Standard PRC Coordination of Generating Unit or Plant Voltage Regulating Controls with Generating Unit or Plant Capabilities and Protection

Similar documents
Standard PRC Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection

Final ballot January BOT adoption February 2015

Standard PRC Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection

Final ballot January BOT adoption February 2015

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

VAR Generator Operation for Maintaining Network Voltage Schedules

Standard COM Communications

Standard MOD Verification of Models and Data for Generator Excitation Control Sys tem or Plant Volt/Var Control Functions

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

VAR Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR Voltage and Reactive Control

Standard Development Timeline

Standard TOP Monitoring System Conditions

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

VAR Generator Operation for Maintaining Network Voltage Schedules

VAR Generator Operation for Maintaining Network Voltage Schedules

VAR Generator Operation for Maintaining Network Voltage Schedules

(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in

VAR Voltage and Reactive Control

A. Introduction. VAR Voltage and Reactive Control

Standard MOD Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

VAR Voltage and Reactive Control. A. Introduction

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE)

5. Effective Date: On the first day of the first quarter, after applicable regulatory approval.

PRC Disturbance Monitoring and Reporting Requirements

WECC Standard VAR-002-WECC-2 Automatic Voltage Regulators

Standard Development Timeline

Standard MOD Area Interchange Methodology

August 25, 2017 VIA ELECTRONIC FILING

THIS DOCUMENT IS RETIRED BY FERC EFFECTIVE SEPTEMBR 5, 2018.

Standard Development Timeline

August 25, Please contact the undersigned if you have any questions concerning this filing.

Standard VAR b Generator Operation for Maintaining Network Voltage Schedules

Definition of Bulk Electric System Phase 2

Standard BAL Frequency Response and Frequency Bias Setting

Standard Development Timeline

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

Implementation Plan Project Modifications to PRC Reliability Standard PRC-025-2

Standard Development Timeline

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

1

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria

BEFORE THE ALBERTA ELECTRIC SYSTEM OPERATOR

Bulk Electric System Definition Reference Document

Cover Sheet. Technical Justification Retirement of WECC Regional Reliability Standard VAR-002-WECC-2 Automatic Voltage Regulators (AVR)

VAR Outreach Presentation

Industry Webinar Draft Standard

An Introduction to Completing a NERC PRC-019 Study for Traditional and Distributed Generation Sources

System Operating Limit Definition and Exceedance Clarification

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

No I am concerned about units that may be individually less than 20 MVA but collectively could eb much larger - wind farms. Yes

4.2.1 Generators Transformers Transmission lines. 5. Background:

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document

Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions

Setting and Verification of Generation Protection to Meet NERC Reliability Standards

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

Loss of Solar Resources during Transmission Disturbances due to Inverter Settings II

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Implementation Plan Project Alignment of Terms

May 30, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme Docket No. RM15-13-_

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Generator Voltage Protective Relay Settings

September 19, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme

Implementation Plan Project Balancing Authority Reliability-based Controls - Reserves

Unofficial Comment Form Project Geomagnetic Disturbance Mitigation

Generator Voltage Protective Relay Settings

INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

Voltage and Reactive Procedures CMP-VAR-01

BED INTERCONNECTION TECHNICAL REQUIREMENTS

APPENDIX 1 to LGIP INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Agenda Notes for 4 th Meeting of Sub Group in respect of Preparation of Reliability Standards for Protection System and Communication System

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

Transmission Interconnection Requirements for Inverter-Based Generation

Inverter Source Requirement Document of ISO New England (ISO-NE)

Southern Company Interconnection Requirements for Inverter-Based Generation

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

Power Plant and Transmission System Protection Coordination

Connection Impact Assessment Application Form

Meeting Notes Project Remedial Action Schemes Standard Drafting Team January 19-22, :00 p.m. 5:00 p.m. PT

TABLE OF CONTENT

Standard BAL b Automatic Generation Control

Transcription:

Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed: 1. SAR posted for comment (April 20 May 21, 2007). 2. Revised SAR and response to comments posted. 3. Revised SAR and response to comments approved by SC (June 14, 2007). 4. SDT appointed on (August 18, 2007). Proposed Action Plan and Description of Current Draft: This is the first draft of the proposed standard including Time Horizons, Data Retention, Violation Risk Factors, and Violation Severity Levels; and is being submitted for a 30-day formal comment period. Future Development Plan: Anticipated Actions Anticipated Date 1. Post first draft revision of standard. April-May 2011 2. Post response to comments and second version draft revision of July August 2011 standard. 3. Post response to comments and request authorization to ballot the revised standard. September - October 2011 4. Conduct initial ballot. November 2011 5. Post response to comments. December 2011 6. Conduct recirculation ballot. January 2012 7. BOT adoption. February 2012 8. File with regulatory authorities. March 2012 June 15, 2011 Page 1 of 10

