Status of the ESS Accelerator Workpackage

Similar documents
The European Spallation Source. Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013

Strategy for the engineering integration of the ESS accelerator

Beam Loss Monitoring (BLM) System for ESS

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University

FREIA Facility for Research Instrumentation and Accelerator Development Infrastructure and Control Architecture

Plans for the ESS Linac. Steve Peggs, ESS for the ESS collaboration

Interfaces with MPS/PSS

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008

ESS Beam Diagnostics Overview. Andreas Jansson, ESS/BI Group IBIC12, Tsukuba, Japan

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE

DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY -

Niowave s Growth and the Role of STTR in its Development

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES

ESS Status and Prospects

ESS Naming Convention

Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension

PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC

The European Spallation Source

ESS Accelerator Design Update Work Packages

5.5 SNS Superconducting Linac

Status of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY

THE CRYOGENIC SYSTEM OF TESLA

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM

Packaging of Cryogenic Components

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University

Motivation: ERL based e linac for LHeC

ESS Naming Convention

Status and Future Perspective of the HIE-ISOLDE Project

Cryogenics, Cryomodule & Superconductivity for Accelerator Programme in Asia

COMMISSIONING AND INITIAL OPERATING EXPERIENCE WITH THE SNS 1 GEV LINAC*

Third Harmonic Superconducting passive cavities in ELETTRA and SLS

Aurélien Ponton. First Considerations for the Design of the ESS Cryo-Modules

Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience

Neutron spallation sources and the status of ESS (under construction)

SPOKE CRYOMODULES CONCEPTUAL DESIGNS FOR ESS & MYRRHA

CURRENT INDUSTRIAL SRF CAPABILITIES AND FUTURE PLANS

Alban Mosnier. CEA-Saclay, DSM/IRFU. Alban Mosnier Sept 29 - Oct 3, 2008 LINAC'08 Victoria British Columbia Canada page 1

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY

Current Industrial SRF Capabilities and Future Plans

Maurizio Vretenar Linac4 Project Leader EuCARD-2 Coordinator

ESS Naming Convention

Status Report. Design report of a 3 MW power amplifier

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

SPES Control System. M. Bellato

Beam Control: Timing, Protection, Database and Application Software

ReA3 Marc Doleans (On behalf of the ReA3 team)

Development of Superconducting CH-Cavities for the EUROTRANS and IFMIF Project 1

CEBAF Overview June 4, 2010

To produce more powerful and high-efficiency particle accelerator, efforts have

R.Bachimanchi, IPAC, May 2015, Richmond, VA

BEAM DYNAMICS SIMULATIONS ON THE ESS BILBAO RFQ

SUPERCONDUCTING CAVITIES AND CRYOMODULES FOR PROTON AND DEUTERON LINACS

Linear Particle Accelerator Control Performance

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS

ESS-Bilbao Contribution to ESS Warm LINAC High Power RF Systems

ESS RF Source and Spoke Cavity Test Plan

SNS CRYOMODULE PERFORMANCE*

A Superconducting Proton Linac for the ESS-Bilbao Accelerator

SPALLATION NEUTRON SOURCE OPERATION AT 1 MW AND BEYOND*

Superconducting RF System. Heung-Sik Kang

Work Package Status Report

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7

Superstructures; First Cold Test and Future Applications

Title: Research and Development on Superconducting Radio-Frequency Technology for Accelerator Application

ACCELERATOR PHYSICS OF HIGH INTENSITY PROTON LINACS

DESIGN STUDY OF A 176 MHZ SRF HALF WAVE RESONATOR FOR THE SPIRAL-2 PROJECT

FLASH at DESY. FLASH. Free-Electron Laser in Hamburg. The first soft X-ray FEL operating two undulator beamlines simultaneously

System Integration of the TPS. J.R. Chen NSRRC, Hsinchu

SNS LLRF Design Experience and its Possible Adoption for the ILC

Progresses on China ADS Superconducting Cavities

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT

Demonstration of exponential growth and saturation at VUV wavelengths at the TESLA Test Facility Free-Electron Laser. P. Castro for the TTF-FEL team

