ECP HV INSULATION TESTING

Similar documents
ECP HV INSULATION TESTING

EI HIGH VOLTAGE INSULATION TESTING POLICY

ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE

ECP DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE

ECP HV METERING EQUIPMENT COMMISSIONING PROCEDURE

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE

ECP GROUND-MOUNTED SWITCHGEAR COMMISSIONING PROCEDURE

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

EDS LV ELECTRICAL SERVICE DRAWINGS

EDS KV TRIPLEX CABLE RATING

EDS KV SINGLE CORE XLPE CABLES

EDS FAULT LEVELS

EDS GRID AND PRIMARY SUBSTATION CIVIL DESIGN STANDARDS

EDS LV WAVEFORM MAINS CABLE RATINGS

Testing of 400 kv GIS

Power Frequency Withstand Voltage On-site testing of 400 kv GIS

RELEVANT ELECTRICAL STANDARDS

UK Power Networks OPERATIONAL BULLETIN

IMP/007/011 - Code of Practice for the Application of Lightning Protection

Substation Preventive Maintenance

Specialists in HV and MV test and diagnostics. Testing in Substations

RELEVANT ELECTRICAL STANDARDS

SUBJECT HEADING: Switching Programmes ISSUE: 18

Condition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology

Earthing, HV Switching and Associated Operational Equipment. Approval: Chief Operating Officer

INTEGRATED TRANSMISSION PLAN Glossary

VI 3 - i TABLE OF CONTENTS

SYNCHRONISING AND VOLTAGE SELECTION

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

شركة الوقت للكهرباء والمقاوالت ذ.م.م.

Distribution transformers Part 2 Ground mounted transformers not closecoupled

EDS EHV NETWORK DESIGN

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it.

A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation Equipment

DEVELOPING TESTING PROCEDURES FOR HIGH VOLTAGE INNOVATION TECHNOLOGIES

TS RES - OUTSTANDING ISSUES

Connection of Embedded Generating Plant up to 5MW

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009

Substation HV Cables. Document Number: 1-11-FR-07

TECHNICAL DESCRIPTION TD-77A/3 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES

EDS LV NETWORK DESIGN

7. INSPECTION AND TEST PROCEDURES

Field Instruction Switching Activities. Purpose. Scope. Objective. Safety

ECP TESTING AND COMMISSIONING GUIDANCE NOTES

Welcome to the Session on. HT Distribution Network

COURSE PLANNER. Subject: TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS ( ) B.E. Fourth Year (8 th Sem) Branch Electrical Engineering

Equipment Description Quantity as per drawings Actual quantity

USING DAMPED AC VOLTAGES

Reference Number PCP 02 (RIC Standard: EP SP)

DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW)

Electrical Switchgear & Power Transformer Testing. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

CIGRE General Session, Paris 2014 Group Meeting SC B1 Insulated Cables, 27th August, 2014 Results of CAG Questionnaire

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

NPS/002/016 Technical Specification for 33 kv Cable Joints and Terminations

POWER TRANSFORMER. Failure Analysis & Troubleshooting. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

Advanced Test Equipment Rentals ATEC (2832) CP RC. Resonance circuit for GIS testing

Partial Discharge Measurement and Monitoring on High Voltage XLPE Cables

PD Testing Considerations for MV Plant Cables

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Single Line Diagram of Substations

Cable testing and diagnostics

MINISTRY OF ELECTRICITY

CONDITIONS FOR A TENTATIVE APROVAL FOR CONNECTION OF TRANSFORMERS

INSTALLATION & TESTING OF UNDERGROUND PRIMARY AND SECONDARY POWER CABLES PRIOR TO ENERGIZATION

GENERATOR TESTING APPLICATION GUIDE. reliable. precision.

