SERIES 300 SINGLE HUNG WITH FIN WINDOW INSTALLATION

Similar documents
SERIES 300 SINGLE HUNG WINDOW INSTALLATION

SERIES 5001 SLIDING GLASS DOOR PATIO DOORS INSTALLATION GUIDE

Storefront Installation Guide

INSTALLATION INSTRUCTIONS SIDELITE ASSEMBLY SERIES 900 TERRACE DOOR AND SERIES 925 PATIO DOOR

GENERAL INSTALLATION GUIDELINES

GENERAL INSTALLATION GUIDELINES

Storefront Installation Guide INSTALLATION INSTRUCTIONS

DHS-500 IMPACT SYSTEM INSTALLATION MANUAL

Installation Guidelines For ALUMINUM M-SERIES 3 PANEL SLIDING DOOR

Thermally Broken Framing and Door Installation

INSTALLATION INSTRUCTIONS SERIES 487 CENTER GLAZED WITH 1-1/2" TRIM OFFICE PARTITIONS

INSTALLATION INSTRUCTIONS

Before installation, check your local and state requirements for this type of install.

Installation Guidelines For Quaker Window Products Aluminum flange fin sub sill & receptor system using a T mulled twin window unit.

Installation Guide for E-Series/Eagle Clad Mechanically Fastened Windows

Tools required by installer: Materials required by installer:

14000 I/O Series Flush Glaze. Fabrication and Installation Instructions

INSTALLATION INSTRUCTIONS for Vinyl Windows with Integral Nailing Fin (JII001) IMPORTANT INFORMATION & GLOSSARY ROUGH OPENINGS

Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows

INSTALLATION INSTRUCTIONS for Wood/Clad Wood Windows without Exterior Trim or Nailing Fin (JII025) ImpOrTaNT INFOrmaTION & GlOssary.

INSTALLATION INSTRUCTIONS for Vinyl Windows with Integral Nailing Fin (JII001)

INSTALLATION INSTRUCTIONS IMPERVIA SLIDING PATIO DOOR WITH FINS

Sun Windows General Information New Construction Hinged Door Installation Instructions

Installation Instructions

INSTALLATION MANUAL STOREFRONT DOORS

INSTALLATION INSTRUCTIONS for Wood/Clad Wood Windows with Exterior Trim or Nail Fin (JII024)

YSD 400 Sliding Door System Installation Manual

Installation Guide. for E-Series/Eagle Clad Hinged Inswing French Door

Installation Recommendations for Finless Frame Doors

4500 Series. Fabrication and Installation Instructions

Window Frame Installation Instructions For Nail-on and Block Frames

Curtain Wall Installation Guide

All Window Installation Instruction

Installation of Fiberglass Windows

Eagle clad double-hung window installation instructions

INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACIÓN FOR CLAD CASEMENT & AWNING WINDOW VENTANA DE DOS HOJAS CON REVESTIMIENTO

Read guide from beginning to end before starting installation. Read all warnings and cautions during unit installation.

14000 Series. Fabrication and Installation Instructions

INSTALLATION INSTRUCTIONS for Wood Bay or Bow Windows with Nailing Fin or Exterior Trim (JII032)

Metal & Vinyl, Flush Mount and Recessed Fin Windows Recommended Installation Instructions

INSTALLATION SHOP DRAWINGS FOR MINNEAPOLIS, MN

Installation Guidelines for all Quaker products with nail fins New Construction nail fin installation with a Zip sheathing system.