Beam Loss monitoring R&D. Arden Warner Fermilab MPS2014 Workshop March 5-6, 2014

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF

Amit Roy Director, IUAC

Structures for RIA and FNAL Proton Driver

Crab Cavities for FCC

Non-invasive Beam Profile Measurements using an Electron-Beam Scanner

REVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES. S. Belomestnykh

Advances in CW Ion Linacs

Advance on High Power Couplers for SC Accelerators

SARAF commissioning & safety issues. L. Weissman on behalf of the SARAF team SPIRAL week 2010

Physical Design of Superconducting Magnet for ADS Injection I

Engineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team

Superconducting 1.3 GHz Cavities for European XFEL

OVERVIEW OF THE HIGH INTENSITY NEUTRINO SOURCE LINAC R&D PROGRAM AT FERMILAB *

Present and future beams for SHE research at GSI W. Barth, GSI - Darmstadt

Cryogenics for Large Accelerators

ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY

HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK

A few results [2,3] obtained with the individual cavities inside their horizontal cryostats are summarized in Table I and a typical Q o

DEVELOPMENT OF ROOM TEMPERATURE AND SUPERCONDUCTING CH-STRUCTURES H. Podlech IAP, Universität Frankfurt/Main, Germany. Abstract

Using Higher Order Modes in the Superconducting TESLA Cavities for Diagnostics at DESY

DEVELOPMENT OF CAPACITIVE LINEAR-CUT BEAM POSITION MONITOR FOR HEAVY-ION SYNCHROTRON OF KHIMA PROJECT

PROJECT X: A MULTI-MW PROTON SOURCE AT FERMILAB *

200 MHz 350 MHz 750 MHz Linac2 RFQ2 202 MHz 0.5 MeV /m Weight : 1000 kg/m Ext. diameter : 45 cm

Transcription:

Status of the ESS Accelerator Workpackage Peter McIntosh STFC Daresbury Laboratory UK ESS Interactions and Opportunities Rutherford Appleton Laboratory 3 Dec 2014

The ESS Linac The European Spallation Source (ESS) will house the most powerful proton linac ever built: Average beam power of 5 MW. Peak beam power of 125 MW Acceleration to 2 GeV Peak proton beam current of 62.5 ma Pulse length of 2.86 ms at a rate of 14 Hz (4% duty factor) 97% of the acceleration is provided by superconducting cavities. The linac will require over 150 individual high power RF sources: With 80% of the RF power sources requiring over 1.1 MW of peak RF power. Expect to cost over 200 M on the RF system alone! 2

Top-Level ESS Project Schedule 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Start Of Construction Construction End Of Construction 3 ESS Program Conventional Facilities Accelerator Target Neutron Scattering Systems Integrated Control Systems Design Design Construction Building Commissioning Design & Prototyping Procurement Design Procurement Concept Devlopment Design Design Development Ground Break Installing Commissioning Licensing Preliminary Design Acccelerator Bldngs Detailed Design Accelerator Bldngs Construction Installation Commissioning Installation Commissioning Commissioning First installations (of Machine Systems) Earth Works G01 Linac Tunnel G02 Klystron Bldng Cryo Kompressor Bldng Commissioning First Neutrons Machine 2.0 GeV Concluding Initial Operation Accelerator, Target, Aux, Office, Lab & Instr Bldngs* Medium Beta Fabrication Spoke Series Procurement High Beta Fabrication 570 MeV Installation Phase 1 CS Network Operational Instrument Selection - Decision 3 Instruments ready for Comm. Innstr 16 Constr & Inst. 1st Call for User Proposals Installed for 2.0 GeV Installation Phase 2 Innstr 16 Cold Comm. 16 Instr

ESS Linac Evolution 1992 2013 4 4

New Baseline New Baseline Headline Parameters: 5 MW Linac 2.0 GeV Energy (30 elliptical cryomodules) 62.5 ma beam current 4% duty factor (2.86 ms pulse length, 14 Hz) First beam by 2019 (1.0 MW at 570 MeV) The new baseline was achieved by: Increasing beam current by 25% Increasing Peak Surface Field by 12% Setting High Beta b g to 0.86 Adopting maximum voltage profile Adopting a uniform lattice cell length in the elliptical section to permit design flexibility schedule flexibility. 5

Linac Design Choices User facilities demand high availability (>95%) ESS will limit the peak beam current below 65 ma Linac Energy > 2 GeV to accomplish 125 MW peak power. Front end frequency is 352 MHz (CERN Standard) High energy section is at 704 MHz 6

