LUSAIL DEVELOPMENT. Utility Application Procedures for District Cooling, Gas and Pneumatic/Traditional Waste Management

Similar documents
LUSAIL DEVELOPMENT UTILITY APPLICATION PROCEDURES FOR PNEUMATIC/TRADITIONAL WASTE MANAGEMENT DOCUMENT NO.: LUS-CPALL-MAQ-PRC-UT-20561

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

SECTION SUBMITTAL PROCEDURES

SECTION III SUBMITTALS AND APPROVALS

BHARAT HEAVY ELECTRICALS LIMITED

INSPECTION AND TEST PLAN

SECTION SUBMITTAL PROCEDURES

Section Meetings Section Material and Equipment. None Required

East Central College

Inspection and Test Plan for Water Tube Boiler

APPLICATION FORM FOR INFRASTRUCTURE NOC

Heat Exchanger Construction Checklist

SECTION SUBMITTAL PROCEDURES

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

Section XV - PER, Design, and Construction Submittal Requirements

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

This specification describes the general requirements for Engineering Services provided to Vale.

Working Drawing Manual

00-General Drawings. Doc. no.: NA-00-STS002

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

FIT-OUT PERMIT REQUEST (GENERAL WORKS)

Working Drawing Procedure

Facility Services Subgroup Preface for Divisions 21` through 28

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

REMARKS: The A.F.F. dimension noted on the drawings to the bottom of the grid is 15 0, this dimension should be 16 0.

PRACTICAL UNDERSTANDING AND INTERPRETATION OF TECHNICAL STANDARD TS30a WELDING SPECIFICATION

SECTION PROJECT MANAGEMENT AND COORDINATION

STANDARD SPECIFICATION FOR CONTRACTOR'S DRAWING AND DATA TRANSMITTAL CONTRACTOR S DRAWING AND DATA TRANSMITTAL STANDARD SPECIFICATION FOR

SUBMITTAL TRANSMITTAL OCPS CLAY SPRINGS ES REVIEWED HVAC WATER TREATMENT CHILLED WATER PIPING TR SUBMITTAL NUMBER: SUBMITTAL DETAILS:

SCOPE: This procedure is applicable to construction projects and is an alternate method of submitting documentation for plan review and permitting.

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION ADMINISTRATIVE REQUIREMENTS

SECTION PROJECT COORDINATION VIA BIM

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

Mailing Address: Fax number: City: State: Zip: Property Owner: City: State: Zip: City: State: Zip:

SECTION 2 GENERAL REQUIREMENTS

Design Deliverables. Summary. A. Expectations for Design Deliverables:

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST

Spec Section: , Complete Elec, Comm, and Fire Alarm , Complete Elec, Comm, and Fire Alarm Data Sheets RAN/GCAN

PROCEDURE FOR PROCESSING WORKING DRAWINGS

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

835 Gil Harbin Industrial Blvd Valdosta, GA 31601

DOCUMENT MINIMUM CONSTRUCTION DRAWING REQUIREMENTS FOR PRELIMINARY REVIEW/APPROVAL 1.2. GALVESTON COUNTY CONSOLIDATED DRAINAGE DISTRICT (GCCDD)

City of Thousand Oaks

Anticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days.

City of Lompoc Building & Safety Services Section 100 Civic Center Plaza Lompoc, CA Phone: Fax:

SUBMITTAL REVIEW COVERSHEET

BAE Systems Combat Vehicles Supplier Quality Assurance AS9102 Requirement

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document.

ADDENDUM #2 September 12, 2018

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

Annexure - V. Specifications, Typical Drawing & Data Sheet for Split TEE (Hot Tapping Material)

DOCUMENT SUBMITTAL REQUIREMENTS FOR A NEW MULTI-FAMILY DWELLING

Certificate by the Architect: Certified that no addition and deletion has been made to the tender documents downloaded from the IIT Madras web site.

Spec Section: Concrete Mix Design psi - Review Form Concrete Mix Design psi Data Sheets GCAN

PITKIN COUNTY STANDARDS for ELECTRONIC DRAWINGS and DOCUMENTS SUBMISSION

U of I Facilities Standards Updates for 2017

CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal

Waste Treatment Plant Project Supply Chain Collaboration Event. QVD How To Get Started

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

SUBMITTAL LETTER Capital Renewal Scoates Hall, Texas A &M University, College Station, TX TAMUS Project

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

APPLICATION FOR COMMERCIAL CONSTRUCTION FIRE AND LIFE SAFETY PLAN REVIEW PROJECT INFORMATION: Project phone: Project Address: City: State: Zip:

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

Commercial Infill Project Guide

TYPE OF PIPING PRESSURE TESTING. For large diameter piping hand wipe/ sweep should be applied as much as possible (inspection to be recorded).

