Advanced Superconducting 10 kv System in the City Center of Essen, Germany

Similar documents
INNOVATIVE PERSPECTIVES FOR ELECTRICITY TRANSPORT

KIT-ENERGY CENTRE. KIT The research University in the Helmholtz Association

DEMO 5: HVDC Superconducting Link

ADVANCING SUPERCONDUCTING LINKS FOR VERY HIGH POWER TRANSMISSION

Lumped Network Model of a Resistive Type High T c fault current limiter for transient investigations

MATEFU Insulation co-ordination and high voltage testing of fusion magnets

SAFETY ISSUES RELATED TO THE CONNECTION OF MV AND HV GROUNDING

StarSine Power Quality Products

HVDC Transmission. Michael Muhr. Institute of High Voltage Engineering and System Performance Graz University of Technology Austria P A S S I O N

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer

ZS8.4 Air-insulated medium voltage switchgear

Recent Development of SFCL in the USA

High Voltage Instrumentation Cables for the ITER Superconducting Magnet Systems

Mosca-Genova: SMART CITY futuro o realtà?

EI HIGH VOLTAGE INSULATION TESTING POLICY

Power Cables and their Application

Superconducting Fault Current Limiter Modules for Power Transmission / Distribution

Simulation of HTS saturable core-type FCLs for MV distribution systems

CVVOZE Power Laboratories (CVVOZEPowerLab)

CONTENTS. 1. Introduction Generating Stations 9 40

Available online at ScienceDirect. Physics Procedia 81 (2016 )

FIELD DEMONSTRATION OF WORLD WIDE LARGEST SUPERCONDUCTING FAULT CURRENT LIMITER AND NOVEL CONCEPTS

TS RES - OUTSTANDING ISSUES

Sub-cooled SFCL Device and Modules for Power Transmission / Distribution

Title: Southern States Type SLS Smart Sectionalizer Solid Dielectric Three Phase Sectionalizer. Product Specification Guide TABLE OF CONTENTS

DC current interruption tests with HV mechanical DC circuit breaker

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Ein supraleitender Strombegrenzer für die Energieübertragung

Fault Current Limiter Selection Considerations for Utility Engineers

EXAMINATION OF TIME DOMAIN REFLECTOMETRY FOR FAULT LOCATING IN PIPELINES

HTS PARTIAL CORE TRANSFORMER- FAULT CURRENT LIMITER

Resistive and Inductive Fault Current Limiters: Kinetics of Quenching and Recovery

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider

OFFLINE PD DIAGNOSTICS USING SEVERAL EXCITATION VOLTAGES

PAPER. Dry-type transformer innovation: HiDry 72 for subtransmission lines

Underground System Design TADP 547

Power Quality in a 110 kv DSO System Measured by Means of Non- Conventional Instrument Transformers

PERFORMANCE ANALYSIS OF SURGE CURRENT PROTECTION USING SUPERCONDUCTORS

VI 3 - i TABLE OF CONTENTS

Current limiting characteristic of saturated iron core SFCLs

Diagnostic testing of cast resin transformers

G. KOEPPL Koeppl Power Experts Switzerland

Power Frequency Withstand Voltage On-site testing of 400 kv GIS

ECP HV INSULATION TESTING

PHG 70 TD PD / PHG 80 TD PD

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION

INTERNATIONAL STANDARD

Gas-Insulated Medium-Voltage Switchgear siemens.com/8dab12

Fault Behaviour of a Superconducting Turboelectric Distributed Propulsion Aircraft Network:

Type Test of a 145 kv Termination Type TS 145-II

Medium-voltage in-phase regulator system Energy Management

3AV1FG 72.5 kv Prototype Vacuum Circuit Breaker (Case Study with Pilot Customers)

Continuous Monitoring on the SSE Networks Transmission System

Device Under Test: ALTEA VS- 24-I VS-24-I. 0 24/09/12 First issue A. Peretto L. Peretto 1 24/06/16 All text review E. Scala L. Peretto J. L.