A. Introduction 1. Title: Coordination of Generating Unit or Plant Voltage Regulating Controls with Generating Unit or Plant Capabilities and Protection 2. Number: PRC-019-1 3. Purpose: To improve the reliability of the Bulk Electric System by preventing tripping of generating units and generating Facilities due to mis-coordination of generating unit and generating Facility voltage regulating controls and limit functions with generator capabilities and protection system settings. 4. Applicability: 4.1. Functional Entities 4.1.1 Generator Owner 4.1.2 Transmission Owner 4.2. Facilities 4.2.1 Individual generating unit or synchronous condenser > 20 MVA (gross nameplate rating) connected at the point of interconnection at 100 kv or above. 4.2.2 Generating plant and generating Facility > 75 MVA (gross aggregate nameplate rating) connected at the point of interconnection at 100 kv or above. 4.2.3 Blackstart Resources, regardless of size included in a Transmission Operator s restoration plan. 5. Effective Date: 5.1. In those jurisdictions where regulatory approval is required: 5.1.1 By the first day of the first calendar quarter, one calendar year following applicable regulatory approval each Generator Owner and Transmission Owner shall have verified at least 20% of its applicable units. 5.1.2 By the first day of the first calendar quarter, two calendar years following applicable regulatory approval each Generator Owner and Transmission Owner shall have verified at least 40% of its applicable units. 5.1.3 By the first day of the first calendar quarter, three calendar years following applicable regulatory approval each Generator Owner and Transmission Owner shall have verified at least 60% of its applicable units. 5.1.4 By the first day of the first calendar quarter, four calendar years following applicable regulatory approval each Generator Owner and Transmission Owner shall have verified at least 80% of its applicable units. June 15, 2011 Page 2 of 10

5.1.5 By the first day of the first calendar quarter, five calendar years following applicable regulatory approval each Generator Owner and Transmission Owner shall have verified 100% of its applicable units. 5.2. In those jurisdictions where regulatory approval is not required: 5.2.1 By the first day of the first calendar quarter, one calendar year following Board of Trustees approval each Generator Owner and Transmission Owner shall have verified at least 20% of its applicable units. 5.2.2 By the first day of the first calendar quarter, two calendar years following Board of Trustees approval each Generator Owner and Transmission Owner shall have verified at least 40% of its applicable units. 5.2.3 By the first day of the first calendar quarter, three calendar years following Board of Trustees approval each Generator Owner and Transmission Owner shall have verified at least 60% of its applicable units. 5.2.4 By the first day of the first calendar quarter, four calendar years following Board of Trustees approval each Generator Owner and Transmission Owner shall have verified at least 80% of its applicable units. B. Requirements R1. Each Generator Owner and Transmission Owner with applicable Facilities shall coordinate its generating unit and generating Facility voltage regulating system controls, including limiters and protection functions with the generating unit and Facility or synchronous condenser capabilities and protective system settings; to include as applicable: [Violation Risk Factor: High] [Time Horizon: Long-term Planning] In-service 1 excitation system and voltage regulating system control, limiters and protection functions In-service generator or synchronous condenser protection system settings Generating equipment or synchronous condenser capabilities Steady state stability limit 1.1. This coordination requires the following steps: 1.1.1. Verify that the limiters are set to operate before the protection and the protection is set to operate before conditions exceed equipment capabilities (including the steady state stability limit) assuming normal AVR control loop and system steady state operating conditions. 1.1.2. Check that the settings determined in Step 1.1.1 are applied to the inservice equipment. 1.2. Each Generator Owner and Transmission Owner shall verify the existence of the coordination identified in Requirement R1 at least once every five years or within 1 Limiters or protective functions that are installed and activated on the generator or synchronous condenser. June 15, 2011 Page 3 of 10

