ANASAC, September 20, 2012

Similar documents
ALMA. ALMA Construction Status. Mark McKinnon. ALMA-NA Project Director/Manager September 28, 2011

ALMA Interferometer and Band 7 Cartridge

Atacama Large Millimeter Array Project Status. M. Tarenghi ALMA Director

ALMA Assembly, Integration and Verification: Overview and Work Plan

Recreation Facility Hours

Time and Frequency Distribution Overview and Issues Rob Selina

UDW Technology Conference Dan McLeod / John Jacobson Lockheed Martin MS2 July 27, Secure Energy for America

Metrological Telecommunication System Development Project

Computing IPT. B.E. Glendenning (NRAO) J. Ibsen (JAO) G. Kosugi (NAOJ) G. Raffi (ESO) Computing IPT ALMA Annual External Review October

Planning ALMA Observations

PLATO Preliminary Requirements Review Technical Report

The Atacama Large Millimeter/submillimeter Array: Current Status. Alison Peck Deputy Project Scientist Joint ALMA Office

Massport Capital Programs Enterprise Schedule Management. Primavera Schedule Toolkit Design. January 2018 Version 1.0

Quarterly Status Update (QSU) January March 2010

Prime Focus Imaging Spectrograph

GPS Modernization and Program Update

Integration of Band 5 receivers at ALMA/JAO. Giorgio Siringo Senior RF Engineer & FrontEnd Technical Lead - JAO on behalf of the B5 integration team

Active Cable TV Connections. Active Residential Cable Modem Customers. Page FIRST QUARTER REPORT

The Second Health Information Technology Summit

Results for the Three-Month Period Ended June 30, 2013

Helioseismic Magnetic Imager Program at LMSAL

HPS Upgrade Proposal

THIS REPORT CONTAINS ASSESSMENTS OF COMMODITY AND TRADE ISSUES MADE BY USDA STAFF AND NOT NECESSARILY STATEMENTS OF OFFICIAL U.S.

Technical Considerations: Nuts and Bolts Project Planning and Technical Justification

Site Surveys for Offshore Windfarms: How to Spend your Money Wisely in an Age of Austerity

EVLA Project Book, Chapter 4 4 Antennas and Feeds. Jim Ruff, Ed Szpindor, S. Srikanth Last changed 2002-Feb-28

Planning (VLA) observations

Technologies for Radio Astronomy Mark Bowen Acting Theme Leader Technologies for Radio Astronomy October 2012 CSIRO ASTRONOMY AND SPACE SCIENCE

Rochester Institute of Technology. Wildfire Airborne Sensor Program (WASP) Project Overview

Research and Statistics Department FOR RELEASE 8:50 A.M. Monday, May 28, 2018

Special Notice # N R-S002 - Frequently Asked Questions #1

Space Technology FY 2013

Estimation of Fault Resistance from Fault Recording Data. Daniel Wong & Michael Tong 2014-November-5

Emergency Pipeline Repair Systems; A Global Overview of Best Practice

Table 5.1 Specifications for The Evaluation Receivers (33-45?) GHz HFET amplifier GHz SIS mixer GHz (HFET amp covers GHz)

NATIONAL INSTITUTE OF ECONOMIC AND SOCIAL RESEARCH ESTIMATES OF MONTHLY GDP. Embargo until hours on 11 th January 2013

Space and Missile Systems Center

Bridge Condition Assessment Using Remote Sensors

ECSEL JU Update. Andreas Wild Executive Director

RADIOMETRIC PERFORMANCE OF THE CRIS INSTRUMENT FOR JPSS-1

Preparation of requirements. Part I Notification principles and time schedule

Miniature Deployable High Gain Antenna for CubeSats

NASA Space Exploration 1 st Year Report

Doug Dunn ASML President and Chief Executive Officer Deutsche Bank Conference London, England September 19, / Slide 1

Innovative Approaches in Collaborative Planning

ANTENNAS. ALMA Project Book, Chapter 4. Jeffrey Kingsley and Jaap Baars Last revised 2002-JAN-12

Seaworthy Quantum Key Distribution Design and Validation (SEAKEY) Contract Period of Performance (Base + Option): 7 February September 2016

Proposal Smart Vision Sensors for Entomologically Inspired Micro Aerial Vehicles Daniel Black. Advisor: Dr. Reid Harrison

CYGNSS Mission Update

VAN BUREN COUNTY TENNESSEE

European Workgroup. 7th May 2015

Information Warfare Research Project

When Failure Means Success: Accepting Risk in Aerospace Projects NASA Project Management Challenge 2009

Hydrocarbon Production Operations

Research and Statistics Department FOR RELEASE 8:50 A.M. Thursday, October 26, 2017


Maldives: Strengthening Capacity for Operations Management

Village of Glenview Appearance Commission

Software as a Medical Device (SaMD)

RDT&E BUDGET ITEM JUSTIFICATION SHEET (R-2 Exhibit)

Economic & Real Estate Outlook. Tax Reform. Michigan 4/26/18

Appendix-1. Project Design Matrix (PDM)

NPN Silicon Planar High Voltage Transistor

SAW components. SAW RF filter Digital radio. RF360 Europe GmbH A Qualcomm TDK Joint Venture. Date: April 26, 2017 Version: 2.1

Canon Digital-Ixus V Jun 2001

SAW components. SAW RF filter Short range devices. RF360 Europe GmbH A Qualcomm TDK Joint Venture. Date: September 15, 2017 Version: 2.

