SeaGen S 2MW Anglesey Skerries

Similar documents
RENEWABLE ENERGY SOLUTIONS. oceaneering.com

Offshore Wind Risks - Issues and Mitigations

IHO Presentation Offshore Renewables

Tidal Energy. Transmission & Distribution Network. Wind Energy. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Challenges in the Construction of Offshore Wind Structures. Dr Ned Minns IT Power UK

James Fisher and Sons PLC. Marine Energy Supply Chain 14 th September 2017

Assessing Tidal Energy Resource

FOUNDATION ISSUES: OFFSHORE WIND FARMS Indian Context

Innovative marine & offshore solutions

Offshore Wind Floating Turbines

Emerging Subsea Networks

9/21/2017 DeepOcean Group 1

3. Existing uncertainties

Jørn Scharling Holm DONG Energy

Digital Data. Its use in geotechnical design & execution. Remedy Geotechnics Ltd. Dr Derek Egan Director.

THE MARINE PARTNER OF CHOICE

Sponsored by. Created and produced by

Vessels ROVs Trenchers & Ploughs. // 1,000 employees // 11 offices in 7 countries. (NL, Norway, UK, Brazil, Mexico, Singapore, Ghana)

Survey and Geosciences. Capability & Experience

The offshore wind puzzle getting the pieces right

The potential for windpower in the Baltic Sea

Optimizing wind farms

Oil and gas diversification Offshore wind NORWEP

HELIX ENERGY SOLUTIONS

SIMON HINDLEY MENG, AMRINA MANAGING DIRECTOR, NAVAL ARCHITECT

Onshore & Offshore Engineering and Management of Subsea Cables and Pipelines

Moorings & Foundations Richard Yemm

Wave & Tidal Safety & Construction Guidelines

MARISSUBSEA.com. Core Values. People. Integrity. Quality. Contents. 02/03 What we do. 04/05 Representatives. 06/07 ROV personnel

Oil and gas diversification Offshore wind NORWEP

Conductor Installation Services. Today s technology traditional values

saipem limited Statoil 2/4S Removal Project GASSCO HSE Summit Removal of the Statoil 2/4 S Platform 23 rd October 2014

Innovative marine & offshore solutions

5.1 Optimal integrated combination of foundation concept and installation method

Next generation WTG foundation and WTG installation. WindDays Rotterdam, 14 June 2018 Arnoud Bosch Engineering Director

Research, testing and demonstration.

Kinsale Area Gas Fields Decommissioning Project Information Leaflet

OUT TO SEA Offshore Geotechnical Investigation

Technological and Logistical Challenges during Construction & Installation of Deepwater Mega Subsea Development in West Africa

Delivering Subsea Solutions Using a Systems Engineering Approach

Ecosse Subsea Systems. Subsea Springboard 2017 David Hunt

Founding Manifesto Friends of Floating Offshore Wind 18 May 2016

SUBSEA SYSTEM ARCHITECTURE FOR CORAL SOUTH FLNG

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015

NER300 Offshore Wind Park Nordsee One. Tobias Griesshaber Shareholder representative of Innogy SE on behalf of project Nordsee One GmbH

--.. G-tec. Geophysics I Geotechnics I E nv1ronment

Dry trees for cost effective solution with the Wellhead Barge: WHB

Conductor Integrity Management & Solutions

Opportunities for Offshore Wind Development in the U.S.

Phil de Villiers 17 April Offshore Wind Accelerator (OWA)

Capability Statement: Offshore & Marine Projects

Falmouth Bay Short Term Test Site for Marine Energy Converters

Coastal Virginia Offshore Wind partnership with Orsted. February 2018 Update

RESEARCH, TESTING AND DEMONSTRATION

Emergency Pipeline Repair Solutions and Future Contingency Planning

ORE SuperGen Marine Challenge Workshop. Jeremy Thake Head of Engineering

Torgeir Ramstad Managing Director, Fred. Olsen United. European projects: Being part of the global supply chain

Site Surveys for Offshore Windfarms: How to Spend your Money Wisely in an Age of Austerity

Derek Robertson. 5 December 2018 SUBSEA MICROPILES PROPRIETARY

Global Subsea University Alliance: Subsea education and research programs. Prof Brian Evans Curtin University, Perth Australia

Morgan Stanley Houston Energy Summit

Workshop on Offshore Wind Energy Standards and Guidelines: Metocean Sensitive Aspects of Design and Operations in the United States July 17, 2014

Lowering The Cost Of Marine Energy With Affordable Subsea Connection Solutions

Remotely Operated Seabed Geotechnical Drilling and Sampling Technology. Performance and Benefits of an Automated System.

