INSTALLATION & TESTING OF UNDERGROUND PRIMARY AND SECONDARY POWER CABLES PRIOR TO ENERGIZATION

Similar documents
METER - INSTALLATION Pad Mount Transformer

Customer Connection Guide Updates Effective May 2017

Single-Phase Mini Pad-Mounted Transformer Specification: Energy+ MPDL

SECTION ELECTRICAL IDENTIFICATION

SOUTH DUBLIN COUNTY COUNCIL Traffic Management Centre Roads (Traffic and Transportation) Department

UNIVERSITY OF MISSOURI Liquid-Filled Utility Transformers 2016 Q1

CONTINUOUS COUNTERPOISE ON POLES

ECP HV INSULATION TESTING

Table of Contents. Introduction... 1

ECP HV INSULATION TESTING

EI HIGH VOLTAGE INSULATION TESTING POLICY

St. Monica Food Pantry Low Voltage (600V and less) Conductors and Cables sys-tek No

CONSULTANT PROCEDURES & DESIGN GUIDELINES Liquid-Filled Utility Transformers UNIVERSITY OF MISSOURI

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-I) UNDERGROUND NETWORK GROUNDING. Rev. 01

SPECIFICATIONS FOR THE INSTALLATION OF CONDUIT SYSTEMS IN RESIDENTIAL SUBDIVISIONS. Notification of Completed Conduit Sections

MGM Transformer. Vacuum Pressure Impregnated (VPI) Dry-Type Substation Transformer Specification Guide

S. C. Electric Cooperative s Specification for a Single-Phase, Single Bushing Overhead Distribution Transformer (Revised 10/2013)

WIRE AND CABLE ENGINEERING GUIDE

Best Practice Reducing The Risk of Arc Flash Cross Over

Brown University Revised 2/1/2006 Facilities Design & Construction Requirements SECTION 16461C - DRY TYPE TRANSFORMERS

Gold plating, 140 Gases compressed, 393 liquid,393 Grounding, safety, 403

Cable Hanging Instruction Manual

SECTION COMMUNICATIONS COPPER OSP CABLING

NSP/004/107 (OHI 7) Guidance on the selection of conductor jumpers and non-tension connections

ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE

Transformers handling and transport

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-II) OVERHEAD NETWORK GROUNDING. Rev. 01

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

MSP-WRTIDSKY1 Light Weight Suspended Ceiling Kit for use with Island Display Skybox

B. Manufacturers: Square-D, G.E. or Westinghosue.

SECTION PANELBOARDS

WESTERN UNDERGROUND COMMITTEE GUIDE 2.6 (2.6/00/0868)

GURANTEED TECHNICAL PARTICULARS OF BACK CLAMP FOR LT CROSS ARM

2/15/2015. Current will always try to return to its source. In order for there to be current, there must be a complete circuit

Understanding and Making Crimp Connections That Last

SECTION COMMUNICATIONS COPPER BACKBONE CABLING

Earthing, HV Switching and Associated Operational Equipment. Approval: Chief Operating Officer

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer

SECTION 5 TRANSFORMERS

4Post Server Rack-111 Assembly For Floor Anchored Models

TECHNICAL SPECIFICATION FOR. CONTACT WIRE HARD-DRAWN COPPER 161mm2

FRAX Series Sweep Frequency Response Analyzers

SECTION COMMUNICATIONS COPPER BACKBONE CABLING

Fluid Sealing Association

CONTINUING EDUC ATION

Wisconsin Contractors Institute Continuing Education

A. Product Data: For each electrical identification product indicated.

Page Electric Utility Service Specifications

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

MESP TECHNICAL SPECIFICATION FOR AN ESSENTIAL SERVICES SUPPLY STEP UP TRANSFORMER

Capstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:

SECTION TRANSFORMERS

NEW OR UPGRADED ELECTRICAL SERVICE

American Electrical Institute

SECTION MEDIUM-VOLTAGE CABLES

ELECTRIC GROUNDING AND WIRING REQUIREMENTS BOOTHS-METAL

INSTALLATION, OPERATION AND MAINTENANCE GUIDE

SPECIFICATION FOR STEP UP TRANSFORMER 0.415/11Kv and (630KVA & 1000KVA)

