PROBABILISTIC ESTIMATES OF DEEPWATER OFFSHORE FIELD ABANDONMENT COST

Similar documents
Marginal Project Development

Subsea Well Abandonment Case Study:

Shell Subsea Experience

Speaker at the Americas: Decommissioning and Well Abandonment. September 23, 2015

Riserless Subsea P&A. Deepwater Decommissioning Workshop 2016 W I L D W E L L C O N T R O L S U B S E A I N T E R V E N T I O N

HELIX ENERGY SOLUTIONS

ANADARKO PETROLEUM CORPORATION

Maximising Well Intervention Efficiency in the Gulf of Mexico: A New Best Practice Model

Increased Safety & Efficiency from a Dedicated Light Well Intervention Vessel on Deepwater Subsea Wells

An Introduction to Oil & Gas Drilling and Well Operations

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015

Subsea Intervention: Is It Worth It? Drummond Lawson

WELLBORE ABANDONMENT CHALLENGES & OPERATIONS A-1, A-2, A-3, A-5, A-6, DEEP MENSA A-4 (PREVIOUSLY ABANDONED)

Emerging Subsea Networks

Deepwater riserless (RLWI) enablers for increased oil recovery. Bringing shallow water experience to deepwater.

Geoprober Drilling Moving from Ideas To Reality (Status August, 2005)

Moduels in PetroTrainer. PetroTrainer. How PetroTrainer is used

SUBSEA WELL CONTAINMENT. Global Basis. Deepwater & Emerging Technologies Group (DETG) AADE Houston Chapter 25 January 2012

ACID STIMULATION CASE STUDY

Analysis of Non-Productive Time in Geothermal Drilling Operations-A Case Study of Olkaria, Kenya

June 24, 2010 RPSEA Project 1502 Thomas E. Williams int.com

Deep Water Definitions

Sinking of the Deepwater Horizon. 11 perish and 115 survive

3/14/2015 Contacted and Solicited bids from construction vendors to build location. (San Jan, Orbit, Sweat, Storm).

SUBSEA 101. Find more Subsea 101 case studies online

Investor Presentation

Digital Oil Recovery TM Questions and answers

Kuala Lumpur 3 October 2012 State of the Industry of Riserless Light Well Interventions (RLWI)

Comprehensive Plug and Abandonment Systems

The Lease Pumper s Handbook. Chapter 4 Understanding the Oil Well. Section B DRILLING OPERATIONS

Marine Well Containment Company Outer Continental Shelf Summer Seminar

Doing More With Lightweight. Well Intervention Subsea Europe Drummond Lawson. London, 30 th October Managing Director

GTSC Rig for Hands-on Training

Appendix F Lock-Down Sleeve Decision. Appendix F Lock-Down Sleeve Decision

Morgan Stanley Houston Energy Summit

Development of the RapidJet Method of Gas Well Deliquification

DE123 Advanced Drilling Practice Technology

Integrated approach to upstream decision making. London January 2010

Technological and Logistical Challenges during Construction & Installation of Deepwater Mega Subsea Development in West Africa

3D OFFSHORE PROJECT SIMULATION. Singapore Shipyard. Replace all chain. Adding a riser

Deepwater well design, construction & drilling operations

Experience, Role, and Limitations of Relief Wells

Deepwater Precommissioning Services

The intent of this guideline is to assist the Drilling Engineer in his preparation of the deepwater drill stem test design and procedure.

Tony Owen, Subsea and Pipelines Decommissioning Delivery Manager AOG February 2017

MIDDLE EAST WELL INTEGRITY WHITEPAPER

BT-4000 LIGHT WORKOVER UNIT

Tomorrow's Energy Designed Today TECHNOVA

37 th Gas-Lift Workshop Houston, Texas, USA February 3 7, Dag Almar Hansen, CEO Gas-Lift Workshop 1. Feb. 3-7, 2014

ILLUSTRATI VE PICTURE. Delivering product under pressure. Pipeline & Specialty Services

Brent Charlie Ultra Late Life. A Journey in Optimising for Platform Decommissioning

Advanced Well Completion Design. 30 Sep - 04 Oct 2018, Dubai. REP logo, PMI & PMP are registered trademarks of Project Management Institute, Inc.

