Overview of Precast ABC Projects in the Pacific Northwest. Chuck Prussack, P.E., Oldcastle Precast, Inc - Spokane

Similar documents
Deep Creek Canyon US Highway 12

Value Engineering Design Build MODULAR INFRASTRUCTURE

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges

ABC and Innovative Bridge Construction for Minnesota Local Roads

Accelerated Bridge Construction (ABC) and the Utah Experience

adopted in Hong Kong

James Luebke, PE Structural Development Engineer WisDOT Bureau of Structures

Precast Bridge. in only Eight Days. profile. Minimizing construction-related traffic delays and improving workzone

Programmatic Implementation of ABC: Module 6 Project Highlights Contractor Perspective

TYPICAL SECTIONS TYPICAL NO. 1 (MAINLINE) STA TO STA STA TO STA ROUNDING DETAIL TYPICAL NO.

11/15/2010. Construction. Accelerated Bridge Construction (ABC) Definition. Systems (PBES) Definition

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422

State-of-the-art Report On FULL-DEPTH PRECAST CONCRETE BRIDGE DECK PANELS (SOA )

Construction Tolerances - The following tolerances apply to cast-in-place structures:

THE TRANSPORTATION ISSUE

24" Dia. 36" Dia. WE BUILD CONFIDENCE

Created from more than 25 years of experience.

SUBSTATION SECURITY WALL INSTALLATION MANUAL

PCI Update on Transportation Activities and elearning Modules for AASHTO Technical Committee T-4 AASHTO SCOBS --- Spokane Washington

Precast Concrete Pavement

BRIDGE TYPE CONCEPT EVALUATION

shawprecastsolutions.com BEBO Arch Systems PRODUCT GUIDE & TECHNICAL REFERENCE MANUAL Providing the right solutions.

FIGG. Accelerated With Bridge Construction. Concrete Segmental. Bridges. William R. (Randy) Cox, P.E. American Segmental Bridge Institute

Jointed Precast Concrete Pavement

Bridge Design and Drafting Manual Oregon Department of Transportation

California Department of Transportation

PRECAST CONCRETE BRIDGE SUBSTRUCTURE COMPONENTS. Presented by: Matthew Youngblood, PE, SE Scott Noyer, PE Janssen & Spaans Engineering

INSTALLATION GUIDE PermaTrak. Patented Product: U.S. Patent #5,906,084 #8,302,362 #8,522,505 #8,839,588 #9,096,975

In Denver, a recently completed flyover

Suggested Reinforcement Detailing Practices Based on comments from R&D and ES ESS Committees

State of the Art Precast, Prestressed Concrete Bridges and Industry Innovations

BUILT TO ENDURE. North Central College s Unique Residence Halls 12-Month Schedule Met. INSIDE: See Features on Safety from Extreme Weather Conditions!

Digitally Signed 06/02/2015

TABLE OF CONTENTS 1200 PLAN PREPARATION

OpenBridge Modeler: What is it and how can I use it today?

How to Estimate the Cost of a. Precast Concrete Parking Structure

No limitations to precast

Manhole or Catch Basin Type A & B Cone Sections Precast - Design F Manhole or Catch Basin Cover (Reducer Cone Section Precast) Design D

2' x 3' Polymer Pull Box Cover 4'-0" 7'-0" 24" x 76" Access Opening 3'-6"

Welcome. Hong Kong Zhuhai Macao Bridge Design & Construction of Marine Viaducts for HKLR

PRECAST CONCRETE DESIGN AND ENGINEERING KNOW HOW ALL UNDER ONE ROOF

DESIGN ALTERNATIVE NO. 1 - PRECAST CONCRETE ARCH STRUCTURE FOR 17TH STREET BRIDGE REHABILITATION

Segmental Bridge Technology Established and Evolving. W. Jay Rohleder, Jr, P.E., S.E. Senior Vice President / Project Development FIGG

SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS

Quality Control and Quality Assurance Guide

Pipe Product Catalog Table of Contents

INDEX. Initial SOL Approval. 1. Evergreen Retaining Wall System (Deleted) 3. Sound Barrier Walls (Deleted) Standard Details

The $13.2 billion Central Artery/Tunnel Project (CA/

Precast Concrete Panels for Rapid Pavement Repair

Current Standard Plates including Transmittal Letters are available on the web at:

Chapter 6: SHOP DRAWINGS AND OTHER SUBMITTALS

SUMMARY SHEETS OF BAR COUPLER CONNECTIONS

RAIL PANEL AT TRANSITION SECTION PLAN - POST DETAIL PLAN - TUBE SPLICE. Colorado Department of Transportation. Staff Bridge Branch