Distribution transformers Part 2 Ground mounted transformers not closecoupled

TRANSMITTAL LETTER. As Builts Change Order Contract Copy of Letter Insurance. For approval Approved as submitted Resubmit copies for approval

Article 250 Grounding & Bonding

Compliant to DOE 10, CFR Part 431 (effective as of January 1 st, 2016)

SECTION LOW-VOLTAGE ELECT. DIST. DESIGN AND CONSTRUCTION STANDARDS _ February 2015 PART I: GENERAL

DTS ISOLATION TRANSFORMER SPECIFICATIONS

EVERGREEN EM INSTALLATION GUIDE

7. INSPECTION AND TEST PROCEDURES

400/480 Volt ProBlue Adhesive Melters

The NOVA Recloser shall be designed and tested in accordance with the following standards as applicable:

CP /240-MC4 User Manual

TABLE OF CONTENTS FOREWORD... 3 INTRODUCTION SCOPE NORMATIVE REFERENCES... 4

Listing Report: AB Reissue Date: 01/21/16 This report is subject to annual review

EDS LV ELECTRICAL SERVICE DRAWINGS

WAVEFORM CORRECTOR (WAVEFORM CORRECTORS) REPLACES SURGE PROTECTION DEVICES (SPD) PREVIOUSLY KNOWN AS (TVSS)

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

ECE 528 Understanding Power Quality

Mighty Mo GX Series Cabinet Installation Guide. OR Rev /11

Installation Instructions

Electric Service Guide. Residential Subdivision

CONDITIONS FOR A TENTATIVE APROVAL FOR CONNECTION OF TRANSFORMERS

Utility Structures. Utility vaults, trenches, transformer pads Electrical Pole Bases and switching cubicles

Component Requirement Specification for SGI 500XT Isolation Transformer

Application Tooling Specification Sheet

6B.6 Substation Grounding

The Importance of the Neutral-Grounding Resistor. Presented by: Jeff Glenney, P.Eng. and Don Selkirk, E.I.T.

COMMERCIAL ITEM DESCRIPTION SPLICE CONNECTORS

Application Tooling Specification Sheet

Substation Preventive Maintenance

ATTENTION: PLEASE READ AND UNDERSTAND ALL INSTRUCTIONS AND WARNINGS BEFORE ASSEMBLING, INSTALLING OR USING THIS PRODUCT.

Name: Craig Goodwin. Company Name: HV Diagnostics Inc

Installation Instructions for OPGW Bolted Dead End

A. Deviation from this standard must be approved by the Project Architect.

Application Tooling Specification Sheet

MESP TECHNICAL SPECIFICATION FOR AN AUXILIARY OR ESSENTIAL SERVICES AND AUXILIARY TRANSFORMER FOR USE IN A RAILWAY SUBSTATION

FAQ ON EARTHING STANDARDS 16/08/2018

Part VIII Electrical GENERAL REQUIREMENTS CHAPTER 33

Isolating Spark Gaps. Isolating spark gaps at an additional earth ring conductor. Isolating spark gaps for Ex zones

Contact Voltage Detection

50-SDMS-01 SPECIFICATIONS FOR

LOCKOUT / TAGOUT PROGRAM

The Variable Threshold Neutral Isolator (VTNI)

Transcription:

TITLE: RECOMMENDED: P. Lemay NO: APPROVED: C. Malone, P.Eng. REV. DATE: 2015-11-02 Working Procedure GCG0001 REV: 3 INSTALLATION & TESTING OF UNDERGROUND PRIMARY AND SECONDARY POWER CABLES PRIOR TO ENERGIZATION See Hydro Ottawa s Web site for the Latest revisions at: www.hydroottawa.com For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 1 of 12

REVISION SHEET Revision Description Date Initial 0 Original document 2001-02-01 md/csm 1 Revise format and update document 2002-08-26 md/csm 2 Assign document number to form 2002-12-09 pl/csm 3 Added residential cable section 2015-11-02 pl/csm Added primary cable check For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 2 of 12

