PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION!

Similar documents
1. All electrical switches and outlets used shall be equal to Hubbell heavy duty, specification grade or equivalent quality.

SECTION LOW-VOLTAGE ELECT. DIST. DESIGN AND CONSTRUCTION STANDARDS _ February 2015 PART I: GENERAL

Michigan State University Construction Standards SWITCHBOARDS, PANELBOARDS, AND CONTROL CENTERS PAGE

SECTION PANELBOARDS

B. Manufacturers: Square-D, G.E. or Westinghosue.

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer

SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

SECTION SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY

2014 NEC Changes Part 1

ELECTRICAL GENERAL DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL Electrical/Telecommunications Design

2. Electrical rooms shall be centrally located and stacked so that feeder conduits and bus duct are run as straight and short as possible.

03/7/12 Issuance UTD Section Page 1 of 5 Electrical General

Electrical Wiring: Commercial, Seventh Canadian Edition

SECTION DISTRIBUTION SWITCHBOARDS

SECTION DISTRIBUTION SWITCHBOARDS

Design Approaches for Hospital Distribution Systems With Considerations for Future Expansion, Operator Safety, and Cost

AN EXAMPLE OF A STANDARD ARC FLASH PPE LABELING STRATEGY

Quality Control Checklist - Design Drawings

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 9/8/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

2018 Consultant s Handbook Division 26 Electrical ARC Flash Hazard Analysis

AN EXAMPLE OF A STANDARD ARC FLASH PPE LABELING STRATEGY

First Draft Language

Brown University Revised 2/1/2006 Facilities Design & Construction Requirements SECTION 16461C - DRY TYPE TRANSFORMERS

Chapter 1. Applied Grounding and Bonding. Applied Grounding and Bonding 9/18/2011. Introduction. Introduction. Paul Dobrowsky Member NEC Panel 5

4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118

Short Circuit Current Calculations

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.

3Ø Short-Circuit Calculations

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 2/9/11 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

Article 225: Outside Branch Circuits And Feeders

LIFE LINE PRODUCT SPECIFICATION FOR A 1 TO 3 KVA, SINGLE PHASE, POWER DISTRIBUTION SYSTEM WITH REGULATION AND CONDITIONING

SECTION COMMUNICATIONS ELECTRICAL POWER DISTRIBUTION

ECET 211 Electric Machines & Controls Lecture 3-1 (Part 1 of 2) Motor Transformers and Distribution Systems

BGE STRATEGIC CUSTOMER ENGINEERING

POWER SERVICE DETAILS

7. INSPECTION AND TEST PROCEDURES

SECTION TRANSFORMERS

2.2 American National Standards Institute Corporation and its applicable standards C39.1, C80.1, C89, C84.1.

SECTION POWER SYSTEMS STUDIES

ADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

a) Determine the smallest, standard-sized circuit breaker that should be used to protect this branch circuit.

UBC Technical Guidelines Section Edition Medium-Voltage Transformers Page 1 of 5

CONSULTANT PROCEDURES & DESIGN GUIDELINES Liquid-Filled Utility Transformers UNIVERSITY OF MISSOURI

National Marine Manufacturers Association Compliance Specialist Examination A.C. Electrical (2018 Model Year) ABYC E-11 Supplement 56

UNIVERSITY OF MISSOURI Liquid-Filled Utility Transformers 2016 Q1

GE Ventilated Dry-Type Transformers. Secondary Substation Transformers - 5 and 15kV Class

SUGGESTED SPECIFICATION for Series 300 Automatic Transfer Switches

POWER DELEGATOR SERIES 7200A POWER DISTRIBUTION UNIT WITH POWER CONDITIONING GENERAL SPECIFICATIONS

DESIGN CHECKLIST INTRODUCTION

Power Processor - Series 700F 10KVA to 150KVA

Note: The let-through of the protective device must be equal to or less than the short-circuit current rating of the component being protected.