Africa Utility Week Focus Day Substation Condition Monitoring Benefits of Ultrasound

SERVICING & METERING SERVICING AND METERING SECTION 5 SEC5:

The NOVA Recloser shall be designed and tested in accordance with the following standards as applicable:

Reference Number PDS 04 (RIC Standard: EP SP)

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Underground System Design TADP 547

EE 1402 HIGH VOLTAGE ENGINEERING

P.O (November 2009) This is an unofficial translation of the latest draft of the Spanish grid code. Source: Jason MacDowell, GE Energy

Form-IV. Form of Inspection/Test Report. (Under Regulation 43)

The Basics of Insulation Testing

Appendix D Fault Levels

Testing Manual for Electrical Equipment

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT CODE & NAME : EE 1402 HIGH VOLTAGE ENGINEERING UNIT I

Aspects of PD interpretation in HV power cables. by Edward Gulski, Piotr Cichecki, Rogier Jongen

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Unit 2. Single Line Diagram of Substations

HIGH VOLTAGE RULES. Document Owner: HV Group. Authorised: Electrical Services Manager Liberty Primary Steel

Hands-On Transformer Testing and Maintenance

Test systems made by SebaKMT. Don t stress over tests! SebaKMT has the right answers: reliability, speed, economy.

HV AC TESTING OF SUPER-LONG CABLES

On-line Partial Discharge Assessment and Monitoring of MV to EHV Cables

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code)

MEDIUM & HIGH VOLTAGE

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007.

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Exploring the Necessity of the Hot Hipot Test

Protection of Electrical Networks. Christophe Prévé

PSSI 27 Work or Testing On or Near to High Voltage Direct Current (HVDC) Plant and Apparatus

Title: Southern States Type SLS Smart Sectionalizer Solid Dielectric Three Phase Sectionalizer. Product Specification Guide TABLE OF CONTENTS

Course No: 1 13 (3 Days) FAULT CURRENT CALCULATION & RELAY SETTING & RELAY CO-ORDINATION. Course Content

PD Diagnostic Applications and TechImp solutions

Ferroresonance Experience in UK: Simulations and Measurements

Identification and recording of 'hot' sites - joint procedure for Electricity Industry and Communications Network Providers

Transcription:

Document Number: ECP 11-0006 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE EPN, LPN, SPN ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing of new and existing high voltage cables, switchgear and transformers. Author: Stephen Tucker Approved By: Paul Williams Approved Date: 16/02/2017 This document forms part of the Company s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue. Applicable To UK Power Networks External Asset Management G81 Website Capital Programme Contractors Connections ICPs/IDNOs Health & Safety Meter Operators Network Operations Procurement Technical Training UK Power Networks Services THIS IS AN UNCONTROLLED DOCUMENT, THE READER SHALL CONFIRM ITS VALIDITY BEFORE USE

Revision Record Version 10.0 Review Date 10/02/2022 Date 10/02/2017 Author Stephen Tucker Why has the document been updated: Alignment with other referenced documents. What has changed: Document references updated (Sections 11and 12). Test form references updated (ECP 11-0006a) Document reviewed and review date extended Version 9.0 Review Date 04/12/2020 Date 04/12/2015 Author Stephen Tucker Why has the document been updated: Renumbered to align with other commissioning documents and new cable insulation test form ECS 11-0006a added. What has changed: Document renumbered from EOS 09-0001 to ECS 11-0006. HV polymeric cable sheath testing document reference updated (Sections 5.4 and 5.8). New test form ECS 11-0006a added to record cable insulation test results (Section 11). Version 8.0 Review Date 31/03/2017 Date 21/03/2014 Author Paul Dyer/Paul Williams Review and additional clarifications added Version 7.2 Review Date Date 19/07/2012 Author Lee Strachan Document reviewed for publishing on G81 website Version 7.1 Review Date Date 21/09/2011 Author Hulya Kiani Document reclassified from EI 09-0001 to EOS 09-0001 Version 7.0 Review Date Date 21/02/2011 Author Paul Williams Clarification for cable sheath test requirements added Version 6.0 Review Date Mariann Mulligan Date 20/10/2010 Author Document rebranded Version 5.1 Review Date Date 17/12/2009 Author Paul Dyer Revised 66 and 132kV switchgear test Version 5.0 Review Date Date 10/03/2009 Author Paul Williams Revision to test voltage for 66 and 132kV cables UK Power Networks 2017 All rights reserved 2 of 17

