A Novel Control Approach for Microgrids Islanded Operation - Load Step Pre-announcement and Bang-Bang Control

Similar documents
Optimal sizing of battery energy storage system in microgrid system considering load shedding scheme

EE 742 Chapter 9: Frequency Stability and Control. Fall 2011

Hybrid Anti-Islanding Algorithm for Utility Interconnection of Distributed Generation

Chalmers Publication Library

Modle 6 : Preventive, Emergency and Restorative Control. Lecture 29 : Emergency Control : An example. Objectives. A simple 2 machine example

Frequency Control Method of Isolated Micro-grid Based on Thermostatically Controlled Load Qingzhu Wan1, a, Yuan Bian1, b and Yalan Chen1, c

Non-detection zone of LOM protection for converter connected wind turbines

Active Power Sharing and Frequency Control of Multiple Distributed Generators in A Microgrid

Chapter 10: Compensation of Power Transmission Systems

Renewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA

EH2741 Communication and Control in Electric Power Systems Lecture 2

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation

CHARACTERISTIC NUMBERS OF PRIMARY CONTROL IN THE ISOLATED ESTONIAN POWER SYSTEM

IJESRT. (I2OR), Publication Impact Factor: (ISRA), Impact Factor: Student, SV University, Tirupati, India.

Islanding Detection Method Based On Impedance Measurement

The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller

Alternatives for Primary Frequency Control Contribution from Wind Power Plants Connected to VSC-HVDC Intertie

UNIVERSITY OF CALGARY. Fuzzy Logic Controller for a Hydro Pumped Storage Plant to Provide Frequency Regulation in. an Isolated Hybrid Micro-Grid

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

Methods to Enable Open-Loop Synchronization For Islanded Systems

Islanding Detection and Frequency Circuit Measurement by Power Distribution Relation Depending on the Angle

Cost Based Dynamic Load Dispatch for an Autonomous Parallel Converter Hybrid AC-DC Microgrid

A Control Method of Parallel Inverter for Smart Islanding of a Microgrid

Application of a MW-Scale Motor-Generator Set to Establish Power-Hardware-in-the-Loop Capability

Protection of Microgrids Using Differential Relays

Considerations and Recommendations for the Harmonisation of Under Frequency Loadshedding Schemes in Multi Zone Meshed Grids

FREQUENCY and VOLTAGE, ranges and durations

each time the Frequency is above 51Hz. Continuous operation is required

Parameters related to frequency stability

Automatic connection/reconnection and admissible rate of change of active power

Lecture 15 EMS Application II Automatic Generation Contol. Davood Babazadeh

INITIAL RfG FREQUENCY PARAMETER SELECTION. BASED ON DRAFT RfG VALUES. Requirement Range Suggested GB Value Comments

A Three-Phase Grid-Connected Inverter for Photovoltaic Applications Using Fuzzy MPPT

An Adaptive V-I Droop Scheme for Improvement of Stability and Load Sharing In Inverter-Based Islanded Micro grids

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

Improvement of Power Quality in Distribution System using D-STATCOM With PI and PID Controller

Internal active power reserve management in Large scale PV Power Plants

1400 MW New Zealand HVDC Upgrade: Introducing Power Modulation Controls and Round Power Mode

Development of an Experimental Rig for Doubly-Fed Induction Generator based Wind Turbine

IMPLEMENTATION OF NEURAL NETWORK IN ENERGY SAVING OF INDUCTION MOTOR DRIVES WITH INDIRECT VECTOR CONTROL

Power Quality Improvement Utilizing Photovoltaic Generation Connected to a Weak Grid

State of Charge (SOC)-Based Active Power Sharing Method for Distributed Generations in an Islanded Microgrid

The Role of Effective Parameters in Automatic Load-Shedding Regarding Deficit of Active Power in a Power System

A Review of Adaptive Under Frequency Load Shedding Scheme on Islanded Distribution System Using MATLAB/SIMULINK

