INVESTIGATION ON THE TECHNOLOGIES FOR DEFECT LOCALIZATION AND CHARACTERIZATION ON MEDIUM VOLTAGE UNDERGROUND LINES

Similar documents
Testing and PD Diagnosis of MV Cable Systems with DAC Voltage Educational Session May St Pete Beach, Fl

USING DAMPED AC VOLTAGES

Partial Discharge Measurement and Monitoring on High Voltage XLPE Cables

THE PROPAGATION OF PARTIAL DISCHARGE PULSES IN A HIGH VOLTAGE CABLE

Investigations on a Combined Resonance/VLF HV Test System Partial Discharge (PD) characteristics at VLF and DAC voltages

EFFECT OF INTEGRATION ERROR ON PARTIAL DISCHARGE MEASUREMENTS ON CAST RESIN TRANSFORMERS. C. Ceretta, R. Gobbo, G. Pesavento

PD Testing Considerations for MV Plant Cables

Extended analysis versus frequency of partial discharges phenomena, in support of quality assessment of insulating systems

Simultaneous Partial Discharge and Tan Delta Measurements: New Technology in Cable Diagnostics

UHF PD-DIAGNOSIS AT HIGH VOLTAGE CABLE TERMINATIONS INTERNATIONAL CASE STUDIES

Online Localisation of Partial Discharge Using Pulse Propagation Parameters in Medium Voltage Cable Network

Aspects of PD interpretation in HV power cables. by Edward Gulski, Piotr Cichecki, Rogier Jongen

The University of New South Wales. School of Electrical Engineering and Telecommunications. High Voltage Systems ELEC9712. Appendix Partial Discharge

NEW MV CABLE ACCESSORY WITH EMBEDDED SENSOR TO CHECK PARTIAL DISCHARGE ACTIVITY

Practical aspects of PD localization for long length Power Cables

Why partial discharge testing makes good sense

BEST PRACTICES FOR OFFLINE DIAGNOSIS OF MV CABLES

Partial discharge diagnostics on very long and branched cable circuits

PARTIAL DISCHARGE LOCATION Selected Topics

Statistical Characteristics of Partial Discharge Caused by Typical Defects in Cable Joint under Oscillating Voltage

OFFLINE PD DIAGNOSTICS USING SEVERAL EXCITATION VOLTAGES

Basics of Partial Discharge. Prepared for 2015 Phenix RSM Meeting January 2015

WIRE AND CABLE ENGINEERING GUIDE

SENSITIVITY ASPECTS OF ON-LINE PD DIAGNOSIS OF MV POWER CABLES

Investigation of PD Detection on XLPE Cables

PULSE-SEQUENCE ANALYSIS OF PARTIAL DISCHARGES IN POWER TRANSFORMERS

Partial Discharge, Survey or Monitor?

Field Experiences. Partial Discharge Diagnosis on MV Cables. Philipp Legler. XVI. Szigetelésdiagnosztikai Konferencia (

Underground System Design TADP 547

Long lengths transmission power cables on-site testing up to 500 kv by damped AC voltages

This is an author-deposited version published in : Eprints ID : 18192

Current Probes. User Manual

MV Power Cable Testing Training

ON-LINE PARTIAL DISCHARGE TESTING OF SOME OF THE WORST PERFORMING CIRCUITS ON A UTILITY DISTRIBUTION SYSTEM

Evaluation and Limitations of Corona Discharge Measurements An Application Point of View

All the standards referred to the most current issue, including all amendment supplements. as of the date of the bid.

NOVEL METHOD FOR ON-SITE TESTING AND DIAGNOSIS OF TRANSMISSION CABELS UP TO 250KV

CITY SERIES. Compact, fully equipped cable fault location, test and diagnostic systems

A COMPARISON OF AC AND DC PARTIAL DISCHARGE ACTIVITY IN POLYMERIC CABLE INSULATION *

IN HOUSE CALIBRATION OF PD DETECTOR SYSTEM FOR FIELD TEST RESULT RELIABILITY

PD Diagnostic Applications and TechImp solutions

Evaluation of Distribution Line Spacers through the Leakage Current Monitoring

Coherence and time-frequency analysis of impulse voltage and current measurements

