Substation Insulation Coordination Study

Similar documents
Insulation Coordination Fundamentals Where Arrester and Insulator Characteristics Meet

ArresterFacts 024. Separation Distance for Substations. ArresterFacts 024 Separation Distance for Substations. September 2014 Rev 7 Jonathan Woodworth

Session Four: Practical Insulation Co-ordination for Lightning Induced Overvoltages

Utility System Lightning Protection

Lightning performance of a HV/MV substation

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS

PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS

Analysis of lightning performance of 132KV transmission line by application of surge arresters

Transformers connected via a cable Overvoltage protection

Parameters Affecting the Back Flashover across the Overhead Transmission Line Insulator Caused by Lightning

2000 Mathematics Subject Classification: 68Uxx/Subject Classification for Computer Science. 281, 242.2

Insulation Co-ordination For HVDC Station

(participation = half letter grade, 5%)

High voltage engineering

Investigation into Transient SFO, FFO, VFTO Overvoltage Characteristics for Typical Gas Insulated Substations

Computation of Lightning Impulse Backflashover Outages Rates on High Voltage Transmission Lines

TECHNICAL NOTE 2.0. Overvoltages origin and magnitudes Overvoltage protection

INSTALLATION OF LSA ON A 400 KV DOUBLE-CIRCUIT LINE IN RUSSIA

Lightning overvoltage and protection of power substations

University of Zagreb Faculty of Electrical Engineering and Computing

Electric Stresses on Surge Arrester Insulation under Standard and

Modeling insulation in high-voltage substations

GIS Disconnector Switching Operation VFTO Study

INTERNATIONAL STANDARD

Arrester Disconnector

The Many Uses of Transmission Line Arresters

Including Surge Arresters in the Lightning Performance Analysis of 132kV Transmission Line

Tab 8 Surge Arresters

Lightning Flashover Rate of an Overhead Transmission Line Protected by Surge Arresters

TECHNICAL REPORT. Insulation co-ordination

Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning

Effect of Surge Arrester on Overhead Transmission Lines as Shield against Over Voltage

Lightning Overvoltage Performance of 110 kv Air-Insulated Substation

What is the Value of a Distribution Arrester

ROEVER ENGINEERING COLLEGE ELAMBALUR, PERAMBALUR DEPARTMENT OF ELECTRICAL & ELECTRONICS ENGINEERING

Effective Elimination Factors to the Generated Lightning Flashover in High Voltage Transmission Network

OVERVOLTAGE PROTECTION OF POLE MOUNTED DISTRIBUTION TRANSFORMERS

APPLICATION OF LONG FLASHOVER ARRESTERS FOR IMPROVEMENT OF LIGHTNING PROTECTION AND OPERATING VOLTAGE RELIABILITY OF DISTRIBUTION LINES

Modeling of overhead transmission lines with line surge arresters for lightning overvoltages. Poland

The Analysis Results of Lightning Overvoltages by EMTP for Lightning Protection Design of 500 kv Substation

ABSTRACTS of SESSION 6

Simulation and Analysis of Lightning on 345-kV Arrester Platform Ground-Leading Line Models

EE 1402 HIGH VOLTAGE ENGINEERING

Tab 2 Voltage Stresses Switching Transients

Comparison of switching surges and basic lightning impulse surges at transformer in MV cable grids

Maximum Lightning Overvoltage along a Cable due to Shielding Failure

ABSTRACT 1.0 INTRODUCTION LIST OF SYMBOLS

Lightning Protection of Distribution Substations by Using Metal Oxide Gapless Surge Arresters Connected in Parallel

The line-lightning performance and mitigation studies of shielded steelstructure

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT CODE & NAME : EE 1402 HIGH VOLTAGE ENGINEERING UNIT I

Analysis of MOV Surge Arrester Models by using Alternative Transient Program ATP/EMTP

Computer Based Model for Design Selection of Lightning Arrester for 132/33kV Substation

Grounding for Power Quality

MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION

International Journal of Advance Engineering and Research Development. Analysis of Surge Arrester using FEM

Effects of Transient Recovery Voltages on Circuit Breaker Ratings

Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers

Simulation of Lightning Transients on 110 kv overhead-cable transmission line using ATP-EMTP

Study of Insulator to Withstand Switching Surges in Conversion Three to Six-Phase Transmission Line: Computer Simulation Analysis

Lightning Performance Improvement of 115 kv and 24 kv Circuits by External Ground in MEA s Distribution System