Contents 1 Introduction... 5 2 Scope... 5 3 Glossary and Abbreviations... 6 4 Testing... 6 4.1 General... 6 4.2 New Apparatus... 7 4.3 Existing Apparatus... 7 4.4 Test Application... 7 4.5 Test Methods... 7 5 Cable Testing... 8 5.1 Acceptable IR Values... 8 5.2 New and Existing Cables up to 33kV... 8 5.3 Cable Fault Location up to 33kV... 9 5.4 Cable Over-sheath Tests 11kV to 33kV Cables... 9 5.5 New and Existing Cables 66kV and 132kV Oil and Gas Pressure Assisted Cables 9 5.6 New and Existing Cables 66kV and 132kV Cables Containing XLPE Insulated Cable... 10 5.7 Cable Fault Location 66kV and 132kV... 11 5.8 Cable Over-sheath Tests 66kV and 132kV Cables... 11 5.9 Switchgear Associated with Cable Testing... 11 6 Switchgear Testing... 12 6.1 Test s... 12 6.1.1 New switchgear... 12 6.1.2 Existing switchgear... 12 6.1.3 Application of Test... 12 6.2 Alternative Soak Test for 66kV and 132kV GIS Switchgear... 14 6.3 Air Insulated Busbars and Disconnectors... 14 7 Transformer Testing... 15 8 Transformer Tails and Test Access... 16 9 Overhead Line Testing... 16 10 Other Equipment... 16 11 Test Results... 16 12 References... 17 12.1 UK Power Networks Standards... 17 12.2 National and International Standards... 17 UK Power Networks 2017 All rights reserved 3 of 17

Tables Table 5-1 Minimum Test s for New and Existing Cables up to and including 33kV. 8 Table 5-2 Maximum Levels for Fault Location for Cable up to and including 33kV 9 Table 5-3 Cable Over-sheath Test s for Cables up to 33kV... 9 Table 5-4 Minimum Test s for New and Existing Fluid and Gas Filled 66kV and 132kV Cables... 10 Table 5-5 Minimum Test s for New 66kV and 132kV XLPE Cables... 10 Table 5-6 Minimum Test s for 66kV and 132kV Cable System Containing Existing Sections of Cable... 10 Table 5-7 Maximum Levels for Fault Location for 66kV and 132kV Cable Systems... 11 Table 5-8 Cable Over-sheath Test s for Cables 66kV and 132kV... 11 Table 6-1 Test s for New Extensible Switchgear... 13 Table 6-2 Test s for Existing Switchgear... 13 Table 7-1 Test s for Transformers... 15 Table 7-2 Maximum Test s for Transformers (for example where other equipment is connected)... 15 UK Power Networks 2017 All rights reserved 4 of 17

1 Introduction This standard details the requirements for the on-site insulation testing of high voltage cables, switchgear and transformers. The purpose of on-site insulation testing is to demonstrate that apparatus can be safely connected to the system. The testing regime detailed in this standard is designed to avoid unnecessary overstressing and to prolong the life of the apparatus. It should identify any gross defect, damage or earths left connected at a remote end. The testing regime is based on current practice from the relevant British and International standards together with current practice used on the three networks within UK Power Networks. Consideration has been given to safety of field staff, the availability of test equipment and the relative merits of ac, dc, oscillating wave (OWTS) and very low frequency (VLF) ac testing. This standard supersedes the following documents: EPN: EDM V12/S1/8 Site Insulation Tests for High Equipment. LPN: E5-6-1 Dielectric Testing. LPN: E5-6-1-1 HV Dielectric Testing. SPN: EI 9-001-12 Site Insulation Testing of Cables, Switchgear and Transformers. SPN: Site Testing & Commissioning Manual 2.N3 On-site Insulation Testing of Cables, Switchgear & Transformers. 2 Scope This standard applies to the insulation testing of cables, switchgear and transformers from 1000V to 132kV on the EPN, LPN, SPN and private networks and includes: New apparatus before it is connected to the system for the first time. Existing apparatus after it has been modified, repaired or moved. Existing solid cable after it has been de-energised for an extended period. Cable fault locating. The testing of insulated cable sheaths. Overhead lines where insulation testing is not considered practicable. This standard does not seek to provide condition monitoring information or partial discharge information. UK Power Networks 2017 All rights reserved 5 of 17

