Wind Requirements and Testing for Steady-State Voltage and Frequency Control

Similar documents
Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

Fault Ride Through Technical Assessment Report Template

Wind Power Facility Technical Requirements CHANGE HISTORY

Harmonizing the Changing Resource Mix Keeping the Grid Together

each time the Frequency is above 51Hz. Continuous operation is required

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

Southern Company Interconnection Requirements for Inverter-Based Generation

DNVGL-ST-0125 Edition March 2016

Final ballot January BOT adoption February 2015

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces

The EU Network Code on Requirements for Generators A Summary

IEEE sion/1547revision_index.html

Transmission Interconnection Requirements for Inverter-Based Generation

Wind Power Plants and future Power System Frequency Stability

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Indication of Dynamic Model Validation Process

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Requirements for Generators European Network Code High Level Implementation Issues

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

DRAFT PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS

Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management

Parameters related to voltage issues

TABLE 1 COMPARISION OF ENTSO-E RfG TO GB GRID CODE

Short Circuit Modeling for Inverter-Based Resources

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Fault current contribution from PPMS & HVDC

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

POWER CORPORATION. Power Quality. Specifications and Guidelines for Customers. Phone: Fax:

SELECTING NATIONAL MW BOUNDARIES

Deleted: 9 4 anuary ... [1] Deleted: much more. Formatted ... [2] Formatted Table. Formatted: Indent: Left: 0.06 cm

POWER QUALITY SPECIFICATIONS AND GUIDELINES FOR CUSTOMERS ENGINEERING STANDARDS CITY OF LETHBRIDGE ELECTRIC

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana

Inverter-Based Resource Disturbance Analysis

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

Influence of Wind Generators in Voltage Dips

Offshore AC Grid Management for an AC Integrated VSC-HVDC Scheme with Large WPPs

Compliance activities

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

MEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN

Operationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0

IEEE Major Revision of Interconnection Standard

Max voltage in 400 kv Networks

SUMMARY. KEYWORDS Advanced Control, Type 4 WTG, Offshore, HVDC, Grid Access, Diode Rectifier Unit. 21, rue d Artois, F PARIS B4-121 CIGRE 2016

CONTROLLABILITY OF WIND POWER PLANTS CAPABILITIES REGARDING VOLTAGE CONTROL AND DATA EXCHANGE

BPS-Connected Inverter-Based Resource Performance

Lessons Learned in Model Validation for NERC Compliance

Analysis of the Effectiveness of Grid Codes for Offshore Wind Farms Connected to Onshore Grid via VSC-Based HVDC

FREQUENCY and VOLTAGE, ranges and durations

DRAFT PROPOSAL FOR NC HVDC REQUIREMENTS OF GENERAL APPLICATION

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014

ENTSO-E Draft Network Code on High Voltage Direct Current Connections and DCconnected

Fault Ride-through Capability Test Unit for Wind Turbines

GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS (RPPs)

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

HARDWARE BASED CHARACTERISATION OF LV INVERTER FAULT RESPONSE

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Open Access Simulation Toolbox for Wind Power Transmission using High Voltage Direct Current Technology

Integration of Wind Generation into Weak Grids

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

Revised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program

1

Grid Converters for Photovoltaic

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks

Version 2.6 October Comments to this document can be forwarded to:

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS

Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

Control of multiple VSC-HVDC converters within an offshore AC-hub

Parameters related to frequency stability

GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS

Performance of Distributed Energy Resources During and After System Disturbance Voltage and Frequency Ride-Through Requirements

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

Active Power Sharing and Frequency Control of Multiple Distributed Generators in A Microgrid

Demonstration of PFR Improvement September ERCOT Operations Planning

Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications

Transformer energisation after network blackout

Netzkurzschlussverhalten von umrichterbetriebenen regenerativen Energieerzeugern und -speichern

On the Evaluation of Power Quality Indices in Distribution Systems with Dispersed Generation

North-West University, 2 Eskom SOC South Africa

The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller

Technical Information Short-Circuit Currents Information on short-circuit currents of SMA PV inverters