International Well Control Forum Well Intervention Pressure Control Subsea Syllabus

Expro Perforation Services

Originally Presented at: Gas Well Deliquification Workshop. European Conference Gas Well Deliquification. Holes in Tubing

Siem WIS. Siem WIS AS. Closed Loop Drilling CLD. August Siem WIS AS.

White Paper. Deepwater Exploration and Production Minimizing Risk, Increasing Recovery

The Marine Well Containment System. LSU Center for Energy Studies Energy Summit 2010 October 26, 2010

From late-life reservoir management through to final permanent abandonment, we create bespoke solutions to meet your specific well requirements.

GWF-1 Development DrillWell

EUOAG Workshop. Workshop on decommissioning of offshore installations Challenges, options and lessons learned PP&A

Design Process for Completions and Workovers Core COPYRIGHT. Design Process. This section will cover the following learning objectives:

Advanced Well Completion Design

Welltec Pareto Offshore Conference September 4, 2013

Intervention/Decommissioning

Suspended Subsea Well Monitoring CaTS TM Wireless Technology. Donald Horsfall RPLM (ECIS)

Training Fees 4,250 US$ per participant for Public Training includes Materials/Handouts, tea/coffee breaks, refreshments & Buffet Lunch

Rod Larson President & CEO

Coiled-tubing operations and basic tools

University of Engineering and Technology, Taxila Department of Civil Engineering

OFFSHORE CLAMP PRODUCT GUIDE INTELLIGENT ENGINEERING

QUARTERLY UPDATE. Summary

A Rebirth in the North Sea or simply a False Dawn

Marine Construction Support & Dimensional Control

Macondo Blowout Lessons Learned for Prevention and Mitigation

M. Kevin McEvoy. Oceaneering International, Inc. Chief Executive Officer 2015 GLOBAL ENERGY AND POWER EXECUTIVE CONFERENCE JUNE 2, 2015 NEW YORK, NY

INDONESIA DEEPWATER INVESTMENT

Well Control Considerations of MPD on Deepwater Rigs

Transition PPT Template. J.P. Morgan. June 2015 V 3.0. Energy Equity Conference June 27, 2017

Noble Corporation. Don Jacobsen Senior Vice President Industry & Government Relations Marine/Offshore Industry Conference 29 March 2012

Casing Recovery. Pre-Job Meeting

OTC seems to be able to afford to fix the problems associated with downtime due to an incomplete design.

Hans J Lindland FMC Kongsberg Subsea Innovative Technologies, Creative Solutions

COILED TUBING DESIGN & OPERATIONS

Well Abandonment Services. Plug into a New Approach

Princess Subsea Gas Lift Start-Up

pipeline FSHR and tether for fatigue, stress, and any other abnormal condition (e.g., corrosion) that may negatively impact the riser or tether; and

Encana Corporation Expression of Interest (EOI)

Click to edit Master title style APPEA AWIC UPDATE. Self Audit Checklist Source Control First Response

Heidrun Inverted Gas Lift System

A marginal field (re-)development using several alternative methodologies 1

In any of the 5 star hotel. The exact venue will be intimated prior to course commencement.

