FAST TRACK WORKSHOP OBJECTIVES

Similar documents
UNIFIED FACILITIES GUIDE SPECIFICATIONS *************************************************************************** SECTION

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

Jacksonville District Master

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SUBMITTAL PROCEDURES

Section Meetings Section Material and Equipment. None Required

East Central College

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SUBMITTAL PROCEDURES

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS

Working Drawing Manual

SECTION PROJECT MANAGEMENT AND COORDINATION

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

Answer: Qualification statement should be provided with the bid.

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum

PROCEDURE FOR PROCESSING WORKING DRAWINGS

Working Drawing Procedure

INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS:

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

ADDENDUM #2 September 12, 2018

SPECIFICATIONS SPECIFICATION TYPES

FTEV Repair Mezzanine Bldg Hurlburt Field, Florida SECTION DESIGN AFTER AWARD

Anticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days.

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

submittals 1s e c t i o n

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)

DESIGN REVIEW PROCESS AND APPLICATION

CHAPTER A-15 INTERIOR DESIGN INDEX

835 Gil Harbin Industrial Blvd Valdosta, GA 31601

FREMONT COUNTY. APPLICATION FOR ZONE CHANGE #2 USE DESIGNATION PLAN (Requires Subsequent Approval of ZC #2 Final Designation Plan) 1.

ADDENDUM NO. 1. November 6, 2016 BIDDING AND CONTRACT DOCUMENTS FOR

White Lake Township Building Dept Highland Rd. (248) White Lake, MI Fax (248)

Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer

SEI Certification Program Manual

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1073 PRECAST CONCRETE CERTIFICATION PROGRAM JULY 20, 2018

THE ADVANCED MODELING SUBMITTAL REVIEW CHECKLIST (CHX)

Heat Exchanger Construction Checklist

1. Land survey Work. 2. Civil and Structural engineering services.

RFP # CULVER CITYBUS: BUS SIGNAL PRIORITY SYSTEMS PROJECT Response to Questions

SECTION ADMINISTRATIVE REQUIREMENTS

PUBLIC ART PROCUREMENT GUIDELINES

APPLICATION FOR SITE PLAN REVIEW

DWG, Inc. Coastal Carolina University State Project No. Consulting Engineers HTC Arena Lighting H17-N112-JM

COMMERCIAL ITEM DESCRIPTION SHIELDING BEADS, FERRITE, LEADED, EMI SUPPRESSOR

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

What Are Submittals?

Windmill Village Homeowners Association

DESIGN REVIEW BOARD APPLICATION EXTERIOR PLAN / LANDSCAPE PLAN

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT

Renewable Water Resources Greenville, South Carolina. CONTRACT DOCUMENTS Reedy River Basin Sewer Tunnel ADDENDUM IV - CONTRACT REVISIONS.

Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review

01100 SUMMARY OF WORK

SECTION SUBMITTALS

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

UNIFIED FACILITIES GUIDE SPECIFICATIONS

State of New Jersey BOARD OF PUBLIC UTILITIES 44 SO. CLINTON STREET 7 TH FLOOR P.O. BOX 350 TRENTON, NEW JERSEY

DEPARTMENT OF THE AIR FORCE. SUBJECT: Excavation Dewatering at Eielson Air Force Base, Alaska

APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED

Electronic Document Review (EDR)

TAB B-9 RECORD DRAWINGS

SECTION 2 GENERAL REQUIREMENTS

APPLICATION FOR CERTIFICATE OF APPROPRIATENESS IN THE HISTORIC DESIGN REVIEW DISTRICT

Section XV - PER, Design, and Construction Submittal Requirements

Submittal Packages Detailed with Items and Reviewers

CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS

Spec Section: Concrete Mix Design psi - Review Form Concrete Mix Design psi Data Sheets GCAN

UNIFIED FACILITIES GUIDE SPECIFICATIONS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PRESSURE GAUGES, Section 15130

James W. Moore, PE / Brandon D. Enevold, PE / Kjersten E. Kuhta, PE Dylan J. Cunningham, PE / Jacob L. Deering, PE / Joel R.

CONVEYANCE PIPELINE AND PUMP STATION

SECTION PANELBOARDS

City of Aspen Electronic File Preparation Standards September 2018

Transcription:

1 FAST TRACKING

FAST TRACK WORKSHOP OBJECTIVES TO UNDERSTAND: 1. WHY ARE CRITICAL PATH ( FAST TRACK ) DESIGN SUBMITTAL PACKAGES ALLOWED 2. WHEN IS FAST TRACK ALLOWED 3. WHEN IS THE CONTRACTOR ALLOWED TO START WORK 4. WHEN IS THE CONTRACTOR NOT ALLOWED TO START WORK 5. ACTIONS REQUIRED WHEN FAST TRACK DESIGN DOES NOT MEET THE RFP REQUIREMENTS. 2

WHY ARE FAST TRACK DESIGN PACKAGES ALLOWED? 1. So that the Government doesn t delay the Contractor by requiring a Final Design for the entire project before they can start construction. 2. Allows the Contractor to start construction work earlier on certain elements of the project concurrent with design development of other parts of the project. 3