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

Inspection and Test Plan for Battery Charger

Residential Construction Checklist Single and Two Family Construction

SUBMITTAL REVIEW B Passenger Elevators Shop Drawings GCAN

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST

SUBMITTAL REVIEW Steel Reinforcement - Slab and Masonry Shop Drawings GCAN. Notes: 1. See comments on submittal.

MESP TECHNICAL SPECIFICATION FOR AN ESSENTIAL SERVICES SUPPLY STEP UP TRANSFORMER

ENGINEERING DRAWINGS MANAGEMENT POLICY (IFC/AS BUILTS)

KC Water Rules and Regulations For Water Main Extensions and Relocations

CLARK COUNTY FIRE CODE AMENDMENTS

APPLICATION FOR CERTIFICATE OF APPROPRIATENESS IN THE HISTORIC DESIGN REVIEW DISTRICT

REVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty

MEC-QW-E-2002 Senior QA/QC Welding Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

BRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006

Connection Impact Assessment Application Form

List of Figures. List of Forms

TECHNICAL SPECIFICATION FOR LEVEL CONTROL VALVE HANDLING WATER

LETTER OF TRANSMITTAL

SUBMITTAL REVIEW Food Service Equipment Data Sheets GCAN. Notes: 1. See D-C Design comments. Submittal: No. 035.

(R) Aerospace First Article Inspection Requirement FOREWORD

SITE PLAN Application Packet (Required For All Non-Residential Development Projects)

Technical Specifications: Supply of Seamless Grade TP304L Pipe and Grade WP304L Pipework Fittings to the ITER Organization (IO).

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

1.0 INTRODUCTION DEFINITIONS DRAWING CONTROL PREPARATION OF SPECIFICATIONS AND DATASHEETS... 5

Transcription:

Utility Application Procedures for District Cooling, Gas and Pneumatic/Traditional Waste Management Document No.: LUS-CPALL-MAQ-PRC-UT-40040 1 P a g e

CONTENTS 1. INTRODUCTION 3 1.1 Definitions 3 1.2 General 3 1.3 Nomenclature 6 2. REGISTRATION AND REQUEST FOR INFORMATION 8 3. DISTRICT COOLING ENERGY TRANSFER STATION (ETS) 9 3.1 ETS Preliminary Design 9 3.2 ETS Detailed Design 9 3.3 ETS Material Submittals 10 3.4 ETS Method Statement 10 3.5 ETS Installation and Inspection 11 4. GAS DISTRIBUTION SYSTEM 12 4.1 Gas Preliminary Design Stage 12 4.2 Gas Detailed Design Stage 12 4.3 Gas Material Submittals 13 4.4 Gas Method Statement 13 4.5 Gas Installation and Inspection 14 5. PNEUMATIC & TRADITIONAL WASTE MANAGEMENT 15 5.1 PWC Preliminary Design Stage 15 5.2 PWC Detailed Design Stage 15 5.3 PWC Material Submittals 16 5.4 PWC Method Statement 16 5.5 PWC Installation and Inspection 16 6. APPENDICES 18 2 P a g e

1. INTRODUCTION 1.1 Definitions Client CAC Marafeq Contractor Customer Building Consultant The Master Developer - Lusail Real Estate Development Company (LREDC) or its appointed representative. City Administration Complex. The Utility Company which provides District Cooling, Gas Supply and Pneumatic/Traditional Waste Management Services. The Organization or its appointed representative, responsible for execution of the works. The Owner of building or his representative. The Consultant employed by the owner and who is responsible for design development. 1.2 General This document describes the procedures for connecting the Customer s building to Marafeq utilities (District Cooling, Gas and Pneumatic/Traditional Waste Management Systems). The Customer to follow the procedures of this documents in compliance with Marafeq guidelines and technical requirements listed in the below table. The full responsibility for the design and installation of each sub-development stays with the Customer for that sub-development. 3 P a g e