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

PROPOSAL FOR NC RFG REQUIREMENTS OF GENERAL APPLICATION

Fault Ride Through Principles. and. Grid Code Proposed Changes

ELEMENTS OF FACTS CONTROLLERS

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

Solar inverter interactions with DC side

POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER

5 Summary test results and additional findings

Implementation of Revised IEEE Standard 1547

Transcription:

1 Wind Requirements and Testing for Steady-State Voltage and Frequency Control IEEE PES General Meeting, Boston: July 18, 2016 Steven Saylors, P.E. Senior Specialist Vestas Wind Systems

2 Voltage Control The central wind generation must not produce voltage variation higher than 5% at the connection point in case of partial or full maneuvering, timely or not, the generation complex. (ONS Submodulo 3.6-Section 8.3.1) Voltage Control is performed through reactive power operations from the WTGs and any additional compensation equipment (Capacitor/Reactor Banks, SVC, STATCOM, & OLTC of Substation Transformer) located at the substation. Voltage control can be performed in two different ways: the Slope voltage controller the PI voltage controller.

Voltage Control 3

4 Voltage Control The voltage controller dynamic response can be tuned according to the Grid Code interconnection requirements from the power off-taker.

Voltage Control 5

6 Commission Testing From ERCOT Nodal Protocol Section 8 Performance Monitoring July 1, 2015 The Resource Entity shall perform the Automatic Voltage Regulator (AVR) tests and shall supply AVR data as specified in the Operating Guides. The AVR tests must be performed on initial qualification. The AVR tests must be conducted at a time agreed on in advance by the Resource Entity, its QSE, the applicable TSP and ERCOT. Lagging Reactive Testing (a) It is recommended, but not required, that lagging reactive tests be performed when system voltage is within the voltage profile, such as during high load periods {specified using the Summer/Fall voltage profile}. (b) Lagging tests should meet the following performance criteria: (i) Lagging Test 1: Test at or above 95% of the unit s High Sustained Limit (HSL) for at least 15 minutes. IRRs should test at or above 60% of their HSL. Testing acceptance criteria is met if the unit achieved no less than 90% of the unit s most recent CURL. (ii) Lagging Test 2: Test at the unit s HSL for at least one hour. IRRs should test with at least 90% of photovoltaic inverters or wind turbines online. Testing acceptance criteria is met if the unit achieved at least 50% of the units CURL for one hour. Leading Reactive Testing (a) It is recommended, but not required, that leading reactive tests be performed when system voltage is within the voltage profile, such as during low load periods {specified using the Winter/Spring voltage profile}. (b) Leading tests should meet the following performance criteria: (i) Leading Test 1: Test at the unit s normally expected maximum real power output during system light load conditions for at least 15 minutes. IRRs should test at or below 60% of their HSL. Testing acceptance criteria is met if the unit achieved no less than 90% of the unit s original manufacturer reactive curve or most recent CURL.

7 Test 5.3: Voltage Control S.NO Voltage Reference Droop Test 5.3.1 Test 5.3.2 Test 5.3.3 Test 5.3.4 Test 5.3.5 Test 5.3.6 Test 5.3.7 Test 5.3.8 Voltage reference changed to 141.8 kv Voltage reference changed to 140.8 kv Voltage reference changed to 139.8 kv Voltage reference changed to 140.8 kv Voltage reference changed to 142 kv Voltage reference changed to 141 kv Voltage reference changed to 140 kv Voltage reference changed to 141 kv Error within +/-10% tolerance band 4% 4% 4% 4% 8% 8% 8% 8%

8 Frequency Control The role of the frequency control is to make a wind power plant contribute to the system-wide frequency regulation scheme put in place by the TSO. The active power reference to the WTG is reduced by over-frequency or increased by under-frequency events.