Well Abandonment Services. Plug into a New Approach

INTERNATIONAL. June 2017 Volume 13. A Buoyant Future. Reducing Cost and Risk in Floating Offshore Wind

WAVE & TIDAL SERVICES WAVE & TIDAL

Learn more at

A marginal field (re-)development using several alternative methodologies 1

ORJIP Bird Collision Avoidance Study. Sonja Pans (DHI Water Environments UK Ltd)

The future of offshore wind in the US

Marine Renewables Commercialisation Fund: Array Technology Innovation Programme. Angus Vantoch-Wood

Neart na Gaoithe Offshore Wind Farm. Project Update 2018

OFFSHORE CLAMP PRODUCT GUIDE INTELLIGENT ENGINEERING

Offshore wind what s it all about? 01/11/2017 Owen Murphy & Andrew Tipping

Getting to Grips with Offshore Handling and Assembly of Wind, Wave and Tidal Devices

Energy Transition Partner. Created and produced by

Seabed and wind farm interaction. A Research Program. B. Mutlu Sumer DTU Mekanik

Control of Floating Wind Turbines

by Tim Baker & Keith O Sullivan

Oil and Gas Diversification: High Potential Areas, Key Challenges (Operations & Maintenance) BVG Associates ~ Alan Duncan

Latest Developments in Subsea Wellhead and Riser Fatigue Monitoring

Vincent/Enfield Conductor and Flowbase Installation Review. Roy Grant, TSMarine

Subsea infrastructure in MRE ICOE November 6, By Don Bryan, BSc, MBA General Manager Pacific Northwest Operations

Exploring the impact of innovative developments to the installation process for an

Advances in Subsea Integrity Monitoring Systems. Ross Macleod Business Development Director, Ashtead Technology

Latest Evolution of Vessel Lay Equipment, to Meet the Challenges of Deepwater Installations. SUT Perth, 14 th February 2018

Accelerating the Deployment of Offshore Renewable Energy Technologies. IEA Implementing Agreement on Renewable Energy Technology Deployment

WORLD CLASS through people, technology and dedication WORLD CLASS through people, technology and dedication

UK offshore wind industry progress to cost reduction

i. Shoring layout. ii. Shoring sections and details (including anchor details, if required).

Update on Ireland Marine Renewables Infrastructure Industry Research. Raymond Alcorn

Cathodic Protection & Monitoring

Strategic Innovation Acceleration - UK marine energy industry: pathway to commercialisation Simon Robertson

This document is a preview generated by EVS

Richard Rickett, General Manager Engineering and Procurement - March Case Study

monopile gripper arms

Lessons Learned Abroad: Cable Best Practices as Examined in London Array and Walney. Howard Kidorf

Orkney Electricity Network Reinforcement Stakeholder Consultation Response. August 2014

Offshore Wind Project Logistics & Unique Site Technology Investigation Fabrication - Installation

Transcription:

Presenter Phil Wilkinson SeaGen S 2MW Foundations @ Anglesey Skerries Answers for energy.

Introduction Page 2

Introduction Phil Wilkinson 20 years experience in offshore marine construction, large diameter drilling and specialist pile installation. Noteable Projects:- North Hoyle OWF - 2003 Flamanville EPR Shaft - 2008 Today s Presentation MCT & History MCT s Tidal Technology Anglesey Skerries Tidal Array - Foundation Requirement Anglesey Skerries - Ground Investigation Discussion & Lessons Learned Page 3

MCT Page 4

MCT Pioneering Bristol based tidal developer First device install in Loch Linnhe, Scotland, in 1994-5, 15kW Second device SeaFlow installed offshore Lynmouth, North Devon in 2003, 300kW test device Third device SeaGen (full scale, grid compliant) installed in 2008, Strangford Narrows, Northern Ireland, 1.2MW Now 100% owned by Siemens, since early 2012 Page 5 5

First Tidal Turbine Array SeaGen S 2MW - Commercial Array 2016 (Planned) Anglesey Skerries, North Wales 3 x SeaGen S 2MW Tidal Current Turbines Page 6 6

The Technology SeaGen S 2MW Page 7

SeaGen S 2MW - Technology SeaGen S 2MW Tidal Turbine Generator Development of the 1.2MW device Surface piercing tower with raisable crossbeam 2 x 1MW drivetrains 3 x variable pitch blades per rotor Tripod foundation Modular topside with power conditioning, exporting grid compliant electricity Page 8

SeaGen S 2MW - Skerries Loads SeaGen S 2MW - Skerries Loads Skerries 50 yr wind = 35 m/s Wind Skerries 50 yr wave = 7.1 m Hs Wave ~50m Skerries 50 yr current = 4.8 m/s + loads due to tide, turbulence, storm surge, temperature, ice/snow, collision etc Current Conclusion = A significant lever arm requiring robust fixity to seabed! Page 9

