. Learn to (Finally) Publish Consistently. Workbook

Digitally Signed 06/02/2015

ALL THE IDEAS BUILDING A STRATEGIC ROADMAP

TELLING STORIES OF VALUE WITH IOT DATA

MITOCW R22. Dynamic Programming: Dance Dance Revolution

Site Name. Bird Dimensions Species Hen harrier = data input required length (m) 0.55 = model calculates value wing span (m) 1.

Engineering and Construction Services Division Construction Drawings for Sewers and Watermains. T No. Revision T No. Revision Remarks All T drawings

24" Dia. 36" Dia. WE BUILD CONFIDENCE

ON THE PATH TO SOLOPRENEUR SUCCESS: YOUR 12 MONTH MARKETING + PROFIT PLAN!

The game consists of 3 rounds where you will build a castle in 30 seconds then place catapults and steal wall pieces from your neighbors.

Start Date. Census Date Delivery Mode EFTSL Unit Fee. End Date

freelancing FOR BEGINNERS

SUBSTATION SECURITY WALL INSTALLATION MANUAL

The Deliberate Creative Podcast with Amy Climer Transcript for Episode #006: Creative Problem Solving Stage 3 - Develop

CONSTRUCTION SPECIFICATION FOR MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION

800MHz Advisory Board August 24, 2017

adopted in Hong Kong

General Layout. Eng. Maha Moddather

Joint System Owners Customer Information Meeting Thursday, December 7, 2017 Environmental Service Building

Transcription:

Linear Scheduling 101 How to create your most-valuable project management tool on a single page.

2 The problem with Gantt charts on major projects: Our schedule has 2,638 activities on 61 pages. This doesn t reflect how our linear activities actually work. My boss doesn t want to see all of that detail. Am I supposed to be able to read this? I can t tell where the work crews will be located. How can we spot conflicts before they happen? Our schedule was supposed to be a planning tool, but it feels like it s mostly a payment tool.

3 We ve been there. Major projects is what we do. This guide was created by two construction managers who needed a better way to communicate complex schedules with their project teams. We live and breathe this stuff every day. James Wonneberg, PE, CCM Managing large-diameter tunnel projects for 9 years, including: 2008-2011: Brightwater Conveyance Project (Woodinville, WA) 2011-2016: DC Clean Rivers Project (District of Columbia) 2016-Present: Alaskan Way Viaduct Replacement (Seattle, WA) Pioneered the use of dynamic Excel graphics that redraw themselves automatically with links to contractors Primavera P6 schedules. Ron Drake, PE Leading complex infrastructure projects for 40 years, including: 1990-1993: Metro Red Line (Los Angeles, CA) 1993-1998: Tri-Met Westside Light Rail (Portland, OR) 2005-2007: Brightwater Conveyance Project (Woodinville, WA) 2014-Present: LA Metro Regional Connector (Los Angeles, CA) Has made linear scheduling a cornerstone of his project management approach for decades.

4 What We Believe: We believe that the vast majority of people that work on these projects really do want to know what s in that huge schedule with thousands of activities. They want to know the master plan. They want to see the big picture and understand the relationships between activities. They want to know about the deadlines that their crew must meet. But our industry lacks the tools to communicate that information in a way that the entire team can understand. We believe that if you make your schedule beautiful, your team will use it! If you place a good-looking linear schedule on the table in any project office or jobsite trailer, people will go out of their way to look at it, pick it up, and study it. Then they will ask questions, and give you valuable feedback about how the work will actually be built. (But if you don t make your schedule beautiful, it will be ignored and forgotten like all the rest.)

5 What We Believe: CONTINUED We believe that schedules should fit on one page. The moment you have to flip the page to see the rest of your sequence of work, you ve lost the relationships between activities. This is not to say that we don t create multiple sheets; in fact we do it all the time to zoom in and zoom out on our projects. But each sheet should tell the whole story of what you are trying to communicate. We believe that adding a simple graphic of what you re building makes your schedule information 10x more useful and effective. Most people are visual learners, and schedule data doesn t sink in unless they can visualize the major work elements and the spatial relationships between them. A one-page illustration of scope of work and schedule becomes a very useful talking paper that helps you quickly explain your entire project to anyone, anywhere. And your team members will undoubtedly start sketching right on top of it for all sorts of problem solving, alternatives, and what-if-scenarios. This is when the magic happens increasing the chances of your team delivering a winning project.