Operational Characteristics of Surge Arresters within High Voltage Substations

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages

Comparison between Different InstallationLocations of Surge Arresters at Transmission Line Using EMTP-RV

Transmission of Electrical Energy

Reducing the magnetizing inrush current by means of controlled energization and de-energization of large power transformers

The Lightning Event. White Paper

Statistical Lightning Simulations for a HV "Mixed" Overhead-Cable Line: Preliminary Studies

Appendix B to Working on Exposed Energized Parts

Modeling and Analysis of a 3-Phase 132kv Gas Insulated Substation

Roll No. :... Invigilator s Signature :.. CS/B.TECH(EE)/SEM-5/EE-502/ POWER SYSTEM-I. Time Allotted : 3 Hours Full Marks : 70

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

Overvoltage Protection

Lightning current field measurement on a transmission line, comparison with electromagnetic transient calculations

A Case Study on Selection and Application of Lightning Arrester and Designing its Suitable Grounding Grid

CHAPTER 2. v-t CHARACTERISTICS FOR STANDARD IMPULSE VOLTAGES

Prediction of Transient Transfer Functions at Cable-Transformer Interfaces

LIMITS FOR TEMPORARY OVERVOLTAGES IN ENGLAND AND WALES NETWORK

Disclosure to Promote the Right To Information

Great Northern Transmission Line: Behind the (Electrical) Design

Research on Lightning Over-voltage and Lightning Protection of 500kV. HGIS Substation

ArresterFacts-002. Field Testing Arresters ArresterWorks.com. ArresterFacts are information modules pertaining to the arrester world.

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

(2) New Standard IEEE P (3) Core : (4) Windings :

Substation Design Volume VII

Surge Protection for Ladle Melt Furnaces

Performance of Surge Arrester to Multiple Lightning Strokes on Nearby Distribution Transformer

Network Standard NETWORK. Document No Amendment No Approved By Approval Date Review Date NW000-S0142 : : : : : Head of AEP&S 08/06/ /06/2017

X International Symposium on Lightning Protection

Study of Tower Grounding Resistance Effected Back Flashover to 500 kv Transmission Line in Thailand by using ATP/EMTP

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS

CHAPTER 10 HIGH VOLTAGE TESTING OF ELECTRICAL APPARATUS

ABSTRACT 1 INTRODUCTION

TECHNICAL SPECIFICATION

PRACTICAL PROBLEMS WITH SUBSTATION EARTHING

IEC Type Test Report Report No. EU1517-H-00.1 H4 Series Porcelain-housed Arrester 20,000 A Line Discharge Class 4

Electrical Transient Interaction between Transformers and Power System. Brazilian Experience

Calculation of Transients at Different Distances in a Single Phase 220KV Gas insulated Substation

Analysis and Mitigation Techniques of Switching Overvoltages for A 500 kv Transmission Line

CLU Arrester. Certified Test Report. IEEE Standard C

Transcription:

[Type the document title] Substation nsulation Coordination Study MEG Energy Christina Lake Regional Project nsulation Coordination Schematic X0057 15km Lines TWR3 TWR2 TWR1 Afrm1 16 230k Source CCT 100 Ohms Strike 50 Ohms 4 Ohms Arr1 190k SA950 MCO H 3.5m L- mpulse J1 CB910 15 CB910 15 23.5 23.5 J2 12.5m Arr4 Afram TWR5 TWR6 Afram TR911 TR-911 BCT Y 22.65 CB915 CB915 22.65 22.65 CB 22.65 190k MCO SA954 X0047 Arr7 TR-C 190k MCO No SA # given J3 15 CB 15 23.5 CB 23.5 J4 12.5m Arr5 Afram Afram 1 ohms SA956 190k MCO TR910 TR-910 BCT Y Arr2 SA952 190k MCO TR912 TR-C 190k MCO 15.3m TR912 BCT Y TR-912 15.3m TR900 TR900 TR900 BCT Y TR-900 TR-C Arr3 190k MCO SA951 SA952 Arr6 190k MCO TR-C By ArresterWorks For June 28 th, 2011 Jonathan Woodworth ArresterWorks Page 1