Microgrids and Energy Management SURYANARAYANA DOOLLA POWER ENGINEERING LAB DEPARTMENT OF ENERGY SCIENCE AND ENGINEERING INDIAN INSTITUTE OF

Regulated Voltage Simulation of On-board DC Micro Grid Based on ADRC Technology

Modelling and Simulation of a DC Motor Drive

Transient Stability Analysis in Micro grids Using P-f & Q-V dot droop controller

Fuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1)

Power Frequency Droop Controller For Stability Analysis In Micro Grids

Broadcast Communication by System Frequency Modulation

Decentralized Model Predictive Load Frequency Control of deregulated power systems in tough situations

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

SIMULATION OF D-STATCOM AND DVR IN POWER SYSTEMS

An Investigation of Controlled System Separation Following Transient Instability

COMPUTATION OF STABILIZING PI/PID CONTROLLER FOR LOAD FREQUENCY CONTROL

Design and implementation of Open & Close Loop Speed control of Three Phase Induction Motor Using PI Controller

Embedded Generation Connection Application Form

Modelling and Simulation of High Step up Dc-Dc Converter for Micro Grid Application

Embedded Generation Connection Application Form

Closed-Loop Position Control, Proportional Mode

Simplified Wind Turbine Model for the Simulation of Frequency Support Mode of Operation

Testing Advanced Photovoltaic Inverters Conforming to IEEE Standard 1547 Amendment 1

Mitigation of Frequency Deviation with Resonant Controller in Microgrid with the Robust Control of an Attached Storage System

Matlab Simulation of a High Step-Up DC-DC Converter for a Micro grid Application

Breakthrough in Test Procedures for Islanding Detection

DEVELOPMENT OF SMART UNDERFREQUENCY LOAD SHEDDING SYSTEM

Control of Load Frequency of Power System by PID Controller using PSO

A Real-Time Regulator, Turbine and Alternator Test Bench for Ensuring Generators Under Test Contribute to Whole System Stability

MODELING AND CONTROL OF DISTRIBUTED ENERGY SYSTEMS DURING TRANSITION BETWEEN GRID CONNECTED AND STANDALONE MODES. A Dissertation.

The Coupling of Voltage and Frequecncy Response in Splitting Island and Its Effects on Load-shedding Relays *

Chapter 3 : Closed Loop Current Mode DC\DC Boost Converter

IMPROVING EFFICIENCY OF ACTIVE POWER FILTER FOR RENEWABLE POWER GENERATION SYSTEMS BY USING PREDICTIVE CONTROL METHOD AND FUZZY LOGIC CONTROL METHOD

A Topology-based Scheme for Adaptive Underfrequency Load Shedding

IEEE Major Revision of Interconnection Standard

A PHOTOVOLTAIC POWERED TRACKING SYSTEM FOR MOVING OBJECTS

Tripping of circuit breakers in PV installations due to zero sequence field impedance

Discussion on the Deterministic Approaches for Evaluating the Voltage Deviation due to Distributed Generation

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management

Transients of a Micro-Grid System with Multiple Distributed Energy Resources

BIDIRECTIONAL SOFT-SWITCHING SERIES AC-LINK INVERTER WITH PI CONTROLLER

AUTOMATIC VOLTAGE REGULATOR AND AUTOMATIC LOAD FREQUENCY CONTROL IN TWO-AREA POWER SYSTEM

SOLAR POWERED REACTIVE POWER COMPENSATION IN SINGLE-PHASE OPERATION OF MICROGRID

A High Voltage Gain DC-DC Boost Converter for PV Cells

5 Summary test results and additional findings

Modelling of Photovoltaic power plants in SIMPOW

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

Combination of Adaptive and Intelligent Load Shedding Techniques for Distribution Network

SYNCHRONOUS MACHINES

INCIDENTS CLASSIFICATION SCALE METHODOLOGY

SCIENCE & TECHNOLOGY

CHAPTER 4 LOAD FREQUENCY CONTROL OF INTERCONNECTED HYDRO-THERMAL SYSTEM

Short Circuit Calculation in Networks with a High Share of Inverter Based Distributed Generation