Advancing Global Deepwater Capabilities

Executive Summary and Table of Contents

Abstract. Mission. Exceptions

Offshore Drilling Rigs

Recent advancement in well-control technology improves safety and allows cost savings for well designs

Subsea Production Market and Industry Teaming. Presented by: Bruce Crager Executive Vice President: Expert Advisory Group Endeavor Management

Mutineer-Exeter Development Drilling & Completions Challenges Darren Greer & Peter Dodd

Pareto s Annual Oil & Offshore Conference

Transcription:

PROBABILISTIC ESTIMATES OF DEEPWATER OFFSHORE FIELD ABANDONMENT COST Authors Robert C. Byrd, Ph.D., P.E. William H. Speck Disclaimer: Whilst every effort has been made to ensure the accuracy of the information contained in this publication, neither Offshore Network Ltd nor any of its affiliates past, present or future warrants its accuracy or will, regardless of its or their negligence, assume liability for any foreseeable or unforeseeable use made thereof, which liability is hereby excluded. Consequently, such use is at the recipient s own risk on the basis that any use by the recipient constitutes agreement to the terms of this disclaimer. The recipient is obliged to inform any subsequent recipient of such terms. Any reproduction, distribution or public use of this report requires prior written permission from Offshore Network Ltd.

Introduction TSB Offshore, Inc. (TSB), formerly Twachtman Snyder & Byrd, Inc. and Proserv Offshore, utilize a comprehensive system of cost estimating which allows the experienced user to evaluate a particular abandonment project and develop a very clear picture of the likely cost. When the necessary work activities/tasks and required resources are determined, the process proves the best possible delineation of the cost. The conventional approach is to apply standard estimating procedures to achieve a single deterministic cost number, to which a contingency is applied for the purposes of arriving at the final budget figure. This approach is appropriate for many well understood project scenarios. However, deepwater field abandonment, well plugging and abandonment (P&A) in particular, presents a much higher level of uncertainty in which it is desirable to know the entire range of possible costs, as well as the confidence limits on the estimate. This can best be done by application of probabilistic methods in the cost estimating process. The following discussion describes the probabilistic estimating method which TSB uses for complex projects and its advantages over the conventional deterministic cost estimating approach. An example of the use of these procedures in a deepwater well P&A cost estimate is presented. DETERMINISTIC versus PROBABILISTIC METHODS The cost estimating procedure used in most projects can be classified as deterministic since it develops an ensemble of specific unit rates, task durations, etc., which result in a single cost figure. The individual values used in assembling the total cost are the best available values for each cost element (task time, resource rate, etc.) and the resulting total is the deterministic cost. In the current context these values may also be referred to as the most likely values. However, when we examine the estimating process closely we can show that there is virtually always some uncertainty in the individual values that make up the total cost. Even with experienced contractors performing familiar activities, the amount of time required to perform a particular task is never exactly the same from one job to the next. When we use the conventional approach we apply a contingency to cover these uncertainties, based on our past experience. When we are dealing with a situation which is relatively straight forward we are correct in our estimates and contingency provisions more often than not. Nevertheless, it is often desirable to know more specifically what the risk of a cost overrun is. This need becomes more acute as more uncertainty enters the estimating process. Uncertainty in general can come from many sources such as: Labor problems. Uncertainty in permit approvals. Failure of acceptance tests. New technology being available. Severe weather. Variations in contractor performance. Variations in site conditions. Political instability in a development area. Inadequate specifications. Delays in management reviews and approvals. Mechanical breakdown and malfunctions. Fortunately, for field abandonments in the Gulf of Mexico we do not need to be concerned about many of these issues. However, uncertainties in site conditions, weather, contractor performance, etc., are always a consideration. In the early days of the U S missile and space programs the government was faced with the task of estimating the time and cost requirements for projects in the face of great uncertainty. The best project management, cost estimating, and applied mathematics minds of the day were focused on the task of developing methods to deal with the problem. From this effort evolved the Program Evaluation and Review Technique (PERT) which was the forerunner of the Critical Path Management (CPM) procedures commonly used in project management today. A distinguishing feature of the early PERT procedure was its application of probabilistic methods for estimating time and cost. This involved the use of distribution functions for individual cost and time estimates, rather than a single number. PAGE 2