Maritime Telecommunication System Development Project (3)

ASX CHESS Replacement Project Webinar

Ultra Low Jitter LVPECL or LVDS Clock

NOTICE OF THE 5TH ANNUAL GENERAL MEETING OF SHAREHOLDERS

Evolution of the Capabilities of the ALMA Array

Ku-Band Receiver System for SHAO

Start Date. Census Date Delivery Mode EFTSL Unit Fee. End Date

CMT 12th LPG Trade Summit Oct, Dubai, U A E

The North America Array

Data Digitization & Transmission Session Moderator: Chris Langley

ABSTRACT. Keywords: ESSP, Earth Venture, program management, NASA Science Mission Directorate, Class-D mission, Instrument-first 1.

COS NCM2 Mirror Substrate Specification

Raven a scientific and technical Multi-Object Adaptive Optics (MOAO) demonstrator

PLETRONICS NCF4 Series

ACA; Atacama Compact Array

The world s largest oil discovery Melbourne Mining Club Cutting Edge Series 15 March 2016

Bourns Transformers Now Available in Lead Free Versions

MADISON PUBLIC LIBRARY PINNEY PINNEY LIBRARY COMMUNITY UPDATE 11 / 09 / 2017

Legislative Joint Transportation Committee Meeting. Arkansas Convention Center Texarkana Thursday, November 21, 2013

PROTECTING mmparadise. Eduardo Hardy

EVLA Science Operations: the Array Science Center. Claire Chandler NRAO/Socorro

OPTICS OF SINGLE BEAM, DUAL BEAM & ARRAY RECEIVERS ON LARGE TELESCOPES J A M E S W L A M B, C A L T E C H

The WVR at Effelsberg. Thomas Krichbaum

LV55D Series 3.3 V LVDS Clock Oscillators February 2016

ANTENNAS. ALMA Project Book, Chapter 4. Torben Andersen and Peter Napier Last changed 2000-Dec-11. Summary

Research and Innovation in Science and Technology Project (P121842)

Model 653 Very Low Jitter LVPECL or LVDS Clock

Industrials China paper

SAW components. SAW RF Uplink 2in1 input diplex filter Base stations LTE band 5 and 13. RF360 Europe GmbH A Qualcomm TDK Joint Venture

Deepwater riserless (RLWI) enablers for increased oil recovery. Bringing shallow water experience to deepwater.

LV77D Series 2.5 V LVDS Clock Oscillators November 2018

MR. DAVID DALE, PE, PMP, SES DIRECTOR, Programs Great Lakes & Ohio River Division. 14 May Braddock Dam

UkrGasVydobuvannya Public invitation for Expression of Interest for participation in the project of gas production enhancement

GLOBAL RIG AND OFFSHORE CONSTRUCTION MARKETS

Transcription:

ANASAC, September 20, 2012 Construction Mark McKinnon Atacama Large Millimeter/submillimeter Array Karl G. Jansky Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array

Antennas at the AOS 64 of 66 antennas at the site (25 NA, 16 EA, 23 EU) 53 antennas accepted (24 NA, 16 EA, 13 EU) 44 through AIV All EA antennas conditionally accepted as of Aug 23, 2012 40 antennas at the AOS (18 NA, 12 EA, 10 EU) ANASAC, September 20, 2012 2

Vertex Antennas - I 24 Vertex antennas accepted. DV24 conditionally accepted on Sep 12, 2012 DV25 Panel installation and photogrammetry complete. Acceptance delayed until mid-oct due to late delivery of encoder Tiltmeter replacement Ethanol-based electrolyte freezes at low temperatures Replaced with methanol-based solution Completed on 22 antennas Surface adjuster replacement Over-torqued adjusters caused depressions in antenna surface Revised installation procedure for proper torque Completed on all affected antennas (DV01-DV11)in Aug ANASAC, September 20, 2012 3

Vertex Antennas - II DV25 from Kilgore on Apr 10 (above) DV25 BUS install on Jul 9 (left) Kilgore project team (lower left) Kilgore integration team (below) ANASAC, September 20, 2012 4

Surface Imperfections on Vertex Antennas - I Astro -holography conducted at AOS shows temperature-dependent imperfections in surfaces of some Vertex antennas (0.8-1.4 um RMS/deg C) Surface pattern appears astigmatic In some cases, magnitude of astigmatic term approaches 25um RMS However, term is not necessarily a proxy for total surface RMS AEM antennas show similar, but smaller effect (< 0.5 um RMS/deg C) Tests indicate effect not due to subreflector or receiver Tower -holography at OSF also indicates temporal dependence Next steps Correct astro-holography analysis for inadvertent inclusion of holography feed correction and report results as total surface RMS to Vertex Consolidate results on temporal dependence from tower holography and report as total surface RMS to Vertex Vertex committed to resolving problem; test preliminary ideas on DV12 ANASAC, September 20, 2012 5