Comparative Study of P&O and InC MPPT Algorithms

Islanding Detection Technique based on Simulation of IEEE16 Bus System

CONCLUSIONS AND SCOPE FOR FUTURE WORK

Differential Protection Optimal differential protection for phase shifter transformers and special transformers

DSP-Based Simple Technique for Synchronization of 3 phase Alternators with Active and Reactive Power Load Sharing

Excitation Systems THYRIPART. Compound-Excitation System for Synchronous Generators. Power Generation

Transcription:

A Novel Control Approach for Microgrids Islanded Operation - Load Step Pre-announcement and Bang-Bang Control Yi Guo*, Wolfgang Gawlik TU Wien, Institut für Energiesysteme und Elektrische Antriebe, Gußhausstraße 25/370-1, 1040 Wien; Tel.:+43-1-58801-370-128; Fax.: +43-1-58801-370199; guo@ea.tuwien.ac.at; www.ea.tuwien.ac.at Abstract: In terms of high penetration of distributed energy resources, power systems undergo challenges on aspects of their operation, stability and control issues. Microgrids gained a lot of research interest because they have a promising future to integrate the distributed energy resources into the power systems, reduce greenhouse gas emissions and increase the reliability and security of the power systems. Frequency control is an important control method applied in power systems. In this paper, an islanded microgrid implementing frequency control is modeled. Furthermore, a novel control method including load step preannouncement and bang-bang control is used together with frequency control and some dynamic simulation results of the islanded microgrid are presented. It compares the results among systems with different starting time constants, control schemes and shares of photovoltaics. It also analyzes whether the implementation of load step pre-announcement and bang-bang controller is feasible and useful. Keywords: Islanded microgrid simulation, distributed generation, frequency control, load step pre-announcement, bang-bang control 1 Introduction The Microgrid (MG) concept has been proposed due to the high penetration of distributed energy resources (DER) in electrical network systems. Diverse MG projects [1] are carried out globally focusing on their different technology aspects. To ensure a more reliable and secure energy supply system, different control strategies of MGs are researched. MGs can be operated both in grid-connected and islanded mode. During the grid-connected operating mode, frequency is controlled by the main grid. However, frequency has to be controlled via coordination among distributed generators (DG) within MGs when the latter are in islanded mode. Unlike large conventional power plants, DERs mostly have low or no inertia [2]. Therefore, when a mismatch between power supply and demand occurs in islanded mode, frequency changes quickly and is difficult to be controlled. In this paper, frequency control is implemented in an islanded MG. In addition, load preannouncement (LSP) together with a bang-bang controller (BB controller), which intend to improve the frequency response of islanded MGs, are presented. Seite 1 von 14

2 Frequency Control In islanded mode, any small change in supplied and demanded power of Microgrids can cause a severe frequency deviation because of the small total size of the system. Hence control of MGs is one of the main concerns for MGs operation. Frequency control [3] is one important control method to maintain the frequency within the nominal operating conditions. In a large power system, frequency control loops, including primary control, secondary control, tertiary and emergency control, are usually available. Among the four control forms, the primary and secondary control are two basic control loops in a power system. 2.1 Primary Control The primary control of generators provides a local droop control [3] and responds to the frequency deviation of power system within a few seconds. The active power and frequency (P/f) droop control characteristic is formulated as: (f f 0 ) = 1 k (P P 0i) (1) The f 0 is the nominal set points of frequency and P 0i is the dispatched power of generator i defined at the nominal frequency. 1/k is the frequency droop control setting, which is the ratio of frequency deviation to the change of generator power output. Droop settings are usually described as % droop. For instance, when k = 25, it indicates a 4% frequency droop, which means that 4% frequency deviation causes 100% change in power output. With a 4% droop, the power output will increase by 25% if the frequency drops by 1%. Figure 1. Active power / frequency droop control characteristic [3] The P/f droop characteristic is shown in figure 1. When the system frequency drops from f 0 to f 1, generators participating in primary control should increase the power output from P 01 to P 1 and from P 02 to P 2. When the lower frequency limit is reached, the generators, which participate in the droop control, reach their maximum power rating, which are P 1max and P 2max as shown in the figure. The droop characteristic allows different generators to operate at the Seite 2 von 14