SeaGen S 2MW - Foundations Foundation Piles 3 x pin piles per device Pile diameter 1.2-1.3m Tubular steel pile installed into circa 1.4-1.5m diameter x 10m deep rock socket Connection between pile and rock, and pile and foot-sleeve to be grout Purpose/Design To transfer all axial, torsional and moment loads from device to the ground To maintain within fatigue (FLS) and ultimate limit state (ULS) design for device lifetime, 20 years Page 10

Foundation Design Requirements SeaGen S 2MW - Anglesey Skerries Page 11

Foundation Design Requirements We need to know loads and what it is to be fixed to... In early 2012, what we knew.. Environmental loads Soil & seabed conditions Geotechnical Desktop Data - SEtech 2009 Geophysical data - EMU 2009 Geotechnical data -?? Note - foundation design requires 15m sample depth, ideally 3 holes across representative area of the site Conclusion We knew the seabed was mainly made of rock, but we could not confirm rock characteristics or overburden details from geophysical data alone, hence geotechnical sampling and lab testing potentially required. Page 12

Geotechnical Survey Options SeaGen S 2MW - Anglesey Skerries Page 13

Geotechnical Survey Options Option 1 Do nothing, estimate rock strength & characteristics from desktop & geophysical data Option 2 Diver with drill Comments Current Foundation design not robust enough to rely on this. Current geophysical survey equipment gives limited subbottom information, unless expensive equipment used. Comments Has been done before. May give cheap solution but small length of core and diver working in tidal regime, so not ideal. Page 14

Geotechnical Survey Options Option 3 Small scale seabed drill Comments Single shot up to 5m core sample. Doesn t meet the sample depth requirement for foundation pile design. Option 4 Full site investigation works, with jackup or DP vessel Comments Meets all technical requirements. One of the most expensive options and generally a long lead, or potentially opportunistic? Page 15

Geotechnical Survey Options Option 5 Seabed carousel drill Comments Can be deployed from a variety of vessels. Meets the sample depth requirement for foundation pile design, and can be cheaper than conventional techniques. Conclusion The option which satisfied the sample depth requirements and was the most cost effective option (at the time) was Option 5, the remotely operated seabed drill rig. Page 16

Geotechnical Site Investigation SeaGen S 2MW - Anglesey Skerries Page 17

Geotechnical Site Investigation Skerries Site Page 18

Geotechnical Site Investigation Plant Marine Support Vessel DP2 Multi-use Deep Cygnus Drill Subsea Drill ROVDrill 2 Page 19

Geotechnical Site Investigation Operations Deck layout Deploying Drill Page 20

Geotechnical Site Investigation Drill Carousel showing drill rods Drill Page 21

Geotechnical Site Investigation Sample Returns Inspecting core samples Core samples Page 22

Geotechnical Site Investigation Temporary Logged Sample Page 23

Lessons Learned SeaGen S 2MW - Anglesey Skerries Page 24

Lessons Learned Overall Success!!!! Samples were recovered to surface and of decent enough quality to test. However The scope of works was for 3 number boreholes to a depth of 15m each. Whereas, only 2 locations were drilled and only one of those was to 15m... Why..and more importantly, what did we learn? Page 25

Lessons Learned Technical Appraisal DP2 vessel proved it could work outside the typical operating tidal current limit. ROVDrill 2 experienced problems stabilising itself on seabed, due to boulders & rocky outcrops. Learning curve problems were encountered during the first hole, and on such short duration works, on-site learning is not viable. Visibility was much less than expected at the site adding to difficult working conditions. Commercial Appraisal As is typical in the industry where specialist short duration works are required, the contract was day-works; at the same time performance warranties were limited, hence when the budget for the works was used up further sampling was not possible. Result Inferior core recovery resulted in less than ideal data for foundation design. Therefore foundation design is less efficient, and potentially more expensive, plus further sampling is being considered for project de-risking. Page 26

Next Steps & The Future SeaGen S 2MW - Anglesey Skerries Page 27

Next Steps & The Future Next Steps - Skerries Additional geophysical data was acquired in 2013, which has been incorporated into the overall geo data set; hence device micro-siting is complete. There is enough geotechnical information to design the foundations. The Future - Questions to answer.. For future tidal sites to be viable can we afford to go down the same route as offshore wind and sample on each foundation location? A mitigation for this is to design more robust foundations, which need less soil data. However, maybe we should adopt a more pragmatic approach to foundation design - review guidance? Seabed conditions on tidal sites is typically rock with limited overburden, hence the above philosophy lends itself to the solution. Are physical boreholes really required to 15m in the rock for a 10m foundation, would a 5m core suffice, and how many cores per device site/project? Latest geophysical survey techniques together with quality desktop study, and sampling using cheaper (shorter sample) coring tools may be adequate e.g. BGS rock corer? Maybe novel geophysical survey tools that can achieve the required sub-bottom profile information? Reducing overall project capex is key to future of renewable projects, we should adopt a pragmatic approach to foundation design and geotechnical investigation requirements. Page 28

Thanks Thank you for listening Questions? Page 29