Dowel Bar Alignment and Location for Placement by Mechanical Dowel Bar Insertion

Similar documents
Dowel Bar Alignment and Location for Placement by Mechanical Dowel Bar Insertion

Mark B. Snyder, Ph.D., P.E.

Design and Construction of Highway Pavement Joint Systems

Dowel Alignment Considerations and Specification Update

ABCDE. TechBrief. Best Practices for Dowel Placement Tolerances

Evaluation of Dowel Bar Inserter Practices in PCC Pavements with Magnetic Tomography Technology

Dowel Alignment: Measurement and Impacts on Pavement Performance

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Plate Dowels. An Innovation Driven by Industrial Concrete Paving. Introduction

R&T UPDATE. An Alternative to Traditional Round Dowel Bars Plate Dowel Innovations Driven by Industrial Concrete Paving

Dowel Bars and Misalignment Tolerances

Design and Construction of Highway Pavement Joint Systems

The Need for Improved Specifications on Dowel Bar Placement Tolerance

Magnetic Imaging Technology

Session 8: Load Transfer Restoration. (Dowel Bar Retrofit, Cross-Stitching, and Slot Stitching)

IGGA Guide Specification: Dowel Bar Retrofit (DBR) Introduction

Initiating Cracks in PCC Pavements. Malcolm K. Lim, PE

4.1. Foremen 4.2. Concrete plant manager 4.3. Concrete plant operator 4.4. Personnel performing saw cutting and joint sealing

Jointed Precast Concrete Pavement

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION

Jointing Rural Intersections

AMENDMENTS Manual of STANDARD SPECIFICATIONS. Adopted by Standard Specifications Committee. Amendment. No. 6. Published by

Corrosion-Resistant Coated Dowel Bars

To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved:

TechBrief. Precast Concrete Panels for Repair and Rehabilitation of Jointed Concrete Pavements

B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following.

A Solution to Cracking and Stresses Caused by Dowels and Tie Bars

Table 5G-2.01: Transverse Joint Requirements. Transverse Joint Type 6 C 12 7 C 15 8 CD CD CD 1 20

JVI Vector Connector

Design and Construction of Highway Pavement Joint Systems

PERFORM WITH PRECISION WELDED DOWEL ASSEMBLY LOAD TRANSFER PRODUCTS CONCRETE CONSTRUCTION SOLUTIONS BROCHURE

Effect of Dowel Bar Embedment Length on Joint Load Transfer Efficiency of MnROAD Concrete Pavement Test Cells

Project No.: VTRC 06-R22 March Period Covered: Contract No.

Special Provision No. 999F29 March 2018 REQUIREMENTS FOR INSTALLATION OF METALLIC DOWELS INTO CONCRETE

Special Provision No. 999S29 May 2010

Glass Fiber Reinforced Polymer (GFRP) Dowel Bars - Aslan 600

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

A. Extent of structural precast concrete work is shown on drawings and in schedules.

Precast Concrete Pavement Background Concepts. Project 1517 FHWA, CTR & TxDOT Gary Graham November 15, 2001

Section 914. JOINT AND WATERPROOFING MATERIALS

Flanged Dowel Box. Load Transfer System INDUSTRIAL SLAB ON GROUND

Precast Concrete Panels for Rapid Pavement Repair

ASLAN 600 GLASS FIBER REINFORCED POLYMER (GFRP) DOWEL BARS FOR LOAD TRANSFER IN CONCRETE SLABS

PCCP Preservation Steps to Take to Extend Pavement Life and Performance of Your Concrete Pavements

PD 3 Dowel Cradle. Load Transfer System Industrial Slab on Ground

Chapter 6: SHOP DRAWINGS AND OTHER SUBMITTALS

Diamond Dowel. Load Transfer System INDUSTRIAL SLAB ON GROUND

SECTION 58 PRECAST CONCRETE BOX CULVERT. This work consists of furnishing and installing Pre-cast Concrete Box Culverts.