Safety earthing. Sector Energy PTI NC. Copyright Siemens AG All rights reserved. Theodor Connor

Markus Abplanalp, 7. Braunschweiger Supraleiterseminar, Strombegrenzerkonzepte im Vergleich

A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems

How to maximize reliability using an alternative distribution system for critical loads

AMENDMENT NO. 1 SEPTEMBER IS (Part 1) : 2001/IEC (1991) SURGE ARRESTORS

QUINT-PS-24DC/24DC/10

The Results of the KSTAR Superconducting Coil Test

Documents and Addresses

Cable testing and diagnostics

MEDIUM VOLTAGE COMPACT STARTER TYPE KAE

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

MAJOR ADVANCES IN MV/LV SUBSTATIONS. Th.Grima et JF.Faltermeier. Groupe CAHORS, France SUMMARY

Modeling insulation in high-voltage substations

SYSTEMS AND COMPONENTS FOR CABLE TESTING

Saturated Core Fault Current Limiters: successful testing/ service performance

NESSY NETWORK VOLTAGE STABILISATION SYSTEM. Permanent protection against voltage fluctuations in the low-voltage network

Compact Systems for HVDC Applications Dr. Denis Imamovic

THE CRYOGENIC SYSTEM OF TESLA

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers

Testing of the Toroidal Field Model Coil (TFMC)

Partial Discharge Measurement and Monitoring on High Voltage XLPE Cables

MFAC. Grid Solutions. High Impedance Differential Relay. MFAC Types. Key Benefits. Application. Description. Imagination at work

Test description for dry-type transformers chapter for special tests

ODEN AT Primary Current Injection Test System

Analysis of Major Changes to Arrester Standards IEC STEVE BREWER

Investigations on a Combined Resonance/VLF HV Test System Partial Discharge (PD) characteristics at VLF and DAC voltages

DEVELOPMENT OF A TEST PROTOCOL FOR A 15 KV CLASS SOLID-STATE CURRENT LIMITER

TT 0710/03. TYPE TEST OF 3 Phase Solid Earthing Bonding Link Box, Type: LB.W.3SA.3.1

Schedule of Accreditation issued by United Kingdom Accreditation Service 2 Pine Trees, Chertsey Lane, Staines-upon-Thames, TW18 3HR, UK

TECHNICAL DESCRIPTION TD-77A/3 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES

PRODUCT PORTFOLIO TEST AND MEASURING SYSTEMS

High-Power Testing of Circuit Breakers

On-load tap-changer VACUTAP VRC and VRE

Poornima G P. IJECS Volume 3 Issue 6 June, 2014 Page No Page 6453

APPARENT POWER DEPENDENT VOLTAGE CONTROL IN THE LV GRIDS WITH DISTRIBUTED GENERATION USING ON-LOAD TAP CHANGING TRANSFORMER

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER

Capacitive voltage transformers

Powered by technology...driven by service CURRENT TRANSFORMERS. Multifunction Meters. Transducers & Isolators. Temperature Controllers

Power System Studies

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it.

Standard Technical Specifications for Electrical Works CABLES AND ACCESSORIES. 11 kv XLPE-Insulated Three-Core Underground Cables

The NOVA Recloser shall be designed and tested in accordance with the following standards as applicable:

Specialists in HV and MV test and diagnostics. Testing in Substations

ECP HV INSULATION TESTING

Solutions to Consider in Current Transformer Selection for APR1400 Nuclear Power Plant Medium Voltage Switchgears

MINI-PS AC/24DC/1.3

Transcription:

Advanced Superconducting 10 kv System in the City Center of Essen, Germany >EUCAS 2015 >September 2015 >Frank Schmidt >Nexans SEITE 1

Content Background and motivation Feasibility study of RWE Deutschland Pilot project of RWE Deutschland in the town centre of Essen Milestones Operational Experience Summary SEITE 2

Today: high voltage levels for high energy densities in conurbations > classical technologies in large city grids Overlaid high voltage grid Transformer stations high voltage/medium voltage Medium and low voltage grids for the further distribution of energy > Conventional cables and inner-city transformer stations show only low potentials for technical and economical optimization because they only have restricted possibilities for new grid concepts claim lots of space due to the high voltage level have relative high losses Background and Motivation Advantages of supercondivity reduced space requirements for stations and cable routes less efforts for installation no electromagnetic impact dropping of transformer stations HV/MV options for new grid structures double garage instead of sports hall SEITE 3