6 What the Industry is Saying: As engineers and contractors, we are taught to break down complex projects into fundamental simpler pieces. Linear schedules are great tools that help us break down complex P6 schedules to help communicate to all team members our plan for success. -Fernando De Leon, Project Director at Shimmick Construction The linear scheduling method really helps to visualize a project s schedule. It makes it possible to not only account for time but also space constraints. -Lisa Mori, Tunnel Engineer at Jay Dee Contractors

7 Coming Up: This guide will walk you through the fundamentals of a linear schedule, give you the vision for how it can be applied, and show you how to put it to work as your project evolves. Along the way you ll hear from more industry leaders about how they re using linear scheduling to execute their own challenging projects. Part 1: The Basics Part 2: Example Projects Part 3: Adapting to Schedule Changes

1 The Basics 8

9 Tunnel Project Example: SOUTH SITE NORTH SITE BORED TUNNEL SOUTH SHAFT NORTH SHAFT

10 Simplified Gantt Chart: ACTIVITY START DATE FINISH DATE PREPARE SOUTH SITE 1-Apr-17 30-Jun-17 2017 2018 2019 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 CONSTRUCT SOUTH SHAFT 1-Jul-17 31-Dec-17 PREPARE NORTH SITE 1-Jul-17 30-Sep-17 CONSTRUCT NORTH SHAFT 1-Jan-18 30-Jun-18 ASSEMBLE TBM 1-Jan-18 31-Mar-18 EXCAVATE TUNNEL 1-Apr-18 31-Mar-19 RETRIEVE TBM 1-Apr-19 30-Jun-19 linear activity PUNCH LIST 1-Jul-19 30-Sep-19 SUBSTANTIAL COMPLETION 30-Sep-19

BORED TUNNEL 11 Page Setup for Linear Schedule: NORTH SHAFT 110+00 90+00 2017 2018 2019 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 X = Time 70+00 50+00 30+00 10+00 SOUTH SHAFT Y = Location

BORED TUNNEL PUNCH LIST 12 Linear Schedule: NORTH SHAFT 110+00 90+00 2017 2018 2019 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 PREP SITE CONSTRUCT NORTH SHAFT RETRIEVE TBM SUBSTANTIAL COMPLETION 70+00 50+00 30+00 10+00 PREP SITE CONSTRUCT SOUTH SHAFT ASSEMBLE TBM SOUTH SHAFT

BORED TUNNEL PUNCH LIST 13 Terminology: Timescale Bar Activity (work at a single location) 2017 2018 2019 Location Axis (distance units or stationing along project alignment) NORTH SHAFT 110+00 90+00 70+00 50+00 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 PREP SITE CONSTRUCT NORTH SHAFT RETRIEVE TBM SUBSTANTIAL COMPLETION Milestone (deadline or major event) Linear Activity (work that moves from Point A to Point B over time) 30+00 10+00 SOUTH SHAFT PREP SITE CONSTRUCT SOUTH SHAFT ASSEMBLE TBM Block Activity (work over a given space for a period of time)

14 Primary Types of Activities: Finish Date Location 2 Location 2 Start Date Finish Date Block Activity Location 1 Location 1 Start Date Work that moves from Point A to Point B over time Work over a given space for a period of time

15 Primary Types of Activities: CONTINUED Date Location Start Date Bar Activity Finish Date Location Milestone Work at a single location Deadline or major event

16 What do the colors mean? Short Answer: Whatever you like. Better Answer: We usually assign one color to each major type of work (similar to layers in a CADD drawing). This makes it easy to see how your crews and equipment will move through the project over time. Or, when illustrating a large program with multiple contracts, we often assign one color to each contract. This helps everyone see how all of the contracts work together to complete the program. It also highlights the interfaces (i.e. touch points) that will require coordination to make sure everything goes smoothly. Color is a good thing. Be creative, and don t hold back! or

