Testing Manual for Electrical Equipment

Similar documents
All the standards referred to the most current issue, including all amendment supplements. as of the date of the bid.

REPORT OF PERFORMANCE TIC

JULY Standards are finally approved by the Standards High Council of Iranian Ministry of Petroleum.

11-SDMS-03 REV. 02 SPECIFICATIONS FOR

MGVCL/MM/ /2082/11KV AB CABLE TECHNICAL SPECIFICATION FOR 11KV AERIAL BUNCHED CABLES FOR OVERHEAD LINES

SPECIFICATION SS-140/9. 0.6/1 (1.2) kv CONTROL AND POWER UNDERGROUND CABLES WITH PVC OR XLPE INSULATION AND PVC JACKET

Specification for pvc-insulated cables for electricity supply

TECHNICAL SPECIFICATION FOR 11KV, 3C x95mm mm 2 AERIAL BUNCHED CABLES FOR OVERHEAD LINES (CROSSED LINKED POLYTHENE DRY GAS CURED)

Standard Technical Specifications for Electrical Works CABLES AND ACCESSORIES. 11 kv XLPE-Insulated Three-Core Underground Cables

SANS 1339:2010 Electric cables Cross-linked polyethylene (XLPE) insulated cables for rated voltages 3,8/6,6 kv to 19/33 kv

Neutral Earthing. For permanent or temporary neutral earthing in HV systems

This Certificate consists of 75 pages in total.

ECP HV INSULATION TESTING

Technical Specification. for 1.1 KV Copper Control Cable

INTRODUCTION NUHAS OMAN QUALITY & RELIABILITY.

VOLUME - 4 (GENERAL TECHNICAL SPECIFICATIONS)

ECP HV INSULATION TESTING

Fault location on power cables. Fault location on power cables

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 BONDING METHODS

DNVGL-CP-0400 Edition December 2015

76 / 132 (145) kv 1x1200 mm 2 CU/XLPE/CWS/AL/HDPE

Tratos High Voltage cables

High Voltage Instrumentation Cables for the ITER Superconducting Magnet Systems

HV SYSTEMS. Prysmian HV Systems Product Range 66kV & 132 kv

Notes 3 Explanatory Information 4-10

EI HIGH VOLTAGE INSULATION TESTING POLICY

6419X Conduit Cable. Dungannon Electrical Wholesale Tel: Page 1 of 10

General Technical Specification and Execution Procedures for Transmission and Subtransmission Networks Cables

Cables. Cables. Power. Fire Resistant WILSON CABLES PRIVATE LIMITED. Distributed By :

Tri-Rated Flexible PVC Equipment Wire

VSD cables in. Working with. industrial & automation applications

Date: / TECHNICAL SPECIFICATIONS FOR 11 KV XLPE INSULATED UNDERGROUND CABLES

XLPE CABLE (33KV) September Engineering Department WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED

شركة الوقت للكهرباء والمقاوالت ذ.م.م.

TECHNICAL SPECIFICATIONS for 300KV CONSTANT POTENTIAL X RAY EQUIPMENT (for industrial applications) S. No. PARTICULARS BHEL SPECIFICATIONS

1.1_KV PVC insulated PVC sheathed multicore Aluminium Cable (armoured & unarmoured)

NPS/002/016 Technical Specification for 33 kv Cable Joints and Terminations

C&G Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations

C&G Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations. Earth Fault Loop Impedance Tests

Form-IV. Form of Inspection/Test Report. (Under Regulation 43)

Enhanced Quality with a Touch of Style

012: 2015 CEB SPECIFICATION GALVANIZED STEEL WIRE (EXCEPT SHIELDING WIRE FOR TOWER LINE APPLICATION)


Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009

STANDARD SPECIFICATION FOR INSTRUMENT CABLES AND RELATED ACCESSORIES DOCUMENT NO : 44-LK /J.02/0014-A4

Cable fault location in power cables. Systematics for cable testing, diagnosis and cable fault location

Partial Discharge Measurement and Monitoring on High Voltage XLPE Cables

MV water-proof and water tree retardant power cable

A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation Equipment

Collection of standards in electronic format (PDF) 1. Copyright

MGM Transformer. Vacuum Pressure Impregnated (VPI) Dry-Type Substation Transformer Specification Guide

Armoured Power and Control Cables to BS7917

Substation Preventive Maintenance

CIR (Crush & Impact Resistant) VFD Power Cable

Armoured Power and Control Cables Fire Resistant

Group F : Sl. No. - 1) 33/0.403 KV, 100 KVA Station Transformer GUARANTEED & OTHER TECHNICAL PARTICULARS. Table : A

Industrial Ethernet OPT cable manufactured for Petrol Forecourt Applications.