90 calendar days following the identification or implementation of systems, equipment or setting changes that are expected to affect this coordination, including but not limited to the following Voltage regulating equipment changes Protection system settings or component changes Generating or synchronous condenser equipment capability changes Generator or synchronous condenser step-up transformer changes C. Measures M1. Each Generator Owner and Transmission Owner will have evidence, such as example plots provided in PRC-019 Section G, to show that its generating unit and generating Facility or synchronous condenser excitation system and voltage regulating system controls and protection functions are coordinated with the generating unit and generating Facility capabilities and protective system settings applied to in-service equipment as specified in Requirement R1, Section 1.1, and one previous dated set of evidence that demonstrates the latest coordination review has been done within the intervals specified in Requirement R1, Section 1.2. If the latest coordination review is performed due to a change in the equipment or settings that changes the coordination, the Generator Owner and Transmission Owner will have evidence (such as a work order) that demonstrates when the change was implemented. D. Compliance 1. Compliance Monitoring Process 1.1. Compliance Enforcement Authority Regional Entity 1.2. Data Retention Each Generator Owner and Transmission Owner shall keep data or evidence to show compliance as identified below unless directed by its Compliance Enforcement Authority to retain specific evidence for a longer period of time as part of an investigation: The Generator Owner and Transmission Owner shall retain the latest and the prior evidence of compliance with Requirement R1, Measure M1. If a Generator Owner or Transmission Owner is found non-compliant, it shall keep information related to the non-compliance until found compliant or for the time period specified above, whichever is longer. The Compliance Enforcement Authority shall keep the last audit records and all requested and submitted subsequent audit records. 1.3. Compliance Monitoring and Assessment Processes Compliance Audit June 15, 2011 Page 4 of 10

Self-Certification Spot Checking Compliance Violation Investigation Self-Reporting Complaint 1.4. Additional Compliance Information None 2. Violation Severity Levels R1 R # Lower VSL Moderate VSL High VSL Severe VSL The Generator Owner or Transmission Owner verified the coordination specified in Requirement R1 more than 90 calendar days but less than or equal to 100 calendar days following the identification or implementation of a change that affected the coordination. The Generator Owner or Transmission Owner verified the coordination specified in Requirement R1 more than 100 calendar days but less than or equal to 110 calendar days following the identification or implementation of a change that affected the coordination. The Generator Owner or Transmission Owner verified the coordination specified in Requirement R1 more than 110 calendar days but less than or equal to 120 calendar days following the identification or implementation of a change that affected the coordination. The Generator Owner or Transmission Owner failed to verify the existence of the coordination specified in Requirement R1 at least once every five years. OR The Generator Owner or Transmission Owner failed to verify the existence of the coordination specified in Requirement R1 within 121 calendar days following the identification or implementation of a change that affected the coordination. E. Regional Variances None. F. Associated Documents None. June 15, 2011 Page 5 of 10

Version History Version Date Action Change Tracking G. Reference Examples of Coordination The evidence of coordination associated with Requirement R1 may be in the form of one or more plots including (but not limited to): P-Q Diagram (Attachment 1), or R-X Diagram (Attachment 2), or Inverse Time Diagram (Attachment 3) These plots contain the equipment capabilities, the operating region for the limiters and protection function such as; under-excitation limiters, steady state stability limits, or loss of field protection curves. Additional limiters and protection function that are installed and inservice can be incorporated as an Inverse Time Limit/Protection Characteristic Plot (Attachment 3) or into the Generator Reactive Capability Curve Plot or an R-X diagram plot, identified above. Equipment limits, types of limiters and protection functions which could be coordinated include: Field over-excitation limiter and associated protection functions. Inverter over current limit and associated protection functions. Volts per hertz limiter and associated protection functions. Stator over-voltage protection system settings. Generator and transformer volts per hertz capability. Time vs. field current or time vs. stator current. Converter over-temperature limiter and associated protection function. NOTE: This listing is for reference only. This standard does not require the installation or activation of any of the above limiter or protection functions. June 15, 2011 Page 6 of 10

For the coordination required by this standard, the Steady State Stability Limit (SSSL) is the limit to synchronous stability in the under-excited region with fixed field current. On a P-Q diagram using X d as the direct axis saturated synchronous reactance of the generator, X s as the equivalent reactance between the generator terminals and the infinite bus including the reactance of the generator step-up transformer and V g as the generator terminal voltage (all values in per-unit), the SSSL can be calculated as an arc with the center on the Q axis with the magnitude of the center and radius described by the following equations C = V 2 g/2*(1/x s -1/X d ) 2 R = V g *(1/X s +1/X d ) On an R-X diagram using X d as the direct axis saturated synchronous reactance of the generator, and X s as the equivalent reactance between the generator terminals and the infinite bus including the reactance of the generator step-up transformer the SSSL is an arc with the center on the X axis with the center and radius described by the following equations: C = (X d -X s )/2 R = (Xd+X s )/2 June 15, 2011 Page 7 of 10

Controls with Generating Unit or Plant Capabilities and Protection Attachment 1 Example of Capabilities, Limiters and Protection on a P-Q Diagram June 15, 2011 Page 8 of 10

Controls with Generating Unit or Plant Capabilities and Protection Attachment 2 Example of Capabilities, Limiters, and Protection on an R-X Diagram June 15, 2011 Page 9 of 10

Controls with Generating Unit or Plant Capabilities and Protection Attachment 3 - Example of Capabilities, Limiters, and Protection on an Inverse Time Characteristic Plot June 15, 2011 Page 10 of 10