Wisconsin Contractors Institute Continuing Education

SECTION AUTOMATIC TRANSFER SWITCH

Technical T TECHNICAL. C o n t e n t s SPEEDFAX TM 2017

INSTALLATION, OPERATION AND MAINTENANCE GUIDE

Education & Training

Liebert Datawave GUIDE SPECIFICATIONS kva Magnetic Synthesizer Power Conditioning System

2015 NFPA 70E. SESHA 2015 ARIZONA MINI CONFERENCE December 10, 2015 Intel Corporation

SINGLE PHASE BUCK & BOOST TRANSFORMERS INSTRUCTION MANUAL

Liebert Datawave. GUIDE SPECIFICATIONS kva Magnetic Synthesizer Power Conditioning System 1.0 GENERAL

and cured to reduce hot spots and seal out moisture. The assembly shall be installed on vibration-absorbing pads.

TABLE OF CONTENT

SECTION 5 TRANSFORMERS

SAFETY AND HEALTH STANDARD ELECTRICAL GROUNDING Effective Date: 07/17/10 Standard: Document Number: KUCSH0039 Rev: 4

Arc Flash Analysis and Documentation SOP

WAVEFORM CORRECTOR (WAVEFORM CORRECTORS) REPLACES SURGE PROTECTION DEVICES (SPD) PREVIOUSLY KNOWN AS (TVSS)

Arc Flash Analysis Training

ARC FLASH PPE GUIDELINES FOR INDUSTRIAL POWER SYSTEMS

A. Product Data: For each electrical identification product indicated.

SOLAR PV MICROINVERTER/ACM STANDARD PLAN - COMPREHENSIVE Microinverter and ACM Systems for One- and Two- Family Dwellings

Residential Construction Checklist Single and Two Family Construction

INTELLIMETER REGISTER

NEC 2014 Code Changes

Capstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:

SECTION LOW VOLTAGE ACTIVE HARMONIC FILTER SYSTEM NEMA 1 ENCLOSED

SPECIFICATION FOR HORIZONTAL AIRFLOW OUTDOOR RESISTIVE LOAD BANK

Protection of Electrical Networks. Christophe Prévé

NORTHWEST FLORIDA STATE COLLEGE MONUMENT SIGNS WITH LED DISPLAYS

PIRANHA 3 (3-phase, Power Conditioning Voltage Regulator)

Electrical IP Red Seal Practice Exam

Paul Dobrowsky Innovative Technology Services

2/15/2015. Current will always try to return to its source. In order for there to be current, there must be a complete circuit

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Low Voltage Power Factor Correction Equipment Specifications Automatic, Automatic Detuned, Automatic Tuned

WESTERN UNDERGROUND COMMITTEE GUIDE 2.6 (2.6/00/0868)

PRODUCT SPECIFICATION FOR A 15 AND 75 kva, THREE PHASE MODULAR POWER DISTRIBUTION SYSTEM WITH REGULATION AND CONDITIONING (Varian)

SECTION EQUIPMENT WIRING

Cutler-Hammer January 1999

Electrical Measurement Safety. Sponsored By:

American Electrical Institute

Description & Applications Questions & Answers Selection Charts Single Phase Selection Charts Three Phase...

SECTION WIREWAYS FOR RADIOLOGY EQUIPMENT

University of Central Florida Main Campus. Electric. Service and Meter Installations Requirements. Issued January 26 th, 2017.