Dowel Placement Tolerances for Concrete Pavements

MIT Product Demonstration

Research A PERFORMANCE TESTING OF EXPERIMENTAL DOWEL BAR RETROFIT DESIGNS PART 1 INITIAL TESTING. Final Report

Special Provision No. 904S14 October OPSS 904, January 1995, Construction Specification for Concrete Structures, is amended as follows:

Double Bar Plate Dowels for Saw-Cut Contraction Joints

Non-Destructive Bridge Deck Assessment using Image Processing and Infrared Thermography. Masato Matsumoto 1

SECTION PRECAST CONCRETE SECTIONAL MANHOLES

Dowel. Design. Performance-Based World of Concrete Official Show Issue. Lift-truck design changes require a new look at joint durability

TECHNICAL MANUAL. TERADOWEL and ULTRADOWEL. Reliable Dowel System for Floor Joints

To Develop a Quality Control/Quality Assurance Plan For Hot Mix Asphalt. AASHTO PP qq

SPECIFICATIONS FOR THE INSTALLATION OF CONDUIT SYSTEMS IN RESIDENTIAL SUBDIVISIONS. Notification of Completed Conduit Sections

6o ft (18.3 m) Southwest Windpower, Inc West Route 66 Flagstaff, Arizona USA Phone: Fax:

Storage and Installation of welded LL Hollow Metal Door Frames in Steel Studs

TxDOT Project : Evaluation of Pavement Rutting and Distress Measurements

Precast Concrete Pavement

Design and Construction of Highway Pavement Joint Systems

CITY OF LA MARQUE CHAPTER GRAPHIC REQUIREMENTS CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS

Design of structural connections for precast concrete buildings

Concrete Pavement Preservation

prepared by Tom Burnham, Co-Chair Minnesota Department of Transportation Mark B. Snyder, Co-Chair Engineering Consultant for National Concrete

Edgerail Aluminum Bridge Railing System Specification & Installation Instructions

A New Load Transfer Assembly for the Jointed Concrete Pavements

Quality Assurance Where does the Future Lead US. John D AngeloD Federal Highway Administration

Full-Depth Concrete Pavement Repairs on the Ohio Turnpike

EXCAVATION AND BACKFILL

STATE OF OHIO DEPARTMENT OF TRANSPORTATION. SUPPLEMENTAL SPECIFICATION 817 SPRAY THERMOPLASTIC PAVEMENT MARKING April 15, 2011

POSTPRINT UNITED STATES AIR FORCE RESEARCH ON AIRFIELD PAVEMENT REPAIRS USING PRECAST PORTLAND CEMENT CONCRETE (PCC) SLABS (BRIEFING SLIDES)

5/16" Flange nut. Bolt Keeper Plate (8" Sq. SYS.) (3) 1/2" x 3" Hex head connector zinc plated bolt w/ washers and nut. Anchor 3" sq. 7 Ga.

² TL Beton-StB 07 = German technical conditions for construction materials for concrete road pavements

Dowels for the 21st Century

Technical Bulletin. Tolerances in the Dimension Stone Industry

Dowel Basket Standardization

SUMMARY SHEETS OF BAR COUPLER CONNECTIONS

2016 Specification Treads, Base, Stringers and other Amenities Wausau Tile Precast Epoxy Terrazzo

MANHOLES PART I: GENERAL. A. Precast Concrete Manholes

1. ANSI/ASME Standard B , Square and Hex Bolts and Screws, Inch Series

State-of-the-art Report On FULL-DEPTH PRECAST CONCRETE BRIDGE DECK PANELS (SOA )

Engineering Policy & Procedure

Joint with Bent Dowels. David Cronin, P.E. City Engineer. Jason Hoskinson, P.E., PTOE BG Consultants, Inc. DATE: January 23, 2014

Chapter 4 Results. 4.1 Pattern recognition algorithm performance

Fast Track Precast Concrete Pavement Rehabilitation Pilot Project

Pave-IR Scan TM Primer

ISO 7438 INTERNATIONAL STANDARD. Metallic materials Bend test. Matériaux métalliques Essai de pliage. Second edition

Why Do We Saw Equipment Types Matching Equipment to the Project Blade Selection Ensuring Construction Quality When Things Don t Go Right The Sawing