Substation nsulation Coordination Contents Summary... 3 Conclusions... 5 Basis of Analysis... 6 Scope of Work... 6 Analysis Methodology... 6 Equipment Characteristics... 6 Lightning Analysis Assumptions... 7 One Line Diagram... 8 Key to One Line Diagram... 9 Scenario Descriptions... 10 ncoming Surge Consideration... 10 Lightning Analysis Results Scenario 1 Arresters at Transformers Only Scenario 1 Waveshapes... 11 Scenario 1 oltage Analysis... 12 Scenario 2 Arresters at Trans and Line Entrance Scenario 2 Waveshapes... 13 Scenario 2 oltage Analysis... 14 Scenario 3 Arresters at All Locations Scenario 3 Waveshapes... 15 Scenario 3 oltage Analysis... 15 Scenario 4 Open Breaker Analysis Scenario 4 Waveshapes... 16 Scenario 4 oltage Analysis... 17 Clearance Analysis... 18 References... 19 Annex A CFO-BL Graphic... 20 Annex B Margin of Protection Definition... 21 Jonathan Woodworth ArresterWorks Page 2

Substation nsulation Coordination Study Substation nsulation Coordination Study Jonathan Woodworth ArresterWorks Analysis Summary.. is expanding a 260k substation to accommodate increased production of bitumen at the --------------- as part of a 3 phase project. This expansion project is part of Phase B2. The substation will be expanded to include two more transformers and a 260k ring bus. This insulation coordination study was commissioned by ------------------------------ to confirm that the proposed arrester locations will adequately protect the substation and transformers from flashover during a lightning strike. This analysis was done using methods as outlined in the application guides EEE 1313.2 [2], EEE C62.22 [3], nsulation Coordination of Power Systems by Andrew Hileman [1] and ATPDraw [6]. ATPDraw is the time domain based transient software used to determine the voltage stresses throughout the station during surge events. Lightning Protection Analysis of Bus The station was modeled in ATP using drawings supplied by --------------------------. The voltages throughout the station were determined with a surge entering the station from the incoming line. The resulting voltage values at specified junctions in the substation were used to calculate the protection margins based on equipment data also supplied by ---------. The bus analysis was completed two ways, with arresters installed only at the transformers (scenario 1) and then including the line entrance arrester (scenario 2). As shown in Table 1, it can be seen that the bus insulation at location J1 is the most highly stress but still has >50% more BL than needed. Even with arresters only installed at the transformers as shown in scenario 1, the insulation has <50% more BL than minimum. The 190k MCO arresters and their location do adequately protect the bus insulation in this substation. Table 1 Scenario 1 Arresters mounted only at Transformers Minimum Required BL ( k 1.2/50 µs mpulse) (k) nstalled nsulation Level (k) % apparatus BL above Min BL EEE Recommended level above Min TR900 1 535.3 1300 142.9% 0.00% TR910 539.9 1050 94.5% 0.00% TR911 549.2 1050 91.2% 0.00% TR912 539.9 1050 94.5% 0.00% oltage at J1 595.8 900 51.1% 0.00% oltage at J2 605.1 900 48.7% 0.00% oltage at J3 530.6 900 69.6% 0.00% oltage at J4 539.9 900 66.7% 0.00% Scenario 2 Arresters mounted at Transformers and Line Entrance TR900 502.7 1300 158.6% 0.00% TR910 349.1 1050 200.8% 0.00% TR911 512.0 1050 105.1% 0.00% TR912 512.0 1050 105.1% 0.00% oltage at J1 591.1 900 52.3% 0.00% oltage at J2 386.3 900 133.0% 0.00% oltage at J3 535.3 900 68.1% 0.00% oltage at J4 502.7 900 79.0% 0.00% Note 1: For all 4 transformers in this table, the analysis in for the bushing only, not winding Jonathan Woodworth ArresterWorks Page 3

Substation nsulation Coordination Study Analysis of Transformer Winding Protection For the protection analysis of the transformer windings, three scenarios were ran with arresters installed at 1) transformers only, 2) transformers and line entrance, and 3) at all 7 locations as proposed. As show in Table 2 the transformer windings have >20% margin of protection above that recommended by EEE even if the only arresters in the station were at the transformers as in scenario 1. With arresters installed at all locations, the worst-case protection is 36% above that recommended by EEE. t can be concluded that the transformer windings are well protected in this station. The two arresters mounted in the center of the station however have very little effect on the transformer protection as can be seen by comparing scenario 2 and 3. Table 2 Transformer Winding Margin of Protection Summary Scenario 1 oltage stress at windings per ATP (k) Arresters at Transformers only BL Transformer Margin of Protection of Transformer EEE Recommendation above Min % above the EEE Recommended Transformer 900 Winding 575 1050 83% 20% 63% Transformer 910 Winding 580 825 42% 20% 22% Transformer 911 Winding 590 825 40% 20% 20% Transformer 912 Winding 580 825 42% 20% 22% Scenario 2 Arresters at Transformers and Line Entrance Transformer 900 Winding 540 1050 94% 20% 74% Transformer 910 Winding 375 825 120% 20% 100% Transformer 911 Winding 550 825 50% 20% 30% Transformer 912 Winding 550 825 50% 20% 30% Scenario 3 with arresters at all proposed locations in Substation Transformer 900 Winding 500 1050 110% 20% 90% Transformer 910 Winding 375 825 120% 20% 100% Transformer 911 Winding 530 825 56% 20% 36% Transformer 912 Winding 550 825 50% 20% 30% Jonathan Woodworth ArresterWorks Page 4