Document No. Description District Cooling DC) LUS-CPALL-MAQ-SPE-UT-00001 LUS-CPALL-MAQ-SPE-UT-00002 LUS-CPALL-MAQ-SPE-UT-00003 LUS-CPALL-MAQ-SPE-UT-00004 District Cooling Distribution System Design Guidelines for Pre-insulated Pipes for Mega-development District Cooling Distribution System Design Guidelines for Civil Works for Mega-development District Cooling Distribution System Design Guidelines for Mechanical Works for Mega-development Marafeq s Design Guidelines for the connection of ETS(s) to the District Cooling System Gas (GAS) LUS-CPALL-MAQ-SPE-UT-00005 LUS-CPALL-MAQ-SPE-UT-00006 LUS-CPALL-MAQ-SPE-UT-00007 Gas Distribution System Design Guidelines for Megadevelopment & Sub-development Gas Distribution System Design Guidelines for Pressure Reducing Station (Primary Customer Meter) Gas Distribution System Risk Assessment Guidelines for Mega-development Pneumatic and Traditional Waste Collection LUS-CPALL-MAQ-SPE-UT-00008 Pneumatic and Traditional Waste Management System Design Guidelines for Sub-development The Customer must coordinate with Marafeq in all of the following stages for the three utilities DC, Gas and Pneumatic/Traditional Waste Management. The detailed requirements of each stage are covered in the next pages. Registration and Request for Information Preliminary Design Detailed Design Material Submittals Method Statement Equipment Installation and Inspection A workflow diagram showing the sequence of submittals and stages of Marafeq review is seen below. Communication to CAC at the respective stages of approval as indicated in the work flow diagram shall be followed accordingly. The Customer should submit all submittals in soft copy (CD) unless otherwise specified. Marafeq review status will be issued to the assigned email address provided by the Customer. Marafeq is holding a technical consultation on Sunday. One half hour allocated for each Customer and the Customer shall send a meeting request with the agenda of meeting to customer.service@marafeq.com.qa by latest two working days before holding the meeting. 4 P a g e

5 P a g e

1.3 Nomenclature This document describes the guidelines to the nomenclature to be followed while providing a document number to a document, like Technical Submittals or Inspection Requests that are to be submitted to Marafeq Qatar. The customer has to strictly follow the guidelines as listed out in the table below and described further. Sl. No. Document Number (Nomenclature) Type of Document 1 LUS-MAQ-(CUSTOMER ID)-INR-(UTILITY)-00XX-RevXX Inspection Request 2 LUS-MAQ-(CUSTOMER ID)-SDW-(UTILITY)-00XXRevXX Shop Drawing 3 LUS-MAQ-(CUSTOMER ID)-PDS-(UTILITY)-00XXRevXX Preliminary Design 4 LUS-MAQ-(CUSTOMER ID)-DDS-(UTILITY)-00XXRevXX Detailed Design 6 LUS-MAQ-(CUSTOMER ID)-MTS-(UTILITY)-00XXRevXX Material Submittal 7 LUS-MAQ-(CUSTOMER ID)-MOS-(UTILITY)-00XXRevXX Method Statement 8 LUS-MAQ-(CUSTOMER ID)-SPE-(UTILITY)-00XXRevXX Specifications 9 LUS-MAQ-(CUSTOMER ID)-WPS-(UTILITY)-00XXRevXX Welding Procedure 11 LUS-MAQ-(CUSTOMER ID)-GEN-(UTILITY)-00XXRevXX General (All other submittals like design conformance application etc.) 6 P a g e

The values mentioned within the closed brackets will change according to the customer and the requirement whereas the 00XX represents the number of the document which will start from 0001 and then move on in the ascending order. The revision number (RevXX) has to be maintained depending on how many times the document has been resubmitted. The first submission will always have a revision, Rev00. [For example, if a customer with customer ID MQ100, wants to raise a Welding Inspection Request for DC, for a joint that was rejected once in the first INR, the document number should be as follows: LUS-MAQ-MQ100-INR-DC-0001-Rev01] The customer should also ensure that for each type of submittal the numbering starts from 0001, irrespective of whether 0001 has already been used for another type of submittal. [For example; a customer has to raise his first Inspection Request as LUS-MAQ-MQ100-INR-DC- 0001-Rev00, even if he already has a submittal for Shop Drawing as LUS-MAQ-MQ100-SDW-DC- 0001-Rev00, because they are two separate types of documents.] The customer has to always ensure that when an already commented document is resubmitted, it should contain the same Nomenclature as the original document with the only change being in the revision number. If an already commented document is resubmitted as a new document, with new number, the document will be rejected at that point itself. 7 P a g e

2. REGISTRATION AND REQUEST FOR INFORMATION The Customer should complete the registration form as provided in Appendix (A) with specifying the applicable utility and submit to Marafeq by email. The registration is essential for the Customer to access any further services from Marafeq. For the purpose of design calculations, the Customer may request the allocated utility (District Cooling, Pneumatic Waste Collection and Gas) pipe sizes and estimated load for the building by completing Appendix (B) and submitting to Marafeq Customer Service by email. Marafeq shall provide the required information within five working days from the date of receiving the application. 8 P a g e