1. Architectural precast concrete cladding units.

Noise Mitigation Study Pilot Program Summary Report Contract No

Retrofit Dowel Bars in Jointed Concrete Pavement Long-Term Performance and Best Practices

SECTION 39 - MANHOLES TABLE OF CONTENTS

Standard Specifications

C. For cold-applied tape, the pavement temperature shall be at least 70 F.

SUPPLEMENT 1127 PAY FACTORS DETERMINATION FOR PAVEMENT AND STRUCTURE CONCRETE

Responses to Concrete Specifications Survey with Summary (2011)

Transcription:

Dowel Bar Alignment and Location for Placement by Mechanical Dowel Bar Insertion January 7, 2013 Scope, Background and Applicability This guide specification is directly applicable to 18 in. (457 mm) long, round metallic dowel bars, with and without coatings, for use in jointed plain concrete pavements with joint sawcuts made perpendicular to the edge of pavement (e.g., non-skewed joints); many of the underlying principles may be applicable to round dowels with other lengths and diameters. The requirements herein recognize that round dowel bars must be: 1) Aligned such that they impose no intolerable restraint on joint opening/closing. 2) Located such that they provide adequate long-term load transfer and have adequate concrete cover to prevent shear failures. The alignment of dowel bars is important because significant misalignment of dowel bars in a doweled joint may prevent that joint from properly opening/closing. The occurrence of a single joint that does not open/close effectively will not necessarily result in a midpanel crack or other pavement defect, but the risk of mid-panel cracking and joint distress increases with each successive joint with limited opening/closing capabilties (see FHWA 2007). Longitudinal translation (see DBAL.1) is important to ensure the proper embedment length of the dowel bar for long-term load transfer. Thus, the allowable longitudinal translation is a function of construction (e.g., location per plans and proper location of sawcut over the dowel) and the dowel bar length. Control of vertical translation (see DBAL.1) is important to ensure that there is enough concrete over the steel to resist corrosion of steel dowel bars and must be such that the concrete will not develop shear cracking or spalling above the dowels as loads are transferred across the joint. Thus, the allowable vertical translation is a function of asconstructed pavement thickness and planned dowel vertical location. 1 Consideration must also be given for sawcut depth such that the dowels are not cut during sawing operations. 1 See NCC 2011 for details on planned dowel locations that do not necessarily place dowel bars at the mid-depth of the pavement.

Horizontal translation (see DBAL.1) is of concern 2 when a dowel is located far enough from its intended location that the redistribution of joint loads negatively impacts the pavement or dowel-concrete system. If a dowel alignment and location specification is included on a concrete paving project, it is suggested that the conditions of the specification be reviewed during a pre-paving meeting. The discussion should include a review of: 1) how the dowel bar insertion equipment will function; 2) the Accept, QA Trigger, and Requires Action limits; 3) the dowel alignment and location testing device, its applicability to the specification, and testing and reporting protocols; and 4) acceptable corrective action scenarios. The following documents were used in preparation of this specification: ACPA 2006, Evaluating and Optimizing Dowel Bar Alignment, American Concrete Pavement Association, SR999P. FHWA 2005a, TechBrief: Use of Magnetic Tomography Technology to Evaluate Dowel Bar Placement, Federal Highway Administration, FHWA-IF-06-002, http://www.fhwa.dot.gov/pavement/pccp/pubs/06002/index.cfm. FHWA 2005b, Use of Magnetic Tomography Technology to Evaluate Dowel Bar Placement, Federal Highway Administration, FHWA-IF-06-006, http://www.fhwa.dot.gov/pavement/concrete/mitreport/. FHWA 2007, Best Practices for Dowel Placement Tolerances, Federal Highway Administration, FHWA-HIF-07-021, http://www.fhwa.dot.gov/pavement/concrete/pubs/07021/. NCC 2011, Recommendations for Standardization of Dowel Load Transfer Systems for Jointed Concrete Roadway Pavements, National Concrete Consortium, http://www.cptechcenter.org/publications/dowel_techbrief_sept2011.pdf. NCHRP 2009, Guidelines for Dowel Alignment in Concrete Pavements, National Cooperative Highway Research Program, Report 637, http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_637.pdf. NCPTC 2011, Guide to Dowel Load Transfer Systems for Jointed Concrete Roadways Pavements, National Concrete Pavement Technology Center, http://www.cptechcenter.org/publications/dowelloadguide.pdf. 2 Software such as DowelCAD (see acpa.org/dowelcad) and the performance of dowel bar retrofit (DBR) installations illustrate that current doweling practices with dowel bars spaced uniformly at approximately 12 in. (300 mm) on-center are overly conservative and that alternate dowel arrangements with less dowels per joint may prove beneficial from both a stress/strain/deflection response and steel optimization standpoints. Horizontal translation may become of concern if alternate, non-uniform dowel spacings are used in the future. January 7, 2013 Page 2 of 12