Substation nsulation Coordination Study Analysis of Open Breaker Protection Because breakers are normally closed, the transformer mounted arrester can protect back through the breaker to other parts of the substation, However if lightning should flashover an insulator several spans from the station and cause a fault on the system, the breaker opens for 4-10 cycles. During this time, a second stroke of the lightning can enter the station and flashover the breaker bushing on the side away from the transformer arrester. This analysis determines the margin of protection of the breaker bushing in the open and most vulnerable state. Table 3 shows the margin of protection with and without an arrester at the line entrance. With no arresters mounted on the line entrance, the post insulators with a 900k BL would be jeopardy if the breakers are caught in the open mode during a surge event. The other bushings are ok. With line arresters installed as proposed in this station, the post insulators upstream from the breakers are adequately protected in an open breaker scenario. Table 3 Open Breaker nsulator Analysis Worst Case nsulator Margin of Protection Min Recommended by EEE Without Line Terminal Arrester -8% 0.0 % With Line Terminal Arrester 18% 0.0 % Clearance Analysis The clearance requirements in a substation are a function of the lightning impulse levels. For this analysis, the worst case voltage levels as calculated using ATP are compared to the lowest actual clearance in the station. From table 4 can be seen that there is ample phase to phase and phase to ground clearance in this sub. Table 4 Substation Clearance Analysis Minimum Required Clearance based on Bus oltages and Elevation (meters) Actual (meters) % above Actual Scenario 1 Arresters at Transformers only Clearance p-p 1.15 3.5 203.8% and p-g 1.15 2.4 108.3% Scenario 2 Arresters at Transformers and Line Entrance Clearance p-p 1.13 3.5 211.0% and p-g 1.13 2.4 113.2% Conclusions and Recommendations 1. Based on the bus voltage analysis, insulation levels selected are appropriate for this substation, as long as line entrance arresters are installed as planned to eliminate any potential flashover during an open breaker event. 2. The transformer windings are very well protected in all cases. The 1050 BL winding rating of transformer 900 is more than needed, but since it is already there, it is ok as is. 3. The arresters installed near the center of the station are not necessary. Recommendations The only recommendation is that the station be built as specified and it will be adequately protected from lightning in all cases. End of Summary Jonathan Woodworth ArresterWorks Page 5

Substation nsulation Coordination Study Bases for the Analysis All insulation will flashover or puncture in the presence of surges with amplitudes and durations above the limit of the design. This study was commissioned to determine if the chosen insulation levels for the bus and transformer are adequate for surges that will enter the station from a backflashover on the incoming line within a few kilometers of the station. This analysis was done using simplified methods as outlined in the application guides EEE 1313.2 [2], EEE C62.22 [3] and Andrew Hileman s book [1]. The transient voltages in the substation were determined using ATPDraw [6]. Scope of Work Station nsulation Protection Determine the margins of protection of the station bus with the installed protection. Determine the effect on the station from an open breaker and no line terminal arresters. Transformer nsulation Protection Determine the margin of protection of the 260/13.8k substation transformers with existing arrester protection. Determine the margin of protection of the 234/25k substation transformers with existing arrester protection. Methods of Analysis Lightning Protection Analysis of Bus The apparatus withstand levels were given by Rising Edge Engineering. These levels were then used in a margin analysis using ATPDraw and ATP to calculate voltages throughout the substation based on methods presented in EEE 1313.2 and nsulation Coordination of Power Systems [1]. The surge arrester characteristics were obtained from Cooper Power Systems AZG catalog section 235-84. Protective Margin Analysis of Transformer Since transformer winding insulation is not self-restoring it is only evaluated using a deterministic analysis. With this method, conventional transformer BL Withstand and Chopped Wave Withstand characteristics of the transformer are compared to the corresponding arrester protective levels and the protective margins. Fast front voltage and standard lighting impulse voltages are calculated using ATP, ATPDraw, and EEE 1313.2 methods. The voltages calculated, include the effect of separation distance and arrester leads. Equipment Characteristics The equipment subjected to surges in these substations are: 1. Post nsulators for bus support 900k BL 2. nsulators on disconnect switches 1050k BL 3. Breaker Bushings 1300k BL 4. Transformer 900 1300k BL Bushings 1050k BL Windings 5. Transformers 910, 911, 912 1050k BL Bushings 850k BL Windings 6. ncoming Line nsulation Level 1350k CFO Jonathan Woodworth ArresterWorks Page 6