Breadth: Change CIP Structural Walls and Beams to Precast

Segmental Bridge Construction. Segmental Bridges It s a Construction Technique with Design Implications. Plans Review Group

OpenBridge Designer Interoperability

ALL YOUR PRECAST SOLUTIONS

Phase 2 Silver Line Update

Precast Concrete Pavement Background Concepts. Project 1517 FHWA, CTR & TxDOT Gary Graham November 15, 2001

Update: July 20, 2012

Chapter 3: APPLICATIONS FOR JOINTED PRECAST PAVEMENT SYSTEMS

MAINTENANCE HOLES, CATCH BASINS AND DITCH INLETS - MTC FORM 407 INDEX

Standard Plate 7036 is discontinued. It is replaced by Standard Plan Pedestrian Curb Ramp Details.

Dauphin Island Bridge

6/19/2014. Milton Madison Bridge Slide. Project Partners. The Challenge. Aaron L. Stover, PE, SE Michael Baker Jr., Inc.

IOWA CITY WASTEWATER TREATMENT PLANT RELOCATION PROJECT NORTH PLANT SALVAGE AND DEMOLITION PHASE CITY OF IOWA CITY FEBRUARY, 2015

MANuFACturers industry QuALity statement.

SUBJECT: Standard Plate Turf Establishment Areas (at Pipe Culvert Ends)

Government Of Newfoundland & Labrador Municipal Water, Sewer And Roads Master Construction Specifications

WELCOME. Open House. meeting is downstairs in the Foot Room RED WING BRIDGE PROJECT. US 63 River Bridge and Approach Roadways.

2. Remove from the Standard Plate manual: Standard Plate Index, Sheets 1-4 of 4, Numerical Index of Standard Plates (August 31, 2012)

TARGET FIELD: REMOVING THE VARIABLES THROUGH BIM

SUBJECT: Standard Plate 9102 Turf Establishment Areas At Pipe Culvert Ends

ProConcrete. Gernot Jeromin Product Manager Bentley Systems, Incorporated

Prefabricated Elements Case Study

Delivering Reliability. Services. Strength You Can Count On. oldcastleprecast.com/services

A1.1 FOX GARAGE VAN VAN VAN VAN 11/16/ WASHINGTON BLVD ST. LOUIS, MO REVISIONS FLOOR PLAN - LEVEL /01/14

BOX CULVERTS DRAINAGE & WATER MANAGEMENT. v2.1

Designer s NOTEBOOK DESIGN ECONOMY, PART 3

SECTION PRECAST CONCRETE SECTIONAL MANHOLES

Precast Concrete Box Culverts

Demolition of Ramp C (SN ): Westbound Ontario Street to Eastbound I-90/94) over I-90/94 (JF Kennedy Expressway)

Proposal PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y. Baker, MT P.O. Box 846

DECK PERMIT APPLICATION PACKET

Fast Track Precast Concrete Pavement Rehabilitation Pilot Project

LETTING : CALL : 029 COUNTIES : GOODHUE

Edgerail Aluminum Bridge Railing System Specification & Installation Instructions

Survey Requirements. Design Guidelines and Standards. June Office of the University Architect

BOX CULVERTS DRAINAGE & WATER MANAGEMENT. v2.1

Amajor transportation infrastructure undertaking, billed

MONTH : December 2015 PHOTOGAPH NO: DESCRIPTION : Rebar Installation Work for 1 st Lift of permanent Manhole at MH-G2

Documents: Response letter and attachments, Prepared by: AMEC Massachusetts, Inc., Dated February 17, 2016.

SUMMIT COUNTY PLANNING AND ENGINEERING DEPARTMENT

DESIGN GUIDELINES (SD) COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 399 ELMHURST STREET HAYWARD, CA

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

StormTrap Guide Specification. StormTrap SingleTrap on Pad Foundation Groundwater BELOW Invert Revised 11/21/18

General Layout. Eng. Maha Moddather

INSTRUCTIONS: 1. Record the transmittal letter number, date, and subject on the transmittal record sheet located in the front of the manual.

