EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

Similar documents
ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE

ECP HV INSULATION TESTING

EDS LV ELECTRICAL SERVICE DRAWINGS

ECP HV INSULATION TESTING

ECP DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE

EI HIGH VOLTAGE INSULATION TESTING POLICY

EDS LV WAVEFORM MAINS CABLE RATINGS

EDS GRID AND PRIMARY SUBSTATION CIVIL DESIGN STANDARDS

ECP HV METERING EQUIPMENT COMMISSIONING PROCEDURE

EDS FAULT LEVELS

EDS KV TRIPLEX CABLE RATING

Company Directive STANDARD TECHNIQUE: SD5F. Relating to connecting multiple small low voltage connections with limited network analysis

TS RES - OUTSTANDING ISSUES

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE

Earthing Requirements for HV Transmission Structures

ECP GROUND-MOUNTED SWITCHGEAR COMMISSIONING PROCEDURE

FAQ ON EARTHING STANDARDS 16/08/2018

Earthing Guidance Notes

Field Instruction. Induced voltages can occur in overhead lines, underground cables, or in switchyards.

EDS LV NETWORK DESIGN

IMP/007/011 - Code of Practice for the Application of Lightning Protection

EDS KV SINGLE CORE XLPE CABLES

Distribution transformers Part 2 Ground mounted transformers not closecoupled

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it.

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-I) UNDERGROUND NETWORK GROUNDING. Rev. 01

Click to edit Master title style. Click to edit Master title style. Northern Powergrid Asset Recording Guidance

Guideline for Creating Disconnection Points and Establishing a Not Electrically Connected Area

Identification and recording of 'hot' sites - joint procedure for Electricity Industry and Communications Network Providers

ACCESS TO HIGH VOLTAGE APPARATUS

Guidance for UK Fire and Rescue Services. Dealing with incidents on or near National Grid high voltage overhead lines

GK/GN0653. Guidance on Control of Unwanted Voltages on Telecommunications. Equipment at Stations. Rail Industry Guidance Note for GK/RT0053

UK Power Networks OPERATIONAL BULLETIN

INTERNATIONAL STANDARD

NSP/007/019 - Guidance on Substation Design: EHV Substation Drawing Policy

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-II) OVERHEAD NETWORK GROUNDING. Rev. 01

Customer Requirements RF Antenna Installations

CONSULTANT PROCEDURES & DESIGN GUIDELINES Liquid-Filled Utility Transformers UNIVERSITY OF MISSOURI

Connection of Embedded Generating Plant up to 5MW

25kV A.C. Electrified Lines - Traction Bonding

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

IMP/010/011 Code of Practice for Earthing LV Networks and HV Distribution Substations

Earthing, HV Switching and Associated Operational Equipment. Approval: Chief Operating Officer

INTERNATIONAL STANDARD

TABLE of CONTENTS ############################# Revised Rule Revised Rule 91.3-B 14. Revised Rule 92.1-F(2). 15

GE/GN8648. Guidance on Positioning of Lineside Telephones. Rail Industry Guidance Note for GE/RT8048

UNIVERSITY OF MISSOURI Liquid-Filled Utility Transformers 2016 Q1

RELEVANT ELECTRICAL STANDARDS

Table of Contents. Introduction... 1

Field Instruction Switching Activities. Purpose. Scope. Objective. Safety

TECHNICAL REPORT. Insulation co-ordination

Electrical Procedure No E032. Procedure No: ELE 032

CONDITIONS FOR A TENTATIVE APROVAL FOR CONNECTION OF TRANSFORMERS

TECHNICAL SPECIFICATION

HV Substation Earthing Design for Mines

Company Directive POLICY DOCUMENT: SD4/7. Relating to 11kV and 6.6kV System Design

EDS GRID AND PRIMARY SUBSTATION EARTHING DESIGN

Standard Prices for Generators 2010

EDS EARTHING DESIGN CRITERIA, DATA AND CALCULATIONS

Insulation co-ordination Part 1: Definitions, principales and rules. IEC 2006 Copyright - all rights reserved

