Grounding Resistance

Similar documents
TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

The Engineering Problem. Calculating GIC Flow through the EHV System

GIC Analysis using PSS E. K.V. PATIL Siemens Power Technologies International Schenectady, New York, USA

Grid Impact of Neutral Blocking for GIC Protection:

Modeling of Three-phase or Bank of Three Single Phase Three Winding Transformers Zero-phase-sequence Leakage Impedance in PSS E Short Circuit Module

Integration of Geomagnetic Disturbance Modeling into the Power Flow: A Methodology for Large-Scale System Studies

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Modeling and Evaluation of Geomagnetic Storms in the Electric Power System

ELECTRICAL POWER ENGINEERING

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

CHAPTER 2. Basic Concepts, Three-Phase Review, and Per Unit

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur

Var Control. Adding a transformer and transformer voltage regulation. engineers loadflow program. The control system engineers loadflow.

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

Exercises on overhead power lines (and underground cables)

GIC Distribution. Carlos David Fernández Barroso. Division of Industrial Electrical Engineering and Automation Faculty of Engineering, Lund University

Spring 2000 EE361: MIDTERM EXAM 1

Transformer Protection

Application Guide. Computing Geomagnetically-Induced Current in the Bulk-Power System. December 2013

Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved.

In Class Examples (ICE)

ELECTRICAL POWER TRANSMISSION TRAINER

ECEN 615 Methods of Electric Power Systems Analysis Lecture 8: Advanced Power Flow

GMD Impacts on Generators

GMD Voltage Collapse Study

Form B. Connection Impact Assessment Application Form Distribution System

Power System Impacts of Geomagnetic Disturbances

Case Study Effects of Geomagnetically Induced Current (GIC) Neutral Blocking Device

Transmission Line Transient Overvoltages (Travelling Waves on Power Systems)

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

FINNISH EXPERIENCES ON GRID EFFECTS OF GIC'S

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

QUESTION BANK ETE (17331) CM/IF. Chapter1: DC Circuits

148 Electric Machines

PowerWorld Simulator GIC

GIC Calculations Using PSS E. Live Demonstration February 16, 2017

MITIGATING GEOMAGNETIC INDUCED CURRENTS USING SURGE ARRESTERS. Alberto Ramirez Orquin Vanessa Ramirez Resilient Grids, LLC.

IGEE 402 Power System Analysis. FINAL EXAMINATION Fall 2004

CHAPTER 3 COMBINED MULTIPULSE MULTILEVEL INVERTER BASED STATCOM

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009

AC Power Instructor Notes

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria

Harmonic control devices

, ,54 A

Operational Experiences of an HV Transformer Neutral Blocking Device

Improving High Voltage Power System Performance. Using Arc Suppression Coils

Connection Impact Assessment Application

Rarely used, problems with unbalanced loads.

Geo-Magnetic Disturbance Analysis of HV and EHV Grids

The power transformer

Capstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:

Magnetohydrodynamic Electromagnetic Pulse Assessment of the Continental U.S. Electric Grid

QUESTIONNAIRE for Wind Farm Power Stations only

A Special Ferro-resonance Phenomena on 3-phase 66kV VT-generation of 20Hz zero sequence continuous voltage

Fatima Michael college of Engineering and Technology

Vulnerability Assessment and Planning

Power Systems Modelling and Fault Analysis

Solar Storm Probabilities Grid Contingencies Harmonic Relay Settings

Analysis of Temporary Over-Voltages from Self-Excited Large Induction Motors in the Presence of Resonance - Case Studies

PAPER-II (Subjective)

Electrical Theory. Power Principles and Phase Angle. PJM State & Member Training Dept. PJM /22/2018

Power Factor & Harmonics

A Comprehensive Approach for Sub-Synchronous Resonance Screening Analysis Using Frequency scanning Technique

Comparison of methods for modelling geomagnetically induced currents

MODELING OF TRANSFORMERS IN WECC BASE CASES. For WECC SRWG By Rohan Chatterjee Electrical Engineer Transmission Planning

AS the power distribution networks become more and more

Module 1. Introduction. Version 2 EE IIT, Kharagpur

Geomagnetic Disturbances. IEEE PES Chicago Chapter Technical Presentation March 12, Alan Engelmann Transmission Planning ComEd.

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

Impacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering

WinIGS. Windows Based Integrated Grounding System Design Program. Training Guide. Last Revision: June 2017

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit

Phase Shifting Transformers. Presented by

Babak Enayati National Grid Thursday, April 17

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Connection Impact Assessment Application Form

Parameter Study of Ferro-Resonance with Harmonic Balance Method

Any wave shape can be reproduced by the sum of sine waves of the appropriate magnitude and frequency.