Note: Installation and Glazing Manuals are product specific. FOR REVIEW ONLY! May 2015

INSTALLATION INSTRUCTIONS for Vinyl Projecting Windows with Integral Nailing Fin (JII023)

Integrity Polygon and Round Top Installation and Finishing Instructions

Installation Guidelines. Next Dimension. Single Hung / Single Hung Fixed / Double Hung / Sliding Window / Fixed Window

Heavy Wall Applied Stop Tube Frame and Door Installation

FG-5100T STORMMAX INSTALLATION AND GLAZING MANUAL NOTE:

INSTALLATION INSTRUCTIONS DOUBLE-HUNG WINDOW WITH FINS

Vinyl Windows and Doors Manufactured by Pella Corporation

Flashing Materials. Rough Opening Preparation

Installation Guide for Andersen 400 Series Tilt-Wash Transom Windows with Stormwatch Protection (PG Upgrade) Manufactured After 2006

SERIES 4070-T GENERAL ASSEMBLY AND INSTALLATION INSTRUCTIONS

Installation Guide. for Andersen 400 Series Tilt-Wash Picture Windows with Stormwatch Protection (High-Performance Impact Resistant Glass)

STACKING MULTI-SLIDE DOOR SYSTEM

NEW CONSTRUCTION, REPLACEMENT AND FLUSH FIN REPLACEMENT WINDOW INSTALLATION INSTRUCTIONS

(773) INSTALLATION INSTRUCTIONS for Vinyl Windows with Integral Nailing Fin (JII001) IMPORTANT INFORMATION & GL OSSARY ROUGH OPENINGS

UNIT 5: EXTERIOR DOORS AND WINDOWS

Series 7650 Installation Instructions Sliding Glass Door

Installation Guide for Andersen 400 Series Tilt-Wash Transom and 200 Series Narroline Transom Windows

Transom Joining. for Andersen Elliptical Windows over Perma-Shield Gliding Patio Door

INSTALLATION INSTRUCTIONS for Wood Bay or Bow Windows with Nailing Fin or Exterior Trim (JII032) IMPORTANT INFORMATION AND GLOSSARY ROUGH OPENINGS

Best Materials LLC distributes backer rod, caulking and sealants for all types of EIFS joints and penetration sealing applications.

Aluminum Clad Wood Window 1/2 Reinforced Field Mulling and Stacking Supplement

PIVOT DOOR 3400P INSTALLATION INSTRUCTIONS

ELEPHANT DOOR SYSTEMS SERIES E1200

14000 Series. Fabrication and Installation Instructions

How To Install Windows: Nail-Fin Application

SERIES 8100 FIXED WINDOW BLOCK OR FIN FRAME

Series Sloped glazed Curtain wall. Installation Instructions

Sun Windows General Information New Construction Sliding Door Installation Instructions H F

Steel Reinforced Joining Thank you for choosing Andersen. Please leave this guide with building owner.

NARROW, MEDIUM AND WIDE STILE, THERMASTILE AND DURASTILE. Installation Instructions

Assembled Patio Door Installation Guide 2-Panel Patio Door with Non-Welded Frame

Installation Guide for Andersen Architectural Clad Awning Windows

INSTALLATION INSTRUCTIONS 2 x 4 1/2 for 1 Glass

INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS

Series 7600 Installation Instructions Aluminum Multi-Slide Door (Pocketing)

Dear Contractor, I am glad that you are interested in our window rebate program.

Installation Guide for Andersen Architectural Clad Inswing Entry and Patio Doors

INSTALLATION INSTRUCTIONS SERIES 3600 SUNSHADE SYSTEM

NEW CONSTRUCTION PATIO DOOR INSTALLATION INSTRUCTIONS (WITH NAILING FLANGE)

26- H i n g e d P a t i o D o o r s - I n s w i n g

Installation Guide for Andersen 200 Series Tilt-Wash Picture, Transom and Circle Top Windows

YOW 225 TU Window System

INSTALLATION GUIDE WOOD PIVOTING CIRCLE/ OVAL

I n s t a l l a t i o n I n s t r u c t i o n s

Norwood Windows Permaglass Fiberglass Products Installation Instruction

Fold-A-Way Patio Door ASSEMBLY & INSTALLATION GUIDE

FOLDING DOOR - FOR FACTORY ASSEMBLED JAMBS WITH APPLIED SILL

INSTALLATION INSTRUCTIONS FOR TEUTONIC ENTRANCE DOOR RECOMMENDATIONS FOR COMMON INSTALLATION OF ENTRANCE DOORS.