Company Directive STANDARD TECHNIQUE: TP21D/2. 11kV, 6.6kV and LV Earthing

Education & Training

G81 PART 1 FRAMEWORK APPENDIX

PRACTICAL PROBLEMS WITH SUBSTATION EARTHING

INTERNATIONAL STANDARD

Embedded Generation Connection Application Form

SYNCHRONISING AND VOLTAGE SELECTION

EDS EHV NETWORK DESIGN

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

GROUNDED ELECTRICAL POWER DISTRIBUTION. Excerpt from Inverter Charger Series Manual BY: VIJAY SHARMA ENGINEER

SUBJECT HEADING: Switching Programmes ISSUE: 18

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code)

Embedded Generation Connection Application Form

Functional Specification Revision History

SERIES K: PROTECTION AGAINST INTERFERENCE

HAWK5000 Operators Manual

INSTALLATION & TESTING OF UNDERGROUND PRIMARY AND SECONDARY POWER CABLES PRIOR TO ENERGIZATION

RELEVANT ELECTRICAL STANDARDS

Customer Connection Guide Updates Effective May 2017

AMENDMENT NO. 1 SEPTEMBER IS (Part 1) : 2001/IEC (1991) SURGE ARRESTORS

Company Directive STANDARD TECHNIQUE: SD5R/2. Earth Fault Loop Impedances and Phase to Neutral Loop Impedances at LV Installations

NOTE: This paper relates to a closed book exam & therefore candidates should attempt this exam paper with no study-notes or text books.

Page Electric Utility Service Specifications

Earthing of Electrical Devices and Safety

COMMISSION REGULATION (EU) No /.. of XXX

SERIES K: PROTECTION AGAINST INTERFERENCE

INTERNATIONAL STANDARD

Title Substation Auxiliary Transformer from Rectifier Transformer Secondary. Reference Number PDS 01 (RIC Standard: EP SP)

CONTINUING EDUC ATION

PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION!

SERIES K: PROTECTION AGAINST INTERFERENCE

Wisconsin Contractors Institute Continuing Education

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer

RELEVANT ELECTRICAL STANDARDS

TABLE OF CONTENTS FOREWORD... 3 INTRODUCTION SCOPE NORMATIVE REFERENCES... 4

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009

Reference Number PCP 02 (RIC Standard: EP SP)

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

Power Frequency Withstand Voltage On-site testing of 400 kv GIS

Transcription:

ENGINEERING DESIGN STANDARD EDS 08-2109 LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS Network(s): Summary: EPN, LPN, SPN This standard provides guidance on the installation of LV supplies for mobile phone base stations associated with antennae mounted on 132, 275 and 400kV transmission towers. Author: Stephen Cuddihey Approver: Paul Williams Date: 09/10/2017 This document forms part of the Company s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue. Applicable To UK Power Networks External Asset Management G81 Website Capital Programme UK Power Networks Services Connections Contractors Health & Safety ICPs/IDNOs Legal Meter Operators Network Operations Procurement Strategy & Regulation Technical Training THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE

Revision Record Version 4.0 Review Date 09/10/2022 Date 01/09/2017 Author Stephen Cuddihey Reason for update: Periodic review, review of LV document numbering and new draft of G78 to be released. What has changed: Document number changed from EDS 08-0030, no changes required from G78 review. Version 3.0 Review Date 01/09/2017 Date 25/05/2014 Author Stephen Cuddihey No major changes; compliance with ENA ER G78 confirmed and layout revised Version 2.0 Review Date 25/05/2014 Date 19/08/2010 Author Lionel Mackay Reviewed and review date extended, document reclassified from EI to EDS. Version 1.0 Review Date 19/08/2010 Date 05/01/2006 Author Paul Williams/Dave Collis Original to replace 24seven policy 03-04-13-0003 UK Power Networks 2017 All rights reserved 2 of 13