Invited presentation 1A-LS-O1.1 given at EUCAS 2015; Lyon, France, September 6 10, 2015. Not submitted to IEEE Trans. Appl. Supercond. High voltage grids in the cities Essen and Mülheim 380 kv transformer stations 220 kv transformer station 110/10 kv transformer station Target area für HTS cables 110 kv cable 110 kv OHL Background and Motivation feeding points in the 10 kv HTS grid 380 kv transformer stations 220 kv transformer stations 110/10 kv transformer station 10 kv load-centre substation basis: actual grid (2010) 10 kv HTS cable 110 kv cable 110 kv OHL City center ring with superconducting MV cables? basis: target grid (2020) SEITE 4 IEEE/CSC & ESAS SUPERCONDUCTIVITY NEWS FORUM (global edition), October 2015.

Feasibility Study of RWE Deutschland Preliminary to a field test of a longer HTS-cable a feasibility study was done > Client RWE Deutschland AG > Overall control Karlsruhe Institute of Technology Institute for Technical Physics > Calculations Leibniz University Hannover Institute for Energy Supply and High Voltage > Technology Nexans Superconducting MV Cables for Power Supply in Urban Areas SEITE 5

Grid Layout with MV HTS Cables 110 kv OHL 110 kv UGC 10 kv UGC 110 kv busbar 10 kv busbar Bus tie (open) 3,0 km A 6,2 km 5,0 km B 4,6 km Future grid structure has been designed based on Conventional 110 kv cables C 4,3 km D 2,2 km E 2,6 km Superconducting 10 kv cables 3,1 km 2,7 km 2,6 km F Perquisites: same redundancy (n-1) G 4,7 km H 3,6 km I Economic viability compared 3,2 km J SEITE 6

Grid Layout with MV HTS Cables Dispensable devices for new grid concept 110 kv OHL 110 kv UGC 10 kv UGC 110 kv busbar 10 kv busbar Bus tie (open) A 6,2 km B 5,0 km 4,6 km 12.1 km of 110 kv cable systems 12 x 110 kv cable switchgear 5 x, 110/10 kv transformers 3,0 km 3,0 km E 5 x 110 kv transformer switchgear D 5 x 10 kv transformer switchgear C 8,4 km 2,7 km 2,7 km 2,6 km 2,6 km Additionally required devices for new grid concept 23.4 km of 10 kv HTS cable system F 16 x 10 kv cable switchgear 3 x 10 kv bus ties G 4,7 km H 6,8 km J 3,6 km I 3,2 km SEITE 7

Feasibility Study - Summary The HTS cable technology offers technical, operational, economical and processual advantages > Increased power density through application of HTS cables Avoiding higher voltage levels for power distribution M > Negligible thermal impact on the environment No drying out of soil, no thermal backfill required No maximum laying depth, no bottlenecks at cable crossings > No outer magnetic field during normal operation > Reduced space for substations and for cable installation 600 650 850 700 400 100 200 100 Simplified cable installation, less civil works Space-savings in urban areas > Increased operating safety due to fault current limitation 1200 175 125 125 175 High voltage cable conventional 1050 125 100 100 100 100 145 125 Medium voltage cable conventional Medium voltage cable superconducting (HTS) SEITE 8

Pilot Project of RWE Deutschland Positive results of the study are the basis for testing an HTS system in the inner city of Essen Start of the project: September 2011 Installation of the cable: 3rd/4th quart of 2013 Inauguration: Spring of 2014 Total duration of project: 4.5 years Proof of the technical suitability of superconducting technologies (cable and fault current limiter) in distribution grids Evaluation of the investment for a 10 kv cable in combination with a superconducting fault current limiter as an alternative to a 110 kv cable system Demonstration of technical advantages of the running system over a period of two years Estimation of further potential applications of the HTS cable technology Due to the innovation character, the project AmpaCity is funded by the German Ministry of Economics SEITE 9

Pilot Project of RWE Deutschland Technical Specification AmpaCity 1 km distance between substations 10 kv system voltage 2.3 ka operating current () Substation Herkules Cable joint Substation Dellbrügge Luftbild: "Darstellung aus HK Luftbilder / Karten Lizenz Nr. 197 / 2012 mit Genehmigung vom Amt für Geoinformation, Vermessung und Kataster der Stadt Essen vom 13.02.2012" SEITE 10