CHAPTER 2. v-t CHARACTERISTICS FOR STANDARD IMPULSE VOLTAGES

BY JASON SOUCHAK, Megger

process has few stages and is highly repeatable. Excellent mechanic properties and electro-magnetic compatibility. Planar design gives the height lowe

Ref: HO 50-S/SP33, HO 100-S/SP33, HO 150-S/SP33, HO 200-S/SP33, HO 250-S/SP33

On-line Partial Discharge Assessment and Monitoring of MV to EHV Cables

I P. /dt. di p V S+ Applications. Standards. 1) IEC ed1.0: 2007; IEC : ed1.0: 2012

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

Comparison of measurement methods for partial discharge measurement in power cables

Partial Discharge Patterns in High Voltage Insulation

= 1000 V. Voltage transducer DVC 1000-P V P N

Condition-based maintenance of power transformers Complete three-phase system Turns Ratio: Recovery Voltage: Winding Resistance:

Estimating the Impact of VLF Frequency on Effectiveness of VLF Withstand Diagnostics

Assuring the Reliability of Critical Power Cable Systems

ABSTRACT. Introduction. Keywords: Powerline communication, wideband measurements, Indian powerline network

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

Africa Utility Week Focus Day Substation Condition Monitoring Benefits of Ultrasound

Abstract. 1 Introduction

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

I P. /dt. di p V S Applications. Standards 1) IEC : 2007; IEC : ) IEC : 2016; IEC : 2017

High-Voltage Test and

Surge Generator for MIL-STD 1275

Extending the Functionality of On-line PD Monitoring Equipment for MV Power Cables

SMART CABLE GUARD A TOOL FOR ON-LINE MONITORING AND LOCATION OF PD S AND FAULTS IN MV CABLES ITS APPLICATION AND BUSINESS CASE

V P N. Voltage transducer DVM 2000-B = 2000 V

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and secondary circuit.

PERMANENT ON-LINE MONITORING OF MV POWER CABLES BASED ON PARTIAL DISCHARGE DETECTION AND LOCALISATION AN UPDATE

PHG 70 TD PD / PHG 80 TD PD

User s Manual Current Probe. IM E 1st Edition. Yokogawa Electric Corporation

ECP HV INSULATION TESTING

Cable testing and diagnostics

New clustering techniques based on current peak value, charge and energy calculations for separation of partial discharge sources

Specialists in HV and MV test and diagnostics. Testing in Substations

PD Solutions. On-Line PD Measurement Devices

H V T E S T S O L U T I O N S PA RT N E RS F O R H V & E M C

OPTIMIZATION OF ON-SITE PD MEASUREMENTS AND EVALUATION OF DIAGNOSTIC PARAMETERS FOR ASSESSING CONDITION OF DISTRIBUTION CABLE SYSTEM ELPIS J SINAMBELA

High Voltage Diagnostics Sarl 4, Rue de Lac CH 1897 Le Bouveret Switzerland

Type Test of a 145 kv Termination Type TS 145-II

TD-100. HAEFELY HIPOTRONICS Technical Document

Suppression of Pulse Interference in Partial Discharge Measurement Based on Phase Correlation and Waveform Characteristics

شركة الوقت للكهرباء والمقاوالت ذ.م.م.

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary circuit and the secondary circuit.

TD-106. HAEFELY HIPOTRONICS Technical Document. Partial Discharge Pulse Shape Analysis to Discriminate Near and Far End Failures for Cable Location

CONDITION ASSESSMENT OF XLPE MV CABLE JOINTS BY USING AN INSULATION TESTER

IEEE Transactions on Power Delivery. 15(2) P.467-P

Earthing of Electrical Devices and Safety

HO 50-S/SP30, HO 100-S/SP30, HO 150-S/SP30, HO 200-S/SP30, HO 250-S/SP30 and HO 200-S/SP31

IRIS POWER PDTracII. Continuous On-line Partial Discharge Monitoring for Motors, Generators, Dry Type Transformers, and Air-Insulated Switchgear.

HV AC TESTING OF SUPER-LONG CABLES

Name: Craig Goodwin. Company Name: HV Diagnostics Inc

7. INSPECTION AND TEST PROCEDURES

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

International Journal of Advance Engineering and Research Development. Comparison of Partial Discharge Detection Techniques of Transformer

PHV RO High Voltage Passive Probe. Instruction Manual

EI HIGH VOLTAGE INSULATION TESTING POLICY

Device Under Test: ALTEA VS- 24-I VS-24-I. 0 24/09/12 First issue A. Peretto L. Peretto 1 24/06/16 All text review E. Scala L. Peretto J. L.