3. DISTRICT COOLING ENERGY TRANSFER STATION (ETS) 3.1 ETS Preliminary Design Marafeq review only the ETS room location after receiving the following submittals from the Customer: 1. Application No. 3 as provided in Appendix (C) to be completed by the Customer. 2. Building site plan drawing. 3. Architectural layout drawing showing the ETS room location. 4. ETS design conformance application duly signed and stamped by the Customer. Cooling demand mentioned on the application shall be the basis of Cooling Supply Agreement. Drawings and documents must be submitted in softcopy (CD) both PDF and editable format (AutoCAD, MS Word, Excel, etc.). Marafeq will provide the review status on Preliminary Design submittal within ten working days from the date of receiving the submittal. After final Preliminary Design approval, the Customer should submit for record purposes one hardcopy A1 size for Marafeq s stamp. 3.2 ETS Detailed Design The Customer should submit the ETS submittal for Marafeq s review comprising of following: 1. Application No. 3 as provided in Appendix (C) to be completed by the Customer. 2. ETS room piping and instrumentation diagram. This drawing shall be developed based on Marafeq Design Guideline for ETS connection. 3. DC primary piping layout inside the plot boundary/basement. Piping layout shall show tie-in points with co-ordinates and invert level. 4. Detailed ETS layout and section drawing showing all equipment inside the ETS room. 5. Secondary side chilled water equipment schedule and schematic drawings. (For information only) 6. Compliance statement to Marafeq s guidelines signed and stamped by the Customer. Drawings and documents must be submitted in softcopy (CD) both PDF and editable format. 9 P a g e

Marafeq will provide the review status on Detailed Design submittal within ten working days from the date of receiving the submittal. After final Detailed Design approval, the Customer should submit for record purposes one hardcopy A1 size for Marafeq s stamp. 3.3 ETS Material Submittals In this stage the Customer should submit the following: 1. Application No. 3 as provided in Appendix (C) to be completed by the Customer. 2. Material submittal for the major materials i.e. plate heat exchanger, primary chilled water pipes with the insulation, pressure independent control valve (PICV), isolation valves and PLC. Material submittal should be provided with selection sheets, detailed calculation of equipment, shop drawings and compliance statement. Drawings and documents must be submitted in softcopy (CD) both PDF and editable format. Marafeq will provide the review status on Material Submittals submittal within ten working days from the date of receiving the submittal. After final Material Submittals approval, the Customer should submit for record purposes one hardcopy A1 size for Marafeq s stamp. 3.4 ETS Method Statement In this stage the Customer should submit the following: 1. Application No. 3 as provided in Appendix (C) to be completed by the Customer. 2. External utilities layout showing the interfacing between infrastructure and building services provided with the coordinates and invert levels. 3. Shop drawings duly approved by the Building Consultant in compliance with Detail Design Approval. (For reference and record only) 4. All welding documents: Welding Procedure Specification (WPS), Procedure Qualification Record (PQR), Welder Qualification Test (WQT), welding certificates, weld maps, etc. 5. Method statement for the installation and testing/commissioning of primary side of equipment inside ETS room. 6. Method statement for flushing the primary chilled water pipes. 10 P a g e

Drawings and documents must be submitted in softcopy (CD) both PDF and editable format. Marafeq will provide the review status on Shop Drawings and Method Statement submittal within ten working days from the date of receiving the submittal. After final Shop Drawings and Method Statement approval, the Customer should submit for record purposes one hardcopy A1 size for Marafeq s stamp. 3.5 ETS Installation and Inspection The Customer shall complete the Inspection Request Form as provided in Appendix (F) for every inspection to be made and submit to Marafeq by latest five working days before the inspection date. Three weeks before the pipe installation inside the ETS room is completed, the Customer should request for Marafeq equipment (energy meter, flow meter, temperature transmitters and pressure differential transmitter). The inspection must be verified by the Building Consultant prior to Marafeq s inspection. Marafeq may inspect the installation at any stage but particularly to the following stages. Initial inspection: 1. Major materials delivery inspection. 2. After plate heat exchangers are put in place. 3. Welding of pipes. 4. Radiographic testing for weld joints. Final inspection: 1. Marafeq will conduct a final inspection after equipment, components and piping are installed and connected. A snag list will be issued to the Customer. 2. Pressure test. 3. After flushing is done, cleaning test results are available. 4. Passivation test results are available. 5. The Customer is responsible to maintain chemicals in the pipeline until finally connected to the network. 6. The Customer should submit the following to Marafeq: Signed pressure test documents. Signed flushing documents with satisfactory water analysis report. Installation compliance statements signed by equipment suppliers. As-built drawings. Marafeq will issue an ETS Conformance Certificate after final inspection is satisfied. 11 P a g e