P [pu] f [Hz] 9 Frequency (Governor) Response Simulated grid frequency excursions are fed to central plant controller and control response command is then distributed to all turbines operating at the time 51.0 Hz 50.0 Hz 0.9 pu Individual wind turbines respond by pitching blades and/or controlling variable frequency converters to produce aggregated plant response at PCC 0.2 pu

10 Commission Testing From ERCOT Nodal Protocol Section 8(C) Turbine Governor Speed Tests Feb. 11, 2014 INTERMITTENT RENEWABLE RESOURCE (IRR) FREQUENCY RESPONSE TEST PROCEDURE 1. The frequency response function of the Intermittent Renewable Resource (IRR) is tested On-Line at a Load level that allows the IRRs to increase or decrease Load without reaching low operating limits or high operating limits. 2. The test is performed by adding a frequency offset signal that exceeds the Governor Dead-Band value to the measured frequency signal. This should create immediate step change in the measured frequency signal. 3. The test starts at time t 0 when the frequency Dead-Band is exceeded. 4. The MW output signal should be recorded at least every two seconds. 5. The duration of the test is 100 seconds. After 100 seconds, the offset signal should be removed and the IRR should return to pretest power output. 6. The test should be conducted both with positive and negative frequency offsets. 7. The test is considered successful after the signal becomes active if at least 70% of the calculated MW contribution is delivered within 16 seconds and the response is maintained for an additional 30 seconds. 8. Droop shall be set not to exceed 5% with a maximum frequency Dead-Band of +/- 0.017Hz (per BAL-001-TRE-1). 9. IRRs located behind one Point of Interconnection (POI), metered by one ERCOT-Polled Settlement (EPS) Meter, and operated as an integrated Facility may combine IRRs for the purposes of this test.

Test 4: Power Reduction during Frequency Change 11 S.NO Test 4.1 Test 4.2 Test 4.3 Test 4.4 Test 4.5 Test 4.6 Test 4.7 Test 4.8 Test Case Frequency reference stepped from 50 Hz to 50.5 Hz Frequency reference stepped from 50.5 Hz to 51 Hz Frequency reference stepped from 51 Hz to 51.5 Hz Frequency reference stepped from 51.5 Hz to 52 Hz Frequency reference stepped from 52 Hz to 51.5 Hz Frequency reference stepped from 51.5 Hz to 51 Hz Frequency reference stepped from 51 Hz to 50.5 Hz Frequency reference stepped from 50.5 Hz to 50 Hz Error within +/-10% tolerance band

Thank you for your attention 12

1 Renewable Energy Resource Requirements for Fault Ride Through and Fault Current Response Dr.-Ing Claudia Rahmann Msc. Ing. Jorge Vega University of Chile

Introduction 2 Grid Code Requirements Transmission system operators (TSO) are responsible for the satisfactory operation of their power systems during normal operation and contingencies TSO set minimum requirements regarding power system performance and define technical requirements that all actors connected to their networks must fulfill Grid code requirements Grid Code Requirements During normal operation During contingencies Fault Ride Through Capability Voltage stability support

FRT 3 Fault Ride Through (FRT) Requirements In a first stage of RER development, the requirements were defined without considering the impacts on power system operation WTs were allowed/forced to be disconnected in case of voltage dips and no contribution to system stability was required Frequency stability problems in countries with high levels of wind power Grid codes have started to include technical requirements regarding the dynamic performance of RER during contingencies Disconnection of RER in case of voltage dips is usually not admitted anymore Grid codes require an uninterrupted operation under fault conditions based on voltage time profiles (FRT capability curves) Unbalanced short-circuits: Possible over-voltages in some of the phases High voltage ride through requirements are sometimes also defined Less common, but present explicitly in some grid codes like South Africa and Germany

FRT 4 FRT-curves and V I q curves Typical voltage time profile (FRT capability curves) V [p. u. ] 1,0 0,8 0,6 0,4 0,2 0 0 0,3 1,0 15 Time [sec] Certain grid codes also impose requirements regarding reactive power response of RER during and after short circuits These requirements are in the form of V I q curves Improvement of system stability Supply 20 100 40 20 20 40 I q In 10 20 30 40 Absorption V Vn