CONTINUOUS ON-LINE MONITORING OF PARTIAL DICHARGES IN HV DISTRIBUTION CABLES

Transcription:

INVESTIGATION ON THE TECHNOLOGIES FOR DEFECT LOCALIZATION AND CHARACTERIZATION ON MEDIUM VOLTAGE UNDERGROUND LINES Gonzalo MAIZ, Iberdrola Distribución, (Spain), gmaiz@iberdrola.es Armando RODRIGO, Instituto Tecnológico de la Energía (ITE), (Spain), armando.rodrigo@ite.es Pedro LLOVERA-SEGOVIA, Instituto de Tecnología Eléctrica-Universidad Politécnica de Valencia, (Spain), pedro.llovera@ite.es Xabier BALZA, General Cable, (Spain), xbalza@generalcable.es ABSTRACT This study is based on the CORPRES project led by the utility Iberdrola and focused on improving the reliability of underground power lines of polymeric insulated Medium Voltage (MV) cables using the latest cable diagnosis technologies, mainly the analysis of partial discharges. The main concern is to detect and locate specific defects produced during the installation of the cable and of its accessories. The ageing of the cable is not considered in this research. A real-scale test bench was built expressly to analyze the validity and the precision of each of the technologies available for the detection of defects and their location in underground cables, fundamentally through the analysis of partial discharges. The voltage sources applied, the acquisition systems and the data analysis procedure were the basic differences between the different technologies used, which were: very low frequency (VLF), 50Hz resonant, resonant at variable frequency and damped alternating voltage (DAC). All the measurements were carried out by experts in each technology. The results show important differences between technologies when we compare the results for the same specific defect and when we compare all the defects on the cables and their accessories. This article describes the configuration of the test bench circuit and the criteria followed on designing the defects. A review of the technologies used was carried out with the aim of describing the main differences. The results obtained were analyzed from the point of view of the detection and of the location of defects. Finally, some processes were proposed for the standardization of the measuring equipment and procedures based on the results obtained. alternating voltage (DAC). The commercial units available on the market fixed the relationship between the measuring units and the high voltage sources used. During the CORPRES project all these partial discharge analysis technologies were tested and compared on a test bench specially designed for this purpose. The objective was to verify the behaviour of the different field technologies used to detect defects in the cable installations. The main objectives were: to establish the typology of defects caused during the installation of the cable and of its accessories, build a work bench reproducing this typology, and compare the technologies and the detection levels achieved by the latter. WORK BENCH AND DESCRIPTION OF THE DEFECTS As explained above, the first step was to establish the most common typology of defects caused during the installation of the cable and of its accessories. Using the historical data file of Iberdrola Distribution and the experience of the workforce, a catalogue of commonly found defects was obtained (see table 1). Defects on joints Irregular cut of external Example photos KEYWORDS Partial discharges, underground cable, underground cable accessories, time domain reflectometry. INTRODUCTION As the network expands and ages it is important to maintain its reliability. For this the utilities and the regulations of each country are developing test criteria for the commission and maintenance of cable systems. Partial discharge tests are becoming the most appropriate tests for the commission of new cable systems, replacing the previous DC tests. The partial discharge tests of cables systems on the field can be carried out using different types of energization sources, mainly very low frequency (VLF), 50Hz resonant, 20-400Hz variable frequency resonant and damped Longitudinal cut on the insulation Incorrect shape of the cable ends