4. GAS DISTRIBUTION SYSTEM 4.1 Gas Preliminary Design Stage Marafeq review only the Pressure Reducing and Metering Station (PRMS) location after receiving the following submittals from the Customer. 1. Application No. 4 as provided in Appendix (D) to be completed by the Customer. 2. Building site plan drawing. 3. Architectural layout drawing showing the PRMS location. 4. PRMS design conformance application duly signed and stamped by the Customer. Gas demand mentioned on the application shall be the basis of Gas Supply Agreement. Drawings and documents must be submitted in softcopy (CD) both PDF and editable format (AutoCAD, MS Word, Excel, etc.). Marafeq will provide the review status on Preliminary Design submittal within ten working days from the date of receiving the submittal. After final Preliminary Design approval, the Customer should submit for record purposes one hardcopy A1 size for Marafeq stamp. 4.2 Gas Detailed Design Stage The Customer should submit the submittal for Marafeq s review comprising of following: 1. Application No. 4 as provided in Appendix (D) to be completed by the Customer. 2. PRMS detail and section drawing showing all components inside the PRMS cabinet includes the cabinet details along with shop drawings. 3. Compliance statement to Marafeq s guidelines signed and stamped by the Customer. 4. Building gas piping details and section drawing showing all components and routing in the building includes details of gas shaft, gas meter room, risers, droppers, pipe in pipe, sleeving, gas leak detection system, supply pressure, air vent, and etc. 5. Specifications for building gas piping system. Drawings and documents must be submitted in softcopy (CD) both PDF and editable format (AutoCAD, MS Word, Excel, etc.). Marafeq will provide the review status on Detailed Design submittal within ten working days from the date of receiving the submittal. 12 P a g e

After final detailed design approval, the Customer should submit for record purposes one hardcopy A1 size for Marafeq stamp. Marafeq will stamp on building gas piping details design drawings and documents (item 4 and 5) for Consultant to submit to Qatar Civil Defense approval. 4.3 Gas Material Submittals In this stage the Customer should submit the following: 1. Application No. 4 as provided in Appendix (D) to be completed by the Customer. 2. Material submittal for PRMS components showing size & material, capacity, pressure rating, standard, manufacturing standard, material mill certificate, material certificates, International Standard Organization (ISO 9000) certificate, manufacturer and country of origin. 3. Material submittal for building gas piping. 4.4 Gas Method Statement In this stage the Customer should submit the following: 1. Application No. 4 as provided in Appendix (D) to be completed by the Customer. 2. External utilities layout drawings showing the interfacing between infrastructure and building services provided with the coordinates and invert levels. 3. Shop drawings duly approved by the Building Consultant in compliance with Detail Design Approval. (For reference and record only) 4. Method statement for the installation, testing, pre-commissioning and commissioning of PRMS. 5. Method statement for the installation, testing, pre-commissioning and commissioning of building gas piping system. 6. All welding documents: Welding Procedure Specification (WPS), Procedure Qualification Record (PQR), Welder Qualification Test (WQT), welders certificate, weld maps, etc. 13 P a g e

4.5 Gas Installation and Inspection The Customer shall complete the Inspection Request Form as provided in Appendix (F) for every inspection to be made and submit to Marafeq by latest five working days before the inspection date. The inspection must be verified by the Building Consultant prior to Marafeq s inspection. Marafeq may inspect the installation at any stage but particularly to the following stages. Initial inspection: A. Material delivery inspection based on the approved materials submittal. B. All welding documents: Welding Procedure Specification (WPS), Procedure Qualification Record (PQR), Welder Qualification Test (WQT), welders certificate, weld maps, etc. C. Relevant Non Destructive Test, e.g. Radiographic testing, Dye Penetrant Test, Magnetic Particles Test for weld joints. D. Test package documents, then shall conduct Pneumatic Pressure Test on PRMS pipe spools and witness by MQ. E. After PRMS cabinet is put in place (installed at site). F. After service line piping and building piping are installed but before piping is connected to the PRMS. Final inspection: 1. Marafeq will conduct a final inspection after equipment components and piping are installed and connected. A snag list will be issued to the Customer. 2. The Customer shall conduct Site Acceptance Test for operational of the PRMS equipment and system witness by Marafeq. 3. The Customer should submit to Marafeq: Signed pressure test documents. Installation compliance statements signed by equipment suppliers. As-built drawings. Marafeq will issue a PRMS Conformance Certificate after final inspection is satisfied and to stamp on the building gas piping as built drawings and documents for submission to Qatar Civil Defense approval. 14 P a g e

