Analysis of Transients during the Power System Restoration

Similar documents
Voltage Sags Evaluating Methods, Power Quality and Voltage Sags Assessment regarding Voltage Dip Immunity of Equipment

POWER PLANT MODEL DESIGN USING MATLAB/SIMSCAPE

Transformer energisation after network blackout

Ferroresonance Experience in UK: Simulations and Measurements

Measuring Electric Parameters in Street Lighting Networks

Long lasting transients in power filter circuits

Ferroresonance in MV Voltage Transformers: Pragmatic experimental approach towards investigation of risk and mitigating strategy

Ferroresonances during Black Starts - Criterion for Feasibility of Scenarios

Simulation of Ferroresonance Phenomena in Power Systems

CONTROLLED SWITCHING OF THE T402 TRANSFORMER IN THE KRIŽOVANY 400kV SUBSTATION

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter

The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller

Multifunctional Relay Developed in ATP FOREIGN MODEL and C++

Study of High Voltage AC Underground Cable Systems Silva, Filipe Miguel Faria da; Bak, Claus Leth; Wiechowski, Wojciech T.

A NEW DIFFERENTIAL PROTECTION ALGORITHM BASED ON RISING RATE VARIATION OF SECOND HARMONIC CURRENT *

Active Elimination of Low-Frequency Harmonics of Traction Current-Source Active Rectifier

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit

Modeling Ferroresonance Phenomena on Voltage Transformer (VT)

Visualization and Animation of Protective Relay Operation

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS

Power Plant and Transmission System Protection Coordination Fundamentals

VOLTAGE OSCILLATION TRANSIENTS CAUSED BY CAPACITOR BANKING ENERGIZING FOR POWER FACTOR CORRECTION IN THE POWER SYSTEM

ANALYSIS OF TRANSIENT ACTIONS INFLUENCE IN POWER TRANSFORMER

Zdeslav Čerina, dipl. ing. Robert Kosor, dipl. ing. Sergio Gazzari, dipl. ing. Hrvatska elektroprivreda d.d., Croatia ABSTRACT

The Effect of Various Types of DG Interconnection Transformer on Ferroresonance

Medium voltage products. Field Application Support Analysis and calculations in Medium-Voltage electrical networks

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow

Arvind Pahade and Nitin Saxena Department of Electrical Engineering, Jabalpur Engineering College, Jabalpur, (MP), India

Simulation Analysis of Ferromagnetic Resonance of Low Magnetic Flux Density-Type PT under Single-Phase Earth Fault of 10kV Power Grid

Spectral analysis of voltages and currents during different modes of ferroresonance in switchgear

Analysis and modeling of thyristor controlled series capacitor for the reduction of voltage sag Manisha Chadar

Transient stability improvement by using shunt FACT device (STATCOM) with Reference Voltage Compensation (RVC) control scheme

Transients impact on power filter circuit sizing

In power system, transients have bad impact on its

P5 Policy 5: Emergency Operations

Capacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices

ANALYSIS OF TRANSIENT ACTIONS INFLUENCE IN POWER

Methodology Utilized in Black-Start Studies on EHV Power Networks

Simulation and Comparison of DVR and DSTATCOM Used For Voltage Sag Mitigation at Distribution Side

PRACTICAL CONSIDERATIONS FOR CONTROLLED SWITCHING OF POWER TRANSFORMERS

1. Introduction to Power Quality

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers

POWER QUALITY A N D Y O U R B U S I N E S S THE CENTRE FOR ENERGY ADVANCEMENT THROUGH TECHNOLOGICAL I NNOVATION

Power Quality enhancement of a distribution line with DSTATCOM

Zambezi (previously Caprivi) Link HVDC Interconnector: Review of Operational Performance in the First Five Years

A SPECIAL CASE OF FERRORESONANCE INVOLVING A SERIES COMPENSATED LINE

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION

A Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Plants

ANALYSIS OF VOLTAGE TRANSIENTS IN A MEDIUM VOLTAGE SYSTEM

Analysis of MOV Surge Arrester Models by using Alternative Transient Program ATP/EMTP

Voltage Sag Effects on the Process Continuity of a Refinery with Induction Motors Loads

Resonances in Collection Grids of Offshore Wind Farms

A New Method of the Load Compensation Use During Creation of Post Blackout Start-up Path in Power System

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Identification of network models parameters for simulating transients

Transients under energizing multiple power filter circuits

of the improved scheme is presented. Index Terms Inrush current, power quality, transformer.