Incorrect distance between the cable insulation and the body of the sleeve Partial perforation by sharp object Incorrect pressing of the body of the sleeve Excessive folding of the cable and return to its original position Inclusion of foreign elements in the body of the joint (water, earth, low voltage insulating tape) Permanent folding of the cable Defects on indoor and outdoor terminations Irregular cut of external Table 1 Typology of defects. Four cables of 12/20kV nominal voltage with HEPRZ1 insulation and cross-sections of 150mm 2 and 240mm 2 were laid in an underground gallery. The length of each cable was approximately 460 metres, approximately 60% installed on trays and 40% buried in dry ground. Prior to the tests the ground was watered to dampen it. Following the typology of defects shown in table 1, a set of accessories with artificial defects was installed on each cable, simulating defective installations like those found in real installations, but with a much greater density of defects. Longitudinal cut on the insulation Defective terminations Defective joints Folding Crushing Perforations Sheath damage Cable1 2 6 1 0 0 2 Incorrect distance between the insulation and the terminal Defects on cable Partial elimination of the sheath affecting the external Crushing of the cable Cable2 2 5 2 1 1 3 Cable3 1 4 1 0 0 1 Cable4 1 5 1 1 2 0 Table 2 Initial number and type of defects on each cable. Six companies tested the cables using different cable diagnosis technologies. The technologies used were very low frequency VLF (1 company), 50 Hz resonant (1 company), 20-400 Hz resonant (1 company) and damped alternating voltage DAC (3 companies). Up to thirty different test configurations were obtained per combination of the cables and tested by each company. The maximum voltage level applied was in all cases 2 U o, with U o = 12kV rms. TDR TEST RESULTS The first analysis was focused on the use of time domain reflectometry (TDR). This technique was used initially for the location of joints and, after the PD tests, for the location of partial discharges.

Table 3 presents the TDR analysis for the location of joints. Letters A to F represent the different companies performing the tests. Company A B C D E F Impedance changes detected 151 190-112 - - Impedance changes which coincide with joints 105 151-65 - - Detection [%] 69.54 79.47-58.04 - - Table 3 TDR statistical data. As shown in table 3, companies A, B and D performed the TDR analysis for joints detection, while C, E and F did not carry out the joint location analysis. The detection levels show that, for example, for company A, 69.54% of times the impedance change locations reported coincided with real joint positions, while 30.46% of times a joint was positioned in a location where there was no joint. An uncertainty of ±1% was used all along the cable to locate the impedance changes. It should be stressed that the detection levels would have been higher if the number of joints being tested had been lower. PD TEST RESULTS The analysis of partial discharges focused on two aspects. First, the study from the point of view of detection, and second, the validity of the data reported, that is how many times a defect existed in the location reported and how many times there was no defect in the position reported (see table 4). The location of the source of partial discharges was carried out in all cases by reflectometry. The uncertainty used for the calculations was ±1% all along the cable being tested. The number of defects generating PD was the number of defects detected at least by two companies. Company A B C D E F Number of cables tested 24 24 30 20 24 23 existing 52 53 53 55 53 55 generating PD 20 20 20 20 20 20 found 15 16 15 8 15 9 PD detection [%] 75 80 75 40 75 45 PD pulses reported 357 3365 209 335 468 69 PD pulses coinciding with defects 350 3197 159 288 455 67 PD pulses not coinciding with defects 7 168 50 47 13 2 PD pulses correctly positioned [%] 98.04 95.01 76.08 85.97 97.22 97.10 Table 4 Overall partial discharge results for each company. The PD detection ratios should be interpreted cautiously. For example, company C has a high number of defects reported which do not correspond to positions of real defects. These data indicate that there is an incorrect interpretation by the operator on carrying out the data analysis and locating the source of the partial discharges. In particular, in this case the importance of the human factor is shown to be clear within this kind of analysis, as there are another two companies using the same technology with better results. CONCLUSIONS There is a certain group of defects which does not produce partial discharges at the time of reception of the installation, and which therefore cannot be detected by means of partial discharge diagnosis techniques, although some of these types of defects can evolve, producing partial discharges and consequently an insulation breakdown in the cable. The TDR analysis shows that this technique can achieve good joint detection levels in cables. Very useful and reliable information can thus be used to contrast the joints found with those declared by the cable installers. The analysis of the results of the partial discharge detection success rate clearly shows the influence of the operator when field tests are carried out, and warns the utilities and the companies which analyze the cables to take into account the training of the personnel involved in this type of tests. Under the conditions in which this project was carried out, the experimental results show that there is not one partial discharge testing technology for installed MV cable systems which provides significantly better results than another. Companies A, B, F and E use different technologies with different types of high voltage sources, different sensors and different data filtering and analysis tools, but have overall similar success rates. Although the analysis of results on a large population of cables shows that similar results can be obtained using different technologies, and moreover it has been confirmed that the influence of the operator is critical, large differences can be found when the analysis of results is focused on one MV cable in particular. An example of this is shown in figure 2, where the axis X represent an MV cable being tested, indicating on the thick line two lengths of cable with a cross-section of 240mm 2 and on the thin line a length of cable with a cross-section of 150mm 2. Each mark represents an artificial defect made on the cable or its accessories. In this case, the defect D1 was detected by companies A and B, while the defect D2 was detected by companies A, C and E, and the defect D3 was detected by companies A, B, C, D and E.