3 Glossary and Abbreviations Term GIS IR NVD OWTS SAP VLF UK Power Networks Definition Gas Insulated Switchgear Insulation Resistance Neutral Displacement Oscillating Wave Test Set Senior Authorised Person Very Low Frequency UK Power Networks (Operations) Ltd consists of three electricity distribution networks: Eastern Power Networks plc (EPN). London Power Network plc (LPN). South Eastern Power Networks plc (SPN). 4 Testing 4.1 General Testing shall be carried out: After apparatus is installed (or re-installed) but before energisation for the first time. After work on the insulation of apparatus but not normally after routine maintenance. After cable with solid insulation has been intentionally left de-energised for more than one month. For new and re-commissioned equipment the interval between testing and energisation from the system should be the minimum practicable: Cables up to and including 11kV no more than 24 hours. Cable systems from 22kV and up to and including 132kV this should normally be no longer than 72 hours. However for cables at all voltages an extension to this period is available to the Senior Authorised Person (SAP) providing the integrity of the system can be assured, for example visual inspection of the route or the completion of another successful sheath test. Swinger transformers and other standby equipment that is left intentionally de-energised will need to be energised monthly to avoid the need for isolation and testing. Dispensation to vary from the test methods and voltage levels set out in this standard for network test voltages above nominal phase to earth voltages can be granted by the UK Power Networks Head of Engineering Standards. Where the network test voltage is lower than the nominal phase to earth voltage, permission to test should be sought from the Director of UK Power Networks Asset Management. UK Power Networks 2017 All rights reserved 6 of 17

4.2 New Apparatus All new apparatus should, following installation, be successfully tested once at the voltage specified in this standard. Where the manufacturer recommends tests that differ from this standard, guidance shall be obtained from UK Power Networks Asset Management. 4.3 Existing Apparatus All apparatus which has been de-energised and has knowingly had the insulation affected (except changing oil and topping up SF 6) shall be subjected to an insulation test as specified in this standard. 4.4 Test Application Where two or more items of apparatus are connected, the apparatus requiring the least onerous test determines the test voltage. Site engineers shall take account of the risks involved in disconnecting equipment compared with the risks of a reduced voltage test. Equipment installed to run initially at a lower voltage than its rating shall be tested according to its rating before connection to the lower voltage system. If, after this test, the insulation is in any way disturbed, e.g. a 33kV cable is jointed to an 11kV cable, an insulation test voltage appropriate to the working voltage shall be applied before commissioning. 4.5 Test Methods This standard includes both dc and ac test methods. A dc test is usually carried out using an insulation tester with the appropriate voltage output, such as a Megger or dc pressure test set. An ac test is usually carried out using an ac test set, OWTS test set or a test van to give the required voltage. Where both dc and ac tests are specified for equipment or cables either test may be used. For cables it is necessary to apply the test voltage and allow the cable to fully charge up. Generally with test sets the timing begins when the test set has reached the required voltage and for insulation resistance (IR) testers the time begins when the IR value has stabilised. Also, with some newer IR test sets, the test is considered a pass if the cable remains at the specified voltage for the duration of one minute the voltage will drop if the insulation breaks down during that time span. Partial discharge testing methods are being developed and operational advice will need to be followed. UK Power Networks 2017 All rights reserved 7 of 17

5 Cable Testing 5.1 Acceptable IR Values It is not possible to specify a lowest acceptable insulation resistance value for dc testing (as it depends on a number of factors including cable type/length, weather conditions, etc.) all three cores should be similar and a different value on one core would indicate a problem. The determining factor is whether any of the phases has an unacceptably low reading (1MΩ) or a drastically different reading. Engineering judgement needs to be applied to the value obtained. If traditional fault location fails to indicate a fault then connecting the circuit to the network for a 24 hour soak test is acceptable. If customers will be affected by the fault occurring during this test the number of customers shall be as low as is reasonably practical. 5.2 New and Existing Cables up to 33kV It is essential before energisation to ensure the cable is continuous from end-to-end. This will check that the cable is laid as planned and that any route joints have been completed. Table 5-1 shows the minimum voltages to be used. s up to those detailed in Table 5-2 are acceptable if site conditions require. These voltages can also be used for testing transformer tails between the winding and earth; refer to Section 8. Table 5-1 Minimum Test s for New and Existing Cables up to and including 33kV Rated Line Cable Type dc Test Duration Test Application 6.6 (2 and 3.3) All Types 11 All Types See note 20 and 22 All Types 33 All Types 5 1 Test voltage applied to one phase with the other two phases connected to earth/metallic screen Test voltage may also be applied to two phases with the third connected to earth/metallic screen Note: Partial discharge mapping carried out in London, mainly at 11kV, is used as a commissioning test. These tests require the test voltage to be of the order of 1.5Uo ac at 0.1Hz for a period of up to 15 minutes. UK Power Networks 2017 All rights reserved 8 of 17