same frequency with different power outputs, track the load change and bring back the frequency. The system frequency stays at a certain value once a new balance between power supply and demand is achieved. However, this new steady point of frequency could be different from the nominal operating point, because of the proportional action of the generators droop control. 2.2 Secondary Control The primary control can react very fast to small frequency deviations in power systems. However, it also allows the power systems to operate at a new set point of frequency, which can be below or above the nominal value, once the balance is established between power supply and demand. Therefore, the secondary control [3] is required to restore the system frequency to the nominal value. The secondary control is a feedback control loop, which reacts on the frequency deviation and is added to primary control loop via a proportionalintegral (PI) controller. The secondary control works in a timescale of several minutes to bring the frequency back to the nominal point. In a severe situation, the tertiary control, emergency control and protection schemes should be considered to re-establish the nominal frequency if the frequency drops quickly to a critical value. Under normal circumstances, tertiary control is used to replace secondary control reserves. 3 Load Step Pre-announcement and Bang-Bang Controller Microgrids have a low inertia in island mode, thus, frequency control of MGs is difficult to be achieved without the support from the overall network. In this paper, load step preannouncement and a bang-bang controller are designed and applied to provide a better control system to MGs. 3.1 Load Step Pre-announcement To anticipate the change between load and generation, LSP is planned for the simulation model. LSP receives signals from the load side and delivers them to the overall system continuously. When LSP gets a load change signal, LSP will delay it for a defined short period and maintains the previous load in the system. Meanwhile, LSP gives a signal within the preset time of the delay period to the bang-bang controller to control the conventional generator in order to start increasing or decreasing power output before the real load change happens. Depending on the system inertia constant and dynamics of the generators participating in primary control, the delay time is set differently. In this system, the delay time for releasing a load change is set to be 40 ms, which can be further optimized. 3.2 Bang-Bang Controller Bang-bang control [4] is often used in the control of non-linear systems. A BB controller is a feedback controller which switches between two states, on and off. Most common residential thermostats are BB controllers which switch on or off based on whether the ambient temperature reaches a preset threshold. Because of their simplicity and convenience, a BB Seite 3 von 14

controller for the conventional generator of the system has been designed. After it receives the signal from LSP, it gives a command to the conventional generator to generate full power, in case the load is about to be increased. Likewise, it gives a command to the conventional generator to start decreasing the power output rapidly when the load is about to be decreased. If no change in load is announced, the BB controller does not take any control action. However, in order to avoid any instability which may occur in microgrids, and not to interfere with the function of the primary and secondary control, this action of the BB controller should only be activated within the delay preset time and within a secure limit, so the advanced power production does not trigger the protection action of the conventional generator and influence the output power of the photovoltaics (PVs). The designed BB controller works as presented in figure 2. Start Load step preannouncement Load change? Yes No No control action Yes Load increase? No Send singal to conventional generator to increase its power output Send singal to conventional generator to decrease its power output Check network frequency Within the limit? Yes No End Bang-Bang control process No Check the preset time of the delay Within preset time? Yes 4 Simulation Model Figure 2. Work process of bang-bang controller A simulation model of an islanded Microgrid, which consists of a conventional generator, a photovoltaic system and lumped load, is built up in the Matlab Simulink environment. The system is modeled based on the swing differential equation: Seite 4 von 14