COMMON WORK RESULTS FOR INTEGRATED AUTOMATION DESIGN AND CONSTRUCTION STANDARD

Kerman & Kavian Cable Industries ( KCI )

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and secondary circuit.

PROTECTION AGAINST FAULT CURRENT

Chapter Seven. Under Ground Cables

COURSE PLANNER. Subject: TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS ( ) B.E. Fourth Year (8 th Sem) Branch Electrical Engineering

2394 EXAM PAPER. 1. State THREE circumstances that would require a periodic inspection and test to be carried out on an installation

VI 3 - i TABLE OF CONTENTS

Armoured Power and Control Cables to BS6883

RF CABLE ASSEMBLY, TNC, VERY HIGH POWER, 50 OHMS, SEMI-RIGID AND FLEXIBLE CABLE, DC TO 8GHZ BASED ON TYPE TNC-VHP

Schedule of Accreditation issued by United Kingdom Accreditation Service 2 Pine Trees, Chertsey Lane, Staines-upon-Thames, TW18 3HR, UK

Information technology. Generic cabling systems, General requirements

Power Frequency Withstand Voltage On-site testing of 400 kv GIS

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

Tests on Extruded Cables

New Report Indicates AC Inductance/Electrodynamic Dust Detectors May Be Hazardous. Ron Dechene Auburn Systems, LLC Danvers MA 01923

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 9/8/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

ANNEXURE-I. Documents to be uploaded 1 Certificate of Registration with Industries 2 VAT Certificate 3 Service Tax Certificate

Y-CY-JZ flexible, CU-screened, transparent, EMC-preferred type, meter marking

The University of New South Wales. School of Electrical Engineering and Telecommunications. High Voltage Systems ELEC9712. Appendix Partial Discharge

EXTREMELY LOW MAGNETIC FIELD (ELMF) XLPE INSULATED CABLES, TYPE N2XY/FR1 0.6/1 KV

Licensed Electricians Practical Assessment (LEP)

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

شركة كهرباء محافظة القدس المساهمة المحدودة JERUSALEM DISTRICT ELECTRICITY CO. LTD.

SINGLE-PHASE VSV SWITCH

7. INSPECTION AND TEST PROCEDURES

Compact Substation or Prefabricated Substation Inside Totally Enclosed Weatherproof Enclosure COPYRIGHT REGISTERED

DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW)

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-I) UNDERGROUND NETWORK GROUNDING. Rev. 01

B. Division-16 Basic Materials and Methods section apply to work specified in this section.

MarineLine YOZp 0,6/1 kv

SAFETY AND HEALTH STANDARD ELECTRICAL GROUNDING Effective Date: 07/17/10 Standard: Document Number: KUCSH0039 Rev: 4

NATIONAL RULES FOR ELECTRICAL INSTALLATIONS. Fourth Edition. Extracts from Amendment No.1: June 2011

DEIF A/S. Insulation monitor. Type SIM-Q

Armoured Instrumentation Cables to BS6883

CONDITIONS FOR A TENTATIVE APROVAL FOR CONNECTION OF TRANSFORMERS

Transformer Factory Testing

ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE

Underground System Design TADP 547

Electrical Measurement Safety. Sponsored By:

SPECIFICATION FOR STEP UP TRANSFORMER 0.415/11Kv and (630KVA & 1000KVA)

Chapter 6. WIRING SYSTEMS Safe Electrical Design

Transcription:

EPPM, Singapore, 20-21 Sep 2011 Abstract Testing Manual for Electrical Equipment Nahed Al-Hajeri 1 and Anantha Madhavan 2 Quality Assurance (QA) refers to a program for the systematic monitoring and evaluation of the various aspects of a project, service, or facility to ensure that standards of quality are being met. The equipment should be suitable for the intended purpose (fit for purpose) and errors/omission should be eliminated before putting the equipment in service.the paper has been developed to capture various aspects/requirements of inspection and test thru Factory Acceptance Test (FAT), Site Acceptance Tests (SAT) and to ensure quality of the equipment/system. Keywords: factory acceptance test,routine test, site acceptance test, type test. Introduction The purpose of this testing manual is to provide guidelines for inspection and testing of various Electrical Equipmentin compliance to relevant international standards/specifications.it provides information on procedures and testing of Major Electrical equipment s to be followed during testing by engineers and also furnish evidence that an electrical equipment/device is free of inherent flaws or faults. The tests on equipment/system have been broadly categorized into two categories viz. Factory Acceptance Test (FAT) and Site Acceptance Tests (SAT). These tests have been tailored to ensure design, construction and performance requirements of each equipment. This testingmanual includes High Voltage Switchboards, Low Voltage Switchboards, Transformer, Diesel Generator Sets, Induction Motors, Cables, Un-interrupted Power Supply (UPS), Ring Main Unit, Light Fittings, MOV Actuators, Isolator Switch and Earthing Systems etc. However in this Paper only highlights the high voltage cables and related test methods. Benefits Most useful practical information regarding the Factory Acceptance Tests (FAT) & Site Acceptance Tests (SAT) activities Highlights the type of test and their desired result values. These values are derived from the International standards, manufacturer s guidelines and good practical experiences. It covers for all major Electrical Equipment. Simplifies procedures/integration 1 This can bereferred by company engineers to ensure the testing and inspection Senior Engineer Projects, Kuwait Oil Company, Kuwait, Tel. +965 23861408 Fax. +965 23861084 Email. nnahed@kockw.com 2 Design Engineer, Kuwait Oil Company, Kuwait, Tel. +965 23861019Fax. +965 23861084 Email. amadhavan@kockw.com 175

Testing Manual for Electrical Equipment requirements are fulfilled. Improve the quality control of the project and simplify the procedures for engineers. Saving of material searching time. Factory Acceptance Tests (FAT) The Routine tests shall be made with each Electrical Equipment and, whenever practicable, at the manufacturer s works to ensure that the product is in accordance with the equipment on which the type tests have been carried out. The factory acceptance tests consist of Routine, Type Tests and Special tests (project specific) as per company and International standards. Routine tests may comprise, Functional tests - Mechanical Operation Test -Test on auxiliary equipment-verification of correct wiring. Dielectric Tests - It is presumed that every such equipment would also comply with the type test, since design is identical. The factory inspection and testing are conducted according to Company/international standards. The Inspection/testing of Electrical Equipment at Factory are carried out as per the flowchart attached below, 176

EPPM, Singapore, 20-21 Sep 2011 Flow Chart for Factory Acceptance Test (FAT) Internal Quality control Certificates shall be reviewed for any components failures and their Corrections Incoming Equipment for Factory Inspection/Testing (FAT) Tests shall be carried out as per Standard, specified procedures Check for FAT Requirements as per Contract, Company Standard & approved ITP (Inspection Test Plan) STEPS 1) Verify the information (Name Plate) and dimensions as per approved drawings not 2) Inspect for damages & missing parts not Corrective action to be taken by manufacturer to rectify and repeat the test procedure 3) Functional check including Mech. not 4) Mechanical Operation Test not (If Applicable) 5) Insulation Resistance Test (I.R. V not Test) Before & After HV Test I.R Value improvement to be done 6) HV Test/ Dielectric Test not (If Applicable, Standard to be followed) 7) All Tests Results are Acceptable/Desired Values not 177

Testing Manual for Electrical Equipment Yes 8) Test ed Equipment- Dispatch clearance may be given Test Methods and Desired Values In this paper we have highlighted only the High Voltage Cables. Similar way it covers to all major Electrical equipment s. Typical FAT Report- A typical Factory Acceptance Tests (FAT) formats for High Voltage Cables is as below; Sr. No. Description Procedure Desired Values / Results All internal quality control certificates shall be reviewed for any component failures and their corrections. 1. Visual Inspection Check the Conductor, General Construction and cable Identification etc.. (as per approved document) 2. High Voltage Test AC Voltage test shall be applied between the conductor and the metallic shield (for 11KV cables 23KV for 5 minutes) at ambient No Breakdown 3. Insulation Resistance Test 4. Partial Discharge Test 5. Voltage Test for 4 Hours. 6. Conductor and screen Resistance test 7. Conductor/Armour wire examination temperature. The measurement shall be made between conductor and the cores & metallic shield. The test voltage shall be applied between each conductor and the metallic shield. The partial discharge is measured at 11KV. The test voltage (25.5 KV AC for 11KV shall be applied between conductors and the metallic shield. (Applied voltage shall be 4Uo for 4 hrs. for XLPE cables sample) The conductor resistance measured atambient temperature by Double bridge method. Outside diameter of conductor shall be measured at 3 points by caliper and average value shall be calculated. And diameter of armour wire shall be measured on 10% of total armour wires. Value shall be Minimum 100 MΩ No detectable discharge/puncture No breakdown As per IEC 60502-2 (approved document) As per IEC 60502-2(As per approved document) 178