Review 5 Considered countries In total, 11 countries were selected

FRT by country 6 FRT curves for RER Europe 1,0 0,9 0,8 0,7 0,6 0,5 0,4 0,3 0,2 Voltage [p.u.] 0 0 0,15 0,5 1,0 1,5 3 4 5 0,25 15 Time [sec] Germany (TenneT) Denmark (WT) England (WT off-shore) Spain Denmark (PV)

FRT requirements for RER 7 FRT curves for RER America 1,0 0,9 0,8 0,7 0,6 0,5 0,4 0,3 0,2 Voltage [p.u.] 0 0 0,15 0,3 0,5 1,0 1,5 3 4 Mexico Canada (AESO) (WT) 0,65 5 Brazil Canada (Hydro Québec) (WT) Chile 15 Time [sec]

FRT by country 8 FRT curves for RER Others 1,0 0,9 0,8 0,7 0,6 0,5 0,4 0,3 0,2 Voltage [p.u.] 0 0 0,15 0,625 3 4 5 15 Time [sec] China (WT) India (400 kv) (WT) China (PV) South Africa

FRT requirements for RER 9 FRT Requirements for RER Comments Some grid codes require different FRT-curves depending on the voltage level Mexico: the maximum time to ride through a voltage dip is 150 ms only for voltage levels between 69 and 161 kv: For voltage levels of 230 kv the time is 100 ms and for voltage levels of 400 kv is 80 ms India: the maximum time to ride through a voltage dip depends on the voltage level: For 400 kv the time is 100 ms for installations with voltages between 110 kv and 220 kv is 160 ms Other grid codes require different FRT-characteristics depending on the short-circuit type Spain: a less severe profile is required during two-phase short-circuits, with a lowest value of voltage of 0.5 p.u. Voltage in the FRT-curves (or measuring point) not always well specified Spain: voltage at the connection point Chile: phase to ground voltage at the connection point Denmark: voltage at the point of connection (line-to-line voltages for the 50 Hz component) ( PV) and smallest line-to-line voltage for the 50 Hz component ( WT) Significant differences between FRT requirements among the countries

Summary 10 Characteristics of selected requirements (1) Country Fault duration (ms) Minimum voltage (p.u.) Includes Off-shore? Includes WT PV? Includes V I q requirements? RER (%) Spain 500 0.2 26 Germany *(TenneT) Denmark (Energinet) England * China 150 0 43 250 (PV) 500 (WT) 140 625 (WT) 150 (PV) 0.1 (PV) 0.2 (WT) 0 0.15 (offshore) 0.2 0 45 Ambiguously established 15 30 India 100 0.15 11 South Africa 150 0 5 * Includes FRT requirements for CGU

Summary 11 Characteristics of selected requirements (2) Country Canada (Alberta) Fault duration (ms) Minimum voltage (p.u.) Includes Off-shore? Includes WT PV? Includes V I q requirements? RER (%) 625 0.15 9 Chile 140 0.1 Mexico 150 0 Only required in case of twophase short circuits Ambiguously established Brazil 500 0.2 4 10 1

Voltage Support Requirements for RER 12 Voltage Support Requirements for RER (1) Germany: TenneT requires that RER support grid voltage with additional reactive current during a voltage dip, as shown in the figure. The voltage control must take place within 20 ms after fault recognition by providing a reactive current on the low-voltage side of the RER transformer Supply 20 100 40 20 20 40 I q In 10 20 30 40 Absorption V Vn V Denmark: the wind power plant must have a control function capable of controlling the reactive current component during voltage dips as specified in the figure 20 100 90 40 20 Area A Area C (disconnection) 10 20 30 100 I q In

Voltage Support Requirements for RER 13 Voltage Support Requirements for RER Spain: the wind power plants are required to be able to inject reactive power within 150 ms of grid recovery as shown in the figure South Africa: the RER must supply I q according to the figure (within its technical design limitations) so as to ensure that the RER helps to stabilize the voltage 110 100 90 50 20 V Area A Area B Area E I q In 20 10 20 30 100