Substation nsulation Coordination Study Lightning Analysis Lightning surge withstand capability of the 230k side of the substation is evaluated by calculating the voltage magnitudes at critical points and comparing them to the BL of the insulation at those locations. ATP and ATPDraw were used to calculate the voltages. oltage levels attained are a function of the incoming surge steepness which is assumed to be the worst case for this analysis (1000k/us). Lightning Analysis Assumptions 1. Transformer Capacitance of 3 nanofarads (nf) (typical per Hileman page 567) 2. The station is shielded and no lightning enters the station directly, only via the lines when a back flashover occurs within a few spans of the station. 3. Transformer Margin of protection of 20% is a minimum for lightning surges (EEE Recommendation) 4. The steepness of the incoming surge is 1000k/us. This is on the high side of typical surges on 230k lines but used for most conservative results. Elevation Coefficient When determining the margin of protection of the insulation within a substation, the station elevation needs to be considered. The impulse withstand capability of air decreases inversely proportionally to the altitude. At 580m altitude, the flashover level of insulation is decreased by 7% as compared to sea level. This 7% reduction is used in these calculations. Table 5 Elevation Coefficient Elevation in Feet 1900 Elevation in Km.579 δ.9341 Jonathan Woodworth ArresterWorks Page 7

Substation nsulation Coordination Study MEG Energy Christina Lake Regional Project nsulation Coordination Schematic X0057 15km Lines TWR3 TWR2 TWR1 Afrm1 16 230k Source CCT 100 Ohms Strike 50 Ohms 4 Ohms Arr1 190k SA950 MCO H 3.5m L- mpulse J1 CB910 15 CB910 15 23.5 23.5 J2 12.5m Arr4 Afram TWR5 TWR6 Afram TR911 TR-911 Y BCT 22.65 CB915 CB915 22.65 22.65 CB 22.65 190k MCO SA954 X0047 Arr7 190k MCO TR-C No SA # given J3 15 CB 15 23.5 CB 23.5 J4 12.5m Arr5 SA956 190k MCO Afram Afram TR910 TR-910 BCT 1 ohms Y Arr2 SA952 190k MCO TR912 15.3m TR912 BCT Y TR-912 TR900 15.3m TR900 TR900 BCT Y TR-900 Arr3 190k MCO SA951 SA952 Arr6 190k MCO TR-C TR-C 190k MCO TR-C Figure 1 One line drawing of Christina Lake Substation Jonathan Woodworth ArresterWorks Page 8

Substation nsulation Coordination Study 16m 50 meters of 230k horizontal transmission line with two overhead shield wires in H format 4 Ohms Towers and A Frame with insulator that flashover at 1350k on C phase only. also 16 meters of bus TR-C Y TR-910 BCT 260-13.8k Transformer with 1.5 meters of bus between arrester and bushing 3nf capacitance is the transformer cap 190k MCO SA950 3.5m Three phase arrester with 1.5 meter lead above and 3.5 meters of lead below the arrester. MCO rating of 190k. Tower ground resistance of in this case. oltage probe at top of arrester 22.65 CB915 22.65 Circuit breaker with voltage probe and 22.65 meters of 260k bus on both sides H L- mpulse Lighting source Current source Figure 2 Key to one line drawing Jonathan Woodworth ArresterWorks Page 9