TECHNICAL BULLETIN 004a Ferroresonance

Assessment of Saturable Reactor Replacement Options

Switching and Fault Transient Analysis of 765 kv Transmission Systems

USING OVER-DAMPING METHOD TO SUPPRESS THE FERRO-RESONANCE OF POTENTIAL TRANSFORMER

PHYSICAL PHENOMENA EXISTING IN THE TURBOGENERATOR DURING FAULTY SYNCHRONIZATION WITH INVERSE PHASE SEQUENCE*

P5 Policy 5: Emergency Operations

Protection of Electrical Networks. Christophe Prévé

CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS

A Study on Ferroresonance Mitigation Techniques for Power Transformer

Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering

PWM DRIVE OVERVOLTAGE TRIPS IN ELECTROCHEMICAL PLANTS

Switch-on-to-Fault Schemes in the Context of Line Relay Loadability

DISTRIBUTION SYSTEM VOLTAGE SAGS: INTERACTION WITH MOTOR AND DRIVE LOADS

Analysis of a 405 km transmission line with series compensation

Simulation Results on the Currents Harmonics Mitigation on the Railway Station Line Feed

Energization of a no-load transformer for power restoration purposes: Impact of the sensitivity to parameters.

ESB National Grid Transmission Planning Criteria

SHUNT COMPENSATOR USED FOR POWER QUALITY IMPROVEMENT

Time over/underfrequency relay with protection assemblies

SIMULATION OF D-STATCOM AND DVR IN POWER SYSTEMS

The Engineering Problem. Calculating GIC Flow through the EHV System

OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES

OVERVIEW OF SVC AND STATCOM FOR INSTANTANEOUS POWER CONTROL AND POWER FACTOR IMPROVEMENT

G. KOBET, I. GRANT, G. GOZA Tennessee Valley Authority USA. R. GIRGIS, M. ESPINDOLA ABB Corporation USA SUMMARY

Reducing the magnetizing inrush current by means of controlled energization and de-energization of large power transformers

Distribution Transformer Random Transient Suppression using Diode Bridge T-type LC Reactor

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

Islanding and Detection of Distributed Generation Islanding using Negative Sequence Component of Current

Measurements for validation of high voltage underground cable modelling

II. RESEARCH METHODOLOGY

Mitigation of Voltage Sag and Swell Using Dynamic Voltage Restorer

ACCURACY OF VOLTAGE TRANSFORMERS DESIGN CRITERIA AND A SURVEY ON THE PRECISION AND REPRODUCIBILITY OF A NEW MODEL-BASED CALIBRATION APPROACH

Influence of Wind Generators in Voltage Dips

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Impact Assessment Generator Form

RESEARCH ON CLASSIFICATION OF VOLTAGE SAG SOURCES BASED ON RECORDED EVENTS

1

Discrimination of Fault from Non-Fault Event in Transformer Using Concept of Symmetrical Component

Traction Drive with PMSM: Frequency Characteristics Measurement

Prevention of transformers damage in HPP with double generating units connected to GIS via HV cables

Power Quality Requirements for Connection to the Transmission System

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

Contents. 1 Introduction Assessment criteria Assessment Recommendations References... 8

Transcription:

Transactions on Electrical Engineering, Vol. 7 (2018), No. 4 73 Analysis of Transients during the Power System Restoration Žaneta Eleschová 1), Martin Jedinák 2) and Rastislav Šmidovič 3) 1) Inst. of Power and Applied Electrical Engineering, FEI STU Bratislava, Slovakia, zaneta.eleschova@stuba.sk 2) Slovenská elektrizačná prenosová sústava, a.s. Bratislava, Slovakia, martin.jedinak@sepsas.sk 3) Slovenská elektrizačná prenosová sústava, a.s. Bratislava, Slovakia, rastislav.smidovic@sepsas.sk Abstract The paper presents simulation results of transients during the power system restoration. The Defence plan and Restoration plan development is a part of transmission system operator s responsibilities and requires thorough calculations, simulations and publication of instructions. The plans focus on extensive failures that have a heavy impact on the system operation and could lead to a blackout. The Restoration plan of power system has to contain procedures for start-up without outside help. TSO regularly checks some part of the Restoration plan. Keywords restoration, black-start, restoration route, auxiliary systems, transients. I. INTRODUCTION Despite the endeavour of transmission system operators (TSO) to design and operate the power system securely, i.e. at least by fulfilment of N-1 criterion, and a low probability of an occurrence of such serious failure as a partial or a complete blackout, experience from real operation shows that this threat is real and quite possible [1]. Every year numerous disturbances within the contemporary power system are detected and recorded. The vast majority of them are handled without serious consequences by automatic designated systems or by human operators. Nevertheless, some of them can lead to a complete failure of a part or even whole system. Changes in conditions related to energy market liberalization create high demands on technical ability of formerly stable system and consequently affect reliability of power generation, transmission and distribution and finally increase the likelihood of a critical event occurrence. SEPS as a TSO of the control area of Slovakia is according to the Dispatch rules for control of the Slovak Republic power system responsible for the system restoration in case of wide area disturbance, so called blackout. The re-energisation procedure of the Restoration plan is possible in two ways: 1. top-down re-energisation strategy in case of capability to support re-energisation from neighbouring TSOs. 2. bottom-up re-energisation strategy creating the route within the home-restoration procedures. This paper is focused on the bottom-up re-energisation strategy. In the case of a blackout system fault, the source of the black-start capability support service is required to run an independent power plant to ensure its own power consumption. Or, if the voltage drops, the generator must run if it is equipped with a technology that allows the automatic start and wake-up of the selected generator without an auxiliary power plant to ensure its own consumption. After securing own consumption, the start of the selected generator starts at the command of the SED dispatcher. The local operating regulations must not be violated when the generator is started. At present, it is not in operation instruction clearly defined, the way of creating the route within the homerestoration procedures (bottom-up re-energisation of power system). In this post, the following alternatives can be considered: 1. Starting the generator at nominal voltage and gradually building the route to the auxiliary systems of the power plant gradual route creation. 2. Creating a route to the auxiliary systems of the power plant without voltage and then switching the generator to a nominal voltage simultaneous route creation. II. EVALUATION OF THE RESTORATION ROUTE BOTTOM-UP RE-ENERGISATION Within preparation of the Restoration plan simulations and calculations are required. The simulations and calculations are focusing on the steady-states and the transients during restoration. Suitability of the route for the power system restoration is evaluated according the next criteria: 1. Evaluation of the route: number of equipment and operation activities, value of short-circuit power. 2. Evaluation of load flow results: reactive power control capabilities of generators for black-start service, rms values of voltage on substations on the route, value of capacitive charging power. 3. Evaluation of transients: voltage drops on terminals of generators during motors starting, frequency drops during motors starting, voltage drops on 6 kv substations in auxiliary systems of the power plants during motors starting, motors start time, overvoltage and overcurrent during switch on operations.

Transactions on Electrical Engineering, Vol. 7 (2018), No. 4 74 III. DESCRIPTION OF THE ANALYSED RESTORATION ROUTE The analysed restoration route is for re-energisation of the thermal power plant TPP Novaky from the hydro power plant HPP Nosice. The re-energization process will begin with the start of the HPP Nosice from the shutdown state, with the loss of the external voltage used to cover its own consumption. At the same time, the voltage drop will be applied to cover all lines and substations in the direction of the route. Each auxiliary system operation of substations is supplied in a spare way according to the technical solutions of each substation. After the starting generator G3 in HPP Nosice and the auxiliary systems securing self-consumption in HPP, a route will be created with 110 kv lines (belongs to distribution companies Stredoslovenská distribučná and Západoslovenská distribučná) up to substation R110 kv in the power plant Novaky (ENO A). After supplying the voltage from the HPP Nosice to ENO A, the next step is connecting auxiliary systems of the block TPP Novaky (ENO B). When all the necessary equipment is connected to the start of the 2 nd block of TPP (ENO B), it will be flooded and connected to the island. A scheme of the implementation of the test from the HPP Nosice to the TPP Nováky (ENO B) is shown in Fig. 1. Fig. 2. Simulation model in the program ATP and load-flow results. A. Transients by the no-load power lines switching Switching of the no-load power lines is accompanied by a transient overcurrent and overvoltage. The amplitude of the inrush current is given:, (1) where the frequency of the transient is given by the frequency of the LC circuit, i.e. the parameters of the switching line and the parameters of the other devices (source inductance, transformer parameters, etc.):. (2) The steady capacitive charge current of the line is: Fig. 1. Single-line diagram of the island operation. IV. MODEL AND SIMULATIONS OF TRANSIENTS The situation for supplying the auxiliary systems of the power plant Nováky (ENO) from the hydro power plant HPP Nosice, was modelled in the ATP program. The aim of the simulations was to point out the occurrence of wave transients related to idling and switching on the selfconsumption transformer in ENO with respect to the nonlinear VA characteristic of the transformer magnetic core. The model is shown in Fig. 2, the results of load flow calculation in steady-state are included. Reactive power control capabilities of the generator in the HPP Nosice: 24 MVAr, +20 MVAr. Short-circuit power on 6 kv substation: 50 MVA. Number of equipment on the route: generator: 1 power lines in the distribution network: 9 Capacitive charging power: 5.8 MVAr. (3) B. Transients by the no-load transformer switching When switching on the transformer, the transients may occur. The occurrence and behaviour of such transients already mainly depend on the magnetizing characteristic of the switched transformer, which is nonlinear. The conditions for ferroresonance are: Source of harmonic voltage (generator). Ferromagnetic inductance (transformer). Capacitance (power line). Low active load (no-load restoration route). All the above conditions are fulfilled during the system restoring. C. Simulation results Simulations, in addition to proving the transients that accompanied the route building, were also a comparison of 2 approaches for creating a route: 1. Simultaneous route creation: all lines are switched on without voltage and connected to generator voltage in 0.1 s, self-consumption transformer in the TPP Nováky (ENO) was connected in 0.5 s. 2. Gradual route creation: sequential switching on of the elements on the route: self-consumption transformer in the TPP Nováky (ENO) was connected in 1 s. In the following figures the voltages and currents are plotted.