17 Advantages of a Linear Schedule: Are we OK with three cranes or do we need to add a fourth? I can just look down a specific month on the linear schedule and see right away how many crews or spreads we will have working and at what locations. All on one page. That is convenient compared to long P6 schedules. -Brett Zernich, Project Manager at Traylor Bros. The linear schedule update is one email that I actually look forward to receiving each month. It provides a concise and useful snapshot of otherwise complex project and program schedules. -Rafael Castro, Principal at JCK Underground Linear schedules have been essential to communicating inter-project and inter-agency construction relationships. -Brian Smith, Program Controls Manager at Mott MacDonald

2019 2018 2017 18 Alternate Page Setup: Time on Vertical Axis SOUTH SHAFT Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 BORED TUNNEL 10+00 30+00 50+00 70+00 90+00 110+00 X = Location Y = Time NORTH SHAFT Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2017 2018 2019

2019 2018 2017 19 Linear Schedule: Time on Vertical Axis SOUTH SHAFT Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 10+00 30+00 50+00 70+00 90+00 110+00 PREP SITE CONSTRUCT SOUTH SHAFT ASSEMBLE TBM BORED TUNNEL PUNCH LIST SUBSTANTIAL COMPLETION PREP SITE CONSTRUCT NORTH SHAFT RETRIEVE TBM NORTH SHAFT Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2017 2018 2019

2019 2018 2017 20 Same Terminology: Location Axis SOUTH SHAFT BORED TUNNEL NORTH SHAFT Timescale Q1 Q2 Q3 Q4 10+00 30+00 50+00 70+00 90+00 110+00 PREP SITE CONSTRUCT SOUTH SHAFT PREP SITE Q1 Q2 Q3 Q4 2017 Bar Activity Block Activity Q1 Q2 Q3 Q4 Q1 ASSEMBLE TBM CONSTRUCT NORTH SHAFT Q1 Q2 Q3 Q4 Q1 2018 Linear Activity Q2 Q3 PUNCH LIST RETRIEVE TBM Q2 Q3 2019 Q4 SUBSTANTIAL COMPLETION Q4 Milestone (can use a line or a diamond)

21 vs. Time from Left to Right: Easiest to read for general audiences (the way we normally read schedules) Expanded timescale accommodates more-detailed schedule activities and labels Differences in linear production rates are more obvious Time on Vertical Axis: Also called a Time-Chainage Diagram Keeps the drawing horizontal (the way we normally read plan & profile drawings) Can illustrate the sequence in the same direction that the work is constructed (i.e. top-down or bottom-up)

22 Which format to choose? Here s our $0.02: People that have never seen a linear schedule before usually find it easiest to read time from left to right. When meeting with executives, third party stakeholders or the Mayor, you need to bring them up to speed quick. So we plot time from left to right whenever possible. However, certain industries and regions have been plotting time on the vertical axis for decades. In that case, stick with the format that your target audience wants to see. (Either way, your linear schedule is sure to communicate your plan far better than that stack of Gantt charts ever could.)

2 Example Projects 23

24 Bridge Project Example: GIRDERS DECK SOUTH ABUTMENT SPAN 1 SPAN 2 SPAN 3 NORTH ABUTMENT PIER A PIER B

2017 2018 25 Page Setup: S. ABUTMENT PIER 1 PIER 2 N. ABUTMENT Jun May Apr Mar Feb Jan Dec Nov Oct Sep X = Location Y = Time Jun May Apr Mar Feb Jan Dec Nov Oct Sep 2018 2017

2017 2018 26 Linear Schedule: S. ABUTMENT PIER 1 PIER 2 N. ABUTMENT Jun May Apr Mar Feb Jan Dec Nov Oct Sep PRECAST GIRDERS SPAN 1 CONCRETE ABUTMENT DRILLED SHAFTS (TYP) SUBSTANTIAL COMPLETION GROUT/CURE/POST-TENSION PRECAST GIRDERS SPAN 2 CONCRETE PIER PRECAST GIRDERS SPAN 3 CONCRETE ABUTMENT CONCRETE PIER Jun May Apr Mar Feb Jan Dec Nov Oct Sep 2018 2017