Guide Specification DBAL.1 TERMINOLOGY Figure 1 illustrates the five types of dowel bar misalignment and mislocation: horizontal skew, vertical tilt, horizontal translation, longitudinal translation, and vertical translation. Figure 1. The 5 types of dowel bar misalignment and mislocation (after FHWA 2007). DBAL.1.1 Dowel Bar Alignment Terms Horizontal Skew The deviation of the dowel bar from true parallel alignment from the edge of the pavement 3, measured over the entire length of the dowel bar. Vertical Tilt The deviation of the dowel bar from true parallel alignment from the surface of the pavement, measured over the entire length of the dowel bar. Alignment The degree to which a dowel bar aligns true (e.g., parallel) to the horizontal and vertical planes of the pavement. Misalignment Any deviation in either the horizontal or vertical plane from a true alignment condition (e.g., horizontal skew or vertical tilt). 3 COMMENT: Horizontal skew measurements are erroneous if the testing device is not oriented perpendicular to the edge of the pavement (e.g., if the device references a skewed joint). January 7, 2013 Page 3 of 12

Single Dowel Misalignment (SDM) The degree of misalignment applicable to a single dowel bar, calculated as: Single Dowel Misalignment (SDM) = (Horizontal Skew) 2 + (Vertical Tilt) 2 Joint Score (JS) 4 Evaluated for a single transverse joint between adjacent longitudinal joint(s) and/or pavement edge(s) (i.e., a typical 12 ft [3.6 m] standard lane or up to 14 ft [4.3 m] widened lane), and calculated as: n where: Joint Score (JS) = 1 + W i i=1 n = number of dowels in the single joint W i = weighting factor (Table 1) for dowel i Table 1. Weighting Factors 5 in Joint Score (JS) Determination Single Dowel Misalignment (SDM) W, Weighting Factor SDM 0.6 in. (15 mm) 0 0.6 in. (15 mm) < SDM 0.8 in. (20 mm) 2 0.8 in. (20 mm) < SDM 1 in. (25 mm) 4 1 in. (25 mm) < SDM 1.5 in. (38 mm) 5 1.5 in. (38 mm) < SDM 10 The potential for locking of a single joint (e.g., transverse joint between adjacent longitudinal joint(s) and/or pavement edge(s)) as represented by the JS is as follows: JS 5 very low risk of joint restraint 5 < JS 10 low risk of joint restraint 10 < JS 15 moderate risk of joint restraint; potentially locked JS > 15 high risk of joint restraint; joint locked Joint Score Trigger (JST) A scaling 6 of the Joint Score risk value to account for the actual number of dowels per a single joint, calculated as: # of Dowel Bars in Single Joint Joint Score Trigger (JST) = 10 12 Maximum Allowable Locked Length (MALL) maximum allowable length of locked-up pavement; 60 ft (18 m), including no more than three consecutive joints with joint scores (JSs) greater than the JST. 4 COMMENT: See Dowel Bar Alignment Calculator (apps.acpa.org) for a JS calculator. 5 COMMENT: Weighting factors may vary with dowel materials, dowel coating type and thickness and embedded dowel length. The weighting factor values presented in Table 1 were developed for 18 in. (457 mm) round metallic dowel bars with and without epoxy coating. 6 COMMENT: Scaling the Joint Score risk value is necessary because the value was developed based on 12 ft (3.6 m) wide single joints with 12 dowel bars. January 7, 2013 Page 4 of 12