Contents 1 Introduction... 4 2 Scope... 4 3 Abbreviation and Definitions... 4 4 Design Requirements... 5 4.1 General... 5 4.2 Load... 5 4.3 Site Assessment... 5 4.4 Supply Options... 6 4.5 Wayleave and Planning Consent... 9 5 Installation Requirements... 10 5.1 HV Option... 10 5.2 LV Option... 10 5.3 Equipment and Materials... 10 5.4 Warning Labels... 11 5.5 Testing and Commissioning... 12 6 Commercial Requirements... 12 6.1 Connection Agreement... 12 6.2 Installer Responsibilities... 12 7 Operational Requirements... 13 7.1 Training... 13 7.2 Site Access... 13 8 References... 13 Figures Figure 4-1 - UK Power Networks Standard Supply Solution... 6 Figure 4-2 Insulated Base Design Supplied from HV Cable with Overhead Span... 7 Figure 4-3 Guidance on Installing Equipment Supplies from Underground Networks... 7 Figure 4-4 Insulated Base Design Supplied from an HV Overhead line... 8 Figure 4-5 Guidance on Installing Equipment Supplies from Existing Overhead Line Networks... 8 Table 5-1 Equipment and Materials... 11 Table 5-2 Warning Labels... 11 UK Power Networks 2017 All rights reserved 3 of 13

1 Introduction This standard provides guidance on the installation of LV supplies for mobile phone base stations associated with antennae mounted on 132, 275 and 400kV transmission towers. A safe system for the provision of such installations has been determined by the Energy Networks Association (ENA) and is detailed in ENA ER G78. Mobile phone installations require a low voltage supply; however when the antennae are mounted on high voltage structures safety issues can arise. Lightning strikes and power frequency events such as power system faults can cause the conductor, earth wires and/or supporting structure to rise in potential. The mobile phone installation shall be designed, as far as is reasonably practicable, to withstand the earth potential rise for both lightning impulse and power frequency events in order to minimise any risk to personnel and the public. The standard applies the principles of ENA ER G78 for UK Power Networks and includes: Arrangements for supplies fed from an overhead line. Arrangements for supplies fed directly from the LV network. Standard designs for supplies for mobile phone base stations. Responsibilities within UK Power Networks. 2 Scope This standard applies to the provision of LV supplies of LV supplies for mobile phone base stations associated with antennae mounted on 132, 275 and 400kV transmission towers in EPN, LPN and SPN. 3 Abbreviation and Definitions Term BIL Definition Breakdown Impulse Level CDM Construction Design and Management Regulations 2007 ENA TS EPR Energy Networks Association Technical Specification Earth Potential Rise HV High Voltage (above 1000V) IBD Insulated Base Design LV Low Voltage (below 1000V) MPBS NGC OHL ROEP UK Power Networks Mobile Phone Base Station National Grid Company Overhead Line Rise of Earth Potential UK Power Networks (Operations) Ltd consists of three electricity distribution networks: Eastern Power Networks plc (EPN). London Power Network plc (LPN). South Eastern Power Networks plc (SPN). UK Power Networks 2017 All rights reserved 4 of 13

4 Design Requirements 4.1 General The design of the supply installation shall meet the requirements of ENA ER G78, specifically those detailed in Annex A for the Insulated Base Design (IBD). To prevent the danger that may occur from a rise of earth potential, the installation shall be protected in line with Section 4.1 Identification and Control of Hazards in ENA ER G78. Specific attention shall be given to the assessment of step, touch and transfer potentials and where required the appropriate measures detailed in Section 5 Construction of ENA ER G78 shall be applied. The construction of each site shall be subject to CDM Regulations. When sites are decommissioned, the CDM regulations shall again apply, with particular attention to the removal of earth conductors or cables, and to the decommissioning of the cables. See Section 8 Decommissioning of ENA ER G78 for further details. The design shall be approved by Connections. 4.2 Load The equipment shall supply a maximum load of 100kVA via three independent three-phase 100A services. 4.3 Site Assessment When approached by a mobile phone operator for the provision of supplies to a base station, UK Power Networks shall: Obtain the ROEP value and a plot of the HOT zone from NGC. Perform a site risk assessment. The site shall be assessed against ENA ER G78 and the requirement of this standard to determine if the proposed connection can be provided, and is practicable for installation and future maintenance. The site risk assessment shall be completed in accordance with HSS 01 062 and the appropriate generic design identified. The assessment shall take into account: Access for maintenance. Local conditions and risk of third party interference. Clearances from associated exposed conductors. Existing network availability and current load levels. The mounting of MPBS antennae introduces a number of hazards ROEP caused by lightning strikes and power system faults. Proximity of live conductors. Proximity of the mobile phone antennae. The design of the installation shall minimise the hazards as far as is reasonably practicable, and/or additional measures shall be put in place to control such hazards (e.g. fencing around the MPBS). UK Power Networks 2017 All rights reserved 5 of 13