P Generator P Load = J ω dω dt where P Generator and P Load are the sum of power output from all generating units and the sum of load consumption in the MG respectively. J 1 is the moment of inertia and ω is the angular speed of the rotor of the conventional generator. The mechanical system starting time constant is defined as: T A = J ω n 2 (2) P n (3) P n is the nominal power and ω n is the synchronous nominal angular speed of the rotor. The nominal angular speed is calculated as: ω n = 2 π f n (4) where f n is the nominal frequency. From the equations (2), (3), and (4), the system dynamics of frequency and power deviation between supply and demand (ΔP/f) is formulated as: df = P Generator P Load f 2 n dt P n f act T A (5) where f act is the current system frequency. The simulation model is set under per unit (p.u.) base. The schematic block diagram of the islanded MG system is shown in figure 3. Load Bang-Bang Controller P Load LSP f_ref P G - Conventional - - + - Generator + System Dynamics ΔP / f f_act - + Δf Photovoltaic P PV PV (P-f) characteristic Primary Control Secondary Control Figure 3. Schematic block diagram of islanded microgrid 1 For the sake of simplicity, only turbo generators with two poles are considered in the equation. For generators with multiple pole pairs, moment of inertia has to be referred to synchronous system speed. Seite 5 von 14

4.1 Conventional Generator A conventional generator is modeled in the simulation as stated in figure 4. In order to have a good overview on frequency response of the MG system, a simple first-order lag element is applied for the main control valve motion of the conventional generator. The primary control has a 4% droop setting with a ±0.0004 p.u. (±20 mhz) deadband. Within the deadband, very small frequency deviations should not activate the primary control. When the frequency deviation exceeds the deadband, the primary control responds to the deviation within a few seconds. Load step pre-announcement and the bang-bang controller are added into the feedback loop of the conventional generator model. In the model, LSP and the BB controller are set to take control actions in 40 ms. The secondary control loop uses a proportionalintegral controller, in which proportional gain is 1 and integral gain is 0.2. It takes 6 to 7 minutes for the secondary control to bring back the frequency to its nominal value if reserve capacity is sufficient. The parameters of the conventional generator are presented in Table 2 in the appendix. Figure 4. Conventional generator simulation model 4.2 Photovoltaic generator Photovoltaic generation, which is one of the most important renewable energy sources apart from wind and hydro, is widely used to provide power supply. Besides its environmental advantage, integration of a large amount of distributed generation into power systems causes some technical problems, for example, reversing power flow in the distribution network, additional power flow in transmission level and grid instability issues [5]. Regarding the stability of the grid, German VDE-AR-N 4105 application standard [5, 6] for medium and low voltage networks provides guidance for PVs to respond smoothly to frequency deviations when the system frequency exceeds certain limits. The frequency characteristic of PVs is presented in figure 5. According to the VDE-AR-N 4105 guide, the PV characteristic of frequency-dependent active power infeed is as follows: When frequency is between 47.5 Hz and 50.2 Hz, PVs feed 100% of their actual power output into the network. When system frequency is between 50.2 Hz and 51.5 Hz, the power infeed of PVs is reduced by 40% per 1 Hz. PVs should be disconnected when frequency is below 47.5 Hz or above 51.5 Hz. Seite 6 von 14

Figure 5. PV frequency-dependent active power infeed characteristic curve [Source: VDE-AR-N 4105] In this simulation, the PV characteristic curve of frequency and active power from VDE-AR-N 4105 guide is implemented. Furthermore, PVs are allowed to reconnect to the overall system when frequency stays between 47.5 Hz and 50.05 Hz for more than 60 s as described in [5]. In addition, PVs feed 10% of their maximum active power per minute into the system after the reconnection and the maximum active power can be reached after 10 minutes. This avoids repeated disconnection of PVs caused by a fast change in frequency. In order to see the dynamic behavior of PVs, it takes 60 s for PVs to fully provide active power in the model. The PV simulation model is shown in figure 6. The parameters of the PV model are presented in Table 3 in the appendix. Figure 6. PV generation simulation model 4.3 Load In the simulation, load change is presented by a step signal. The step signal is connected with LSP. When the load does not make any change, LSP sends continuous load signals to the system. When a load change is noticed by LSP, it delays the change of the signal and maintains the previous state of the system. After the delay time period, the real load change will be sent by LSP to the system. Seite 7 von 14