DBAL.1.2 Dowel Bar Location Terms Horizontal Translation Location of dowel bar relative to the planned location from the pavement edge, nearest longitudinal joint, or nearest parallel dowel bar. Vertical Translation Location of dowel bar relative to the depth in the pavement, referenced from the nominal mid-depth of the slab thickness including tolerances for placement technique. Longitudinal Translation Location of the middle of the dowel bar length with respect to the joint saw cut created over it. Embedment Length Length of dowel bar embedded to either side of the joint saw cut. Mislocation Any deviation of a dowel bar from its planned location. Required remedial action depends on the degree of mislocation. DBAL.2 ALIGNMENT TOLERANCES Dowel alignment tolerances are summarized in Table A.1. in Appendix A. DBAL.2.1 Alignment Tolerances for an Individual Dowel Bar Install dowel bars within the following alignment tolerances for individual dowel bars, based on a combination of horizontal skew and/or vertical tilt criteria and the dowel s single dowel misalignment (SDM): Horizontal Skew AND Vertical Tilt < 0.6 in. (15 mm) Accept Horizontal Skew OR Vertical Tilt 0.6 in. (15 mm) QA Trigger SDM > 1.5 in. (38 mm) DBAL.2.2 Alignment Tolerances for a Single Joint Install dowel bars within the following alignment tolerances for a single joint, based on the Joint Score (JS): JS JST 7 JS > JST JS > JST for all doweled joints over MALL Accept QA Trigger 7 COMMENT: The Joint Score Trigger (JST) equals 10 for the standard case of 12 dowel bars across a 12 ft (3.6 m) wide joint but this value must be scaled if the joint has more dowels (e.g., widened lane) or less dowels. January 7, 2013 Page 5 of 12

DBAL.3 LOCATION TOLERANCES FOR AN INDIVIDUAL DOWEL BAR Dowel location tolerances are summarized in Table A.1. in Appendix A. Install individual dowel bars within the following longitudinal translation tolerances 8 : Longitudinal Translation 2 in. (50 mm) Longitudinal Translation > 2 in. (50 mm) Longitudinal Translation > 5 in. (125 mm) Accept QA Trigger Install individual dowel bars within the following vertical translation tolerances 9 : Vertical translation above nominal mid-depth: Vertical Translation 1 in. (25 mm) Vertical Translation > 1 in. (25 mm) Concrete Cover 10 < 2.5 in. (64 mm) Accept QA Trigger AND Provide 0.5 in. (12 mm) Between Top of Bar and Bottom of Joint Saw Cut Provide < 0.5 in. (12 mm) Between Top of Bar and Bottom of Joint Saw Cut Provide < 0.25 in. (6 mm) Between Top of Bar and Bottom of Joint Saw Cut Vertical translation below nominal mid-depth: Vertical Translation 1 in. (25 mm) Vertical Translation > 1 in. (25 mm) Concrete Below Bar < 2.5 in. (64 mm) Accept QA Trigger Accept QA Trigger Install individual dowel bars within the following horizontal translation tolerances: Horizontal Translation 2 in. (50 mm) Horizontal Translation > 2 in. (50 mm) Horizontal Translation > 3 in. (75 mm) Accept QA Trigger 8 COMMENT: These limits were calculated to ensure at least 4 in. (100 mm) of embedment length on either side of the joint saw cut (see NCPTC 2011). The Accept and QA Trigger limits were calculated as (18 in. [450 mm] dowel bar length - 2* 4 in. [100 mm] of embedment)/2-3 in. [75 mm] as a safety factor = 2 in. [50 mm]. The Requires Action limit was calculated as (18 in. [450 mm] dowel bar length - 2* 4 in. [100 mm] of embedment)/2 = 5 in. [125 mm]. Similar calculations can be conducted to determine allowable horizontal translation tolerances for other dowel bar lengths. 9 COMMENT: While vertical translation defines the vertical mislocation of a dowel bar, the vertical translation actionable conditions are written in terms of concrete cover depth (both top and bottom) and sawcut depth to normalize the specification for varying concrete pavement thicknesses. 10 COMMENT: Concrete cover is impacted by both vertical translation and vertical tilt and should be considered as the minimum distance between the dowel bar and the concrete surface or base, which is not necessarily located at the joint. January 7, 2013 Page 6 of 12

