OBSI Testing of Iowa US 30 Diamond Ground Surfaces Preliminary Report

Similar documents
Arizona I-10 EB NGCS and CDG Test Section Draft Construction Report

Tire/Pavement Noise 1

PCCP Preservation Steps to Take to Extend Pavement Life and Performance of Your Concrete Pavements

Precast Concrete Pavement Background Concepts. Project 1517 FHWA, CTR & TxDOT Gary Graham November 15, 2001

Jointing Rural Intersections

Responses to Concrete Specifications Survey with Summary (2011)

Effectiveness of Tire/Road Noise Abatement through Surface Retexturing by Diamond Grinding for Project SUM

The Influence of Quieter Pavement & Absorptive Barriers on US 101 in Marin County

ITS specification Inductive loops and feeder cables (ITS-03-01)

The Shoppes at Forney Crossings

TRAFFIC ENGINEERING SAB3843. CHE ROS BIN ISMAIL and OTHMAN BIN CHE PUAN

Application Guidelines for Pavement Markings in Grooved Pavement Surfaces

IGGA Guide Specification: Dowel Bar Retrofit (DBR) Introduction

Design and Construction of Highway Pavement Joint Systems

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION

Appendix Traffic Engineering Checklist - How to Complete. (Refer to Template Section for Word Format Document)

Dowel Bar Standardization. NC^2 Spring Meeting Savannah, GA

Methods for Reducing Emissions from Switching Power Circuits. A. McDowell, C. Zhu and T. Hubing

Effectiveness of Noise Barriers Installed Adjacent to Transverse Grooved Concrete Pavement

-_if-;reliminary STUDY IN THE DEVELOPMENT OF A METHOD FOR / EVALUATING THE RELATIVE POLISHING CHARACTERISTICS OF I BITUMINOUS PAVING MIXTURES

Patented Precision. 8 August US Patent 6,775,914 Can Patent 2,405,133 Other Patents Pending. surpro.com

Appendix B: Transportation B-10 Toll Plaza Analysis

AMENDMENTS Manual of STANDARD SPECIFICATIONS. Adopted by Standard Specifications Committee. Amendment. No. 6. Published by

Stamark Pavement Marking Tape and Liquid Pavement Markings Application Guidelines for Pavement Markings in Grooved Pavement Surfaces

Noise Mitigation Study Pilot Program Summary Report Contract No

Fast Track Precast Concrete Pavement Rehabilitation Pilot Project

Jointed Precast Concrete Pavement

REVIEW TOPICS CEEN 2320 FINAL EXAM

OPERATING PAVEMENT PROFILOGRAPH AND EVALUATING PROFILES

FINAL REPORT. On Project Supplemental Guidance on the Application of FHWA s Traffic Noise Model (TNM) APPENDIX K Parallel Barriers

Development of a Pavement Marking Condition Index from Retroreflectivity and Presence Measurements

4.1. Foremen 4.2. Concrete plant manager 4.3. Concrete plant operator 4.4. Personnel performing saw cutting and joint sealing

DELINEATOR REFERENCE POINT 200' TYPICAL SPACING (YELLOW DELINEATORS) END OF MERGE LANE TAPER DELINEATOR REFERENCE POINT

Stones and Beads Manufacturing Company. Lapidary/Faceting Machinery Catalog

BARRELL VAULT BATTENLESS

USE OF TEAR-OFF RECYCLED SHINGLES IN ASPHALT PAVEMENTS

THE ATTENUATION OF NOISE ENTERING BUILDINGS USING QUARTER- WAVE RESONATORS: RESULTS FROM A FULL SCALE PROTOTYPE. C.D.Field and F.R.