Table of Contents Page 1.0 Introduction 4 2.0 References 4 3.0 Scope 4 4.0 Installation and Testing of Secondary Service Cables at Pad-mounted Transformers 5 5.0 Installation and Testing of Secondary Cables at Vault Type Transformers 6 6.0 Installation and Testing of Primary Cables 7 Schedule 1: Installation and Testing of Secondary Cables at Pad mounted Transformer 10 Schedule 2: Installation and Testing of Secondary Cables at Vault Type Transformer 11 Schedule 3: Installation and Testing of Primary Cables 12 For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 3 of 12

1.0 Introduction Proper installation and testing of primary and/or secondary underground electrical power cables are vital to prevent a safety hazard and ensure the long term reliability of the electrical installation. Hydro Ottawa may add to the Ontario Electrical Safety Code (OESC) requirements for the specification, termination and testing of the underground cables. These requirements may differ depending on the type of service (primary vs. secondary, overhead vs. underground) and/or the proposed supply point (such as overhead lines, pad mounted transformer, vault type transformer etc.). 2.0 References Hydro Ottawa ESG0001 Construction Verification Program (CVP) Hydro Ottawa ECS0012 Conditions of Service Hydro Ottawa ECS0002 - Primary Voltage Service Specification Hydro Ottawa GCS0012 Electrical Underground Distribution Plant Identification IEEE 400.1 Guide for Field-Testing of Laminated Dielectric, Shielded Power Cable Systems Rated 5kV and Above with High Direct Current Voltage Ontario Electrical Safety Code current edition Ontario Regulation 22/04 - Electrical Distribution Safety Regulation 3.0 Scope This document covers the general requirements for the installation and testing of underground power cables to connect to the Hydro Ottawa power distribution system. Although this procedure is intended for electrical contractors installing customer owned underground power cables, it also applies to contractors that install and terminate underground cables for Hydro Ottawa. Hydro Ottawa reserves the right to refuse to connect and/or energize an underground power cable that does not satisfy these installation requirements. Nothing contained in this specification shall prejudice or supersede any regulation and/or requirement(s) specified under the OESC for customer owned cables. For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 4 of 12

4.0 Installation and Testing of Secondary Service Cables at Padmounted Transformers Listed below are the guidelines for the installation, termination, and acceptance testing of secondary cables at a pad-mounted transformer supplied and installed by Hydro Ottawa. The acceptance testing shall be conducted after the cable installation is complete including cable terminations but before the service cables are terminated to the transformer LV spades and/or placed into service/energized. 4.1 All secondary service cables for general, residential and/or commercial installation shall be installed by an electrical Contractor in compliance with the OESC and applicable Hydro Ottawa requirements. With customer owned cable, the Contractor is also responsible for procuring an authorization for connection from the Electrical Safety Authority (ESA) inspection department five (5) days prior to the proposed energization date. Contractors working for Hydro Ottawa shall comply with Ontario Regulation 22/04 and Hydro Ottawa s CVP quality assurance program (ESG0001). 4.2 Typically the secondary service cables are the first cables pulled within the equipment base. Cable tails must be provided within the equipment base to allow for proper cable training/racking: 4m minimum within a transformer base or 8m minimum within a manhole. 4.3 For secondary service cables larger than 250MCM or installation with multiple services, the cables shall be supported from within the transformer enclosure. The Contractor shall install a section of 41mm x 41mm [1-5/8 x 1-5/8 ], 12 gauge galvanized, solid channel (such as unistrut or cantruss framing structure) across the opening of the transformer base pad. The support channel shall be fixed to the pad using removable screw type concrete anchors. The secondary cables must be secured to the cable support channel, using tie wraps, to relieve/minimize the downward stress from the secondary cables. 4.4 Customer owned secondary cables will be racked and tagged by Hydro Ottawa at the electrical ownership demarcation point to suit as per GCS0012. 4.5 Terminations of all secondary cables at the Hydro Ottawa transformer shall be the Contractor s responsibility. Terminations shall be compression single hole lugs for small cables and double hole lugs (2 x ½ holes with 1 ¾ hole spacing C/L to C/L) for cables 500 MCM with extended barrel for double crimp and superior pull-out resistance. The lugs must be CSA certified or equivalent. 4.6 Secondary cables shall be megger tested by the electrical Contractor a maximum of five (5) days prior to energization. The testing shall be conducted after the cable installation is complete at the main service entrance disconnect/switchboard including phase markers (R/W/B), terminations and splices, but before the cable is terminated to the transformer LV spades. The megger test shall be applied as a diagnostic test (Type 2 - Non Destructive Field Test) to identify potential cross phasing connection. The megger test shall be performed by applying an elevated DC voltage to the conductor and measuring the current flow to a ground reference. It is understood that testing low For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 5 of 12