DBAL.4 DBAL.4.1 FIELD MEASUREMENT PROCEDURES Trial Section Measure the alignment and location of each dowel bar in the first 50 joints as a trial section; this test section can be the start of production paving at the contractor s discretion. The process will be considered acceptable with approval of the Engineer if each Joint Score (JS) is less than the JST (per DBAL.2.2) AND ninety percent (90%) of the dowel bars are within the Accept limit and none of the dowel bars exceed the Requires Action limits in DBAL.2.1 and DBAL.3. Use the data to refine the paving process and reduce/eliminate misalignments and mislocations. If the dowel bar installation method is not accepted by the Engineer after assessing the trial section, if paving operations have been suspended for more than 15 days, or if the concrete mixture or dowel installation method or equipment setup changes during production after approval to proceed, additional trial sections and appropriate corrective action (see DBAL.6) shall be required at the contractor s expense. DBAL.4.2 Quality Control (QC) Measurements Measure dowel bar alignment and location as follows for Quality Control (QC): 1. Measure the alignment and location for every 10th joint. 2. If ALL misalignments, mislocations, AND Joint Scores (JSs) are within the Accept limits in DBAL.2 and DBAL.3, use the data to refine the paving process and reduce/eliminate misalignments and mislocations. 3. If ANY misalignments, mislocations, OR Joint Scores (JSs) exceed a QA Trigger limit in DBAL.2 and DBAL.3, perform Quality Assurance (QA) measurements per the direction of the Engineer (see DBAL.4.3). 4. The Engineer shall consider the dowel alignment process to be under satisfactory control when ALL misalignments, mislocations, AND JSs are within the Accept limits for two consecutive production days or over a paving distance specified by the Engineer prior to construction. Upon establishing satisfactory control, measure and evaluate every 20th joint. If the alignment or location of any individual dowel bar or the Joint Score (JS) of the joint exceed the QA Trigger limits in DBAL.2 and DBAL.3, the frequency of testing will resume to every 10th joint until control is re-established. DBAL.4.3 Quality Assurance (QA) Measurements Measure dowel bar alignment and location and take corrective actions as follows for Quality Assurance (QA): 1. If the alignment or location of any individual dowel bar or the Joint Score (JS) of a joint is found to exceed a QA Trigger limit per the tolerances in DBAL.2 and DBAL.3, measure the joints on each side of the QA Trigger exceeding dowel bar or joint that exceeds the QA Trigger, as directed by the Engineer, until five (5) consecutive joints are found within the Accept limits. In exceptional cases with apparent systematic misalignment and/or mislocation, the Engineer may opt to measure and assess all dowels/joints from a single day s production. January 7, 2013 Page 7 of 12