Section 16621A - AUTOMATIC TRANSFER SWITCH. Part 1 General

The NOVA Recloser shall be designed and tested in accordance with the following standards as applicable:

Dry Type Transformers Full Line Catalog. jeffersonelectric.com

MGM Transformer. Vacuum Pressure Impregnated (VPI) Dry-Type Substation Transformer Specification Guide

Upgrading Your Electrical Distribution System To Resistance Grounding

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

Distribution/Substation Transformer

Transcription:

PREFACE This publication has been prepared as a guide for Architectural and Engineering (A&E) firms in the preparation of documents for the design and construction of new structures and the remodeling of existing structure for Indiana University. Items pertinent to requirements of Indiana University are contained herein. The specification section numbers referenced by these standards are to help the A&E firms identify where IU Engineering standards are to be applied. These specification section numbers are based upon CSI standards and may not correspond to a particular A&E firm s standard specification section numbering scheme. Compliance with codes and OSHA regulations are minimum requirements. When requirements of Federal and/or State Codes are at variance with the contents of this publication, the most demanding requirements shall be observed. ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION! MATERIAL CONTAINED HEREIN SHALL NOT BE COPIED VERBATIM IN SPECIFICATIONS OR IN NOTES ON THE DRAWINGS EXCEPT WHEN INSTRUCTIONS ARE GIVEN TO COPY CERTAIN ARTICLES OR PARAGRAPHS. ********************************************************** Changing technology and changes in State or University policies will require continuing revisions of these standards. Revisions will be maintained online at www.indiana.edu/~uao. Architects and Engineers doing work for the University are expected to ensure that they are working with the latest revision of the standards. Throughout these standards, cross-references have been made frequently to emphasize the importance of coordination of all parts of the contract documents for a project. Because of the requirement for complete coordination, the holder of this document is cautioned to furnish complete standards to consultants or to ascertain that consultants have copies of the referenced sections and paragraphs affecting the consultant s work. If questions arise concerning instructions contained herein, please request clarification from Indiana University, Department of Engineering Services, (812) 856-7055. Preface to IU Electrical Engineering Standards Page 1 of 1

26 20 00 Low-Voltage Electrical Distribution Also Included: 26 11 16 - Secondary Unit Substations 26 22 13 - Low Voltage Distribution Transformers 26 24 13 - Switchboards 26 24 16 - Panelboards 26 25 00 - Enclosed Bus Assemblies 26 28 16 - Enclosed Switches and Circuit Breakers A. General 1. The University does not accept Series-Rated equipment for power distribution switchboards, distribution panels and branch circuit panelboards. Equipment must be fully-rated to minimum short circuit ratings specified. 2. Provide electrical metering where directed by Engineering Service or CFS. Electric meter shall be Schneider Electric PowerLogic ION 7650, and shall be installed in a separate, arc flash resistant compartment. Electric meter shall have the following features and accessories. a. Meter shall have minimum 10Base-T and/or 10Base-FX Ethernet option as specified by Engineering Services or CFS. b. Provide ANSI Accuracy Class 0.3 current transformers. CT range shall be selected appropriately for the load and shall not exceed the load by more than 50%. c. Provide CT shorting block and/or test switches. d. Provide voltage transformers as necessary. e. Meters shall have fuse protection for voltage and power supply inputs. f. For each meter, supply a data jack in the metering enclosure, connected to the campus Ethernet. 3. Lock Out TagOut (LOTO) a. Refer to latest version of Indiana University Building Design Standards, Section 01 92 14 for LOTO procedures. This standard can be found on IU University Architects Office (UAO) web site; http://www.iu.edu/~vpcpf/consultant-contractor/standards/building.shtm 4. Arc Flash a. Power distribution equipment shall be labeled for Arc Flash Hazards as required by NFPA 70E and NFPA 70. 26 20 00 Low-Voltage Electrical Distribution Page 1 of 6