5. PNEUMATIC & TRADITIONAL WASTE MANAGEMENT 5.1 PWC Preliminary Design Stage Marafeq review only the Discharge Valve (DV) room location after receiving the following submittals from the Customer. 1. Application No. 5 as provided in Appendix (E) to be completed by the Customer. 2. Building site plan drawing. 3. Architectural layout drawing showing the DV room location. 5. PWC design conformance application duly signed and stamped by the Customer. Drawings and documents must be submitted in softcopy (CD) both PDF and editable format (AutoCAD, MS Word, Excel, etc.). Marafeq will provide the review status on Preliminary Design submittal within ten working days from the date of receiving the submittal. After final Preliminary Design approval, the Customer should submit for record purposes one hardcopy A1 size for Marafeq stamp. 5.2 PWC Detailed Design Stage The Customer should submit the Pneumatic/Traditional Waste Management submittal for Marafeq s review comprising of following: 1. Application No. 5 as provided in Appendix (E) to be completed by the Customer. 2. PWC piping detailed layout and section drawing including pipe network, compressed air system, control cable system and DV room details. The drawing should indicate the limit of works at the plot boundary connection. 3. Garbage chute detail drawing indicating waste inlet volume control hopper door and chute diameter. (For information only) 4. Compliance statement to Marafeq s guidelines signed and stamped by the Customer. Drawings and documents must be submitted in softcopy (CD) both PDF and editable format (AutoCAD, MS Word, Excel, etc.). Marafeq will provide the review status on Detailed Design submittal within ten working days from the date of receiving the submittal. 15 P a g e

After final Detailed Design approval, the Customer should submit for record purposes one hardcopy A1 size for Marafeq stamp. 5.3 PWC Material Submittals In this stage the Customer should submit the following: 1. Application No. 5 as provided in Appendix (E) to be completed by the Customer. 2. Material submittal for PWC pipes and fittings. 5.4 PWC Method Statement In this stage the Customer should submit the following: 1. Application No. 5 as provided in Appendix (E) to be completed by the Customer. 2. External utilities layout showing the interfacing between infrastructure and building services provided with the coordinates and invert levels. 3. Shop drawings including pipe network, compressed air system, control cable system and DV room details duly approved by the Building Consultant in compliance with Detail Design Approval. (For reference and record only) 4. Method statement for the installation of pipes and fittings (from tie-in point up to DV room). 5. Method statement for CCTV inspection and pressure testing of complete internal pipe (from tie-in point up to DV room). 6. All welding documents: Welding Procedure Specification (WPS), Procedure Qualification Record (PQR), Welder Qualification Test (WQT), welding certificates, weld maps, etc. 5.5 PWC Installation and Inspection The Customer shall complete the Inspection Request Form as provided in Appendix (F) for every inspection to be made and submit to Marafeq by latest five working days before the inspection date. The inspection must be verified by the Building Consultant prior to Marafeq s inspection. Marafeq may inspect the installation at any stage but particularly to the following stages. 16 P a g e

Initial inspection: 1. Material delivery inspection. 2. Welding of pipes. 3. Radiographic testing for weld joints. 4. Installation of DV room components. 5. After CCTV inspection is done and report is available. 6. Pressure test inspection and report is available. Final inspection: 1. Marafeq will conduct a final inspection after equipment, components and piping are installed and connected. A snag list will be issued to the Customer. 2. The Customer shall submit to Marafeq the following: Compressed air test results for pressure loss. I/O test results for individual components to the control box. Installation compliance statement signed by equipment suppliers. As-built drawings. Marafeq will issue a PWC Conformance Certificate after final inspection is satisfied. 17 P a g e

6. APPENDICES Appendix A Application No. 1 Registration Form Appendix B Application No. 2 Request for Information Appendix C Application No. 3 District Cooling Appendix D Application No. 4 Gas Appendix E Application No. 5 Pneumatic & Traditional Waste Management Appendix F Application No. 6 Inspection Request Form 18 P a g e