Conclusions 14 Outlook (1) Different criteria are applied when defining the requirements for RER within the grid codes RER penetration level and its location in the network, energy policies, network robustness, system characteristics, utility practices, among others Requirements may vary considerable from operator to operator and thus from one country to another Difficulties in their direct comparison Diversity of requirements poses important burdens on RER manufacturers Interpretation of the underlying meaning of the grid code documents, managing the differences in formats (terminology and definitions) Development of hardware and software solutions for the specific requirements of each grid code Diversity of requirements increases the costs of RER

Conclusions 15 Outlook (2) Need of harmonization? Harmonization process has been proposed by Wind Europe (ex EWEA) in a two-step scheme: Structural harmonization Generic grid code format (structure, designations, figures, method of specification, definitions and units) Technical harmonization Standardization from a technical viewpoint is difficult since the requirements depend on the technical characteristics of each power system Structural harmonization in the sense of a generic grid code format should be possible to implement Consistency in the grid codes would assist RER manufacturers to move from market-oriented solutions to universal ones Efforts should be made to move towards this objective

16 Thank you!!! Do you have any question??

Requirements for Modeling and Validation of Power System Models for Wind Generation Boston, 18.07.2016 Frank Martin, Siemens Wind Power A/S

2 Why requirements for modeling and validation? Need for (validated) simulation models: Enable system operator to perform grid integration studies Enable WPP developer to perform studies to verify compliance of the WPP with grid code requirements / design WPP equipment...

Wind Turbine vs. Wind Power Plant modeling and validation Wind Turbine Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar 132/400 kv 400/16 kv Fault Ride Through Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar 33 kv Busbar 33/132 kv Park Trafo 132 kv Busbar 132 kv PCC Power Station Power Quality Harmonics Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar HPPP 132/50 kv 50/10 kv 10/0.4 kv Flicker Control Features Consumer PQ Capability P(f) Function Protection

Wind Turbine vs. Wind Power Plant modeling and validation Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar Wind Power Plant 132/400 kv 400/16 kv Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar 33 kv Busbar 33/132 kv Park Trafo 132 kv Busbar 132 kv PCC Power Station Active Power Response Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar HPPP 132/50 kv 50/10 kv 10/0.4 kv Ramp rates Frequency Control Consumer LFSM FSM V, Q, PF Control WPP features

5 Requirements for simulation models / studies TenneT Offshore [1] (Source: TenneT TSO GmbH) NGET Grid Code[2] (Source: National Grid ) Commission Regulation (EU) NC RfG [3] (Source: European Commission) Hydro Quebec [4] (Source: Hydro Quebec) TCC High-Voltage [5] (Source: VDE)

6 Requirements for simulation models / studies Grid Code TenneT Offshore Scope (studies) Time step? RMS vs. EMT Validation and accuracy Blackbox vs. open model + both o - Generic model vs. manufacturer specific? Tool dependency NETOMAC, PSCAD NGET + RMS o - no ENTSO-E NC RfG Hydro Quebec TCC High- Voltage) o Both + Both o o - no + PSS/E, EMTP- RV o RMS + - no

7 Electrical simulation models Simulation models are available: Generic WT and WPP controller models WECC IEC 61400-27-1 (CD) Manufacturer specific WT and WPP controller models in relevant simulation tools RMS e.g. PSS/E, DIgSILENT Power Factory,... EMT e.g. PSCAD, EMTP-RV,... Models for other type of studies (e.g. harmonics)

8 Electrical simulation models necessary investigations / studies Steady state investigations e.g. load flow, loading of cables and transformers, voltage drop, reactive power capability Dynamic stability investigations e.g. verify if WPP stays connected and support the grid during UVRT as well as OVRT situations Short Circuit Studies and protection design Harmonics analysis and stability Transient investigations e.g insulation coordination, detailed transient studies

Requirements for model validation - example FRT SWT-3.0 / 3.2 MW DD 2000 tests SWT-4.0 MW 2200 tests SWT-6.0 MW DD 900 test

10 Requirements for model validation - example FRT Requirements and guidelines for model validation: Grid codes (generic) WECC IEC 61400-27-2 (approach without success criteria) FGW TR4 (approach and success criteria, FRT) PVVC (approach and success criteria, FRT)