voltage cables/unshielded cables may produce inherent results due to the lack of uniform ground plane over the dielectric of the cables. 4.7 Each lug must be wire brushed and have oxide inhibitor applied before bolting to a transformer LV spade. 4.8 The lugs must be secured to the transformer LV spades using ½ silicone bronze bolt(s) complete with nut(s) and ½ silicon bronze Belleville spring washers and silicon bronze split lock washers. 4.9 The final connection shall be torqued to the manufacturer specification and/or to the OESC Table D7 specification. 4.10 Hydro Ottawa s report for Installation and Testing of Secondary Cables at Padmounted Transformer, refer to attached report Schedule 1, must be completed by the electrical Contractor five (5) days before the proposed energization date. The installation report must be received and accepted by the Hydro Ottawa Project Manager before the service is scheduled for energization. 5.0 Installation and Testing of Secondary Cables at Vault Type Transformers The proposed vault equipment layout and the proposed routing/training of secondary cables must be submitted to the Hydro Ottawa Project Manager for comment prior to finalizing the vault design. Listed below are the guidelines for the installation, termination and acceptance testing of secondary cables at vault type transformers supplied and installed by Hydro Ottawa. The acceptance testing shall be conducted after the cable installation is complete including cable terminations but before the cables are terminated to the transformer LV spades and/or placed into service/energized. 5.1 All secondary service cables within a building electrical vault shall be installed by an electrical Contractor in compliance with the OESC and applicable Hydro Ottawa requirements. With customer owned cable, the Contractor is also responsible for procuring an authorization for connection from the Electrical Safety Authority inspection department five (5) days prior to the proposed energization date. Contractors working for Hydro Ottawa shall comply with Ontario Regulation 22/04 and Hydro Ottawa s CVP quality assurance program (ESG0001). 5.2 Secondary cables installed within a building electrical vault shall be racked by the electrical Contractor as directed by Hydro Ottawa. The secondary cables must be trained and supported to relieve/minimize the cable stress transfer to the transformer LV spades. 5.3 The secondary cables shall not interfere with the removal of adjacent transformers and shall not either be located above or behind the transformers. For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 6 of 12

5.4 All secondary cable terminations at the vault transformers shall be visible from the operating area of the vault. 5.5 Terminations of all secondary cables at the transformer LV spades shall be the Contractor s responsibility. Terminations shall be compression single hole lugs for small cables and double hole lugs (2 x ½ holes with 1 ¾ hole spacing C/L to C/L) for cables 250 MCM with extended barrel for double crimp and superior pull-out resistance. The lugs must be CSA certified or equivalent. 5.6 Secondary cables shall be megger tested by the electrical Contractor a maximum of five (5) days prior to energization. The testing shall be conducted after the cable installation is complete at the main service entrance disconnect/switchboard including phase markers (R/W/B), terminations and splices, but before the cable is terminated to the transformer LV spades. The megger test shall be applied as a diagnostic test (Type 2 - Non Destructive Field Test) to identify potential cross phasing connection. The megger test is performed by applying an elevated DC voltage to the conductor and measuring the current flow to a ground reference. It is understood that testing low voltage cables/unshielded cables may produce inherent results due to the lack of uniform ground plane over the dielectric of the cables. 5.7 The lugs must be secured to the transformer LV spades using ½ silicone bronze bolt(s) complete with nut(s) and ½ silicon bronze Belleville spring washers and silicon bronze split lock washers. 5.8 Each lug must be wire brushed and have oxide inhibitor applied before bolting to a transformer LV spade. 5.9 The final connection shall be torqued to the manufacturer specification and/or to the OESC Table D7 specification. 5.10 The transformer secondary cable neutral bus shall be grounded in one location inside the transformer vault in compliance with Hydro Ottawa engineering specification GCS0002. In order to reduce circulating current, the ground conductor shall connect with the service neutral conductor(s) at the same transformer LV spade. 5.11 Hydro Ottawa s report for Installation and Testing for Secondary Cables at Vault transformers, refer to attached report Schedule 2, must be completed by the electrical Contractor five (5) days before the proposed energization date. The installation report must be received and accepted by the Hydro Ottawa Project Manager before the service is scheduled for energization. 6.0 Installation and Testing of Primary Cables The proposed primary design must be submitted to the Hydro Ottawa Project Manager for comment prior to finalizing the HV design. Hydro Ottawa s requirements for specification, installation and termination of primary cables/lines shall depend on the type of installation (overhead vs. underground), the service configuration (radial vs. loop), the primary voltage, and the electrical ownership demarcation point with Hydro Ottawa. For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 7 of 12