2. Take corrective actions per DBAL.6 on any individual dowel bar that exceeds a Requires Action limit per the tolerances in DBAL.2 and DBAL.3. 3. Take corrective actions per DBAL.6 if successive joints having Joint Scores (JSs) greater than the JST indicate potential to lock up a section of pavement longer than the maximum allowable locked length (MALL) (see DBAL.3). DBAL.4.4 Dowel Location Measurement Equipment Provide an operator who is properly trained to operate the measurement device. Measure the dowel location using a device with the following capabilities and degree of accuracy: 1. An operating temperature range within the range of ambient temperatures anticipated at the time of testing. 2. Minimum measurement range: a. Dowel bar depth 11 measurement as necessary to accurately locate dowel bars for the pavement thickness b. Horizontal and vertical misalignment 12 to at least 1.5 in. (38 mm) c. Horizontal translation to at least the Requires Action level defined in DBAL.3 3. Maximum measurement tolerances: a. Repeatability: 0.125 in. (3 mm) b. Horizontal and vertical alignment: ±0.25 in. (±6 mm) c. Horizontal translation: ±0.5 in. (±12 mm) d. Longitudinal translation: ±0.5 in. (±12 mm) e. Depth (cover): ±0.25 in. (±6 mm) Calibrate the measurement device per the recommendations of the device manufacturer for the project conditions (including dowel bar size, material, and spacing; and testing environment), and provide calibration documentation to the Engineer prior to construction. DBAL.4.4.1 Measurement Equipment and Interference Prior to paving, review the measurement equipment applicability for the project conditions with the Engineer, including: ambient moisture conditions, dowel material, metallic concrete aggregate and potential contributors to magnetic interference (presence of tiebars, reinforcing steel or other embedded or underlying steel items that may affect measurement accuracy). Establish how the measurement device can meet the project conditions. 11 COMMENT: A device s depth measurement capability becomes critical for thicker pavements. For instance, measurement equipment with an upper limit of 7.5 in. (190 mm) for depth measurement may not be sufficient for testing 13 in. (330 mm) pavements. In that case, to meet a minimum cover of 3 in. (75 mm), a depth at which dowel bars are considered acceptable, a device must capable of measuring to as deep as 9.25 in. (235 mm) (FHWA 2007). 12 COMMENT: Skewed joints need special consideration for testing. (FHWA 2005b). January 7, 2013 Page 8 of 12

To account for magnetic interference from embedded tiebars, exclude from Joint Score (JS) calculation any dowel bar(s) closer than 12 in. (300 mm) in any direction 13 to tiebars in the longitudinal joint(s) due to magnetic interference. At the Engineer s discretion, establish the location of excluded dowels by another equivalent non-destructive method or by probing. DBAL.4.5 Reporting Prepare and submit to the Engineer no later than 48 hours after each day s production a report including at least the following: 1. General Details: Contract number, placement date, highway number or countryroute-section, direction of traffic, scan date, contractor, and name of operator. 2. Measuring Device Data and Printouts: Provide all data in the manufacturer s native file format, including all calibration files. Provide the standard report generated from the on-board printer of the imaging technology used for every dowel and joint measured. 3. Dowel Details: For every dowel measured, provide the joint ID number, lane number and station, dowel bar number or x-location, direction of testing and reference joint location/edge location, dowel misalignment (e.g., horizontal skew, vertical tilt, and single dowel misalignment [SDM]) and dowel mislocation (e.g., longitudinal translation, vertical translation, and horizontal translation). 4. Misalignment and Mislocation Identification: Identify each dowel bar with a misalignment or mislocation greater than the individual dowel bar QA trigger for each alignment and location parameter listed in DBAL.3 and DBAL.4. 5. Joint Score Details: Provide the joint ID number, lane number, station, and calculated Joint Score (JS) for every joint measured. 6. Locked Joint Identification: Identify and highlight in red each joint with a Joint Score (JS) greater than the JST. All printouts and reports submitted by the Contractor shall remain the property of the Owner. DBAL.5 EXCLUSIONS Exclude the following from dowel location and alignment measurement: Transverse construction joints (headers). Dowels within 24 in. (609 mm) of metallic manholes, inlets and other in-pavement utility castings or other reinforced objects. 13 COMMENT: Interference from nearby tiebars and other embedded metal objects is a known issue with MIT-Scan and MIT-Scan II. January 7, 2013 Page 9 of 12