AmpaCity One Line Diagram Initial Situation Substation Dellbrügge Substation Herkules 110-kV-cabel 10 kv 110-kV-cabel 10 kv 110 kv SEITE 11

AmpaCity One Line Diagram Current Situation Substation Dellbrügge Substation Herkules 10-kV-HTS-cable 110-kV-cabel SSB 10 kv Reduction of one transformer 110/10 kv 10 kv 110 kv SEITE 12

HTS-Cable with concentric design The components of AmpaCity Phase 1 Phase 2 Phase 3 Screen Inner LN 2 Cooling Former Dielectric Outer LN 2 Cooling Cable Cryostat SEITE 13

Termination Phase connection to Fault Current Limiter L1 L2 The components of AmpaCity L3 Connection screen Cooling system inlet / return LN 2 connection HTS-cable SEITE 14

Joint The components of AmpaCity > Connection of two sections midway between the two substations Due to transport reasons it is neccessary to divide the cable length of one kilometer in two sections Electrical connection coupling cable core Thermal connection coupling cryostat SEITE 15

Superconducting fault current limiter The components of AmpaCity Parameter Nominal power Nominal voltage Operating current Rated lightning impulse withstand voltage Rated AC withstand voltage Prospective unlimited peak current Prospective unlimited symmetric current Limited peak current Limited symmetric current Limitation time Recovery time Value 10 kv 2.3 ka 75 kv 28 kv 50 ka 20 ka < 13 ka < 5 ka 100 ms < 10 min SEITE 16

Cooling System 4 kw cold power @ 67 K Subcooled liquid nitrogen Closed circulation of nitrogen in the cable High availability and reliability ln 2 Storage Tank Vacuum Pump Circulation Pump Pressure Built-Up HTS Cable SFCL SEITE 17

Milestones Pilot Project of RWE Deutschland Submission of the grant application to the German Federal Ministry of Economics and Technology (BMWi) at April 19th,2011 and July 15th, 2011 Receipt of the grant decision of the BMWi at September 5th, 2011 Production of the prototype cable in the second half of 2012 Completion of the type test in the first quarter of 2013 Starting production of the cable system at the end of first quarter 2013 Turning of the first sod in Essen April 9th, 2013 Installation of the complete system in the third and fourth quarter of 2013 On-site test and first commissioning trial in December 2013 Putting into operation on April 30 th 2014 Testing from 2014 to 2016 Evaluation of the results and commitment of further steps in the beginning of the year 2016 SEITE 18

The components of AmpaCity Test set-up for type test (Nexans, Hannover) > Qualification test of the system previous to the installation in Essen Test set-up: two cable sections (total 25 m), two terminations, one connection coupling Tests according to German standard DIN VDE 0276 and relevant IEC-drafts (IEC: international Electrotechnical Commission) Succesfully completed March 2013 production of the components started SEITE 19

Components layout on site The components of AmpaCity Transformer box in the substation Herkules 1 Cable 2 Termination To switchgear 2 3 Fault current limiter 1 4 4 cooling system L1 L2 L3 3 SEITE 20

Civil engeneering Routing in the center of Essen > Elaborate preparations were neccessary Very high density of different supply and disposal lines in the inner-city area (electricity, gas, water, district heating, canalisation, telecommunication, ) requires detailled preliminary planning Agreements with different companies and authorities Blueprints and reality a great number of surprises (dead-end conductions, contaminated soils, heaps of ruins, changes of location and depth, ) SEITE 21

Civil engeneering an essential component for the realization of the project > Reduction of the expense and the negative impacts Less amount of space for the HTS system Division into construction phases Laying of empty conduits for cable pulling SEITE 22

> Cable system Delivery Installation and pre-commissioning Installation of the components September - November 2013 > Cable system Assembly of the U-Bend > Cable system Pulling > Cable system Connection joint and joint pit SEITE 23

Installation and pre-commissioning Installation of the components September - November 2013 > Refrigeration system Delivery, installation of the LN-tank > Superconducting fault currrent limiter Installation > Refrigeration Cable system system Mounting Pulling > On-site cable test Voltage test, tan d, PD SEITE 24