b. The University s goal is to have, and the Consultant should strive to design, a system such that no more than PPE Class 1 is required for maintenance of any electrical equipment with the exception that in main electrical rooms, PPE Class 3 is acceptable. c. When designing electrical distribution equipment (main unit substations and main switchgear), the use of a coordinated system to temporarly reduce arc flash potential while the equipment is being maintained is encouraged. The arc flash reduction system is to be activated by manually operating switches or keypads located at the distribution equipment or at individual power circuit breakers. d. Electrical Contractor shall be responsible for supplying a complete arc flash, short circuit and time-current coordination study for the entire electric distribution system from the building service entrance to branch circuit panelboards and for applying appropriate labels to all equipment. 5. For buildings greater than approximately 10,000 square feet per floor, consider the use of multiple power distribution risers to limit the number of branch circuits over 100 feet long. If the floor plan is such that two telecommunications risers would be required to limit any run to less than 300 feet, then the use of multiple power distribution risers in separate closets shall also be provided. 6. There shall be no foreign systems installed in low voltage electrical rooms unless they are associated with the room function. B. Unit Substations (Section 26 11 16) 1. The secondary section of unit substations shall utilize copper bussing and fused switches, or air circuit breaker overcurrent devices like Type AKR from General Electric Co. Device hoists for drawout type devices shall be unit mounted. In some instances molded case breakers may be acceptable; coordinate with Engineering Services or CFS. 2. Unless directed otherwise the outgoing equipment shall consist of a single main overcurrent device with separate feeder devices. Metering and ground fault protective schemes shall be as detailed below in Power Distribution Switchboards section. 3. Air circuit breakers shall be drawout type with stored energy, manual operation. 4. Circuit breaker type overcurrent devices shall utilize solid state trip units. 5. The interrupting rating for overcurrent devices shall be specified by the consulting engineer. Engineering Services or CFS will provide the available fault current on the primary distribution system at a point nearest to the building when structure is served by the campus distribution system. 26 20 00 Low-Voltage Electrical Distribution Page 2 of 6

C. Power Distribution Switchboards (Section 26 24 13) 1. Power Distribution Switchboards (PDS) shall be specified with copper bus and shall have bus extensions provided at ends where future sections can be added. 2. On 277/480 volt systems that require the installation of Ground Fault Protection (GFP) both the main overcurrent device and the feeder overcurrent devices shall have GFP. The GFP system shall utilize a zone interlock technique. 3. The PDS shall have a copper equipment ground bus installed for its entire length. 4. On systems where the grounded circuit (neutral) conductor is distributed (120/208 & most 277/480) a 100% capacity neutral bus shall be provided. On systems where the grounded circuit (neutral) conductor is not distributed (480 and 277/480 serving only 3 phase loads) lugs for proper bonding of the equipment grounding conductor shall be provided. 5. Where applicable, the PDS shall be U.L. listed suitable for use as service entrance equipment. 6. A minimum of 4 spare overcurrent devices shall be provided with space for an additional 4 devices. 7. The minimum interrupting rating of overcurrent devices and bus bar bracing of the PDS shall be determined by calculations made by the consulting engineer. These ratings shall be specified in the construction documents. 8. Care should be used in locating the PDS. At minimum the location should meet requirements of NEC Table 110.26(A)(1) for a Type 2 condition. The exclusively dedicated space requirements of NEC Article 110.26(F) shall be strictly enforced. Additional space for maintenance, future extensions, and possible replacement should be factored into the location selected. The consultant shall work with the Engineering Services or CFS in locating this equipment. 9. Preferred equipment suppliers for Power Distribution Switchboards 26 20 00 Low-Voltage Electrical Distribution Page 3 of 6