5.3 Cable Fault Location up to 33kV It is permissible to apply higher dc voltages for fault location up to the maximum shown in Table 5-2. Table 5-2 Maximum Levels for Fault Location for Cable up to and including 33kV Rated Line dc Test to Earth 6.6 7 11 12 20 and 22 24 33 36 5.4 Cable Over-sheath Tests 11kV to 33kV Cables The test voltages for over-sheath tests are given in Table 5-3. Tests are required for new cables (having an insulated sheath) prior to energisation. Also, when returning an insulated sheath cable to service following diversion or repair then a sheath test as shown in Table 5-3 is required. All cable over-sheath tests shall be carried out as specified in ECP 11-0007. Table 5-3 Cable Over-sheath Test s for Cables up to 33kV System Nominal Minimum dc Test New cables Minimum dc Test On return to service Test Duration Maximum Leakage Current (ma) Test Application 11 20 and 22 5 Not Applicable 33 5 5 1 10 Between metallic sheath and earth Note: Specially bonded cable circuits complying with the requirements of ENA ER C55/4 may require further tests in addition to the over-sheath tests above. 5.5 New and Existing Cables 66kV and 132kV Oil and Gas Pressure Assisted Cables It is essential before energisation to check the cable is continuous from end-to-end. This will ensure that the cable is laid as planned and that any route joints have been completed. The cable shall withstand a dc test voltage of negative polarity applied between the conductor(s) and sheath with the sheath earthed. Table 5-4 shows the minimum voltages to be used. No breakdown of the insulation shall occur. UK Power Networks 2017 All rights reserved 9 of 17

Table 5-4 Minimum Test s for New and Existing Fluid and Gas Filled 66kV and 132kV Cables Rated Line dc Test for New Cable Systems Minimum dc Test for Systems with old Cable Duration Test Application 66 170 71 132 305 130 15 Test voltage applied to one phase with the other two phases connected to earth/metallic screen 5.6 New and Existing Cables 66kV and 132kV Cables Containing XLPE Insulated Cable It is essential before energisation to check the cable is continuous from end to end. This will ensure that the cable is laid as planned and that any route joints have been completed. The cable shall withstand an ac test voltage applied between a conductor and sheath or all conductors with the sheath earthed. Where possible a Partial Discharge (PD) test shall be carried out during the ac test. The test will normally be provided by a series resonant or OWTS test set operating close to power frequency. Table 5-5 shows the minimum voltages to be used. No breakdown of the insulation shall occur. If the cable system contains sections of existing fluid filled, gas filled or XLPE cable the test voltage should be reduced in line with Table 5-6. Table 5-5 Minimum Test s for New 66kV and 132kV XLPE Cables Rated Line ac Test for New Cable Systems Frequency (Hz) Duration 66 72 132 132 20-300 60 Table 5-6 Minimum Test s for 66kV and 132kV Cable System Containing Existing Sections of Cable Rated Line Existing cable less than 5 years old ac Test Duration Existing cable less than 20 years old ac Test Duration Existing cable more than 20 years old ac Test Duration 66 72 61 54 60 60 132 132 114 95 60 UK Power Networks 2017 All rights reserved 10 of 17