Listed below are the guidelines for the installation, termination and acceptance testing of primary cables at pad-mounted and/or vault type switching equipment supplied and installed by Hydro Ottawa. The acceptance testing shall be conducted after the cable installation is complete including cable terminations but before the primary cables are terminated to the Hydro Ottawa switching equipment and/or placed into service/energized. 6.1 All primary service cables shall be installed by a High Voltage electrical Contractor in compliance with the OESC and applicable Hydro Ottawa requirements. With customer owned cable, the HV Contractor is also responsible for procuring an authorization for HV connection from the Electrical Safety Authority inspection department five (5) days prior to the proposed energization date. Contractors working for Hydro Ottawa shall comply with Ontario Regulation 22/04 and Hydro Ottawa s CVP quality assurance program (ESG0001). 6.2 The termination of the primary cables ready for connection shall be the HV contractor responsibility. 6.3 Primary cables part of an underground power distribution system, will be racked and tagged (as per GCS0012) by Hydro Ottawa where both the utility and customer owned cables share the same underground structures. 6.4 Primary cables installed within a building electrical vault or switching room shall be racked and tagged by the HV Contractor as directed by Hydro Ottawa. The cables must be trained and supported to relieve/minimize the cable stress transfer to the switching equipment. 6.5 The final connection of the customer owned primary cables/lines at the Hydro Ottawa distribution system shall be Hydro Ottawa s responsibility. 6.6 A visual inspection shall be performed before the final acceptance testing to evaluate the condition of the cables. The visual inspection shall include but not be limited to the condition of the cables, the conditions of the terminations and splices, the arc proofing of cable (if required), the bending radius not to exceed the manufacturer recommendations, the shield and/or concentric neutral terminations. As a minimum acceptance testing, the primary cables shall be checked for continuity and phase meggered by the HV electrical Contractor a maximum of five (5) days prior to energization. 6.7 DC hi-pot acceptance testing is conducted after the primary cable system installation, including all terminations and joints (splices), but before the cable system is placed into normal service. The test is intended to detect installation damage and to show any gross defects or errors in installation of other system components/accessories. For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 8 of 12

DC hi-pot leakage current test technique shall be preformed for the primary cable voltage rating as follows: Table 1: Hi-pot Test Limits for Underground Primary Power Cables Maximum Insulation Test Voltages Cable Rating DC HI-Pot 5 kv 10 kv 15 kv 30 kv 28 kv 50 kv 46 kv 85 kv For testing, bring DC voltage up to prescribed test level in five equal steps. Raise the voltage at an even rate, so as to reach the required level in not less than 10 seconds. Hold the voltage at each step for 60 seconds. Hold the full test voltage for not less than 10 minutes or more than 15 minutes. Read and record the leakage current. After the initial cable charging period, leakage current greater than 15mA is considered a test failure and the cable system should be reviewed for damage and corrected as required before retesting. 6.8 Hydro s report for Installation and Testing of Primary Cables, refer to attached report Schedule 3, must be completed by the electrical Contractor five (5) days before the proposed energization date. The completed report must be received and accepted by the Hydro Ottawa Project Manager before the service is scheduled for energization. For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 9 of 12