D. Motor And Circuit Disconnects (Section 26 28 16) 1. Motor and circuit disconnects shall be provided at all motor and equipment locations. Utilizing the lock-out feature on remotely located motor controllers is not acceptable as a disconnecting means. The University has dedicated maintenance crews who do such things as oil and grease bearings and replace belts on equipment. These personnel are not expected to be familiar with the location of starting equipment for the device being serviced. A non-fusible disconnect shall be provided on or adjacent to equipment for maintenance personnel use. 2. Heavy-duty type disconnects shall be specified with NEMA enclosure suitable for the environment to be encountered. 3. Preferred manufacturers for motor and circuit disconnects E. Dry Type Transformers (Section 26 22 13) 1. Dry type transformers shall be specified with temperature rating of 150 degree C rise above a 40 degree C ambient. Units 30 KVA and larger shall be floor mounted only. Taps to adjust the secondary voltage, 2 2.5% above and 2 2.5% below nominal shall be provided. 2. Where variable frequency drives 100HP and larger are used, a drive isolation transformer shall be installed ahead of each unit. These transformers shall be specifically designed for the application and shall include symmetrically placed taps and added coil bracing. Locate the transformers adjacent to the drive. 3. Shielded isolation transformers shall be utilized where load requires such enhanced protection. These units shall have copper shielding with appropriate connections for grounding the shield. 4. Secondary feeder conductors from transformers shall have overcurrent protection installed within 10 feet of transformer. 5. Care shall be used in locating dry type transformers. Adequate clearances around units shall be provided and minimum clearances from walls and etc. should be specified in the contract documents. Consideration should be given for how the units would be replaced in event of failure. Where units are installed adjacent to offices, library areas, or other noise sensitive locations, consideration shall be given to specifying quiet rated transformers. An excellent reference standard for use by the consulting engineer is the ANSI C57.X series. 26 20 00 Low-Voltage Electrical Distribution Page 4 of 6

6. Transformers shall meet NEMA TP-1 efficiency requirements. 7. Preferred manufacturers for dry type transformers F. Feeder And Plug-In Busway (Section 26 25 00) 1. Bus material shall be copper with full capacity neutral, separate equipment ground bus, and standard impedance. Enclosure shall be non-ventilated type. Splice plates and all component contacts shall be silver plated. 2. Floor Penetrations. a. Where busways penetrate walls or floors specify an integral fire stop as a part of the system. b. NEC required curbs shall be cast-in-place concrete that are formed as an integral part of the floor. 3. Plug-in units shall be fusible type. 4. Preferred manufacturers of bus ways G. Distribution Panelboards (Section 26 24 16) 1. Distribution panelboards shall have copper bus with full capacity neutral and equipment ground bus. Over current devices shall be fusible switch type wherever possible. Circuit breaker style distribution panelboards shall have a minimum AIC rating of 35,000 amps symmetrical. If a distribution panel board must be located in an area of a building which may be accessed by the general public it shall have a full cover door over all overcurrent devices. Exposed switch or circuit breaker handles in areas accessible to the public are not allowed. 2. Preferred manufacturers for distribution panelboards 26 20 00 Low-Voltage Electrical Distribution Page 5 of 6

H. Branch Circuit Panelboards (Section 26 24 16) 1. Branch circuit panelboards shall have copper bus, full capacity neutral, and equipment ground bus. Circuit breakers shall be bolt-on type with a minimum interrupting rating of 22,000 amps symmetrical at 240 volt and 14,000 amps symmetrical at 480 volt. Specify a panelboard with a concealed trim and recessed lock. Where isolated ground devices are connected to panel specify a separate insulated equipment ground bus in panel. Provide minimum 20% spare capacity in panelboards. 2. Specify multi-pole circuit breakers that have one (1) operating handle. Using circuit breakers with handle ties is not acceptable. 3. Where panelboards are flush mounted specify a minimum of (3) 1 spare conduits to be installed from panelboard to ceiling space for future use. 4. In new buildings, panelboards shall be labeled as Panel - floor/source/voltage/riser/panel according to the following code. a. floor = building floor per architectural drawings b. source = N for normal, E for emergency c. voltage = H for 480V or 480/277V, L for 120/208V d. riser = number risers consecutively beginning with 1 e. panel = number panels by floor beginning with 1 5. In existing buildings, match existing panel nomenclature. 6. Preferred manufacturers for branch circuit panelboards END OF 26 20 00 26 20 00 Low-Voltage Electrical Distribution Page 6 of 6