27 Streetcar Project: 130+00 120+00 110+00 100+00 90+00 80+00 70+00 60+00 50+00 40+00 30+00 20+00 10+00 0+00 2018 2019 A M J J A S O N D J F M A M J J Maintenance Facility PLATFORM (TYP.) TPSS RAILCAR DELIVERY TESTING & COMMISSIONING PLACE INTO OPERATION PRE-REVENUE TESTING

28 Industry Perspectives: The intuitive format of a linear schedule helps us transform detailed CPM schedules from overwhelming to understanding. -Brian Ellingson, Schedule Engineering Supervisor at Sound Transit Linear scheduling provides a graphic display of how crews and equipment move through the project over time. This 1) helps contractors depict their plan to construct the work and 2) allows for constructability analysis of the schedule that may be lost by Gantt Chart review only. -Amy Heine, Principal at Hirschmugl, Heine & Associates Our linear schedule was extremely helpful on the floating bridge project. We used it to manage the job and communicate with the public. -Walter Tarr, Principal at Polaris Project Controls

Pipeline Project Example: 29

30 Gantt Chart for Pipeline Project: ACTIVITY START DATE FINISH DATE 2017 Jan Feb Mar Apr May Jun Jul ENVIRONMENTAL SHUTDOWN WINDOW (NO WORK) 15-Mar-17 15-Apr-17 GRADING & PIPE STRINGING 1-Feb-17 24-Apr-17 PIPE WELDING 9-Feb-17 11-Jun-17 TRENCHING 16-Apr-17 26-Jun-17 LOWER PIPE & BACKFILL 23-Apr-17 3-Jul-17 RESTORATION & CLEANUP 16-May-17 13-Jul-17

2017 31 Linear Schedule for Pipeline Project: Kilometers: 0+000 3+000 6+000 9+000 12+000 15+000 18+000 21+000 Jul Jul Jun Jun May May Apr Mar ENVIRONMENTAL SHUTDOWN WINDOW (NO WORK) Apr Mar 2017 Feb Feb Jan Jan

Tower # Type Foundation 32 Transmission Line Project: SUBSTATION 14 T DS 2017 2018 Sep Oct Nov Dec Jan Feb Mar Apr 13 T DS 12 T DS 11 T DS 10 T DS 9 T DS 8 T DS 7 T DS 6 L HP 5 L HP 4 L HP 3 L HP 2 L HP WIND FARM 1 L HP

So far these examples have all been infrastructure projects. This method works for vertical construction too. 33

34 High Rise Building Project: 2017 2018 MECH. L11 S O N D J F M A M J J A S O N D L10 L9 L8 L7 L6 L5 L4 L3 L2 MECH. M G P1 P2 EXCAVATE & BRACE PILES PILE CAPS & SLAB LANDSCAPING

3 Adapting to Schedule Changes 35

36

BORED TUNNEL PUNCH LIST 37 Updating a Linear Schedule: Add a Data Date Line NORTH SHAFT 110+00 90+00 2017 2018 2019 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 PREP SITE CONSTRUCT NORTH SHAFT RETRIEVE TBM SUBSTANTIAL COMPLETION Show Planned Start & Finish Dates for Remaining Work 70+00 50+00 Show Actual Start & Finish Dates for Completed Work 30+00 SOUTH SHAFT ASSEMBLE CONSTRUCT TBM PREP SITE SOUTH SHAFT 10+00 ACTUAL PLANNED Show Actual Daily Progress To-Date for Linear Activities