STACKING MULTI-SLIDE DOOR SYSTEM INSTALLATION INSTRUCTIONS

Kinro Metal, Vinyl, Flush Mount and Recessed Fin Windows OEM INSTALLATION MANUAL

MULTISLIDE DOORS INSTALLATION GUIDE & SITE PREPARATION

INSTALLATION INSTRUCTIONS for Custom and Premium Pocket Windows (JII022) IMPORTANT INFORMATION AND GLOSSARY SAFETY AND HANDLING

POCKETING MULTI-SLIDE DOOR SYSTEM

YES 45 XT High Performance Thermal Storefront System

Installation Instructions

YES 45 TU Thermal Storefront System Installation Manual

INSTALLATION INSTRUCTION FOR WOOD DOUBLE-HUNG AND CASEMENT WINDOWS USING WOOD BRICKMOULD OR FLAT CASING

Transcription:

IMPORTANT INFORMATION: WHETHER IT BE LOCATION OR INSTALLATION TYPE, NOT ALL WINDOW TYPES CAN BE INSTALLED IN ALL AREAS OR WALL CONDITIONS. CONSULT YOUR LOCAL BUILDING CODE DEPARTMENT FOR ANY REGULATIONS OR CODES THAT WILL AFFECT YOUR PROJECT. GENERAL OVERVIEW Windows are not to be used in any manner other than their intended use, and never for scaffolding, work benches, or shelving materials, etc. Report any damage or missing items to Boyd Aluminum and the freight carrier immediately. NOTE: Check all materials at the time of delivery. STORAGE AND PROTECTION Practice safe material handling and distribution. Do not drop, drag, or walk on packaged or boxed materials. Always stack windows with correct directional stickers on all packages in the proper orientation. If packages are wet or contaminated by other work site products, remove from contaminated packaging and repackage. Store in a safe, dry location; secure in place to protect from wind or other potential threats if needed. CLEANING WINDOWS Cement, plaster, acid, and petroleum cleaners can be harmful to finishes on windows. Extended use of duct tape, masking tape, or similar products is not recommended. These products may also damage finishes. For cleaning of anodized aluminum surfaces, refer to AAMA 609.1-85 Voluntary Guide Specification for Cleaning and Maintenance of Architectural Anodized Aluminum. For cleaning of painted aluminum surfaces, refer to AAMA 610.79 Voluntary Guide Specification for Cleaning and Maintenance of Painted Aluminum Extrusions and Curtain Wall Panels. DOWNLOAD: Complete cleaning instructions can be downloaded at: CONSTRUCTION AND JOB SITE NOTES All materials need to be inventoried to be certain everything required for installation is accounted for. Materials need to be installed plumb, level, and true for units to operate properly. Work from project-defined benchmarks like center column lines, finished floors, or wall openings as defined by the architectural drawings and/or the shop drawings. Isolation of dissimilar materials (like aluminum and uncured concrete) needs to be prepared for. Use a heavy bituminous paint, zinc chromate coating, or approved equal to isolate incompatible materials. All sealants need to be compatible with all windows and surrounding materials. The glazing contractor, general contractor, or owner are responsible for supplying compatible sealants. Sealants are always required to be tooled into the opening crevices. Take care to protect the window units from tooling damage. Painter s masking tape works extremely well for protection and straight lines. Remove as soon as the desired finish is achieved. Excess will generally need to be removed or cleaned. Protection and cleaning of materials are the responsibility of the glazing contractor, general contractor, or owner. (Reference AAMA documentation for care and maintenance.) Compliance with all federal, state, and local building codes is the responsibility of the architect, contractor, and customer to interpret for the window products used on the project. Boyd Aluminum is only a material supplier. Blocking, anchors, sealants, flashing, and fasteners to the surrounding conditions should be defined on the shop drawings, and they are normally the responsibility of the glazing contractor. Due to variable opening conditions, window sizes, and building location requirements, fasteners should be determined by the project architect, glazing contractor, or your local code department. Boyd Aluminum is the material supplier of the window product defined in the drawings and contract documents. Only fasteners and accessories within the system are supplied. Due to changing window parameters and evolving product lines, Boyd Aluminum reserves the right to change detailing and documentation without notification. DOWNLOAD: Complete care and maintenance instructions can be downloaded at: Page 1 of 5