Commissioning Test > Standard cable test with VLF equipment > PD measurement (20 kv @ 0,1 Hz) > Dielectric loss factor measurement (10 kv, 15 kv, 20 kv @ 0,1 Hz) > AC withstand voltage test (30 kv @ 0,1 Hz for 1 h) SEITE 25

Commissioning Official inauguration on 30th April, 2014 World premiere in Essen: RWE integrates for the first time a superconducting cable system in existing city grid Energieunternehmen testet gemeinsam mit Partnern die innerstädtische Stromversorgung der Zukunft Fördermittel vom BMWi ermöglichen Pilotprojekt AmpaCity Prime Minister Hannelore Kraft: high significance for energy country NRW From left to right: Dr. Joachim Schneider, CTO RWE Deutschland AG, Dr. Arndt Neuhaus, CEO RWE Deutschland AG, Peter Terium, CEO RWE AG, Reinhard Paß, Lord Mayor of the City of Essen, Dr. Johannes Georg Bednorz, Nobel laureate 1987, Dr. Hans-Christoph Wirth, German Federal Ministry for Economic Affairs and Energy, Hannelore Kraft, Prime Minister of the German federal state North Rhine-Westphalia, Christof Barklage, CEO Nexans Deutschland GmbH, Prof. h.c. Dr. Joachim Knebel, area manager Karlsruhe Institute for Technology SEITE 26

> Balancing the earth capacitance Compensation of the unsymmetric earth capacitances of the AmpaCity cable by installation of capacitors Operation - lessons learned Operation without problems since commissioning, however some optimisations during operation > Optimisation cooling system Modification of the vacuum pumps after freezing of humid air; some smaller optimisations > Optimisation system control Increase of the response time after automatic reclosing for non-disruptive operation SEITE 27

Invited presentation 1A-LS-O1.1 given at EUCAS 2015; Lyon, France, September 6 10, 2015. Not submitted to IEEE Trans. Appl. Supercond. Operation - some data > since starting the operation 16 months ago About 60 Million kwh had been transmitted with the AmpaCity cable Roughly 100 groups with in total more than 2,000 interested participants from Europe and various parts of the world (e.g. U.S., China, Australia, Korea) visited the HTS installation in the station Herkules, SEITE 28

Short circuit and ground fault tests Operation - short circuit tests In order to study the short-circuit behavior of the high-temperature superconductor, on June 23 rd, 2015 the HTS system was subject to various short circuit and ground fault scenarios to study the performance under these conditions. For the experiments, special circuits were constructed to eliminate negative influence of customers or other networks. To limit the ground fault current, the transformer 15 has been turned on in the station Dellbrügge for supplying the subnet Dellbrügge. Short circuit tests AmpaCity - Special circuit SEITE 29

Short circuit and ground fault tests Operation - short circuit tests > The following tests were carried out: Short circuit test, three poles, without earth contact two tests Short circuit test bipolar, without earth contact one test1 Ground fault test single-pole, duration 5 min, then short grounding system Earth fault current < 20 A SEITE 30

Short circuit and ground fault tests Operation - short circuit tests Detail view cooling system scheduled release Pressure profile during short circuit Temperature profile during short circuit SEITE 31

Short circuit and ground fault tests Operation - short circuit tests Logging of current and voltage Operating parameters of the fault current limiter Ready for operation after a short recovery time Fault Temperaturverlauf current limiter ready während for operation Kurzschluss again SEITE 32

Short circuit and ground fault tests Operation - short circuit tests All tests conducted gave the expected results The HTS system works exactly as expected including the fault current limitation Protokollierung von Strom und Spannung Betriebsparameter des Strombegrenzers The test proves the maturity of the technology under real grid conditions Betriebsbereitschaft nach kurzer Erholzeit Temperaturverlauf Strombegrenzer während wieder einsatzbereit Kurzschluss SEITE 33

The HTS technology has an important future potential Summary Feasibility study with very positive results; amongst others: HV/MV stations in conurbations can be dropped by using HTS sytems smarter grid structures and less requirement of space by extension of the grid with HTS cables Testing the superconducting cable in practical use at RWE The field test in Essen is proving the maturity of HTS system under real grid conditions Superconducting components will become more competitive to conventional technology increasing capacity for the production of superconducting tapes scaling effects for cable system production reduced development and engineering optimized cable laying SEITE 34

Thank You for Your Attention SEITE 35