EPPM, Singapore, 20-21 Sep 2011 8. Measurement of thickness of insulation, bedding sheath and outer covering 9. Measurement of overall diameter 10. Hot set test for XLPE insulation 11. Flame Retardant Test CAT A i) Thickness of insulation shall be measured at 6 points by projector. ii) Thickness of bedding sheath shall be measured at 6 points by vernier caliber iii) Thickness of outer-covering shall be measured at 6 points Cable overall diameter shall be measured by diameter tape. The test pieces shall be suspended in the oven and weight (20N/cm2) attached to bottom. After 15Min. in the oven temp. The elongation calculated. The mounted sample shall be placed in the test chamber; the test flame shall be applied for 40min. after which it shall be extinguished. The charred portion shall be measured in meters from the bottom edge of burner to onset of char. As per IEC 60502-2(As per approved document) As per IEC 60502-2(As per approved document) Elongation under load : Max 175% Permanent elongation after cooling : Max 15% Max. length of charred portion should not exceed 2.5m Test Results for FAT (Implementation): The tests carried out at manufacturer s facility for the following type of new cable, 3 Core 300 mm2 Copper Conductor, XLPE Insulated, Copper tape screened, PVC innersheathed, Galvanized Steel Wire Armoured and black PVC outer sheath 11KV cable to IEC-60502-2 and Flame Retardant to IEC 60332-3 Cat.A Specification. The test result values are tabulated below: Sr. No. Description Test Values/Results Remarks All internal quality control certificates are reviewed for any component failures and their corrections. 1. Visual Inspection. (As per approved document). i.e.. physical dimensions are verified 2. High Voltage Test AC Voltage test applied between the conductor and the metallic shield (for 11KV cables 23KV for 5 minutes) at ambient temperature. No Breakdown. 179

Testing Manual for Electrical Equipment 3. Insulation Resistance Test 4. Partial Discharge Test 5. Voltage Test for 4 Hours. 6. Conductor and screen Resistance test 7. Conductor/Armour wire examination 8. Measurement of thickness of insulation, bedding sheath and outer covering 9. Measurement of overall diameter The measurement shall be made between conductor and the cores & metallic shield. Before and after HV test carried out the values are more than 21.2 GΩ (Giga Ohm). The test voltage shall be applied between each conductor and the metallic shield. The partial discharge is measured at 11KV. No detectable discharge/puncture The test voltage (25.4 KV AC for 11KV shall be applied between conductors and the metallic shield. (Applied voltage shall be 4Uo for 4 hrs. for XLPE cables sample). No breakdown The conductor resistance measured atambient temperature by Double bridge method.( 0.2437Ω/Km at 20 Deg. ) Outside diameter of conductor measured at 3 points by caliper and average value calculated. And diameter of armour wire measured on 10% of total armour wires. a) Thickness of insulation measured at 6 points by projector. b) Thickness of bedding sheath measured at 6 points by vernier caliber c) Thickness of outer-covering measured at 6 points Cable overall diameter measured by diameter tape. 10. Hot set test for XLPE insulation 11. Flame Retardant Test CAT A The test pieces suspended in the oven and weight (20N/cm2) attached to bottom. After 15Min. in the oven temp. The elongation calculated. (Elongation under load 75% & 0%) The mounted sample placed in the test chamber; the test flame applied for 40min. after which it 180