STATE UNIVERSITY CONSTRUCTION FUND

GCG ASSOCIATES, INC. February 8, Mr. Nathaniel Strosberg, Town Planner 101 Main Street Town of Ashland Ashland, MA 01721

Transcription:

Overview of Precast ABC Projects in the Pacific Northwest Chuck Prussack, P.E., Oldcastle Precast, Inc - Spokane 1

Techniques Additional prefabrication of units to reduce field timeline Simplify deck installation to reduce field forming Precast substructure elements Match elements to site constraints spans, traffic needs, soil parameters Use proven details Goal of all techniques is Accelerated Bridge Construction 2

Dayton Street Bridge Replacement, Kennewick, WA 12 Solideck, 46 x 4 (16 pieces); abutments with footings (6 pieces), 36 skew Contractor: Accelerated Construction and Excavating, Plummer, ID Owner: City of Kennewick, WA Longitudinal elevation of abutment 2 Abutment cross-section 3

Dayton Street Bridge Replacement, Kennewick, WA Three-piece sloped abutments Edge to edge deck simplified deck pour Tight timeline due to school session Dayton Street in process 4

Dayton Street Bridge Replacement, Kennewick, WA Finished job just in time to re-open for school 5

Kittitas Highway, WA 18 Solideck, 36-6 x 4 (9 pieces); abutments with footings (7 pieces), 62 skew Contractor: Belsaas & Smith Construction, Ellensburg, WA Owner: Kittitas County Department of Public Works, WA 6

Kittitas Highway, WA Abutment walls with footing being set 7

Kittitas Highway, WA Deck being set 8

Swan & Willow Creek Bridges, Kootenai County, ID Contractor: Apollo, Inc, Kennewick, WA Owner: Idaho DOT Swan Creek Three-sided Box Culvert (9 pieces) Precast headwalls (2 pieces) Swan in process Swan complete 9

Swan & Willow Creek Bridges, Kootenai County, ID Willow Creek Trideck (8 pieces), Precast pile caps (4 pieces) Plant precast parapet barriers (2 pieces) Edge-to-edge deck elements Willow pile cap Willow parapet 10

Swan & Willow Creek Bridges, Kootenai County, ID Willow in process Willow closure pour 11

Deep Creek Structures, Broadwater County, MT Three trideck bridges (15 pieces), pile caps (6 pieces) Curbs cast on at plant Different slopes and elevations Weekend highway closures for each bridge replacement; 24-hour work schedule 100 mile detour; some trucks on far side for delivery Trial fit in precast yard Contractor: Dick Anderson Construction, Great Falls, MT Owner: Montana DOT Consultant: Morrison Maierle Engineers 12

Deep Creek Structures, Broadwater County, MT Trial fits in precast yard 13

Deep Creek Structures, Broadwater County, MT Deck being placed Pile cap being placed 14

Deep Creek Structures, Broadwater County, MT One bridge complete, keyways grouted 15

Swiftcurrent Bridge, Glacier National Park, MT 30 Voided slabs, 85 x 4 5 (6 pieces), abutments (2 pieces), wing walls (4 pieces), deck overhang Post-season, pre-winter install; crane on far side of creek Trial fit in precast yard Contractor: Northbank Civil & Marine, Vancouver, WA Owner: USDOT, Federal Highway Administration 16

Swiftcurrent Bridge, Glacier National Park, MT Note color of exterior girders to diminish visibility of depth Secondary pour of overhang to reduce field time Utility pipe cast in to voids at plant (5 places) Trial fit in precast yard 17

Swiftcurrent Bridge, Glacier National Park, MT Set in progress 18

Swiftcurrent Bridge, Glacier National Park, MT Finished bridge 19

French Creek Bridge, Gallatin National Forest, MT 15 Solid slab 37 x 4 (4 pieces), grade beams (2 pieces), wing walls (4 pieces) Contractor: Battle Ridge Builders, Belgrade, MT Owner: U.S.D.A. Forest Service Region 1 Slab set on grade beams 20

Glover Creek Bridge, Clearwater National Forest, ID Trideck 37 x 4 (4 pieces), grade beams (2 pieces), abutments w/footings (3 pieces), wing walls (2 pieces) Colored concrete with stone pattern on abutment walls and wing walls Contractor: Cook & Sons, Whitebird, ID Owner: U.S.D.A. Forest Service Region 1 21

Glover Creek Bridge, Clearwater National Forest, ID Typical large plant-cast USFS curbs Finished bridge in place Stone pattern repair 22

Summary Use of full deck horizontal elements To minimize field forming To expedite deck timeline Precast substructures with just in time delivery To avoid jobsite congestion To expedite substructure timeline Wide array of precasts elements are available depending on the type of abutment Spread footing or pile cap Deck type differs depending on span Appurtenances such as curbs, parapet, or railing Aesthetics can be addressed with all of the available precast expertise 23