6 S OF THE RFP Statement of work 4 Proposal Forms & Documents (FAR Clauses, etc.) General Requirements (Division 01 UFGS) Project Program (Project Description, Objectives, Requirements, & Site Analysis) Performance Technical Specifications Prescriptive Specifications (Generally Military Unique Specs) Attachments (As-builts, soils data, asbestos & lead surveys, concept design, etc.) www.wbdg.org/ndbm 1 2 3 4 Fast Tracking 5 6

RFP 2 DIVISION 01 GENERAL REQUIREMENTS Section 01 31 19.05 20 Post Award Meetings Section 01 14 00.05 20 Work Restrictions Section 01 35 13.05 20 Special Project Procedures Section 01 20 00.05 20 Price and Payment Procedures Section 01 30 00.05 20 Administrative Requirements Section 01 32 16.00 20 Design and Construction Progress Documentation Section 01 32 17.05 20 Network Analysis Schedule Section 01 33 10.05 20 Design Submittal Procedures Section 01 33 00.05 20 Construction Submittal Procedures Section 00 31 10 Metric Measurements Fast Track Design Submittals Section 01 45 00.05 20 Design and Construction Quality Control Section 01 50 00.05 20 Temporary Facilities Section 01 35 29.05 20 Safety Requirements Section 01 74 19.05 20 Construction and Demolition Waste Management Section 01 57 19.05 20 Temporary Environmental Controls Section 01 78 24.05 20 Facilities Operation & Maintenance Support Information 5

MULTIPLE FAST TRACK FINAL DESIGN PACKAGES DEMOLITION SITE DESIGN SITE DESIGN CRITICAL PATH DESIGN CONSTRUCTION FOUNDATION DESIGN FURNITURE PACKAGE DESIGN & CONSTRUCTION PHASE REMAINING DESIGN Note: Generally a maximum of two submittals are preferred: Site Development & Remaining Design 6

FAST TRACK DESIGN PACKAGES 7 RFP 2 - SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES : 2.2.1 Design Submittal Packages The Government prefers to review for Quality Assurance (QA) as few submittal packages as possible. Site and Building Design Submittal Packages are required, however Critical Path Design Submittals are acceptable if they are substantiated as having an impact to the critical path in the Government approved Network Analysis Schedule. A Critical Path submittal shall include all design analyses, drawings, specifications and product data required to fully describe the project element for Government review. Examples of project elements that may be submitted as Critical Path Design Submittal Packages are: Master Plan Design, Demolition Design, Foundation Design, Structural Design, Building Enclosure Design, Remaining Work Design, Furniture/Equipment Design, long lead items, or any other construction activity or project element that can be organized into a submittal package that can be reviewed and approved by the Government without being contingent upon subsequent design submittals.

WHEN IS THE CONTRACTOR ALLOWED & NOT ALLOWED TO START WORK? RFP 2 - SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES : 1.5.4 Contractor Construction Actions: Upon submission of sealed and signed design documents certified by the DOR, the Design Quality (DQC) Manager and the Quality Control (QC) Managers, the Contractor may proceed with material and equipment purchases, fabrication and construction of any elements covered by that submittal [, except as specified in the following paragraph]. 1.5.4.1 Exception to Contractor Construction Actions: The Government will approve the following final submittals before the Contractor shall be allowed to proceed with construction: a. [Seismic Damping Systems] b. [Historical Preservation] c. [Other unique/critical items] Notes: 1. QC Plan must also be approved by the Government before starting construction work. 2. By default Government approval is not required before construction. Consult with technical team to edit. 8

ACTIONS REQUIRED WHEN FAST TRACK DESIGNS DO NOT MEET THE RFP RFP 2 - SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES : 1.5.7.1.c Submittals marked "revise and resubmit" or "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with appropriate changes. If work has been started on the unacceptable portion of the design submittal, the Contractor shall propose corrective action. No further work shall proceed until the issue is resolved in a manner satisfactory to the Government. 9

TAKEAWAYS 1. THE CONTRACTOR DOESN T NEED GOVERNMENT APPROVAL OF THE FINAL DESIGN PACKAGES BEFORE STARTING WORK, EXCEPT FOR SUBMITTALS IDENTIFIED IN 2 THAT ARE RESERVED FOR GOVERNMENT APPROVAL. 2. THE CONTRACTOR NEEDS TO PROVE THAT FAST TRACK DESIGN PACKAGES HAVE AN IMPACT TO THE SCHEDULE. GOVERNMENT PREFERS TWO MAXIMUM. 3. FAST TRACK DESIGN PACKAGES MUST NOT BE CONTINGENT UPON SUBSEQUENT DESIGN SUBMITTALS. STAND-ALONE PACKAGES 4. STOP WORK IF FAST TRACK DESIGN DOES NOT MEET RFP (PORTIONS THAT DON T MEET THE RFP). 10

11 QUESTIONS?