Chapter 6: SHOP DRAWINGS AND OTHER SUBMITTALS

PUBLICATION 213. Think Safety First

State Road A1A North Bridge over ICWW Bridge

MODULE 10: INTELLIGENT TRANSPORTATION SYSTEMS: SMART WORK ZONES LESSON 1: WORK ZONE SAFETY

Exit 61 I-90 Interchange Modification Justification Study

Diversion Analysis. Appendix K

Mobile Survey of Rail Track and Bed

Single Point Urban Interchange (SPUI) with Signals

Table 5G-2.01: Transverse Joint Requirements. Transverse Joint Type 6 C 12 7 C 15 8 CD CD CD 1 20

Diamond D Commstones

FINAL REPORT. On Project Supplemental Guidance on the Application of FHWA s Traffic Noise Model (TNM) APPENDIX L Tunnel Openings

Driving Performance in a Simulator as a Function of Pavement and Shoulder Width, Edge Line Presence, and Oncoming Traffic

2012 PURDUE ROAD SCHOOL Session 56. JW Stanger, P.E. Rieth-Riley Construction Co., Inc.

Performance of Roadside Sound Barriers with Sound Absorbing Edges

Project No.: VTRC 06-R22 March Period Covered: Contract No.

SPECIAL PROVISION TO SPECIAL SPECIFICATION Reflectorized Pavement Markings with Retroreflective Requirements

FINAL REPORT. On Project Supplemental Guidance on the Application of FHWA s Traffic Noise Model (TNM)

PAVEMENT SURFACE CHARACTERISTICS. Task 3 DEVELOPMENT OF A SOUND ABSORPTION PROTOCOL. Principal Investigator:

B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following.

Design and Construction of Highway Pavement Joint Systems

APPENDIX C: MAIN RIVER BRIDGE PLANS. The graphics in this appendix depict the Practical Alternatives.

Plan Preparation Checklist

Pavement Markings Under Wet Night Road Conditions. A Comparison of 2 Beads in Grooved High Build Waterborne on I-215I

Ohio Department of Transportation Office of Roadway Engineering January 18, 2013

Section 914. JOINT AND WATERPROOFING MATERIALS

ENTERPRISE Transportation Pooled Fund Study TPF-5 (231)

Applying Fret Space Numbers and/or the Label Set to a Fretted Fingerboard

Glass Fiber Reinforced Polymer (GFRP) Dowel Bars - Aslan 600

King Mill Lambert DRI# 2035 Henry County, Georgia

State of the Art Precast, Prestressed Concrete Bridges and Industry Innovations

Full-Scale Testing of Single and Parallel Highway Noise Barriers

TURNING TOOLS CARVING TOOLS

Introduction...2 Product Application Requirements...3 Adhesive Series of Stamark Tapes...3 Hot Inlay Application of Long Lines...

Precast Concrete Panels for Rapid Pavement Repair

Session 8: Load Transfer Restoration. (Dowel Bar Retrofit, Cross-Stitching, and Slot Stitching)

Test Protocol for the Rolling Density Meter

Concrete Pavement Preservation

Washington County Road Engineering Plan Submittal/Review Checklist

BRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006

U. M. ARMY Texas Conference. Wheel Chair Ramp Manual

Abilene District Traffic Signal Timing and Capacity Analysis

Evaluation of In-Pavement Light Fixture Designs and Performance

5/16" Flange nut. Bolt Keeper Plate (8" Sq. SYS.) (3) 1/2" x 3" Hex head connector zinc plated bolt w/ washers and nut. Anchor 3" sq. 7 Ga.

AngelusPavingstones.com. Courtyard Stone. Sq Ft per Stone Stones per Sq Ft Sq Ft per Pallet Stones per Pallet Weight per Stone

I-W07/W77. Couplings DETAIL A WARNING. Photo Showing Pipe with Weld Seam Ground 6 inches/152 mm Back from Pipe End and an AGS Groove

EVALUATING AN ADAPTIVE SIGNAL CONTROL SYSTEM IN GRESHAM. James M. Peters, P.E., P.T.O.E., Jay McCoy, P.E., Robert Bertini, Ph.D., P.E.