4.4 Supply Options The UK Power Networks standard supply solution shown in Figure 4-1 should be used for all MPBS mounted on transmission towers. UK Power Networks preferred option is to provide an LV supply via a pole-mounted transformer supplied from either an HV overhead line or HV underground cable. In both cases the final connection between the transformer and the 11kV network shall be via at least one span of overhead line. The underground cable option is shown in Figure 4-2 and Figure 4-3. The overhead line option is shown in Figure 4-4 and Figure 4-5. ENA ER G78 also allows supplies to be derived from the local LV network feeding a motoralternator set mounted on the MPBS. The supplier shall provide proof that the motor-alternator complies with the technical requirements of ENA ER G78. Most services will be in rural locations and wherever possible the use of overhead lines throughout the system shall be preferred to reduce costs of installation. Where it is not possible to obtain wayleaves, the use of long LV cable within the constraints of voltage drop shall be used to connect the LV supply from the transformer to the services. The LV connection shall only supply the MPBSs associated with the specific tower. No other supplies shall be connected to the transformer or to the HV overhead line on the span or spans between the SA3 surge arrester and the pole-mounted transformer. Note: drawing not to scale TF SA3 SA2 Pole Mounted Transformer Earthing point supplied by Tower Owner Anti Climb Protection I M I Key: = Insulated duct = Earth cable or tape = LV CNE cable = RF Feeder Cable M = Meter TF = DNO Transformer SA = Surge Arrester I = IBD Insulator Sicame Underground Distribution box Note: Connection of the insulated duct and earth cable to the earthpoint on the tower must be completed by NGC staff or UK Power Networks Staff for UK Power Networks owned 132kV towers. The earth cable and duct should be left long enough to allow connection to the earth bar and to ensure the insulated duct ends above the anti-climb guards Note: The insulated platform is owned by a third party, usually one of the mobile phone operators. Before starting work contact the owner to obtain permission to work on their property. Figure 4-1 - UK Power Networks Standard Supply Solution UK Power Networks 2017 All rights reserved 6 of 13

Overhead Span TF Additional Bonding as required SA3 SA2 Note: Fencing is required around MPBS installation M MPBS Cable termination pole and its earth electrode must be outside area affected by ROEP Pole Mounted Transformer SA1 Earthing facility for first MPBS Earthing facility for additional MPBS Underground HV Cable Network KEY: = Insulated Duct = RF Feeder M = Meter Position TF = DNO Transformer = Earth Cable or Tape = LV CNE cable SA = Surge Arrester I = IBD Insulators = HV cable (phase conductors and screen drawn separately) Figure 4-2 Insulated Base Design Supplied from HV Cable with Overhead Span 10m minimum distance TF Cable termination and its earth must be outside electrode area affected by ROEP The cable will normally be connected to OH line using Live Line Taps SA3 SA3 and its earth must be outside electrode area affected by ROEP SA2 Pole Mounted Transformer HV Cable Network The installation above provides guidance for the connection of the HV supply to the existing network. The energisation of surge arresters from the pole where they are installed is not allowed due to the risk of failure of the unit. Area of ROEP Due to the size of the area affected by ROEP, intermediate poles may be required between the pole mounted transformer and the SA3 surge arrester. Figure 4-3 Guidance on Installing Equipment Supplies from Underground Networks UK Power Networks 2017 All rights reserved 7 of 13

Overhead Span HV Overhead line SA3 SA2 TF Additional Bonding as required Note: Fencing is required around MPBS installation M MPBS Pole Mounted Transformer I I Earth electrode may be installed within soil affected by ROEP as long as there are no cable terminations on the pole KEY: SA1 Earthing facility for first MPBS Earthing facility for additional MPBS = Insulated duct = RF Feeder Cables = Earth cable or tape = LV CNE cable M = Meter Position TF = DNO Transformer SA = Surge Arrester I = IBD Insulators Figure 4-4 Insulated Base Design Supplied from an HV Overhead line Existing network 10m minimum distance TF The connection to the existing OH line will normally be connected using Live Line Taps Note only single phase show n SA3 SA3 and its earth must be outside electrode area affected by ROEP SA2 Pole Mounted Transformer The installation above provides guidance for the connection of the HV supply to the existing network. The energisation of surge arresters from the pole where they are installed is not allowed due to the risk of failure of the unit. Area of ROEP Due to the size of the area affected by the ROEP, intermediate poles may be required between the pole mounted transformer and the SA3 surge arrester. Figure 4-5 Guidance on Installing Equipment Supplies from Existing Overhead Line Networks UK Power Networks 2017 All rights reserved 8 of 13