BORED TUNNEL 38 Plotting Actual Progress for Linear Activities: NORTH SHAFT 110+00 90+00 70+00 50+00 30+00 10+00 SOUTH SHAFT 2017 2018 2019 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 PREP SITE PREP SITE CONSTRUCT SOUTH SHAFT CONSTRUCT NORTH SHAFT ASSEMBLE TBM Breakdown Launch/Learning Curve Hole-through Replace Cutting Tools Date Location 31-May-18 10+00 30-Jun-18 12+50 31-Jul-18 12+50 31-Aug-18 14+74 30-Sep-18 25+31 31-Oct-18 42+00 30-Nov-18 50+07 31-Dec-18 50+07 31-Jan-19 63+87 28-Feb-19 76+03 31-Mar-19 76+03 30-Apr-19 76+03 31-May-19 94+46 30-Jun-19 110+00

BORED TUNNEL PUNCH LIST 39 Comparison to Baseline: Add a Data Date Line 2017 2018 2019 Show Baseline Activities as a Faded Background Layer NORTH SHAFT 110+00 90+00 70+00 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 PREP SITE CONSTRUCT NORTH SHAFT RETRIEVE TBM SUBSTANTIAL COMPLETION Overlay Planned Activities for Remaining Work 50+00 Overlay Actual Progress To-Date 30+00 SOUTH SHAFT ASSEMBLE CONSTRUCT TBM PREP SITE SOUTH SHAFT 10+00 ACTUAL PLANNED

BORED TUNNEL PUNCH LIST 40 Great for Markups & Alternatives: 2017 2018 2019 NORTH SHAFT 110+00 90+00 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 PREP SITE CONSTRUCT NORTH SHAFT RETRIEVE TBM SUBSTANTIAL COMPLETION 70+00 50+00 30+00 10+00 PREP SITE CONSTRUCT SOUTH SHAFT ASSEMBLE TBM SOUTH SHAFT

2017 41 Highlighting the Critical Path: Kilometers: 0+000 3+000 6+000 9+000 12+000 15+000 18+000 21+000 Jul Jun May Jul Jun May These links represent the spacing between work crews as they advance. (Also called a buffer ) Apr Mar ENVIRONMENTAL SHUTDOWN WINDOW (NO WORK) Apr Mar 2017 Feb Feb Jan Jan

42 A Simple-Yet-Powerful Tool: From a risk management perspective, I find great value in using linear schedules to compare complex base (deterministic) schedules and risk-based (probabilistic) schedules. This helps identify the trouble activities where uncertainty is the highest. Overlaying the two schedules is a simple, quick, and effective way to help project managers focus their attention and manage their resources. -Norman Perez, Senior Engineer at Schnabel Engineering One page, one clear pathway to completion, and infinite combinations of tasks for multi-faceted projects. Brilliant. -Allen Jensson, Mechanical Engineer at The Boring Company This is what our Director wants to see. -Steve Wheeler, Construction Program Scheduler at Shrewsberry & Associates

43 Thanks for making it this far! Here s where we ve been together: You ve seen how a 1-page linear schedule can effectively communicate your plan to a wide variety of audiences. You ve seen how this method can be applied to all sorts of projects where location of the work is key. And you ve learned how to maintain your linear schedule during construction, when the rubber meets the road. We hope you ve enjoyed this guide. But more importantly, we hope you ll do something with it.

44 Is there an app that creates linear schedules? We thought you d never ask. There are a few products out there. Some are extremely powerful and sophisticated, and can practically cook you breakfast if you can get past the steep learning curve. We re taking a different approach; developing an app that s easy to use by non-schedulers and runs right in Microsoft Excel, which most of you already use every day. If that sounds interesting to you, visit GraphicSchedule.com to learn more.

Want to help more people discover linear scheduling? and get an awesome PowerPoint deck in the process. 45 Step 1: email james@graphicschedule.com and ask him to send you the animated PowerPoint version that brings these examples to life. Step 2: share this guide with your project team, your network, and your boss. (Bosses love 1-page linear schedules because they can show it to their boss too ) Step 3: start sketching up a linear schedule for your own project and let us know if you need any help along the way.

Create something your entire team will love! 46

47 About GraphicSchedule: We re a small startup with a big mission: to help teams communicate their schedules more effectively and deliver winning projects. We got tired of drawing linear schedules by hand so we developed an Excel app that makes it easy. Visit our website: GraphicSchedule.com Read our origin story Get in touch: james@graphicschedule.com