Requirements for model validation - example FRT (IEC 61400-27-2) 11 No individual values for the error in the standard (Source: IEC 61400-27)

Reactive Power [Mvar] +Ve Sequence Voltage [pu] Active Power [MW] Reactive Current [ka] Active Current [ka] D3 Platform Model Validation Grid Modeling 4 3 2 1 0 Measured Simulation -1 0 1 2 3 4 5 6 7 8 9 10 4 3 2 1 0 Measured Simulation -1 0 1 2 3 4 5 6 7 8 9 10 0.8 0.7 0.6 0.5 0.4 4 3 2 1 0-1 Measured Simulation -2 0 1 2 3 4 5 6 7 8 9 10 0.3 2 0.2 0.1 Measured Simulation 0 0 1 2 3 4 5 6 7 8 9 10 1.5 1 0.5 0 Measured Simulation -0.5 0 1 2 3 4 5 6 7 8 9 10

LV Side +Ve Sq. Voltage [kv] Reactive Power [MVAr] MV Side +Ve Sq. Voltage [kv] Active Power [MW] Reactive Current [ka] Active Current [ka] D3 Platform Model Validation Playback 4 3 Measured Simulation 2 1 0-1 0 1 2 3 4 5 6 7 8 9 10 Time [s] 4 3 Measured LV Simulation ref 2 1 0-1 0 1 2 3 4 5 6 7 8 9 10 Time [s] 12 10 8 6 4 2 Measured Simulation 0 0 1 2 3 4 5 6 7 8 9 10 4 3 2 1 0-1 Measured Simulation -2 0 1 2 3 4 5 6 7 8 9 10 0.8 0.6 0.4 2 1.5 1 0.5 Measured Simulation 0.2 Measured Simulation 0 0 1 2 3 4 5 6 7 8 9 10 0-0.5 0 1 2 3 4 5 6 7 8 9 10 Time [s]

Requirements for model validation other than FRT Model validation focus on FRT Other aspects: Reactive Power Control function and features Harmonics... Model validation for EMT models

Frequency [Hz] Active Power [MW] Wind Power Plant Frequency Control Model Validation 50.6 120 50.4 100 50.2 80 50 60 49.8 40 49.6 20 49.4 49.2 0 100 200 300 400 500 0 Measured Simulation -20 0 100 200 300 400 500

Points for Discussion Models for what kind of studies Validation requirements mostly unclear (e.g. tolerances, EMT model) Will an generic model (IEC 61400-27-1 / -2) be used

Thank you for your kind attention!

Further information: Frank Martin Siemens Wind Power A/S Grid Connection Elektrovej 325 DK-2800 Kgs. Lyngby Denmark Mobile: +45 3037-5363 frank.martin@siemens.com

Disclaimer This document contains forward-looking statements and information that is, statements related to future, not past, events. These statements may be identified either orally or in writing by words as expects, anticipates, intends, plans, believes, seeks, estimates, will or words of similar meaning. Such statements are based on our current expectations and certain assumptions, and are, therefore, subject to certain risks and uncertainties. A variety of factors, many of which are beyond Siemens control, affect its operations, performance, business strategy and results and could cause the actual results, performance or achievements of Siemens worldwide to be materially different from any future results, performance or achievements that may be expressed or implied by such forward-looking statements. For us, particular uncertainties arise, among others, from changes in general economic and business conditions, changes in currency exchange rates and interest rates, introduction of competing products or technologies by other companies, lack of acceptance of new products or services by customers targeted by Siemens worldwide, changes in business strategy and various other factors. More detailed information about certain of these factors is contained in Siemens filings with the SEC, which are available on the Siemens website, www.siemens.com and on the SEC s website, www.sec.gov. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in the relevant forward-looking statement as anticipated, believed, estimated, expected, intended, planned or projected. Siemens does not intend or assume any obligation to update or revise these forward-looking statements in light of developments which differ from those anticipated. Trademarks mentioned in this document are the property of Siemens AG, it's affiliates or their respective owners.