1" SHIM Backer rod, rigid insulation, or foam as required for continuous fillet bead of sealant, required for proper sealing of window. (TYP) All screw heads must be completely covered with sealant to ensure watertight seal (TYP) 2-piece snap trim to match window finish 1" SHIM Backer rod, rigid insulation, or foam as required for continuous fillet bead of sealant as required by window installer (TYP) Shim as required by window installer (TYP) All screw heads must be completely covered with sealant to ensure watertight seal (TYP) 1/ SHIM WINDOW INSTALLATION USING NAILING FINS AT POSITION 1 Exterior veneer Through wall flashing by others (TYP) WINDOW INSTALLATION USING NAILING FINS AT POSITION 2 WINDOW WINDOW INSTALLATION INSTALLATION WITH NAILING WITH FINS NAILING Backer rod, rigid insulation, FINS or foam as required for continuous fillet bead of sealant, required for proper sealing FIGURE of window. 1.0 (TYP) All screw heads must be completely covered CHECK CONTRACT DOCUMENTS AND SHOP DRAWINGS with sealant to ensure watertight seal (TYP) Understand and clarify any field verify notes and Screws approvals through of flashing architectural into and shop drawings. window frame Get familiar with the products needed for installation of the project. Installation instructions are intended to be a reasonable guideline for the installation of window units and trims, based on common conditions. Conditions on a project vary, and deviations and/or special Through wall WALL ASSEMBLY flashing instructions by should be defined in the shop drawings. See Figure 1.0 for installation. others Check (TYP) to be certain these installation instructions are compatible with the project conditions and will not compromise WINDOW INSTALLATION the window USING units THROUGH or surrounding WALL FLASHING products (YOU installation or warranty. WILL HAVE EXPOSED FASTENERS ON JAMBS AND HEAD LIKE OPTION D) OPTION C WALL ASSEMBLY WINDOW INSTALLATION USING THROUGH FRAME FASTENERS OPTION D Backer rod, rigid insulation, or foam as required for continuous fillet bead NOTE: Local of sealant, codes, required then shop for proper drawings, sealing of window. (TYP) should take precedence and define Screws through window frame project-specific product and installation. Page 2 of 5