4.5 Wayleave and Planning Consent The standard procedure shall be used to obtain the necessary landowner and statutory consents in order to satisfy property and planning legislation. However, if the tower is owned by UK Power Networks, use of the structure by a Mobile Phone Operator shall be by formal completion of an asset usage agreement arranged by UK Power Networks. For the purpose of connecting a mobile telephone customer, it may be assumed that the supply can be treated as a single service line, unless two or more customers have made applications for supply. In the event that after the installation for a single customer, an additional request for supply from a second customer is received, then the relevant retrospective planning consents shall be obtained. UK Power Networks 2017 All rights reserved 9 of 13

5 Installation Requirements 5.1 HV Option The following requirements are derived from ENA ER G78 and provide additional guidance for implementing the standard supply solution from an HV underground cable or HV overhead line. The connection to the existing overhead line shall normally be made using live line taps. Surge arresters SA2 and SA3 shown in Figure 4-1 shall be installed at all sites. The surge arrester SA2 shall be specified to the ROEP declared by NGC. SA3 is a standard stock item unit. The pole supporting the SA3 surge arrester and the 100kVA pole mounted transformer shall be placed outside the zone of ROEP and be a minimum distance of 10m from the 100kVA pole mounted transformer. Sites where the ROEP is greater than 21kV shall use a transformer with an Impulse level of 125kV. The 11kV connection to the existing network shall not be energised from the pole containing the SA3 surge arrester. The LV supply shall be protected by a standard pole-mounted cut-out. The Sicame underground distribution box (which has been modified to allow four insulated service ducts to be heat fused to it) shall be installed centrally under the tower. A 95mm 2 waveform cable shall be installed in an insulated duct between the pole and underground the distribution box. A 35mm 2 three-phase cable shall be installed in an insulated duct between the distribution box and the tower. A maximum of three services may be provided from each distribution box. A 70mm 2 earth cable shall be installed in an insulated duct between the pole and the tower. All of the cables shall be pre-installed in the insulated duct. Standard Rigid Duct shall not be used. The insulated duct runs for the supply and earth cables shall be continuous and shall be terminated above the anti-climb guards on the pole. The insulated duct for the service cable to the base station shall be continuous and shall terminate within the cut-out enclosure. The insulated duct containing the earth cable shall not be connected to the tower by UK Power Networks staff or their contractors. The duct and earth cable should be left sufficiently long to allow NGC to terminate the earth cable to their nominated earth connection. 5.2 LV Option The LV cable shall extend to the local network used to supply the MPBS and shall be installed in an insulated duct from the point of connection to the MPBS refer to ENA ER G78 Section 4.3.3 DNO LV Connection. 5.3 Equipment and Materials All electrical equipment shall meet the materials and equipment requirements ENA ER G78. All equipment and materials shall be approved by UK Power Networks Asset Management. Unless otherwise stated standard overhead line and underground equipment and materials shall be used in the installation. Table 5-1 details the specific non-standard items required to comply with the requirements of ENA ER G78. UK Power Networks 2017 All rights reserved 10 of 13