Substation nsulation Coordination Study Scenario Descriptions Scenario 1: Analysis of Station with Arresters at the transformers only This would be the minimum protection in a substation of this type. This scenario is ran for comparison purposes only. Scenario 2: Analysis of Station with Arresters at the transformers and at the line entrance This scenario generally offers very good transformer protection and improved bus protection. Often times it is the only way to insure no flashover during an open breaker situation. Scenario 3: Analysis of Station with Arresters at the transformers, center and entrance This scenario was completed to evaluate the added value of the two arresters sets installed in the center of the station. Scenario 4: Open Breaker Scenario This scenario is for an incoming surge where the breaker is open (generally during a fault clearing event). The only part of the station that is affected by this scenario is the line terminal and the bus up to the open breaker. ncoming Wave Considerations The steepness of the incoming surge into a substation is an important factor in how well the arresters are able to protect the equipment. For surges greater than 1000k/us the inductance in the arrester leads start to become an issue in protection by causing voltages that add to the arrester residual voltage and in effect reduce the protection of the insulation installed in parallel with the arrester. For this study, the rate of rise at the struck point was 3000k/us but by the time it reached the station entrance, it was reduced to 1000k/us by corona and capacitance of the lines. Per EEE1313.2, a 1000k/us surge rise is typical for 230k stations. Figure 3 shows the surge at tower 2 and at the station entrance A-frame. 3.0 [M] 2.5 2.0 1.5 1.0 3000k/us at Tower2 Phase C 1000k/us at Aframe 1 Phase C 0.5 0.0-0.5-1.0 0 2 4 6 8 [us] 10 (file MEG_Sub6.pl4; x-var t) v:twr2c v:twr1c v:afrm1c Figure 3 Waveshape of incoming surge from flashover on line at tower 2 Jonathan Woodworth ArresterWorks Page 10

Substation nsulation Coordination Study Scenario 1: Analysis of Station with Arresters at installed at the Transformers Only The purpose of this scenario was to determine the voltage levels at the transformers and juncions on the ring bus. Figures 4 and 5 show the output of ATP. The figures also show the level of the surge entering the substation at Aframe 1. The analysis is completed on phase C only because that is the phase that is flashed over at tower 2 and experiences the worst stress in this case. Figure 4 oltages at transformer bushings and windings with arresters mounted at transformers only Figure 5 oltages at J1 thru J4 Jonathan Woodworth ArresterWorks Page 11

Substation nsulation Coordination Study Table 6 summarizes the substation protection at transformers and points on the bus if arresters are installed at the transformers only. The results show that protection in this case is all acceptable since all locations exceed that recommended by EEE standards. Table 6 Scenario 1 Arresters at Transformers only External nsulation BL Calculations Peak Fast Front oltages from ATP (k) Minimum Required BL (Note 1) ( k 1.2/50 µs mpulse) nstalled nsulation Level (k) (Note 2) % apparatus BL above Min BL (Note 3) EEE Recommended above Minimum Transformer Winding 900 575 535.3 1300 142.9% 0.00% Transformer Bushing (External) 910 580 539.9 1050 94.5% 0.00% Transformer Bushing (External) 911 590 549.2 1050 91.2% 0.00% Transformer Bushing (External) 912 580 539.9 1050 94.5% 0.00% oltage at J1 640 595.8 900 51.1% 0.00% oltage at J2 650 605.1 900 48.7% 0.00% oltage at J3 570 530.6 900 69.6% 0.00% oltage at J4 580 539.9 900 66.7% 0.00% Actual % above Actual Require Clearance p-p (m) 1.15 3.5 203.8% (Note 4) and p-g 1.15 2.4 108.3% Delta (Elevation Factor) 0.9341 1. Minimum Required BL: Min BL= (Peak ATP oltage /1.15)/Delta 2. nsulation Level These are potential BL levels of equipment in the substation. 3. % above Min BL (Apparatus BL/Min BL) -1 in percent 4. Clearance: This is both phase to phase and phase to ground clearance. This is the minimum clearance needed to achieve the desired performance on the on the bus. Clearance = (Peak voltage from ATP)/605k/m Transformer Winding Margin of Protection Calculations Winding oltages BL Transformer Margin of Protection of Transformer EEE Recommendat ion % above the EEE Recommended Transformer 900 Winding 575 1050 83% 20% 63% Transformer 910 Winding 580 825 42% 20% 22% Transformer 911 Winding 590 825 40% 20% 20% Transformer 912 Winding 580 825 42% 20% 22% Jonathan Woodworth ArresterWorks Page 12

Substation nsulation Coordination Study Scenario 2: Analysis of Station with Arresters at the transformers and at the line entrance This scenario was completed to show the protection levels with arresters installed at transformers and line entrance only which is most common for this size substation. Figures 6 and 7 and Table 7 show the output from ATP. The results show that there is good protection in this scenario. Figure 6 oltages at bus junctions with arresters at transformers and line entrance Figure 7 oltages at transformer bushings and windings with arresters at transformers and line entrance Jonathan Woodworth ArresterWorks Page 13