EPPM, Singapore, 20-21 Sep 2011 extinguished. The charred portion measured in meters from the bottom edge of burner to onset of char. (1.0 m) All above test results from the witnessed inspection tests are found satisfactory. Site Acceptance Tests (SAT) These tests, as defined in the Contract specification, are carried out by the vendor/contractor during commissioning at site and are witnessed by Company Engineer. Typical SAT Report - A typical Site Acceptance Tests (SAT) formats for High Voltage Cables is as below; Site Acceptance Test (SAT) TEST REPORT FORM NO.1 PAGE 1 OF 1 Unit No. : Type. : Service : Size : Voltage : Sr. No. 1 Inspect both ends of cable for safety 2 Check that cable is disconnected Check List Desired Values/Results Remarks. Both side cable core separated 3 4 5 6 Test Insulation resistance, mega ohms, R-Y B-R R-G B-G Y-B Y-G Test high potential capability Apply different set of Test Voltage (KV) (DC) and corresponding leakage current is to be measured (Micro Amps). Continuity Test Ambient temperature 11KV- 5000V Megger 3.3KV-2500V Megger For HV cable-100mω min For HV(11KV)- 23 KV For HV (3.3 KV)-6.9 KV for 5 Min. with stood ok OK 50 0 C (actual) 181

Testing Manual for Electrical Equipment Company Engineer : Contractor s Engineer : Date : Test Results for SAT (Implementation): The tests were carried out at Site facility for the following type of new cable, 3Core, 300 mm 2 Copper Conductor, XLPE Insulated, Copper tape screened, PVC innersheathed, Galvanized Steel Wire Armoured and black PVC outer sheath 11KV cable to IEC-60502-2 and Flame Retardant to IEC 60332-3 Cat.A Specification. Site Acceptance Test (SAT) TEST REPORT FORM NO.1 PAGE 1 OF 1 Unit No. : 1 Type : XLPE/LC/PVC/GSWA/PVC Service : Incoming Feeder Size : 3Core x 300 sqmm Copper Armoured Voltage : 11KV Sr. No. Check List Desired Values/Results Remarks. 182

EPPM, Singapore, 20-21 Sep 2011 1 2 3 4 5 6 Inspect both ends of cable for safety Check that cable is disconnected Test Insulation resistance, mega ohms, R-Y : 20 G Ohm Y-B : 20 G Ohm B-R : 22 G Ohm R-G : 15 G Ohm Y-G : 16 G Ohm B-G : 15 G Ohm Test high potential capability Apply different set of Test Voltage (23KV) (DC) and corresponding leakage current is measured (Micro Amps). Continuity Test Ambient temperature Both side cable core separated 5000V Megger For HV(11KV)- 23 KV for 5 Min. with stood ok OK 40 0 C (actual) Conclusions It may be observed that by way of implementing Testing Manual it can be very easily ensured that all critical parameters are checked&verified. Also, it enables us to ensure that the equipment is in compliance with desired specifications and standards, before they are actually put into service. References British Standard BS 5467: 1997. Electric Cables- Thermosetting insulate, armoured cables For voltages of 600/1000 V and 1900/3300 V. International Standard, IEC 60332-1-2, edition 1.0., year 2004. Tests on electric and optical fibre cables under fire conditions - Part 1-2: Test for vertical flame propagation for a single insulated wire or cable. International Standard, IEC60502-2, second edition 2005-03. Power cables with extruded Insulation and their accessories for rated voltages from 1 kv up to 30 kv, Part 2: Cables for rated voltages from 6 kv up to 30 kv. International Standard, IEC 60885-1-2-3, edition 1.0, year 1987. Electric Test Methods for Electric cables. 183

Testing Manual for Electrical Equipment Appendix-I Factory acceptance test (FAT)- is carried out at Manufacturer s Factory premises. Routine test - are intended to detect faults in materials and workmanship and ascertain proper functioning of the equipment. They shall be made on each individual piece of equipment. Site acceptance test (SAT)- are carried out during commissioning/pre-commissioning at site. Type test - are intended to verify compliance of the design of given equipment with this standard, where applicable, and the relevant product standard. They may comprise, as appropriate, the verification of, Constructional requirement, Temperature rise, Dielectric properties, Making and breaking capabilities, Operating Limits, Operational performance, Degree of protection of enclosed equipment. Type Tests are performed on single specified Electrical Equipment of one type and are intended to check the design characteristics. Type test usually relates to the first unit manufactured by a firm to given specification. 184