DBAL.6 CORRECTIVE ACTION Submit a proposal for corrective action to the Engineer for each case of actionable (.e.g, exceeds a Requires Action limit) single dowel misalignment, single dowel mislocation, and/or joint scores identified by quality control or quality assurance testing. Do not proceed with corrective action until the Engineer approves the proposed method of correction. As a minimum, the corrective action proposal shall include the following: 1. Actionable dowel misalignment and mislocation identification information. 2. Locked joint identification information. 3. Proposed method of remediation for each unique identified case, including supporting documentation of the effectiveness of the means of proposed remediation. Consider the following corrective actions for actionable individual dowel bars: For misalignment due to horizontal skew or vertical tilt, assess the potential of the dowel bar to cause slab or joint damage, or locking of the joint by the joint score : o Where JS < JST and an individual misaligned dowel is not likely to cause pavement damage or complete joint restrain, do nothing. o Saw through actionable dowel bar to reduce opening/closing restraint. o Saw through actionable dowel bar(s) to reduce restraint and retrofit dowel bar(s) at appropriate location(s). o Place full-depth repair to remove joint with actionable dowel bar(s). o Replace full slabs to remove joint with actionable dowel bar(s). For mislocation due to longitudinal translation of individual dowel bar(s), assess the potential of the dowel bar to cause slab or joint damage, or locking of the joint by the joint score: o Where JS < JST and an individual misaligned dowel is not likely to cause pavement damage or complete joint restrain, do nothing. o Retrofit dowel bars using DBR between 14 or over/through actionable dowel bar(s). o Place full-depth repair to remove joint with actionable dowel bar(s). o Replace full slabs to remove joint with actionable dowel bar(s). For mislocation due to longitudinal translation caused by an errant saw cut: o Do nothing if the damage potential is minimal. o If the joint has not activated, saw new joint at the proper location and epoxy and/or cross-stitch the mislocated saw cut. o If the joint has activated, retrofit dowel bars using DBR between 8 or over/through actionable dowel bar(s). For mislocation due to vertical translation toward pavement surface: o Do nothing if the damage potential is minimal. o Saw through actionable dowel bar(s) to remove shearing restraint. o Retrofit dowel bars using DBR through actionable dowel bar(s). o Place full-depth repair to remove joint with actionable dowel bar(s). 14 COMMENT: When dowel spacing becomes too close, a risk is created for a horizontal crack at the depth of the dowel bars. Thus, if dowel bar retrofits are to be constructed between the existing dowel bars, it is preferred to only provide the minimum necessary number of dowel bar retrofits. January 7, 2013 Page 10 of 12

o Replace full slabs to remove joint with actionable dowel bar(s). For mislocation due to vertical translation toward pavement base: o Do nothing if the damage potential is minimal. o Saw through actionable dowel bar to remove potential for shear failure. o Place full-depth repair to remove joint with actionable dowel bar(s). o Replace full slabs to remove joint with actionable dowel bar(s). For mislocation due to horizontal translation: o Do nothing if the damage potential is minimal. o Retrofit dowel bars using DBR where dowel bar(s) are missing. o Place full-depth repair to remove joint with actionable dowel bar(s). o Replace full slabs to remove joint with actionable dowel bar(s). Consider the following corrective actions for consecutive joints with actionable Joint Scores (JSs): Saw through actionable dowel bar(s) to remove opening/closing restraint and retrofit dowel bars using DBR in enough joints to meet the requirements of the maximum allowable locked length (MALL). Place full-depth repair(s) to remove joint(s) with actionable dowel bar(s) and to meet the requirements of the maximum allowable locked length (MALL). Replace full slabs to remove joint(s) with actionable dowel bar(s) and to meet the requirements of the maximum allowable locked length (MALL). January 7, 2013 Page 11 of 12

Appendix A. Summary of Dowel Bar Alignment and Location Tolerances Table A.1 provides a summary of the dowel bar alignment and location tolerances presented in this guide specification. Table A.1. Summary of Dowel Bar Alignment and Location Tolerances Alignment Tolerances QA Trigger Requires Action Dowel Horizontal Skew 0.6 in. (15 mm) Dowel Vertical Tilt 0.6 in. (15 mm) Dowel SDM > 1.5 in. (38 mm) Joint JS > JST > JST for all dowels over MALL Location Tolerances QA Trigger Requires Action Dowel Longitudinal Translation > 2 in. (50 mm) > 5 in. (125 mm) Dowel Vertical Translation > 1 in. (25 mm) Vertical Concrete Cover Over/Under Dowel < 2.5 in. (64 mm) Dowel Depth Below Saw Cut < 0.5 in. (12 mm) < 0.25 in. (6 mm) Dowel Horizontal Translation > 2 in. (50 mm) > 3 in. (75 mm) January 7, 2013 Page 12 of 12