While the PERT procedure was shown to be very appropriate for large government programs, it required massive computer resources and technical support which was generally not available in commercial applications. The probabilistic features were generally discarded as CPM was developed for industry use. However, with the development of very powerful desk-top computers and the parallel improvement in commercially available software, it is now relatively straight forward to apply probabilistic cost and schedule forecasting methods to practical problems in project management. In particular, this allows us to use all of the information and experience which we have available to provide a complete picture of cost risk in any situation where uncertainty exists. The use of probabilistic methods in this context is generally referred to as Risk Analysis. Probabilistic modeling involves the establishment of a numerical model of a project similar to a conventional cost estimate, but in a form such that its important cost elements, typically task times and resource rates, can be represented as distributions and repeatedly calculated in project simulations. In our case the characteristic that we are most interested in is the total cost to complete the project. Each time the calculation is made; individual elements of the project that contribute to cost and which contain uncertainty are allowed to have different values in accordance with the assumed distribution. These varying elements might be such things as the time required to set up a semi-submersible drilling vessel over a subsea well, for example. The way in which these elements are allowed to vary is controlled by a specific probability distribution function, as will be discussed below. The strength of the simulation process lies in the fact that we can usually identify the variability (uncertainty) in individual parts of a project - while we cannot always see how these individual variables interact to influence the overall project. In the past we have been forced to deal with this situation with the use of what if analyses which change a limited number of variables at any one time. To vary more than a few values at once makes this type of deterministic analysis too complicated to carry out and readily understand. Powerful personal computers and the available software now give us a better option than the above approach. Since project task performance uncertainties are in most cases unrelated (random events), we are able to use a mathematical device called a random number generator, along with the individual element s distribution function, to select the particular values for each simulation cycle of the project. A pair of unloaded dice is a random number generator which produces a well-defined distribution of results after many tosses, thus the name Monte Carlo (MC) simulation. As with a single toss of the dice, we are not able to predict the outcome of a single simulation of the project. However, after many simulations the results form a pattern which describes the statistical characteristics of the project variables that are of interest, cost in this case. From these characteristics we are able to develop the distribution of possible cost results for the project and the likelihood (risk) that a particular result will be achieved, or not. There are other possibilities, but this method is by far the most practical in project management applications. Probabilistic cost estimating is particularly suitable for complex decommissioning projects such as deepwater well P&A. This application will be the focus of the remaining discussion. PROBABILISTIC PROJECT COST MODELLING FOR DEEPWATER WELL P&A The process of developing a probabilistic model for use in project simulation is essentially the same as that for a conventional cost estimate. The project execution plan is developed in the form of a Work Breakdown Structure (WBS) which identifies the sequence and relationships between the various activities and events that make up the project. Figure 1 shows the activity/task network for a deepwater well P&A performed by a dynamically positioned (DP) semi-submersible (SS) mobile offshore drilling unit (MODU) in the Gulf of Mexico. Table 1 below shows the detailed WBS for the project. In the process of determining the relationships between individual activities/tasks and their durations, the resources (drilling rigs, tugs, barges, etc.) required to execute the work are also determined. It is at this point that the probabilistic cost estimating process deviates from the conventional approach. In the latter a single most likely value estimate would be required for each cost or time element. In the probabilistic model we develop a Probability Distribution Function (PDF) for each cost element that has uncertainty to replace the single value of a deterministic estimate. PAGE 3

In practice this means that we determine three values for each item that require a PDF: 1) the minimum likely, 2) the maximum likely, and 3) the most likely (mode) value. With these values we can define a triangular PDF for any cost element. An example of this type PDF is shown in Figure 2. In actual project situations there is always some chance that values could occur outside the range estimated. In this example we have selected a distribution which defines our selected minimums and maximums as the P10 and P90 values for this cost element. This means that these values have a 10% and 90% chance of not being exceeded, respectively. The most likely or statistical mode (highest probability) value would be the only value used in a conventional cost estimate. Project Mobilization Sea Trials & Initial site setup Place Lower Balanced Plug Cut & Pull Tubing Cut & Pull Prod Csg Cement B Annulus CIBP & Surface Plug Cut & Pull WH Secure Well & Equipment Relocate to the next Well Figure 1 - Flow chart for a Deepwater Well P&A Figure 2 - Typical Task PDF Triangle with defined P10 and P90 PAGE 4