The study of cables separately shows differences Fig. 2 PD activity on a cable measured by different companies. between technologies, possibly due to the different voltages levels of PD inception on each defect depending on the type of the voltage source. In conclusion, the partial discharge tests cannot be compared among themselves if different types of voltage sources are used for testing. The possible relationship between the magnitude of the partial discharges and the type of high voltage source used was investigated, but no relationship was found between them due to the great dispersion of results. The same conclusion was reached on researching the possible relationship between the PD inception voltage levels and the type of voltage source used. It was not possible to establish any correlation. It was observed that there is no unanimity among the different equipment available on the market when it comes to determining the form in which the assessment of the PD level is carried out. Of the four technologies used in this project, three different methods were found to carry out the assessment of the PD level. The simplest method obtains the calibration constant starting from the relationship between the injected calibration charge and the peak value of the pulse recorded. Another method obtains the calibration constant starting from the relationship between the calibration load and a partial integration of the pulse detected. The final method consists of obtaining the calibration constant with the regulatory method described in IEC 60270 which consists of obtaining the calibration constant from the relationship between the calibration pulse and the peak value of a quasi-integration of the pulse. Independently of the method in which the PD level is assessed, all the methods obtain their reference constants from the calibration process, so the calibrators play a fundamental role in the process. It was detected that there are calibrators with excessively small rise times, which causes high current peaks with equal charge, thus increasing the difference of results between technologies. The differences in load obtained between different types of technologies could be reduced partially if the characteristics of the calibrators, the sensors and the way in which the load is assessed were more delimited for the field tests. Figure 3 shows an example of three types of wave belonging to three calibrators from different manufacturers. The pulses shown were captured on an analog bandwidth oscilloscope of 500MHz with a sampling of 1.25GS/s. The load resistance of the oscilloscope of 50Ω was used. All the calibration pulses correspond to the 200pC range of each calibrator. Fig. 3 Pulses of 200pC of three different calibrators. As can be seen in figure 3, the load injected values from the calibrators expressed in picocoulombs (pc), do not correspond to the 200pC range chosen, presenting differences of up to 22%. In addition, the rise and fall times and duration of the pulses present substantially different durations. Therefore, even the 163pC pulse presents a peak value above the pulse of 183pC. These variations obviously influence the assessment of the magnitude of the PD and the processes to estimate the sensitivity of the measurement and the noise. An example of difference in the PD level obtained for different technologies is shown in figure 4, where the magnitudes obtained by each company are shown for the same defective accessory, in this case a joint. Fig. 4 PD activity on a joint. It is also important to stress that during the partial

discharge tests it was demonstrated that the use of simple clips as an element of connection between the cable being tested and the high voltage source may generate PD. To avoid generating corona type partial discharges at the connection point, connection clips should only be used when the connection is made between discs, plates or toroids at the same potential as the clip, and only when there is no termination installed at the connection point. For cell type connectors the appropriate connector must be used (see figure 5). REFERENCES [1] IEC 60270 High-voltage test techniques - Partial discharge measurements. [2] IEEE 400-2001 Guide for Field Testing and Evaluation of the Insulation of Shielded Power Cable Systems. [3] IEEE 400.2-2004 Guide for Field Testing of Shielded Power Cable Systems Using Very Low Frequency (VLF). [4] IEEE 400.3-2006 Guide for Partial Discharge Testing of Shielded Power Cable Systems in a Field Environment. [5] IEC 60885-2, 1987, Electrical test methods for electric cables Part 2: Partial discharge tests. [6] IEC 60885-3, 1987, Electrical test methods for electric cables Part 3: Test methods for partial discharge [7] ICEA T-24-380-1994, Guide for Partial-Discharge Test Procedure. GLOSSARY Fig. 5 Connections free from PD appropriate for use in field tests. PD: Partial discharge TDR: Time domain reflectometry Acknowledgments Project CORPRES was supported by the Spanish ministry Ministerio de Industria, Turismo y Comercio under program PROFIT 2007-2010. Many thanks to partial discharge test equipment manufactures and their staff involved.