GrindLazer. Scarifier Systems

DESIGN OF VOICE ALARM SYSTEMS FOR TRAFFIC TUNNELS: OPTIMISATION OF SPEECH INTELLIGIBILITY

Structural Criteria for Residential Rooftop Solar Energy Installations

Demolition of Ramp C (SN ): Westbound Ontario Street to Eastbound I-90/94) over I-90/94 (JF Kennedy Expressway)

Oakland International Airport Master Plan Update

Structural Criteria for Residential Rooftop Solar Energy Installations

See Detail C 1. 30'' Long Tie Bar. at 12'' Centers 'DW' 3. Pavement Edge. 24'' min. Plastic or Tarpaper Wrapped. Header Block

Meeting customer requirements for ROEBEL cable for ac applications

ATOMIC. ASM Panel Brochure ARCHITECTURAL SHEET METAL,

RIDGEMASTER PLUS CAUTION INSTALLATION INSTRUCTIONS ALWAYS WEAR SAFETY GLASSES TOOLS NEEDED GENERAL GUIDELINES FOR RIDGEMASTER PLUS AND HIPMASTER

Research. Maria Masten, P.E and Gordy Bruhn MnDOT Concrete Engineering Unit CPAM Concrete Paving Workshop March 9, 2017

Errata to Procedural Standard for Sound & Vibration Measurement 2015 Third Edition

IPRF Research Report Innovative Pavement Research Foundation Airport Concrete Pavement Technology Program

Segmental Bridge Technology Established and Evolving. W. Jay Rohleder, Jr, P.E., S.E. Senior Vice President / Project Development FIGG

W 869 SN 303 S. Paterson Street, Ste. 1 Madison, WI ph Structural Engineering: /Users/paulcuta/Desktop/1603 Finals/1603

Diamond Knowledge Base. Inductive Loop Guide. Introduction

EXTRACTING REAL-TIME DATA FROM A DRIVING SIMULATOR SEYED AMIRHOSSEIN HOSSEINI. Bachelor of Engineering in Civil Engineering QIAU May 2012

Transcription:

2010 OBSI Testing of Iowa US 30 Diamond Ground Surfaces 9-29- 10 Preliminary Report On September 29, 2010 the ACPA conducted OBSI testing of three diamond ground surfaces constructed by Manatts Incorporated for the IGGA. Three diamond ground surfaces were constructed, a flush ground surface with ¾ c-clongitudinal grooving, a conventional diamond ground surface (CDG) with 1/8 grooves spaced at ¾ c-c, and a CDG section. Each section was approximately 600 ft long. The OBSI testing indicated the flush ground and grooved surface produced an OBSI Level of 99.1 dba, the CDG with grooving 100.6 dba, and the CDG 100.4 dba. 1 ACPA Larry Scofield 10/19/2010