Customer Registration Form Land Details Application Date Municipality Application Number Plot Number Plot Type and Use Requested Utility APPENDIX A MQID: طلب تسجيل عميل معلومات العقار تاريخ الطلب رقم طلب بلدية الظعاين رقم القطعة نوع القطعه واإلستخدام الخدمة المطلوبة DC PWC GAS Expected Connection Date DC: PWC: GAS: التاريخ المتوقع لتوصيل الخدمة Type of Customer: Company Individual Information Update نوع العميل: شركة شخصي تحديث معلومات عميل Owner Name اسم المالك C.R NO. OR Owner ID No. رقم السجل التجاري أو الرقم الشخصي C.R Expiry Date OR Owner ID Expiry Date تاريخ انتهاء السجل التجاري أوالبطاقة الشخصية للمالك Authorized Person Name Mobile Land Line Phone Number P.O. Box Email اسم المخول بالتوقيع الهاتف الجوال رقم الهاتف األرضي صندوق البريد البريد اإللكتروني Owner OR Authorized Signature توقيع المالك أو المخول بالتوقيع Company Stamp ختم الشركة CONSULTANT Company Name C.R No. C.R Expiry Date Name Authorized Person Contact Person Mobile Land Line Phone Number P.O. Box Email Authorized Person Signature اإلستشاري اسم الشركة رقم السجل التجاري تاريخ انتهاء السجل التجاري اسم المخول بالتوقيع اسم المسؤول الهاتف الجوال رقم الهاتف األرضي صندوق البريد البريد اإللكتروني توقيع المخول بالتوقيع Company Stamp ختم الشركة Attachment: A. Individual: 1. ID Copy both sides 2. Proof of ownership B. Companies: 1. C.R Copy 2. Computer ID Copy 3. ID of Authorized Signatory Note: If the consultant was changed or terminated prior to the completion of the project, the owner shall update Marafeq Qatar immediately. مالحظه: في حال تم انهاء خدمات اإلستشاري المذكور أعاله من أعمال المشروع أو تغييره على المالك إخطار شركة مرافق قطر وتحديث البيانات الخاصة باإلستشاري الجديد Marafeq Qatar L.L.C P.O. Box 5651, Doha, State of Qatar T: +974 4012 0140 F: +974 4012 0121 DL: +974 4012 0162 Mobile: +974 33569449 Email: customer.service@marafeq.com.qa Website: www.marafeq.com.qa Doc. /Form No.: MQ LD CS-INSP M 02 Rev.2

APPENDIX B APPLICATION NO.2 REQUEST FOR UTILITIES INFORMATION CUSTOMER ID: DATE: PLEASE TICK FOR REQUIRED INFORMATION FOR MARAFEQ USE DISTRICT COOLING Total cooling load: Pipe size: GAS Total Gas load: Pipe size: PWC Pipe size: Date: Date: (Signature and Stamp of Consultant) (Signature and stamp of Marafeq Qatar) 1 P age Document Name: Application No.2 Request for Utilities Information - Rev. 0

APPENDIX C APPLICATION NO.3 DISTRICT COOLING APPLICATION FOR MARAFEQ UTILITIES TO BE COMPLETED BY THE CONSULTANT CUSTOMER ID DATE: DOCUMENT NUMBER: CONSULTANT INFORMATION Name: Contact Person: Address: Telephone: Fax: Mobile: Email: STAGE Preliminary Design Detailed Design ETS Material Submittals Method Statements and Other Documents DOCUMENTS CHECK LIST Preliminary Design: Building site plan drawing. Architectural layout drawing showing the ETS room location. ETS design conformance application duly signed and stamped by the Customer/Consultant. Index sheet for the contents of the submittal. Detailed Design: ETS design conformance application. ETS Room Piping and Instrumentation Diagram. DC primary piping layout inside the plot boundary/basement.piping layout shall show tie-in point with co-ordinates and invert level. Detailed ETS layout and section drawing showing all equipment, piping and instruments inside ETS room. ETS Material Submittals: Material submittal for plate heat exchanger, primary DC pipes, PICV, strainer, isolation valves and PLC. Index sheet for the contents of the submittal. Method Statements and Other Documents: External utilities layout showing the interfacing between infrastructure and building services provided with the coordinates and invert levels. etc.). Welding documents (WPS, PQR, Welding certificates, weld maps, Method statement for the installation and testing/commissioning of equipment inside ETS room. Method statement for flushing the primary chilled water pipes. Index sheet for the contents of the submittal. Chilled water Equipment schedule and schematic diagram for secondary side. (For Information). Compliance statement to Marafeq s guidelines. Index sheet for the contents of the submittal. ------------------------------------------------------ --------------------------------------------------- (Signature, Date and Stamp of Consultant) (Checked and Received by MQ Customer Service) 1 P a g e Document Name: Application No.3 District Cooling - Rev. 2