PROBABILISTIC ESTIMATES OF DEEP WATER In practice estimators and engineers always consider the range of costs which might occur when putting together a project cost estimate. Unfortunately, this information is not fully utilized in a conventional determinant estimate. In this case a specific set of assumptions and related costs must be selected, with the other possibilities contributing only to the contingency applied. Probabilistic modeling using tools like Palisade Corporation s @ RISKTM for Excel, used in this example, allows the use of everything that is known to produce the most accurate picture of the future cost performance of a project that is possible to achieve. AN EXAMPLE OF A PROBABILISTIC DEEPWATER WELL P&A COST ESTIMATE To illustrate how probabilistic cost estimating can be used, we provide below a variation of a cost estimate which TSB recently performed for an existing well in approximately 2700 feet water depth. The WBS and task details are shown in Table 1. The table also shows the minimum, most likely (mode) and maximum task times and the resulting expected task times. The expected value is defined as the numerical average, or mean, of all values in the sample set. This is specifically determined by the PDF type which was chosen. Table 2 shows the running times that are believed to be the most likely task times. For the purpose of this example, a variation of -25% and +40% is used to determine the minimum and maximum task times for all tasks except those involving waiting on cement (WOC). In an actual estimate to be used for project planning or execution, these values would be considered individually by knowledgeable persons for each task. This process has been shown to produce a very good cost estimate result. The right-hand column in Table 1 shows the expected or mean cost of each task. This is derived by applying the individual task times to the expected SS MODU spread rate for each particular task. The makeup of this rate is shown in Table 3. For the purposes of this example, we have allowed for the possibility of a rig rate fluctuation of -25% and +40%, independent of the individual task fluctuations. This may not be a realistic rate range, but that would ultimately depend on the time period in which a particular project is to be contracted. The results of this example probabilistic deepwater well P&A cost estimate is shown in Figures 3 and 4 and discussed below. PAGE 5