Introduction On August 16, 2010, Manatts Incorporated constructed three diamond ground test sections on the eastbound roadway of US30 beginning at approximate milepost 194 and proceeding in an easterly direction as indicated in Figure 1. Each of the three sections was approximately 600 ft in length (e.g. 200m) as the project is stationed in meters. The three test sections consisted of a flush grind and grooved section (1/8 grooves ¾ oc), a conventional diamond ground (CDG) section with grooves spaced on ¾ centers and a CDG only section. To produce the flush grind and grooved section, the 110 spacers normally used between the cutting blades were removed so that the segments were flush with each other. The flush ground surface was then grooved with 1/8 wide blades spaced on ¾ centers. The same grooving equipment was used to groove sections TS-1 and TS-2. The CDG performed on sections TS-2 and TS-3 used 125 blades with 110 spacers. The three test sections were constructed just west of an earlier experiment constructed by CP Tech Center in 2005 1. The earlier project consisted of placing 18 test sections of various forms of tined and drag surface textures. One short (approximately 170 ft) diamond grind texture was also incorporated in that experiment. The current test sections were placed to provide linkage between the earlier work on tined textures and diamond ground surfaces. Since there was insufficient area to place the three new sections within the 2005 as-built project, the three sections were located on a 2001 as-built project that was constructed from material from the same pit and used the same joint spacing and dimensions as the 2005 as-built project. Figure 1 Test Section Layout for Diamond Ground Surfaces Manatts used a PC6000 diamond grinder with a 4 ft head to CDG all three test areas first 2. Then, for the flush grind and grooved surface, they used a PC-150 with the head staked to 19 inches in width 2. They eliminated the spacers for this pass so that the blade segments were flush to each other enabling a smooth, flush ground texture. Older blades (123) were used to produce the texture on the lands. Upon completion of the flush grinding, the PC-150 head was restacked to a grooving head to groove TS-1 and TS-2 at the same time. The grooving head was 32 inches in width and stacked with 125 blades set at ¾ centers 2. All three test sections in the EB roadway were constructed in one day. The eastbound roadway consisted of a 14ft travel lane and a 12 ft passing lane. Both EB lanes were ground in all three test sections. The CP Tech Center observed construction of the sections and prepared a construction report see reference 1 for construction details. Figure 2 indicates close up photos of each of the textures. Additional texture photos are included in Appendix 1 thru 3 which contain photos of Test Sections 1 thru 3, respectively. As indicated in Figure 2, the flush ground and grooved pavement exhibits approximately 5 ridges 1

Test Section 1 Flush Grind and Groove Test Section 2 CDG and Groove Test Section 3 CDG Figure 2 Close Up Views of Test Section Textures 2

on the land area, where the CDG with grooves exhibits three ridges per land area. The CDG texture also exhibits three ridges in the same distance since it was constructed with the same conventional grinding head as section 2. Figure 3 indicates the location of the sections east of Marshalltown, Iowa. Figure 3 Location of Test Sections Indicated by Red Flag Near Marshalltown, Iowa OBSI Test Results On September 29, 2010 the ACPA conducted OBSI testing of these sections using the ACPA dual probe OBSI system, ACPA 2009 SRTT tire, and a 2010 Chevy Malibu. Testing was conducted at 60 mph using the vehicle cruise control. Due to the rolling terrain, it was difficult to maintain speed without driver input to the vehicle speed. Test section 1 (e.g. flush grind and groove) was located at the bottom of a sag curve on the uphill side of the sag. Test sections 2 and 3 continued on the same uphill grade. This roadway geometry would tend to accelerate the vehicle into the sag and then reduce the speed on the uphill grade. Testing was conducted between 4 and 6 PM and temperatures ranged between 78 and 81 o F with most of the testing conducted between 80 to 81 o F. Three repeat runs were made for each section by testing all three textures in sequence before conducting the next set of replicate runs. Five second OBSI tests were conducted for each test and analyzed between 500 Hz to 5000 Hz. Figure 4 indicates the overall A-weighed OBSI level for each texture. As indicated, the flush ground with grooved section (TS-1) was the quietest section by approximately 1.5 dba. The sections had received approximately six weeks of traffic at the time of OBSI testing so there may be additional reduction of texture on the CDG sections in the future. 3

Sound Intensity Level, dba Sound Intensity Level, dba Figure 5 indicates the one-third octave spectra for each of the center band frequencies between 500 Hz and 5000 Hz. As indicated, the flush ground and grooved texture was the quietest of the textures below 1000 Hz and between 1000 Hz and 1600 Hz. Future additional fin breakage on the CDG sections may reduce the frequency levels below 1000 HZ. 106 104 102 100 98 96 99.1 Flush Grind & Grooved 3/4" oc 100.6 Conventional Diamond Grind & Grooved 3/4" oc 100.4 Conventional Diamond Grind 94 105 100 Pavement Section Figure 4 Overall A weighted OBSI Levels Flush Grd - Grooved CDG-Grooved CDG 95 90 85 80 75 500 630 800 1000 1250 1600 2000 2500 3150 4000 5000 1/3 Octave Band Center Frequency, Hz Figure 5 One-Third Octave Spectra for Each Texture Type 4