5.7 Cable Fault Location 66kV and 132kV It is permissible to apply higher dc voltages for fault location up to the maximum shown in Table 5-7. Table 5-7 Maximum Levels for Fault Location for 66kV and 132kV Cable Systems Rated Line dc Test to Earth 66 50 132 50 5.8 Cable Over-sheath Tests 66kV and 132kV Cables The test voltages for over-sheath tests are given in Table 5-8. Tests are required for new cables (having an insulated sheath) prior to energisation. Also, when returning an insulated sheath cable to service following diversion or repair then a sheath test as shown in Table 5-8 is required. All cable over-sheath tests shall be carried out as specified in ECP 11-0007. Table 5-8 Cable Over-sheath Test s for Cables 66kV and 132kV System Nominal Minimum dc Test New cables Minimum dc Test On return to service Test Duration Maximum Leakage Current (ma) Test Application 66 Not Applicable 132 10 5 1 10 Between metallic sheath and earth Note: Specially bonded cable circuits complying with the requirements of ENA ER C55/4may require further tests in addition to the over-sheath tests above. 5.9 Switchgear Associated with Cable Testing It shall be established whether the switchgear is capable of withstanding the cable test voltage, otherwise, the least onerous test voltage shall be used. Note: The specification for new switchgear ensures that all cable test access points will withstand the highest cable test voltages detailed in this document. UK Power Networks 2017 All rights reserved 11 of 17

6 Switchgear Testing 6.1 Test s 6.1.1 New switchgear The test voltages to be used for new switchgear are given in Table 6-1. These test voltages shall apply to: All extensible switchgear which incorporates site-made high voltage connections. Any non-extensible switchgear where work has been carried out affecting the insulation. Note: For clarification, removal and replacement of the SF 6 gas does not require dielectric retesting of the system. Where factory assembled and tested GIS panels are supplied, comprising circuit-breaker, disconnectors and earth switches, dielectric testing of individual panels is not required on-site. If work on site requires dismantlement of any factory built and tested equipment, then an assessment of the re-testing required shall be made and agreed with UK Power Networks Asset Management. For non-extensible switchgear at all voltages (including, for example, dead and live tank 132kV circuit-breakers) which has been factory tested, and on which no work has been carried out on the insulation, a test voltage of 5kV dc shall be applied for one minute. 6.1.2 Existing switchgear The test voltages to be used for existing switchgear are given in Table 6-2. These test voltages shall apply to: All switchgear where work has been done affecting the insulation (where the insulation has not been disturbed a 5kV megger test for 1 minute shall be carried out). All switchgear which has been re-installed. 6.1.3 Application of Test The test voltages shall be applied: 1. Between phases and phase to earth with the contacts closed: Test voltage applied to Earth applied to Test voltage applied to OR L1 L3 + L2 L1 and L2 L3 L2 L1 + L3 L2 and L3 L1 L3 L1 + L2 Earth applied to 2. Across the open contacts (unless assembled and dielectric tested in the factory): Test voltage applied to Earth applied to L1, L2 and L3 L1, L2 and L3 opposite contacts UK Power Networks 2017 All rights reserved 12 of 17

If the equipment has been assembled and tested in the factory, a valid test certificate shall be provided with the equipment, demonstrating the method of testing and the results. If surge diverters, neutral voltage displacement (NVD), capacitor bushings, etc. cannot be disconnected then the manufacturer s advice should be obtained before proceeding. Table 6-1 Test s for New Extensible Switchgear Rated Line Switchgear Rated ac Test Test Duration Up to 11kV 12kV 22 (see note 1) 20/22 24kV 40 (see note 1) 33 36kV 56 (see note 1) 1 66 72.5kV 112 (see note 1) 132 145kV 220 (see note 1) Table 6-2 Test s for Existing Switchgear Rated Line Switchgear Rated 3 ac Test Test Duration Up to 6.6 7.2kV 10 (see note 2) 11 12kV other than above 16.5 (see note 2) 20/22 24kV other than above 33 (see note 2) 33 36kV 50 (see note 2) 1 66 (see note 3) 72.5kV 99 (see note 2) 132 (see note 3) 145kV 198 (see note 2) Notes: 1. The ac test voltage for new extensible switchgear is 80% of factory test and should also include a 5kV IR result both before and after the ac test. 2. The switchgear will withstand the full test voltage applied to new equipment but to reduce the stress for this and subsequent tests the test voltage for existing switchgear has been reduced to 1.5 times the line voltage. 3. See alternative soak test for 66kV and 132kV GIS switchgear. UK Power Networks 2017 All rights reserved 13 of 17