APPENDIX D APPLICATION NO.4 GAS APPLICATION FOR MARAFEQ UTILITIES TO BE COMPLETED BY THE CONSULTANT CUSTOMER ID DATE: DOCUMENT NUMBER CONSULTANT INFORMATION Name: Contact Person: Address: Telephone: Fax: Mobile: Email: STAGE Preliminary Design Detailed Design PRMS Material Submittals Method Statement and Other Documents DOCUMENTS CHECK LIST Preliminary Design Stage: Building site plan drawing. Architectural layout drawing showing the PRMS location. PRMS design conformance application. Index sheet for the contents of the submittal. Detailed Design Stage: PRMS detailed drawing and section showing all components inside PRMS cabinet. Compliance statement to Marafeq s guidelines. PRMS Material Submittals: Material submittal for PRMS components. Index sheet for the contents of the submittal. Method Statement and Other Documents: External utilities layout showing the interfacing between infrastructure and building services provided with the coordinates and invert levels. Method statement for the installation, precommissioning and commissioning. Index sheet for the contents of the submittal. Index sheet for the contents of the submittal. ------------------------------------------------------ --------------------------------------------------- (Signature, Date and Stamp of Consultant) (Checked and Received by MQ Customer Service) 1 P a g e Document Name: Application No.4 Gas - Rev. 2

APPENDIX E APPLICATION NO.5 PNEUMATIC AND TRADITIONAL WASTE MANAGEMENT APPLICATION FOR MARAFEQ UTILITIES TO BE COMPLETED BY THE CONSULTANT CUSTOMER ID DATE: DOCUMENT NUMBER CONSULTANT INFORMATION Name: Contact Person: Address: Telephone: Fax: Mobile: Email: STAGE Preliminary Design Detailed Design PWC Material Submittals Method Statement and Other Documents DOCUMENTS CHECK LIST Preliminary Design Stage: Building site plan drawing. Architectural layout drawing showing the DV room location and space for bulky waste. Access to bulk waste room by waste truck. PWC design conformance application. Index sheet for the contents of the submittal. Detailed Design Stage: PWC piping detailed layout and section drawing indicating the limit of works at the plot boundary connection as per Design Guidelines. Garbage chute detail drawing indicating waste inlet volume control hopper door, chute diameter and DV room. panel. Indicate chute cleaning and fire alarm signal to PWC control PWC Material Submittals: Material submittal for PWC pipes and fittings. Index sheet for the contents of the submittal. Method Statement and other documents: External utilities layout showing the interfacing between infrastructure and building services provided with the coordinates and invert levels. Method statement for the installation of pipes and fittings (from tie-in point up to DV room). Method statement for CCTV inspection and pressure testing of complete internal pipe (from tie-in point up to DV room). etc.). Welding documents (WPS, PQR, Welding certificates, weld maps, Index sheet for the contents of the submittal. Compliance statement to Marafeq s guidelines. Index sheet for the contents of the submittal. ------------------------------------------------------ --------------------------------------------------- (Signature, Date and Stamp of Consultant) (Checked and Received by MQ Customer Service) 1 P a g e Document Name: Application No.5 Pneumatic and Traditional Waste Management - Rev. 0

APPENDIX F APPLICATION NO.6 INSPECTION REQUEST FORM APPLICATION FOR MARAFEQ UTILITIES CUSTOMER ID: DATE: District Cooling Pneumatic & Traditional Waste Management Gas INR NO: Type of Inspection: Location and Quantity of Works: Attached Reference Documents: Requested Inspection Date: Inspection Time: COMMENTS: Approved: Yes No CONTRACTOR BUILDING CONSULTANT INSPECTOR MARAFEQ QATAR PROJECT MANAGER Name: Name: Name: Name: Signature: Signature: Signature: Signature: Date Date Date Date Stamp: Stamp: Stamp: Stamp: 1 P a g e Document Name: Application No.6 Inspection Request Form - Rev. 0

APPENDIX G APPLICATION NO.7 INSPECTION REQUEST FOR CONNECTION WITH INFRASTRUCTURE PIPES APPLICATION FOR MARAFEQ UTILITIES CUSTOMER ID: DATE: District Cooling Pneumatic & Traditional Waste Management Gas INR NO: Type of Inspection: Location and Quantity of Works: The consultant to provide approval reference number for the following submittals: Pipe Material Submittal Method Statement for Flushing of Primary Pipes Shop Drawing Passivation Test Results Requested Inspection Date: Comments: Inspection Time: STATUS: NO OBJECTION REJECTED CONTRACTOR BUILDING CONSULTANT MARAFEQ QATAR Inspector Project Manager Network Contractor Name: Name: Name: Name: Name: Signature: Signature: Signature: Signature: Signature: Date: Date: Date: Date: Date: Stamp: Stamp: Stamp: Stamp: Stamp: 1 P a g e Document Name: Application No.7 Connection Inspection - Rev. 0