Transactions on Electrical Engineering, Vol. 7 (2018), No. 4 75 Simultaneous route creation Gradual route creation Fig. 3. Voltage generator in HPP Nosice. Fig. 4. Voltage 110 kv substation HPP Nosice. Fig. 5. Current block transformer HPP Nosice. Fig. 6. Voltage self-consumption transformer in TPP Novaky 110 kv side.

Transactions on Electrical Engineering, Vol. 7 (2018), No. 4 76 Simultaneous route creation Gradual route creation Fig. 7. Voltage self-consumption transformer in TPP Novaky 6 kv side. Fig. 7. Current self-consumption transformer in TPP Novaky. Fig. 8. Details of no-load current self-consumption transformer in TPP Novaky L1 phase.

Transactions on Electrical Engineering, Vol. 7 (2018), No. 4 77 Simultaneous route creation Gradual route creation Fig. 9. Details of no-load current self-consumption transformer in TPP Novaky L2 phase. In the figures above it is possible to see the difference between the transients for restoration route building gradually and simultaneously. The difference is in the amplitude of the transient line charging current. When the route is switched on at the same time, this current is given by the capacitances of all lines (the circuit is only a onetime overcurrent and the amplitude is higher) and in the case of the switching on of the lines step by step, the amplitude of the overcurrent is given only by the capacitance of the already switched line (several overcurrents in the circuit). Switching on the transformer is also connected by an overcurrent, which is characterized by a DC component and 2 nd harmonic, as seen from the FFT analysis of the noload transformer current (Fig. 8, 9) [5]. Steady-state noload current is shown in Fig. 10, where there are significant: 3 rd, 5 th and 7 th harmonics. Fig. 10. No-load current of transformer in steady-state (3 phases, detail of L1 phase, FFT analysis).

Transactions on Electrical Engineering, Vol. 7 (2018), No. 4 78 There is not a significant difference in the transient voltage nor current during switching on gradually or simultaneously. One reason is the magnetization characteristic of the transformer, which is another reason for a relatively high value of 110 kv power lines resistance, which positively affects the transients. V. CONCLUSION Preparation of the power system restoration after a blackout is an important part of the Restoration plan. Black-starts, island operation and system resynchronization are very rare cases, but a grid operator should be prepared. The computer simulation is usually used for planning, test preparing and post-process analysis. It enables to investigate dynamic behaviour of the power system during the above-mentioned cases [3]. According to the obtained load-flow results and transient simulations results we can say that the analysed route for re-energisation of the TPP Novaky from the HPP Nosice is suitable. The calculation proved that there is not risk of ferroresonance phenomena (these phenomena caused unsuccessful black-start test in 1996 [2]). The conclusion is that analysed route can be used for the Restoration plan of the power system of the Slovak Republic. REFERENCES [1] K. Máslo a kol., Řízení a stabilita elektrizační soustavy, 2003, AEM, ISBN 978-80-260-44671-1, 272 str. [2] K. Máslo, and J. Fantík, Electromechanical and Electromagnetic Phenomena During Power System Restoration, in IXth Int. Scientific Conf. EE '98, St. Lesná 1998 [3] I. Chemišinec, J. Tůma, and K. Witner, Přípravy na řešení havarijních stavů v elektrizační soustavě in Proceedings of the 6th International Scientific Conference Electric Power Engineering EPE, Dlouhé Stráně, Czech Republic, 2005 [4] A. Greenwood, Electrical transients in power systems, 2. ed., New York: John Wiley & Sons, 1991, ISBN 0-471-62058-0. [5] F. Janíček, V. Chladný, A. Beláň, and Ž. Eleschová, Digitálne ochrany elektrických strojov. ELFA Košice, 2000. [6] M. Jedinák, R. Šmidovič, and Ž. Eleschová, The Simulation Test of Black-Start Capacity in Western Part of Slovakia, in Proceeding of the 13th International scientific conference Control of Power System 2018, Tatranské Matliare, Slovakia. June 5-7, 2018, ISBN 978-80-89983-01-8.