PROBABILISTIC ESTIMATES OF DEEP WATER TABLE 1 RESOURCES for the Semi-Submersible MODU Lowest Time (Hrs) Most Likely Time (Hrs) Highest Time (Hrs) Expected Time (Hrs) Work Breakdown Structure Expected Cost 4.5 6 8.4 6.4 Dock Loadout and unload is Shared btw # of wells $238,618 1.3 2 2.4 1.8 Mobilize and Demobilize is Shared btw # of wells $67,167 4.5 6 8.4 6.4 Sea Trials (Ballast) $238,618 9.0 12.0 16.8 12.8 RU riser, attach to well head, pull tree cap $454,575 3.8 5.0 7.0 5.3 RU SL for dummy run, Run dummy run to perf depth $189,406 6.8 9.0 12.6 9.6 RU e-line, RIH perf assy to perf to establish communication to each zone $356,531 5.3 7.0 9.8 7.5 RU CT, RIH to perf depth $265,169 6.8 9.0 12.6 9.6 Perform injectivity test, POOH CT, RIH CT with cement head $340,931 3.0 4.0 5.6 4.3 RU cementing equipment, mix, pump, & squeeze perforations $170,025 24.0 24.0 24.0 24.0 WOC $854,092 3.8 5.0 7.0 5.3 Pressure test and Bubble test TBG and TBG x CSG, POOH CT $189,406 Lower Balance Plug 6.0 8.0 11.2 8.5 RU e-line, RIH set plug above packer, POOH, RIH and punch tubing above packer, POOH $310,850 6.8 9.0 12.6 9.6 RU CT, RIH to depth, establish circulation $340,931 3.0 4.0 5.6 4.3 Circulate clean with 9.0 ppg SW $151,525 4.5 6.0 8.4 6.4 RU, mix, pump, spot 200 balance plug $245,788 24.0 24.0 24.0 24.0 WOC $909,150 4.5 6.0 8.4 6.4 Pressure test and Bubble test tbg and tbg x csg, POOH CT $227,288 8.3 11.0 15.4 11.7 RIH E-line with gun, perf at 2500 BML, POOH, RIH CT with cement BHA perform inj test $399,259 4.5 6.0 8.4 6.4 RU, mix, pump, spot 300 balance plug $232,023 24.0 24.0 24.0 24.0 WOC $909,150 3.8 5.0 7.0 5.3 Pressure test and Bubble test tbg, tbg x csg, and csg x csg, POOH CT $189,406 Cut & Pull the Tbg 4.5 6.0 8.4 6.4 RU e-line, GIH and cut the tubing @ 700 BML, POOH e-line $235,088 4.5 6.0 8.4 6.4 Circulate well clean (2 Bottoms up) $227,288 18.0 24.0 33.6 25.5 ND Tree, Recover & riser, RIH to recover cut tbg POOH and lay down the cut tbg $909,150 0.0 0.0 Cut & Pull the Prod Csg 9.0 12.0 16.8 12.8 RIH cutting equipment & cut Casing, POOH $462,375 13.5 18.0 25.2 19.2 ND Csg head, RIH Casing Spear, Pull and Lay Down $681,863 2.3 3.0 4.2 3.2 Circulate well clean $113,644 Cement in B annulus 5.3 7.0 9.8 7.5 RU e-line, GIH and set EZSV at 680 BML, POOH, RIH and punch tubing at 450 $272,969 3.0 4.0 5.6 4.3 GIH with CT, sting into EZSV, mix and circulate a 200 surface plug in the csg - TOC @ 450 BML $170,025 24.0 24.0 24.0 24.0 WOC $909,150 3.8 5.0 7.0 5.3 Pressure test and Bubble test tbg, tbg x csg, and csg x csg, POOH CT $189,406 CIBP & 200 Cmt surface plug 4.5 6.0 8.4 6.4 RU e-line, GIH and set CIBP in csg @ 350 BML $227,288 5.3 7.0 9.8 7.5 GIH with work string, mix and spot a 200 surface plug in the csg on top of the CIBP - TOC @ 150 BML $283,669 18.0 24.0 33.6 25.5 PU work string and WOC $909,150 3.8 5.0 7.0 5.3 Weight test with WS, POOH $189,406 Cut & Pull WH 12.0 16.0 22.4 17.0 RIH cutting equipment & cut Casing, POOH $613,900 6.0 8.0 11.2 8.5 RIH Casing Spear, Pull and Lay Down $303,050 Spot and secure Well and P&A Equipment 6.0 8.0 11.2 8.5 Clean area of all debris $303,050 3.0 4.0 5.6 4.3 Secure all equipment and prep for move or demob $151,525 0.8 1.0 1.4 1.1 Relocate to next well $39,770 Expected Hours 404.2 Working days per well 16.5 Number of Wells 1 Subtotal (Mean) $14,509,673 Total Hours 443.8 10% Weather $1,416,589 Total Days 18.5 10% Engineering $1,447,168 Mean Cost Total $17,373,429 PAGE 6