6.2 Alternative Soak Test for 66kV and 132kV GIS Switchgear An alternative regime for retesting 66kV and 132kV GIS switchgear, following an earlier full test, is to connect the switchgear to the network for a 24 hour period to soak test it rather than apply a voltage test. This test has been approved because: The difficulty, expense and risk of providing full test voltage immediately prior to energisation. Connecting and disconnecting the test set to GIS equipment, involves work on the equipment; consequently the reconnection and re-gassing after removing the test set is not then tested. This option is available to the SAP who will supervise the re-commissioning if: The switchgear is GIS, requiring opening of gas compartments for connecting and disconnecting the test connections. No external insulation has been disturbed in the parts being tested. The protection is arranged such that in the event of a fault on the equipment being tested no loss of supplies to customers shall occur. The system fault level is reduced to the lowest possible level and access to the plant under test is restricted. 6.3 Air Insulated Busbars and Disconnectors Testing of air insulated busbars, air break isolators or post insulators, etc. is not required by this standard providing a visual inspection is made prior to energisation. UK Power Networks 2017 All rights reserved 14 of 17

7 Transformer Testing The assembly of transformers, transport arrangements, quality controls during installation and sealing is such that high voltage insulation testing is generally unnecessary. Unless otherwise agreed with the manufacturer the only testing required for transformers (including polemounted) is insulation resistance testing using the test voltages given in Table 7-1. The insulation resistance shall be comparable with the original test documentation (if available). If, in order to test other equipment, it is necessary to apply a higher test voltage to the windings, then the voltages given in Table 7-2 should not be exceeded. Table 7-1 Test s for Transformers Test System Nominal dc Test Test Duration Test Application Winding Insulation Core Insulation Up to 6.6 11 1 22 1 33 1 2.5 (see note) 66 2.5 132 All 1 1 Apply to each winding in turn with the other winding(s) earthed Core insulation should be clear of earth with core earth link removed and connected to earth after core earth link replaced Note: The test voltage specified in the manufacturers test documentation should be used. Table 7-2 Maximum Test s for Transformers (for example where other equipment is connected) System Nominal dc Test Test Duration 6.6 6.6 11 11 22 22 33 33 66 66 66 (graded insulation) 30 132 (graded insulation) 50 1 Note: If a higher test voltage is to be considered, the manufacturer should be consulted prior to testing. UK Power Networks 2017 All rights reserved 15 of 17

8 Transformer Tails and Test Access Where test access is available transformer tails shall always be tested. Where test access requires the dismantlement of apparatus and the SAP considers the risk to personnel of gaining the test access is higher than the risk of failure then the test may be omitted. This will usually apply at 11kV primary substations where the cable tails are within the UK Power Networks site and there is no reason to believe there has been any damage. 9 Overhead Line Testing Insulation testing of overhead lines is not considered reasonably practicable. However, before commissioning, a visual inspection shall be made of new overhead lines and the modified parts of previously energised lines. Also, before re-commissioning overhead lines that have been de-energised for an extended period of time, a risk assessment shall be made to decide if a visual inspection is required. This assessment shall take into account factors, such as the activity of third parties in the vicinity of the circuit and severe weather conditions. 10 Other Equipment Other equipment that has been factory assembled, subjected to routine factory testing and for which a test certificate is available on site, and where no disturbance to the insulation has been made, shall be subjected to the following. A visual inspection for damage or deformation before and after installation; A 5kV megger test for 1 minute. An example of other equipment is a 33kV through wall bushing. 11 Test Results The results of the all tests shall be recorded as specified in ECP 11-0001 and ECP 11-0002. All cable insulation test results shall be recorded on test form ECP 11-0006a unless the cable testing is part of substation commissioning when the results should be recorded on appropriate test form ECP 11-0501a (secondary) or ECP 11-0202 (grid and primary). UK Power Networks 2017 All rights reserved 16 of 17

12 References 12.1 UK Power Networks Standards UK Power Networks Distribution Safety Rules ECP 11-0001 Grid and Primary Installation Commissioning Requirements ECP 11-0002 Secondary Commissioning Requirements ECP 11-0006a EHV and HV Cable Insulation Test Form ECP 11-0007 HV Polymeric Cable Sheath Testing Procedure ECP 11-0202 HV Pressure Test Form ECP 11-0501a Secondary Substation Commissioning Form 12.2 National and International Standards ENA ER C55/4 Insulated Sheath Power Cable Systems UK Power Networks 2017 All rights reserved 17 of 17