5 Simulation Results Simulation results are collected to evaluate the performance of the islanded microgrid system with different control schemes, including frequency control, load step pre-announcement and bang-bang controller. In the model, the initial value of load is set to be 0.5 p.u. and the power set points of the conventional generator and PV are both at 0.5 p.u. 5.1 Dynamic Behavior In the first simulation, the frequency response of the islanded MG is observed. The load steps down from 0.5 p.u. to 0.1 p.u. at 100 s which has been delayed for 40 ms by LSP. The system is modeled with 0.6 s starting time constant T A and a 12.5% share of PVs. The simulation results are presented in figure 7. 0.6 P G (p.u.) 0.4 0.2 0 0 100 200 300 400 500 600 700 800 900 0.6 P PV (p.u.) P Load (p.u.) Frequency (Hz) 0.4 0.2 0 0 100 200 300 400 500 600 700 800 900 0.6 0.4 0.2 0 0 100 200 300 400 500 600 700 800 900 52 51 50 0 100 200 300 400 500 600 700 800 900 Time (s) Figure 7. Dynamic simulation results (P G: the power output of the conventional generator; P PV: the power output of the PV; P load: the power consumption of the load; Frequency: the system frequency) As it can be seen in the picture, both the conventional generator and PV system react to the frequency change and contribute to stabilize and restore the nominal frequency. When the load decreases from 0.5 p.u. to 0.1 p.u. at 100 s, the frequency increases rapidly. The primary control of the conventional generator reacts in approximately 2 s, afterwards the secondary control starts to recover the frequency slowly. The PV system disconnects from the network shortly after the step change at 100 s when the frequency exceeds 51.5 Hz. The frequency condition for PV reconnection is fulfilled at 455 s, when the frequency is brought to 50.05 Hz by the secondary control. The system frequency is stable between 47.5 Hz and 50.05 Hz for 60 s, so at 515 s the PV generation starts to reconnect to the overall system Seite 8 von 14

and then feeds in its power step by step in one minute. The PV feeds 100% of its actual power output into the overall system at 575 s. The reconnection of the PV system causes slight frequency deviation and the primary and secondary control of the system finally brings the frequency back to nominal value at approximately 820 s. 5.2 Results Comparison In order to find out the impact of LSP and the BB controller on the system, a comparison of the simulation results with different control schemes is made as shown in figure 8. The load step increases from 0.5 p.u. to 0.65 p.u. at 100 s and the share of PVs is 25%. The blue solid line and brown dash-dotted line indicate the frequency response in the islanded MGs having T A = 0.6 s with LSP and the BB controller and T A = 0.6 s without LSP and the BB controller respectively. Figure 8. Results comparison of systems with different control schemes The conventional generator starts to generate additional power at 99.96 s before the load change due to the implementation of LSP and the BB controller. In figure 8, corresponding to the increased power of the conventional generator, the frequency increases and reaches approximately 50.1 Hz. When the load change happens at 100 s, the frequency sags by approximately 0.3 Hz less than the frequency of the system without LSP and the BB controller at the first peak value. By applying LSP and the BB controller, the system frequency dropping does not exceed 49 Hz. Possible load shedding action in case that frequency falls below 49 Hz is avoided. Therefore, the system with LSP and the BB controller has a better reaction on the power disturbance and lower frequency deviation than the one without LSP and the BB controller. It indicates that the designed LSP and BB controller enhance the performance of the MG control system. Seite 9 von 14