Ion Source and NC Linac The RFQ and DTL will be similar to the CERN Linac4 design. The RFQ: 4.5 m long Energy of 3.6 MeV The DTL: Will consist of five tanks Tank length ~7.5 m Final energy of 88 MeV Six klystrons: Operating at 352 MHz Max. saturated power of 2.8 MW Duty factor of 4% Prototype proton source operational, and under further development, at ESS-Bilbao (Spain). Output Energy 75 kev. Design exists for ESS RFQ similar to 5m long IPHI RFQ at CEA-Saclay (France). Energy 75 kev -3.6 MeV. Picture from CERN Linac4 DTL. DTL design work at ESS and INFN-Legnaro (Italy), Energy 3.6-90 MeV. 7 Design work at ESS-Bilbao for MEBT with instrumentation, chopping and collimation.

Spoke Cavities Superconducting double-spoke accelerating cavity, for particles with b=0.5, energy 90-216 MeV. ESS will be the first accelerator to use 352 MHz double spoke cavity resonators. Design performed by CNRS-IN2P3 (France). 28 cavities with an accelerating gradient of 9 MV/m, requiring 320 kw peak power. What type of power source to choose? Tetrode Klystron IOT Solid State First cavity @ IN2P3 in Oct 2014 8

Elliptical Cavities Universal Cryomodule: Cryomodules are expensive and difficult to fabricate. Pick cavity b and number of cells: Optimize power transfer Optimize length Power in couplers is limited to 1200 MW (peak). Cavity and cryomodule design well advanced at CEA-Saclay (France). Medium b = 0.67 6 cell cavities Cavity length = 0.86 m 32 cavities in 8 cryomodules Maximum peak RF power = 800 kw High b = 0. 86 5 cell cavities Cavity length = 0.92 m 88 cavities in 22 cryomodules Maximum peak RF power = 1100 kw 9

10 Universal Cryomodule

First Test of ESS high-b Prototype Cavity Expected in vertical cryostat Rs = 9 nw Test limited by RF amplifier (saturation at 190 W) and high X-ray level Specification in cryomodule No quench observed Vertical test done the 22th of May 2014 at CEA Saclay Next plans: Measurement of resonant frequency of 1st bandpass mode at 2K Measurement of resonant frequency of HOM at 2K If possible, increase accelerating field up to the quench limit Perform heat treatment at CERN at 650 o C under vacuum 11 11

Spoke Linac (352 MHz) RF System Layout 26 Double Spoke cavities Power range 280-330 kw Combination of two tetrodes Other options: Solid State Amplifiers Large power supply (330 kva) to supply 8 stations (16 tetrodes) 12

ESS Linac RF System 13 Each ESS cavity to be individually powered: 36 med-b amplifiers (klystrons) 84 high-b amplifiers (IOTs/klystrons) Total 120 high power RF amplifier systems delivering 1.1 MW each! 4 amplifiers per modulator anticipated.

Elliptical (704 MHz) RF System Layout Klystrons Racks and Controls Modulator WR1150 Distribution 14 4.5 Cells of 8 klystrons for Med-b 10.5 Cells of 8 klystrons (IOTs) for High-b

ESS Cryogenics Three cryogenic plants: Accelerator: - 3.1 kw @ 2K, - 12.8 kw @ 40-50 K - plus 8 g/s helium liquefaction Target: - ~ 20 kw @ 16K Test & Instruments - ~ 250 W@ 4.5 K - 200 W @ 40K Distribution system: Permits independent cool down & warm up of cryomodules, likely IKC Cryoplant orders to be placed in 2015 with operations starting in 2017/18 Valve box Cryoline Jumper connection Cryomodule 15