Substation nsulation Coordination Study Table 7 Scenario 2 Arresters at Transformers and at Station Entrance External nsulation BL Calculations Peak Fast Front oltages from ATP (k) Minimum Required BL (Note 1) ( k 1.2/50 µs mpulse) nstalled nsulation Level (k) (Note 2) % apparatus BL above Min BL (Note 3) EEE Recommen ded above minimum Transformer Winding 900 540 502.7 1300 158.6% 0.00% Transformer Bushing (External) 910 375 349.1 1050 200.8% 0.00% Transformer Bushing (External) 911 550 512.0 1050 105.1% 0.00% Transformer Bushing (External) 912 550 512.0 1050 105.1% 0.00% oltage at J1 635 591.1 900 52.3% 0.00% oltage at J2 415 386.3 900 133.0% 0.00% oltage at J3 575 535.3 900 68.1% 0.00% oltage at J4 540 502.7 900 79.0% 0.00% Actual % above Actual Require Clearance p-p (m) 1.13 3.5 211.0% (Note 4) and p-g 1.13 2.4 113.2% Delta (Elevation Factor) 0.9341 1. Minimum Required BL: Min BL= (Peak ATP oltage /1.15)/Delta 2. nsulation Level These are potential BL levels of equipment in the substation. 3. % above Min BL (Apparatus BL/Min BL) -1 in percent 4. Clearance: This is both phase to phase and phase to ground clearance. This is the minimum clearance needed to achieve the desired performance on the on the bus. Clearance = (Peak voltage from ATP)/605k/m Transformer Winding Margin of Protection Calculations Winding oltages BL Transformer Margin of Protection of Transformer EEE Recommendatio n % above the EEE Recommen ded Transformer 900 Winding 540 1050 94% 20% 74% Transformer 910 Winding 375 825 120% 20% 100% Transformer 911 Winding 550 825 50% 20% 30% Transformer 912 Winding 550 825 50% 20% 30% Jonathan Woodworth ArresterWorks Page 14

Substation nsulation Coordination Study Scenario 3: Analysis of Station with Arresters at the transformers, center and entrance This scenario is for the substation as proposed. The only difference between this scenario and scenario 2 is the addition of the two sets of arresters in the center of the station. The voltage levels for this scenario are marginally better than without the center sets of arresters installed. 1.2 [M] 1.0 0.8 0.6 0.4 0.2 0.0 TR900= 500k TR912= 550k TR911= 530k TR910= 375k -0.2 0 5 10 15 20 [us] 25 (file MEG_Sub6.pl4; x-var t) v:tr900c v:tr912c v:tr910c v:tr911c Figure 8 Transformer winding voltages with arresters installed at all proposed locations Table 8 Scenario 3 Arresters at Transformers, Station Entrance, and Station Center Transformer Winding Margin of Protection Calculations Winding oltages BL Transformer Margin of Protection of Transformer EEE Recommendation % above the EEE Recommended Transformer 900 Winding 500 1050 110% 20% 90% Transformer 910 Winding 375 825 120% 20% 100% Transformer 911 Winding 530 825 56% 20% 36% Transformer 912 Winding 550 825 50% 20% 30% Jonathan Woodworth ArresterWorks Page 15

Substation nsulation Coordination Study Scenario 4: Open Breaker Scenario Because breakers are normally closed, the transformer mounted arrester can protect back through the breaker to other parts of the substation, However if lightning should flashover an insulator several spans from the station and cause a fault on the system, the breaker opens for 4-10 cycles. During this time, a second stroke of the lightning can enter the station and flashover the breaker bushing on the side away from the transformer arrester. This analysis determines the margin of protection of the breaker bushing in the open and most vulnerable state. Figures 9, Figures 10 and Table 9 show the voltage stresses experienced during an open breaker event. With no arresters mounted on the line entrance, the post insulators with a 900k BL would be jeopardy if the breakers are caught in the open mode during a surge event. The other bushings are ok. With line arresters installed as proposed in this station, the post insulators upstream from the breakers are adequately protected in an open breaker scenario. 1.5 [M] 1.0 TR900= 1055k 0.5 0.0-0.5-1.0 0 5 10 15 20 [us] 25 (file MEG_Sub6.pl4; x-var t) v:afrm1c v:cb910c v:cb915c Figure 9 oltage levels on bus with breakers open and not line entrance arresters 1.5 [M] 1.0 TR900= 816k 0.5 0.0-0.5-1.0 0 5 10 15 20 25 [us] 30 (file MEG_Sub6.pl4; x-var t) v:afrm1c v:cb910c v:cb915c Figure 10 oltage levels on the bus and breaker bushing with line entrance arresters installed Jonathan Woodworth ArresterWorks Page 16