Surface Imperfections on Vertex Antennas - II Astigmatism component vs temperature, DV08 Difference map of DV02 T = 9.3 C elev = ~20 deg t = 3 hours ANASAC, September 20, 2012 6

Optical Pointing Telescope (OPT) OPTs used to verify pointing performance of antennas. Prototype units now in use for NA and EU antennas OPT design revised to minimize thermal effects Status of 4 remaining units Units 1-3 at OSF Factory acceptance completed at vendor facility in Tucson On-antenna tests for Unit 1 completed; JAO acceptance to be held upon delivery of test report Unit 4 assembled; deliver to OSF after factory acceptance ANASAC, September 20, 2012 7

Nutator Chopping secondary (5) used for total power measurements Delayed due to issues with servo control of secondary and stiffness of mirror back plate Factory acceptance of first unit still scheduled for mid-oct 2012 Anticipate on-antenna tests in Nov Four remaining units to ship to Chile in Jan 2013 Three mirrors at coating vendor (CMA) in Tucson for resurfacing using new 3-layer process. CRE to document changes in nutator performance specifications in preparation. ANASAC, September 20, 2012 8

Site AOS Roads All 67km completed in late Apr JAO acceptance review on Nov 1 AOS Utilities (fiber and electrical power to antenna stations) Utilities work estimated at 85% complete as of Aug 31 Contractor remobilized to site this month after Chilean winter Estimate completion in Dec 2012 2 arbitration cases resulting from termination of original Utilities contract E&K vs AUI: E&K sought ~$5M for profit loss & damages Resolved in AUI s favor on May 30; no reparations due E&K AUI vs E&K insurance company, for refusing to pay performance guarantee (~$1M) on contract termination. Process terminated on Jul 31 with no decision New process to be initiated; use E&K result as supporting evidence ANASAC, September 20, 2012 9

Front End 59 assembled Front Ends (FEs) delivered to Chile (22 EA, 20 NA, 17 EU) NA FEIC assembly status: 20 of 22 NA FEs shipped to Chile 2 remaining units to ship in Sep 2012 Delivery of NA FE components complete! Production of Band 3 CCAs completed in Feb 2012 Production of Band 6 CCAs completed in Aug NA FEs on schedule despite delay caused by ITAR export control issue. NA could not deliver FEs and components or have technical discussions with partners until issue resolved. US Department of State determined that FEs are not subject to ITAR export control on Jun 15 Plan developed to ship FE test measurement system from NA FEIC to OSF Integration of Band 4, 8 & 10 to occur at OSF, instead of EU & NA FEICs ANASAC, September 20, 2012 10

Band 3 CCAs HIA Feb 20, 2012 ANASAC, September 20, 2012 11

Front End Service Vehicle (FESV) FESVs (2) are used to transport FEs to/from AOS antennas/osf. Fabricated in Taiwan FESV1 accepted on Aug 30, 2011 FESV2 accepted Dec14, 2011 ANASAC, September 20, 2012 12

Front End Handling Vehicle (FEHV) Custom cart (4) designed to move FEs between the FESV and antennas Designed and fabricated in Chile CDR on December16 Antenna IPTs confirmed antennas can accommodate additional weight of FEHV In process of verifying maneuverability within AEM antennas Deliver 4 months after delta-cdr Pallet jack used in interim ANASAC, September 20, 2012 13

Backend, Correlator, and Computing Backend (BE) Central Local Oscillator Article completed in Aug 2011 All BE components delivered Correlator Fourth quadrant installed in AOS Technical Building Turnover to CSV to occur on Sep 21 Computing Currently restricted to 32 antenna operation because of memory allocation problem. Software modification underway. Final release of software (R9.1) under the construction project is now in use by CSV R9.1 to be implemented for Cycle 0 observations by Oct 3 ANASAC, September 20, 2012 14

Operations Organization Ops AD M. McKinnon (Interim) NAASC A. Woo&en (Interim) OCA M. Pilleux Off- site Hardware TBD Offsite So;ware B. Glendenning Development B. Randolph Transition of construction staff to operations largely complete Transition was managed & targeted a planned organizational structure Search for NRAO AD for -NA Operations is nearing completion ANASAC, September 20, 2012 15

Construction Budget Project-wide cost to complete exercise is underway Current estimate is budget is sufficient to complete the project Very little margin to cover risk Increased costs in NA Site IPT Unfavorable currency exchange rate Increased scope of work (e.g. gas pipeline crossing) Increased fuel costs Legal fees for E&K arbitrations ANASAC, September 20, 2012 16

Schedule Major remaining milestones End of construction review Oct 2012 Power generation transition Oct 2012 AOS Utilities complete (NA) Dec 2012 Delivery of last FE (EU) Feb 2013 Inauguration Mar 2013 Delivery of last antenna (EU) Jul 2013 66 antennas in service Sep 2013 Residencia complete (EU) Dec 2014 ANASAC, September 20, 2012 17