Table 5-1 Equipment and Materials Description ROEP < 10kV Equipment ROEP < 21kV Equipment ROEP < 29kV Equipment Surge Arresters SA2 Standard Raychem HAD - 20N Raychem HDA - 26N Surge Arresters SA3 Standard Earth Cable for SA2/SA3 70mm 2 PVC Covered Copper Cable (Material Code: 05865J) Pole Transformer Standard 95kV BIL Standard 95kV BIL Underground Distribution Box CNE Cable Duct Service Cable Duct Earth Cable in Duct Sicame G78-1 Phone Mast 12 way Unit (LVD12S-F) (Material code: 02503B) Emtelle 95mm 2 CNE Waveform Cable in 63/50mm 2 Duct (Material code: 25441A) Emtelle 35mm 2 CNE Service Cable in 50/40mm 2 Duct (Material code: 25440Q) Emtelle 70mm 2 Earth Cable in 50/40mm 2 Duct (Material code: 25442K) Special order 125kV BIL 5.4 Warning Labels The warning labels detailed in Table 5-2 shall be applied to the installation where applicable. All warning labels shall have black writing on a yellow background and comply with EDS 07-0009. Table 5-2 Warning Labels Label Location ROEP < 10kV Equipment ROEP < 21kV Equipment ROEP < 29kV Equipment On pole adjacent to transformer n/a n/a 125kV high impulse transformer - do not replace with standard unit On pole n/a Non-standard surge arrester replace with Raychem HAD - 20N Underground distribution box Internal components subject to rise in potential. Contact Network Control before opening Internal components subject to rise in potential. Contact Network Control before opening Non-standard surge arrester replace with Raychem HDA - 26N Internal components subject to rise in potential. Contact Network Control before opening UK Power Networks 2017 All rights reserved 11 of 13

5.5 Testing and Commissioning The standard test regime for the installation of overhead lines, HV and LV cables and HV and LV equipment shall be applied in accordance with the UK Power Networks commissioning standards. As a minimum the tests shall include: 5000V insulation resistance tests for HV equipment. HV pressure tests for HV cables. 500V insulation resistance tests for LV cable and equipment. Earth resistance test for local earth pins. Any other special test requirements recommended by ENA ER G78 or the equipment manufacturer. 6 Commercial Requirements 6.1 Connection Agreement The supply shall be subject to specific connection agreement. The connection agreement shall include a site responsibility schedule that defines the ownership, maintenance, operation and control responsibilities. Inspection and maintenance of the MPBS equipment and associated earthing connections and other cabling shall be the responsibility of the Mobile Phone Operator unless otherwise agreed and detailed in the connection agreement. Inspection and maintenance of the overhead line equipment shall be the responsibility of the UK Power Networks. The responsibility for security and control of access to the MPBS and compound shall normally rest with the Mobile Phone Operator and/or the site owner. However, shared locking arrangements shall be provided to allow access to the UK Power Networks, Supplier and Meter Operator as required. Details of the shared access arrangements and the responsibility to control access shall be detailed in the connection agreement. Such arrangements shall also detail contact names, telephone numbers and the reporting requirements before entering a MPBS site. 6.2 Installer Responsibilities The installer is responsible for the provision of competent staff to complete both the HV and LV installation from the HV supply up to and including the mounting of the cut-out on the insulated base. The Installer shall: Liaise with the mobile phone operator owning the insulated base to co-ordinate the installation of the LV supply to the insulated base. Liaise with tower owner to co-ordinate the installation of the earth connection to the tower. Ensure that only approved materials and subcontractors are used. UK Power Networks 2017 All rights reserved 12 of 13

7 Operational Requirements 7.1 Training All UK Power Networks staff entering the MPBS enclosure shall be competent for this purpose and have received appropriate training. Staff shall be made aware of the requirements of ENA ER G78 Section 6 Operational Requirements and Section 7 Maintenance and Inspection, the Distribution Safety Rules and codes of practice applicable to work on the insulated platform. 7.2 Site Access Before any MPBS site may be entered to operate the equipment or to undertake inspection and maintenance work, the following criteria shall be satisfied: 1. Confirm acceptable weather conditions are prevailing. 2. Obtain any necessary authorisations to access site. 3. Ensure that staff are familiar with site safety rules and working procedures and have the appropriate competency level. 4. Ensure that staff have received adequate training has been received. 5. Where work exceeds the day-to-day operation and maintenance requirements complete a risk assessment. 6. Ensure that the insulated platform has been correctly maintained (undertake a visual inspection and refer to the platform owner s maintenance records). 8 References EDS 07-0021 HSS 01 062 ENA ER G78 Signs and Labels for Operational Sites.doc Undertaking On-site (Point of Work) Assessment Energy Network Association Engineering Recommendations for Low Voltage Connections to Mobile Telephone Base Stations with Antennae on High Voltage Structures UK Power Networks 2017 All rights reserved 13 of 13