Substation nsulation Coordination Study Table 9 Scenario 4 Open Breaker Scenario Peak Fast Front oltages from ATP (k) Minimum Required BL (Note 1) ( k 1.2/50 µs mpulse) nstalled nsulation Level (k) (Note 2) No Arresters on the line entrance % apparatus BL above Min BL (Note 3) EEE Recommended level above minimum Line Post nsulators 1055 982.1 900-8.4% 0.00% Disconnect Switch nsulators 1055 982.1 1050 6.9% 0.00% Breaker Bushings 1055 982.1 1300 32.4% 0.00% Arresters nstalled on the line entrance Line Post nsulators 816 759.6 900 18.5% 0.00% Disconnect Switch nsulators 816 759.6 1050 38.2% 0.00% Breaker Bushings 816 759.6 1300 71.1% 0.00% Delta (Elevation Factor) 0.934 1. Minimum Required BL: Min BL= (Peak ATP oltage /1.15)/Delta 2. nsulation Level These are potential BL levels of equipment in the substation. 3. % above Min BL (Apparatus BL/Min BL) -1 in percent 4. Clearance: This is both phase to phase and phase to ground clearance. This is the minimum clearance needed to achieve the desired performance on the on the bus. Clearance = (Peak voltage from ATP)/605k/m Jonathan Woodworth ArresterWorks Page 17

Substation nsulation Coordination Study Clearance Analysis The clearance requirements in a substation are a function of the lightning impulse levels. For this analysis, the worst-case voltage levels as calculated using ATP are compared to the lowest actual clearance in the station. From table 4 can be seen that there is ample phase to phase and phase to ground clearance in this sub. Table 10 Substation Clearance Analysis Minimum Required Clearance based on Bus oltages and Elevation (meters) Scenario 1 Arresters at Transformers only Actual (meters) % above Actual Clearance p-p 1.15 3.5 203.8% and p-g 1.15 2.4 108.3% Scenario 2 Arresters at Transformers and Line Entrance Clearance p-p 1.13 3.5 211.0% and p-g 1.13 2.4 113.2% End of Main Body See Summary at the Beginning of the report for the final Summary and Conclusions Jonathan Woodworth ArresterWorks Page 18

Substation nsulation Coordination Study References [1] Hileman, A.R., nsulation Coordination for Power Systems, Marcel Dekker, nc., New York, 1999, SBN 0-8247-9957-7. [2] EEE Std 1313.2-1999 (R2005) EEE Guide for the Application of nsulation Coordination, nstitute of Electrical and Electronic Engineers, New York, 1999 [3] EEE Std C62.22-2009 EEE Guide for the Application of Metal Oxide Surge Arresters for Alternating-Current Systems, nstitute of Electrical and Electronic Engineers, New York, 2009 [4] G.W. Brown, Designing EH Lines to a given outage rate - Simplified Techniques, EEE Transactions on PA&S, March 1978 Pg 379-383. [5] EEE Std C57 12 00-2006 EEE Standard for Standard General Requirements for Liquid-mmersed Distribution, Power, and Regulating Transformers nstitute of Electrical and Electronic Engineers, New York, 2006 [6] ATP and ATPDraw Alternative Transients Program www.emtp.org the world s most widely used Electromagnetic Transients Program. Jonathan Woodworth ArresterWorks Page 19

Probability of Flashover 0.1.2.3.4.5.6.7.8.9 1 Substation nsulation Coordination Annex A Comments on the Relationship of CFO and BL Note on BSL, BL and CFO CFO of an insulator is the voltage at which flashover occurs 50% of the time. Also because the actual level has a normal distribution it also has an associated standard deviation. Experience indicates that one standard deviation for switching CFO is 7% and one standard deviation for a lightning CFO is 3%. BSL (Statistical) is the voltage at which flashover only occurs 10% of the time. t also has a sigma associated with it. BSL (Conventional) The voltage where there is no flashover with a switching surge. BL (Conventional) The voltage where there is no flashover with a standard 1.2/50 µs surge voltage.. Figure 1 is a graphic representation of the relationship between BL, BSL, and CFO. The Lightning and Switching Sigma bars indicate that the standard deviation of lightning and switching CFOs are.03 and.07 respectively. Lightning Sigma BL s and BSL s CFO Switching Sigma BSL BL X axis is Peak oltage Figure 1 CFO-BL-BSL Relationships (Probability vs. Peak oltage of Surge) Jonathan Woodworth ArresterWorks Page 20

nsulation Coordination Study Orrington Substation Annex B Margin of Protection Definition Jonathan Woodworth ArresterWorks Page 21