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

Distributed Generation Application Form (Generation of Greater than 20 kw to 15 MW)

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Optimizing HV Capacitor-Bank Design Protection & Testing

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages

Three-Phase/Six-Phase Conversion Autotransformers

LOW-RESISTANCE grounding resistors (LRGs) appear

OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES

Wind Power Facility Technical Requirements CHANGE HISTORY

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

GREEN TRAFO PRODUCTS SHR - THREE-PHASE SHUNT REACTOR

Ferroresonance Conditions Associated With a 13 kv Voltage Regulator During Back-feed Conditions

Analysis of a 405 km transmission line with series compensation

WECC Data Preparation Manual

Southern Company Interconnection Requirements for Inverter-Based Generation

SRI VIDYA COLLEGE OF ENGG AND TECH

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

Improving High Voltage Power System Performance. Using Arc Suppression Coils

Transmission Interconnection Requirements for Inverter-Based Generation

DIRECT CURRENT COMPENSATION FIELD EXPERIENCE UNDER SERVICE CONDITIONS

Transcription:

Grounding Resistance Substation grounding resistance is the resistance in ohms between the substation neutral and earth ground (zeropotential reference) An actual fall of potential test is the best way to determine this resistance Simulator provides defaults based on number of buses and highest nominal kv, but research has shown this to be a poor substitute for actual measurements Simulator defaults range from 0.1 to 2.0 Substations with more buses and higher nominal kv are assumed to have lower grounding resistance Grounding resistance is not necessary for substations that have no transformer or switched shunt connections to ground 1

Substation Coordinates Longitude and latitude should be provided for all substations that contain terminals of lines for which a GIC equivalent DC voltage is applied Generally this includes all lines greater than minimum length and nominal kv specified on GIC Analysis Form Series compensated line terminals may be disregarded, if there are no other lines that meet above criteria The need for coordinates applies regardless of whether the substation contains grounded transformers If there are no grounded transformers, the location may be approximate (e.g. within 100 km) 2

Transformer Inputs Key inputs Coil resistance (DC ohms) Grounding configuration Autotransformer? (Yes/No) Core Type Most essential parameters; these determine the basic topology of the GIC network 3

Transformer Inputs Manually Enter Coil Resistance Yes : user enters High Side Ohms per Phase and Medium Side Ohms per Phase No : Simulator estimates values XF Config High and XF Config Med: most common options are Gwye and Delta Tertiary windings are assumed Delta Is Autotransformer: Yes, No, or Unknown Core Type 4

Simulator Assumptions It is always best to provide known quantities, especially for configuration and autotransformer fields If any transformer information is unknown, Simulator uses default values Coil Resistance ohms per phase estimate based on positive sequence AC per unit series resistance and transformer impedance base Assumed split between each winding:, 5

Coil Resistance: Autotransformers Series Winding Simulator Fields Coil Resistance (Ohms) for High Winding Common Winding Coil Resistance (Ohms) for Medium Winding Tertiary Windings are assumed delta connected and coil resistance is not normally populated 6

Simulator Assumptions: Autotransformers Some parameters for assumptions applied to unknown transformers are at Options DC Current Calculation Units are assumed to be autotransformers if all of the following criteria are met unit is not a phase shifting transformer high side and low side are at different nominal voltages high side nominal voltage is at least 50 kv turns ratio is less than or equal to 4 These parameters may be adjusted at Op ons DC Current Calculation 7

Simulator Assumptions: Transformer Configuration Unknown windings are assumed either Delta, Grounded Wye, or Ungrounded Wye Autotransformer Minimum High Side Winding Voltage (kv) is also the assumed delineation between transmission and distribution voltages (default 50 kv, referred to as kv min hereafter on this slide) If high side > kv min and low side is connected to a radial generator OR if high side >= 300 kv and low side < kv min, unit is assumed a GSU with high side Gwye and low side Delta If both sides > kv min OR both sides < kv min, both are assumed Gwye Otherwise, if high side > kv min and low side < kv min or has radial load, use Default Trans. Side Config and Default Dist. Side Config on Options DC Current Calculation (or as specified by area) 8

Simulator Assumptions I Eff is per phase effective GIC, computed from GIC in high and low side windings and turns ratio (a t ), K Factor relates transformer s effective GIC (I GIC ) to 3 phase reactive power loss at nominal voltage Q V K I loss,pu pu pu Eff,pu This looks like a constant current MVar load at the transformer s high side bus 9

K Factor K Factor may be entered directly as a 2 step piecewise linear value with GIC Model Type set to Piecewise Linear User specified Values Break point is I eff,pu values Used With GIC Model Type set to Default, K Factor is based on Core Type and parameters at Op ons AC Power Flow Model 10

K Factor Q loss,pu (3 phase, at 1.0V pu high side) Slope = GIC Model Used First Segment Slope = GIC Model Used Second Segment GIC Model Used Breakpoint I eff,pu 11

Transmission Line Inputs DC resistance is derived from AC per unit resistance and the impedance base by default (assumes skin effect is negligible at 60 Hz) You may also specify DC resistance Manually Enter Line Resistance = YES Provide value in Custom DC Resistance (Ohms/Phase) 12

Switched Shunt Inputs Shunts operating as inductors can also provide a conducting path for GIC Simulator assumes shunts have infinite resistance by default, but resistances may be provided by the user Inductors are assumed to have non magnetic core designs and thus not subject to saturation and MVar losses as in transformers (i.e. K=0) Shunts operating as capacitors always have infinite resistance 13