ALLOWABLE LOAD STEP (P.U.) 14. Symposium Energieinnovation, 10.-12.02.2016, Graz/Austria 5.3 Results Analysis Figure 9 presents the allowable positive and negative load step in the systems with different control conditions, starting time constants and shares of PVs. For instance, when T A is 0.6 s and the share of PVs is 0%, the system without LSP and the BB controller has the maximum positive load step as 0.299 p.u., which means that the load can raise from 0.5 p.u. up to 0.799 p.u. Under the same conditions, if LSP and the BB controller are applied, the allowable positive load step is 0.349 p.u. Because of low control possibility of PVs and no inertia from them, a higher share of PVs decreases the maximum load change. 0.4 ALLOWABLE C HANGE OF L OAD WITH DIFFERENT SHARES OF PVS 0.3 0.2 0.1 0 0.0% -0.1 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% -0.2-0.3-0.4-0.5-0.6 SHARE OF PHOTOVOLTAICS (%) T_a = 0.6s, with LSP and BB controller T_a = 0.6s, with LSP and BB controller T_a = 0.6s, without LSP and BB controller T_a = 0.6s, without LSP and BB controller T_a = 0.3s, with LSP and BB controller T_a = 0.3s, with LSP and BB controller T_a = 0.3s, without LSP and BB controller T_a = 0.3s, without LSP and BB controller Figure 9. Allowable change of load with different shares of PVs (T_a: system starting time constant) As shown in figure 9, the implementation of LSP and the BB controller can improve the maximum possible positive load step depending on different shares of PVs based on the same T A. The influence of LSP and the BB controller on the positive load step reduces when MGs have more power production from PVs, since they are only applied in the conventional generator. Although LSP and the BB controller improve the control ability of the system, they do not influence the amount that the load can be decreased by, no matter how big the system T A is. This is because if a large load disconnects from the system, the control system brings the frequency to the acceptable range - between 47.5 Hz and 50.05 Hz - for at least 60 s, then PVs reconnect to the overall network. When the reconnection happens, due to the low consumption of load, the low available capacity of conventional generators and the integrated PVs, the frequency goes over 51.5 Hz before the PV system reaches its steady operating point, which triggers the disconnection of PVs. Hence the reconnection of PVs causes frequency oscillation. In this case, the utilization of LSP and the BB controller does not improve the maximum possible negative load step of the system. The allowable decrease of the load depends on the capacity of the conventional generation and the share of PVs in the system. Additionally, the maximum negative load step is generally bigger than the Seite 10 von 14

maximum positive load step, since both the conventional generator and PVs can reduce their power output when the load decreases but only the conventional generator can react to the load increase. Table 1 presents what a percentage of load increase the application of LSP and the BB controller enables. For example, in the system whose T A is 0.6 s, share of PVs is 0% and LSP and the BB controller are applied, the load can raise 69.8% more than the initial value (from 0.5 p.u. up to 0.849 p.u.). The system without LSP and the BB controller, based on the same conditions of T A and the share of PVs, is able to increase the load by 59.8%. Thus, applying LSP and the BB controller in the system enlarge the maximum load increase by approximately 16.7%. Due to the fast reaction of the system when T A is 0.3 s, the system frequency exceeds 50.2 Hz within the preset 40 ms if the share of the conventional generator is high. Hence the power infeed of PVs goes down along the PV characteristic curve. However, this reduction of the PV infeed does not diminish the benefit of the BB controller to the system. As shown in the table, in the system with T A = 0.3 s and LSP and the BB controller, load can be increased by an additional 17.6% more than the one without LSP and the BB controller depending on 0% share of PVs. Therefore, LSP and the BB controller have a greater effect in a T A = 0.3 s system than a T A = 0.6 s system in the 40 ms preset time. It is expected that these results will change in case the preset time is optimized for each incident. Table 1. The percentage of the load can increase by applying LSP and the BB controller 6 Conclusion Comparison between the systems with and without Share of LSP and the BB controller PVs T A = 0.6 s T A = 0.3 s 0% 16.7% 17.6% 12.5% 15.2% 20.9% 25% 13.5% 19.6% 37.5% 9.6% 19.5% 50% 7.5% 16.8% 62.5% 6.1% 13.5% 75% 1.6% 9.2% 87.5% 0% 1.6% Load step pre-announcement and bang-bang controller are designed and implemented in the Matlab Simulink environment. According to the simulation results, because of the low control ability of PVs, the load can only change less in systems with a higher share of PVs. Instead of the only reaction from the conventional generator when there is a load increase, both the conventional generator and PVs can reduce their power when the load declines, therefore the maximum possible negative load step is greater than the maximum positive load step. When LSP and the BB controller are applied in the islanded microgrid system, they improve the maximum load increase depending on the share of PVs. However, they do not have any impact on a large negative load step. The allowable load decrease is mainly influenced by the capacity of the conventional generator and the share of PVs. In conclusion, LSP and the BB controller have a positive effect on the maximum load increase in islanded microgrids. Moreover the BB controller is only activated during the Seite 11 von 14