1" STEP 1: INSPECT THE OPENINGS Verify that the rough opening sizes and locations match the architectural and shop drawings. Verify window unit sizes that are received. They should typically be ½" smaller than rough openings. Identify any high points on the sill openings. Using a level and string line, follow Figure 1.1 to find any out of square or out of level places, as this will be important when installation begins. Any damage to the sill or opening structure will need to be fixed before installation can begin. WINDOW INSET NOTE: For proper operation and weeping, windows must be installed plumb, level, and square. NOTE: For proper operation and weeping, windows must be installed plumb, level, and square IS THE WINDOW PLUS 1/2" SHIMMING NOTE: Inset is measured from the face of finished wall or the face of sheathing depending on the stage of the project NOTE: Inset is measured from face of finished wall or the face of sheathing depending on stage of project. WINDOW INSET NOTE: Hole opening size is measured NOTE: Hole opening comparing both sides and the top and size bottom is measured comparing both sides and top and bottom. IS THE WINDOW PLUS 1/2" SHIMMING NOTE: Squareness Squareness is measured by equal dimensions diagonally measured by equal dimensions diagnally FIGURE 1.1 STEP 2: PREPARE THE OPENINGS Using self-adhesive flashing to waterproof the window opening, cut two (2) horizontal flashing tape pieces 12" longer than the opening. Place flashing tape along the sill (A) to overlap around 1" of the exterior building wrap material or condition, and 6" up the jambs. Slit a 1" tab at the center of each corner so the 1" tabs will bend at 45 degrees along the exterior surface. Place flashing tape (B) over the inside overlapping first tape by 1". See Figure 1.2. Cut two (2) more flashing tapes equal to the opening height. Apply them up each side, overlapping the exterior surface 1". Repeat step 1 at the top of the window. Place flashing tape that overlaps the exterior lap from the starting flashing from step 1 above. See Figure 1.2 (C) below. Repeat at the sides then the top. Seal the corners and staple the tape if needed to hold them in place. Using the architectural drawings or shop drawings, establish a window face line at the head, jambs, and sill. This sets the inset distance into the wall location from the exterior wall face. See Figure 1.1. Attach the head flashing in location as shown on the shop drawings. After determining the sill location, install the sill flashing per the shop drawings, making sure to seal the screw heads. Apply sealant along the ends of the flashing where the window will be located. Place the flashing on the rough opening at the sill. Wrap the flashing up 6" on each jamb as shown Place flashing on rough opening at the sill. Wrap the flashing up 6" on each jamb as shown 6" Place the flashing on Place flashing on 1" rough the rough opening opening, 1" overlapping the overlapping previous the sill wrap previous as shown sill wrap as shown Overlap the previous Overlap the previous sill sill wrap wrap as shown. as shown 6" Overlap the sill wrap as shown Overlap the sill wrap as shown. Caulk both corners at the sill Caulk both corners at sill A B CC D FIGURE 1.2 Page 3 of 5

STEP 3: PREPARE FOR INSTALLATION Inspect the window joints, confirming that they have not been broken loose by the dynamics involved in shipping and handling. Use appropriate compatible shimming, blocking or use manufacturers frame filler primarily at the anchor points commensurate with the anchor locations and requirements of the project. There are various ways to anchor windows. Always follow local codes for anchoring windows; if not covered by local or county jurisdictions, typical anchoring for all type installations would be from the top and bottom of the side s rails, from the sides on the top rail, and 12" apart along the balance of the window. See Figure 1.3. IS THE WINDOW PLUS 1/2" SHIMMING S'S WINDOWS WINDOW'S WIDTH DIMENSION EQUAL OR EQUAL OR EQUAL OR 12" MAX 12" MAX 12" MAX IS THE WINDOW PLUS 1/2" SHIMMING WINDOWS WINDOW'S WIDTH DIMENSION S'S EQUAL OR EQUAL OR EQUAL OR 12" MAX 12" MAX 12" MAX Window WINDOW Shimming SHIMMING ANDand Anchoring ANCHORING LOCATION Location Diagram DIAGRAM SHIM LOCATION FASTENER EQUAL OR EQUAL OR EQUAL OR 12" MAX 12" MAX 12" MAX FIGURE 1.3 Page 4 of 5

STEP 4: ANCHOR THROUGH THE NAILING FLANGE Line the window up in the prepared opening, shimming as necessary. See Figure 1.1. When square, attach at each corner with one fastener. Fasten the window snugly but do not tighten to the point of deforming the window frame, which would affect the operation of your new windows. Do not fasten to ceiling supports, drapery tracks, or other building components other than the intended rough opening substrate. Do not force the window into the opening; if it does not fit, it is probably the wrong window for the opening. The window should be anchored to allow for appropriate expansion and contraction of building movement. Before sealing the perimeter, mask the window face and insert the backer rod. After appropriately cleaning and priming the window and rough opening substrate per sealant manufacturer's instructions, seal all openings. NOTE: Always check window operations after anchoring corners. Carefully operate windows to ensure proper movement with no binding before final anchoring. NOTE: Complete cleaning instructions can be downloaded at: Windows, Patio Doors, Storefront Doors, and Stock Lengths by Boyd. PO Box 1565, Springfield, MO 65801.1565 2018 Boyd Aluminum Manufacturing Company. The Logo including the sunburst is a registered trademark of Boyd Aluminum Manufacturing Company. All rights reserved. 024A 04/18 Page 5 of 5