Friction Test Results On September 26, 2010 the Iowa DOT conducted ASTM E-274 testing using both the ribbed tire (E-501) and the smooth tire (E-524). Testing was conducted at 40 mph approximately three weeks after construction. The results of that testing are indicated in Table 1. As indicated, the flush grind and groove has the lowest friction for both the ribbed and smooth tire results. However, as the textures age and the CDG fins are reduced under traffic the three textures may become more similar in friction levels. It should be noted that only the CDG texture with grooves exhibited the higher smooth tire than rib tire friction result. TABLE 1 FRICTION TEST RESULTS Test Section Description Ribbed Tire Result Smooth Tire Result Flush Grind and Groove (TS-1) 48.0 46.6 CDG and Groove (TS-2) 49.4 49.9 CDG (TS-3) 50.4 47.2 References 1. Cable, Jim, Final Report-Surface Characteristics Next Generation Grooving and Grinding Test Site- Construction Report, July 16-17, 2010. 2. Frentress, Dan, Iowa Trip Report, August 26, 2010 5

Appendix 1 Flush Ground and Grooved Test Section 1 Figure 1-1 Overview Photo of Flush Ground and Grooved Test Section 1 Figure 1-2 Close Up of Flush Ground and Grooved Texture in Test Section 1 6

Appendix 1 Flush Ground and Grooved Test Section 1 Figure 1-3 View of Flush Ground and Grooved Texture Across Lane in Test Section 1 Figure 1-4 Close Up of Flush Ground and Grooved Texture on Section 1 7

Appendix 1 Flush Ground and Grooved Test Section 1 Figure 1-5 Ground Level View of Flush Ground and Grooved Texture on Section 1 Figure 1-6 Close Up of Texture in Flush Ground and Grooved (3/4 ) Texture on Section 1 8

Appendix 1 Flush Ground and Grooved Test Section 1 Figure 1-7 Stationing 100 Indicating Beginning of Flush Ground and Grooved Section 1 9

Appendix 2 CDG with ¾ Grooved Test Section 2 Figure 2-1 Overview of Test Section 2 for CDG with ¾ Groove Spacing Figure 2-2 Overview of CDG with ¾ Grooving on Section 2 10

Appendix 2 CDG with ¾ Grooved Test Section 2 Figure 2-3 Close Up of CDG Texture with ¾ Groove Spacing on Section 2 Figure 2-4 Close Up of CDG Texture with ¾ Groove Spacing on Section 2 11

Appendix 2 CDG with ¾ Grooved Test Section 2 Figure 2-5 Beginning Station for CDG with ¾ Groove Spacing on Section 2 12

Appendix 3 CDG Test Section 3 Figure 3-1 Overview Photo of CDG Test Section 3 Figure 3-2 Ground Level View of CDG Texture in Section 3 13

Appendix 3 CDG Test Section 3 Figure 3-3 Ground Level View of CDG Texture in Section 3 Figure 3-4 Close Up of CDG Texture in Section 3 14

Appendix 3 CDG Test Section 3 Figure 3-5 Very Close Up View of CDG Texture in Section 3 Figure 3-6 Photo of Station at the Beginning of CDG Section 3 15

Appendix 4 Miscellaneous Project Photos Figure 4-1 Photo of Transverse Joint Sealant on Existing US 30 EB Pavement Figure 4-2 Photo of Transverse Joint Sealant Condition and Width 16

Appendix 4 Miscellaneous Project Photos Figure 4-3 View of Aggregate Size Evident in Original Pavement Figure 4-4 Photo of Original Asbuilt Construction Data for Existing Pavement Construction 17