preset delay time of the load change from LSP, which does not affect the other control actions. Additionally they both are simple and easy to be designed, implemented and operated. It is reasonable to add them into MGs during the islanded operation to improve the control ability. 7 Outlook In order to enhance the performance of the bang-bang controller, the preset time should be further optimized based on different system starting time constants and dynamics of generators participating in primary control. Besides, load step pre-announcement can be developed to be more intelligent, which can decide how long time in advance conventional generators should produce or reduce their power according to the amount of the load change. Since the frequency of the MG system swings after reconnection of the integrated PVs, other control methods for decreasing a large amount of load or a big load loss in MGs should be considered. Abbreviations MG DG DER LSP BB controller PV p.u. f f 0 f 1 f min P 0i P i P imax P Generator P Load J ω P n ω n Microgrid Distributed generation Distributed energy resource Load step pre-announcement Bang-bang controller Photovoltaic Per unit System frequency Nominal set point of frequency Changed frequency Lower frequency limit Dispatched power of ith generator defined at nominal frequency Changed power output of ith generator The maximum power rating of ith generator Sum of power output of all generating units Sum of power consumption of load and losses Intertia moment Angular speed Nominal power Nominal angular speed Seite 12 von 14

T A, T_a f act, f_act f n f_ref Δf ΔP P act P G P PV P Load System starting time constant Current system frequency Nominal frequency Nominal frequency (reference) Frequency deviation Power mismatch between power supply and demand The actual power output of PVs Power output of the conventional generator PV power infeed Power consumption of the load Appendix Table 2. Parameters for the conventional generator model Parameter Description Set Value p_ref Power set point [p.u.] 0.5 p_actual Actual power output of conventional generator [p.u.] Variable f_ref Nominal frequency [p.u.] 1 f_act Actual frequency [p.u.] Variable KV Valve gain 5 Saturation Maximum/minimum limit of power output [p.u.] Max: 1; Min: 0 Deadband Deadband for primary control [p.u.] ± 0.0004 K Frequency droop (primary control) 25 PI Proportional-Integral controller K p = 1; K I = 0.2 Table 3. Parameters for the PV model Parameter Description Set Value p_ref Power set point [p.u.] 0.5 p_actual Actual power output of photovoltaic [p.u.] Variable f_act Actual frequency [p.u.] Variable p.u. to standard Converting frequency from p.u. to Hz 50 PV characteristic PV active power/frequency characteristic Look-up table Rate Limiter PV stepwise reconnection slope [p.u. / s] 0.0083 Seite 13 von 14

References [1] Guo, Yi, and Wolfgang Gawlik. "A Survey of Control Strategies Applied in Worldwide Microgrid Projects." Tagungsband ComForEn 2014 (2014): 47. [2] Tielens, Pieter, and Dirk Van Hertem. "Grid inertia and frequency control in power systems with high penetration of renewables." status: published (2012). [3] Bevrani, Hassan. Robust power system frequency control. Vol. 85. New York: Springer, 2009. [4] Rubaai, Ahmed, and Jan Jerry. "Hybrid fuzzy bang-bang mode controller for electric motor drives applications." Industry Applications Society Annual Meeting (IAS), 2011 IEEE. IEEE, 2011. [5] von Appen, Jan, et al. "Time in the sun: the challenge of high PV penetration in the German electric grid." Power and Energy Magazine, IEEE 11.2 (2013): 55-64. [6] Boemer, Jens C., et al. "Overview of german grid issues and retrofit of photovoltaic power plants in germany for the prevention of frequency stability problems in abnormal system conditions of the ENTSO-E region continental europe." 1st International Workshop on Integration of Solar Power into Power Systems. Vol. 24. 2011. Seite 14 von 14