Schedule 1: Installation and Testing of Secondary Cables at Pad-mounted Transformer Business Name: Phone Number: Contractor s Address: E-mail: Proposed energization date: Hydro project number: Civic Address of Installation: Please complete the following installation report: 1. Secondary cable size: Number of cables per phase: 2. Confirm installation of the cable support channel at the transformer pad opening: Yes / No 3. Confirm cable tails to be 4 m in transformer base or 8 m into the manhole: Yes / No 4. Confirm the cable lugs are double crimp for cable > 500MCM: Yes / No 5. Meggering results of cables Phase to Ground: (grounded neutral at the main service entrance) @ 1000V DC A-N GND, B-N GND, C-N GND 6. Meggering Results of cables Phase to Phase: @ 1000V DC A-B, A-C, B-C 7. Confirm secondary spades and lugs were wire brushed and oxide inhibitor applied: Yes / No 8. Confirm use of ½ silicon bronze bolt c/w Belleville spring washer and split lock silicone bronze washers: Yes / No 9. Specify torque strength at transformer LV spades (as per OESC or bolt manufacturer): ft lbs / N m Hydro Ottawa shall accept no responsibility, direct or indirect, for personnel injury or equipment damage due to faulty installation or improper testing of customer owned secondary cables. Please be aware that Hydro may not continue with the energization of a faulty installation for safety reasons. Contractor Signature: Date Signed: Contractor Name (Print): For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 10 of 12

Schedule 2: Installation and Testing of Secondary Cables at Vault Type Transformer Business Name: Phone Number: Contractor s Address: E-mail: Proposed energization date: Hydro project number: Civic Address of Installation: Please complete the following installation report: 1. Transformer rating: kva 2. Transformer LV spades and tank ground lugs visible from operating area: Yes / No 3. Secondary cable size: Number of cables per phase: 4. Type of cable lugs/connectors (2 crimp lug > 250 MCM): 5. Meggering results of cables Phase to Ground: @ 1000V DC A-N GND, B-N GND, C-N GND 6. Meggering results of cables Phase to Phase: @ 1000V DC A-B, B-C, A-C 7. Secondary spades and lugs wire brushed and oxide inhibitor applied : Yes / No 8. Installed ½ silicon bronze bolt c/w Belleville or split lock silicone bronze washer: Yes / No 9. Specify torque strength at secondary spade (as per OESC or bolt manufacturer): ft lbs / N m 10. Transformer ground conductor size (ref. to GCS0002 ) : 11. Transformer tank bond conductors size (ref. to GCS0002): Hydro Ottawa shall accept no responsibility, direct or indirect, for personnel injury or equipment damage due to faulty installation or improper testing of customer owned secondary cables. Please be aware that Hydro may not continue with the energization of a faulty installation for safety reasons. Contractor Signature: Date Signed: Contractor Name (Print): For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 11 of 12

Schedule 3: Installation and Testing of Primary Cables Business Name: Phone Number: Contractor s Address: E-mail: Proposed energization date: Hydro project number: Civic Address of Installation: Please complete the following installation report: 1. Primary cable field data: Manufacturer: Rated voltage: Insulation type: Rated insulation level: Conductor size: Conductor material: MFG year: Temp rating: Note: Parallel cable runs are not acceptable if the cables are to terminate to Hydro owned equipment. 2. Termination field data: Manufacturer: Termination type: 3. Confirm cable tails to be 4m in transformer base or 8m in manhole: Yes / No 4. Perform a visual inspection of the cable to be tested for physical cable condition, terminations, shield grounding, bending radius and concentric neutral. Report any problems/recommendations: 5. Meggering of cables between isolated neutral and grounded phase conductor: @ 5kV DC A-N, B-N, C-N 6. Hi-pot Test: A-N ma, B-N ma, C-N ma Hydro Ottawa shall accept no responsibility, direct or indirect, for personnel injury or equipment damage due to faulty installation or improper testing of customer owned secondary cables. Please be aware that Hydro may not continue with the energization of a faulty installation for safety reasons. Contractor Signature: Date Signed: Contractor Name (Print): For Hydro Ottawa Use Only 2015 GCG0001 Rev. 3 Page 12 of 12