TABLE 2 Most likely running speeds TABLE 3 RESOURCES for the Semi-Submersible MODU feet/hour Ave Perf Depth= 7,848 SL run speed First RIH 18,000 Ave Packer depth= 7,425 Sub RIH 25,000 COST DESCRIPTION P&A: Rig / Lift Boat Semi Sub & IRS on DP E-line run speed First RIH 15,000 Sub RIH 17,000 CT-run speed First RIH 3,500 Sub RIH 5,000 Riser run speed 500 Pipe run speed 900 Average Daily Cost for most equipment. Some cost are lump sum MODU 505,000 Transportation Trucking 4,547 150 Supply Boat 5,000 170 Assist and Supply 7,500 Dock Service 971 P&A: Crew & Equip Cased Hole E-line 11,142 Slick line 9,318 Cutting & Milling 14,199 Wireline Purchases 23,328 Cementing crew & Equipment 7,639 Onsite Supervisor 5,000 Quarters/meals for 28 per 2,800 DP OPS Personnel 2,200 7.0 Package IWOCS Personnel 11,522 IWOCS Package 13,688 Archer Tongs 6,757 Wellhead Personnel 4,260 Coil Tbg 55,000 ROV 39,064 TEST TREE, BASS SYS 47,000 Drill Pipe & Drill Collars 8,000 Drill Pipe Riser 10,000 P&A: Purchases Fuel - P&A Equip 5,800 SOAP 2,125 TANK CLEANING 508 Most Likely Cost Risk Weighted Cost -25%, +40% Average Spread Cost per Day on DP $802,368 $854,092 Average Spread Cost per Day on DP $33,432 $35,587 Average Spread Cost per Hour in Transit $35,099 $37,361 PAGE 7

Figure 3 - Deepwater Well P&A Cost Probability Distribution Function (PDF) Figure 4 - Deepwater Well P&A Cost Cumulative Distribution Function (CDF) PAGE 8

PROBABILISTIC ESTIMATES OF DEEP WATER There are a number of points to be noted about the cost estimate results, the most obvious being that the median (P50) cost for this well P&A is $17.1 million and that the possible range of costs is from $9.2 to $27.1 million. It is significant to note that the latter extreme cost outcomes have essentially zero probability of occurrence according to our project model. The practical range of outcomes is defined by the P10 and P90 values of $12.7 and $22.4 million. Other points that might not be as obvious are: a. Referring to Table 1, the expected or mean well P&A cost is slightly different from the median cost, i.e., $17.4 versus $17.1 million. Noting that the mean cost is the numerical average of all project cost simulations, this difference reflects the fact that the distribution of cost is slightly skewed toward the higher cost end, per the PDF in Figure 3. This is not particularly unusual for this type of project. It is simply easier to screw a project up than it is to make it run better. b. There is a relatively wide range between the P10 and P90 cost, i.e., $9.6 million or 57% of the P50 cost. This is a clear indicator that the cost risk is very high. This is also reflected in the relatively flat shape of the CDF curve in Figure 4. A steep curve with a relatively short cost range would reflect lower overall risk than a flat curve with a wider range of possible cost. We note that in this example the relatively high risk has resulted from our choice of a -25% and +40% range for the SS rig rate. The challenge for the operator and its project managers will be to pick a budget for this particular well P&A. Typically that would be the P50 cost, $17.1 million. However, there might be good reasons to select a different figure. If the consequences of being wrong are very severe, a budget with a lower probability of being exceeded, e.g., a P60 or P75 budget might be in order. On the other hand, if the project team have a high level of confidence in their ability to control the project and the resource costs in particular, a lower budget might be appropriate. In any case it is very helpful to have a complete picture of the cost outcome possibilities. CONCLUSION The use of probabilistic cost estimates for deepwater decommissioning allows the project team to take advantage of all of the information that is available about the project at any particular time. The results do not produce a single cost number, but do produce a much more complete picture of the project cost risk. This provides for the best possible project planning and execution. This is particularly important for deepwater decommissioning and abandonment. Offshore Network Ltd. is an independent business intelligence & conference provider catering specifically to the offshore oil & gas industry. We exist to facilitate a safe and efficient future for the exploration and production of oil & gas around the globe. We do this by uniting the most influential figures in the industry to challenge the status quo and share cutting edge innovations. This all happens at our industry leading conferences and through our original content. If you would like to contribute to this discussion or are interested in taking part in a future Q&A or article, please contact Offshore Network today: info@offsnet.com Join the Deepwater Decommissioning Group on LinkedIn UK Telephone: (0)203 411 9937 US Telephone: 713-5706-576 Follow Offshore Network on Twitter www.offsnet.com PAGE 9