ESS Beam Diagnostics Beam Loss Monitor Beam Current Monitor Beam Position Monitor Slit (H & V) Grid (H & V) Faraday Cup Wire Scanner Non-Invasive Profile Monitor Optical Imaging Halo Monitor LEBT 0 2 0 1 2 1 0 0 0 0 0 MEBT 0 4 6 1 1 1 4 2 0 0 1 DTL 15 7 15 0 0 2 1 1 0 0 1 Spoke 39 0 26 0 0 0 1 1 0 0 0 Med-b 27 1 18 0 0 1 3 3 0 0 1 High-b 63 1 42 0 0 0 1 1 0 0 0 Upgrade High-b 67 2 44 0 0 0 4 1 0 0 1 A2T 19 2 11 0 1 0 3 3 2 3 0 DumpLine 6 2 3 0 0 0 0 0 1 1 0 TOTAL 236 21 165 2 4 5 17 12 3 4 4 Day 1 Day 1+ Note: These numbers were the result of an scope reduction from the initial diagnostics to meet budget targets. Still need to be confirmed by beam physics studies and commissioning planning. Bunch Shape Monitor 16

Diagnostics In-Kind Status BLM (IC) BCM BPM FC EMIT WS/Halo IPM Lumi/BIF BSM Imaging SEM TC LEBT MEBT DTL Spoke MBE HBE HEBT A2T BLD procurement with CERN DAQ BLD Bilbao DAQ BLD Bilbao Legnaro DAQ BLD procurement Bilbao DAQ BLD Saclay Bilbao DAQ Saclay Bilbao BLD Bilbao DAQ BLD DAQ BLD Bilbao DAQ BLD Bilbao DAQ Bilbao BLD DAQ BLD DAQ BLD DAQ Overarching agreement exists, technical details/specification to be refined Discussions with potential partner ongoing (e.g. DESY, Trieste, Legnaro, CI, RAL/ISIS, PSI, GSI ) 17

Linac Warm Section Layouts BPMs BPMs BSM BCT WS BIF BPMs WS BPMs IPM 18

Diagnostics Prototypes Position Monitors Current Monitors 19

ESS Integrated Control System The ESS Control System is a complex network of hardware, software, and configuration databases that integrate the operations of the Accelerator, Target, Instruments and Conventional Facility infrastructure. Hardware platforms MicroTCA High performance applications such as fast signal processing EtherCAT Distributed, khz range acquisition PLC Low-end I/O, interlocking, etc. Software EPICS Used for control of the entire facility(some offline use of LabVIEW) CS-Studio Generic user interface tool (GUI, Alarms, Archiving) DISCS Distributed Services for Controls (databases, configuration, ) 20 20/

ESS Control System Work Packages The ESS Cost Book lists 39 separate control system work packages, 30 of which include provision for a significant In-Kind contribution. In addition, many other technical work packages either include a requirement for a control system interface or are interested in adding this as an option. The main areas covered are: Application software Development of application, frameworks and toolkits Core Software Databases, software tools and services Core Hardware Development of timing system and control boxes Equipment Supply of computer/electronics hardware Infrastructure Control room, data centre and network equipment Integration Support Integration of Accelerator, Target and Conventional Facilities 21 21/

What s Happening Now? Accelerator areas being investigated: RF: SRF elliptical cavity procurement (med-b and high-b), test and delivery: STFC ASTeC/Technology. RF Distribution systems: Huddersfield University. Diagnostics: Target diagnostic imaging: Liverpool University, STFC ISIS Other diagnostic systems being discussed: Liverpool University, STFC Technology/ISIS. Vacuum: Vacuum component test facilities (incl. Controls): STFC ASTeC/Technology. Design and supply of Linac Warm Units (incl. Controls): STFC ASTeC/Technology. Controls: EPICS for Freescale PowerPC P2020 FPGA controllers: STFC Technology Timing and Event EPICS applications: STFC Technology Other control system areas: STFC Technology/ISIS 22

23 RF & Vacuum

Diagnostics & RF Targetry Beam Imaging RF Distribution Spoke Distribution Elliptical Distribution C Welsch (Liverpool University & opac) 24 R Edgecock (Huddersfield University)

UK Opportunities RF: High power amplifiers Klystrons, IOT s or SSA s. RF distribution systems. RF control systems. Cryogenics: Cryogenic distribution systems. Diagnostics: Diagnostic device production (wide variety). DAQ/Interfacing. Vacuum: Pumps, controllers, gauges Controls: I/O controllers, DAQ units, software development. Generic: Cabling 25

ACCSYS update in-kind discussions Potential partners identified for 47% of the total planned/potential in-kind value, contracting under way! Planned/potential in-kind is 78% of accelerator budget Many activities start 2014, reflecting the importance of reaching agreements soon 26 Håkan Danared, ACCSYS in-kind manager 26