UNC Mod Proposal 373. GSOG suggestions on. Jacopo Vignola. 18 th May 2011 UNC Transmission Workstream

Similar documents
European Update. 3 rd December 2015

European Workgroup. 7th May 2015

European Update. 5 th May 2016

Recreation Facility Hours

PROJECT BRIEF PROJECT NEXUS. Development of Requirements FINAL DRAFT V1.0. Project Nexus Development of Requirements Project Brief.

VAN BUREN COUNTY TENNESSEE

LIBRA PROJECT Production Development Projects: NW Region

July Contents. Gas Demand Side Response Methodology Final Version. UK Gas Transmission

National Grid Gas Transmission (NGGT) Gas Quality Consultation Questions - Draft

Practice Test Chapter 8 Sinusoidal Functions

GMDN An Introduction. Mark Wasmuth CEO, GMDN Agency

Demonstration of PFR Improvement September ERCOT Operations Planning

NATIONAL INSTITUTE OF ECONOMIC AND SOCIAL RESEARCH ESTIMATES OF MONTHLY GDP. Embargo until hours on 11 th January 2013

MARSHALL. Comprehensive Long Range Facility Study / Plan. Facility Planning Committee Meeting 4 INDEPENDENT SCHOOL DISTRICT 413

Hardware Commissioning

Indonesia s Preparation for WRC-19

Unit 6 - Number Games and Crayon Puzzles Unit 8 - Twos, Fives, and Tens Unit 7 - Color, Shape, and Size. Unit 9 - Blocks and Boxes.

University of Bristol - Explore Bristol Research. Peer reviewed version. Link to published version (if available): /geng.13.

Village of Glenview Appearance Commission

Oct-09 Nov-09 Dec-09. Jan-10 Feb-10 Mar-10. Apr-10 May-10 Jun-10

STRLodgingPerformanceSnapshotAugust2017CYTD

60% 100% 100% Performance Report YTD YTD YTD. June Development Services Division. In this Edition. target: 100% target: 100% target: 100%

Drought Update for March 2006

Representation - Draft Modification Report UNC A 0636B 0636C 0636D Updating the parameters for the NTS Optional Commodity Charge

Demand Side Response Methodology (DSR) for Use after a Gas Deficit Warning (GDW) Background. Draft Business Rules

FORESIGHT METHOD HORIZONS. Module. Introduction to Foresight for Canada Beyond 150

Mercury Minimization Plan City of Otsego

Estimation of Fault Resistance from Fault Recording Data. Daniel Wong & Michael Tong 2014-November-5

Homogenisation of Maximum and Minimum Air Temperatures in Ireland. Mary Curley * and Seamus Walsh

National Radio Channels. PPM measurement October 2017

Massport Capital Programs Enterprise Schedule Management. Primavera Schedule Toolkit Design. January 2018 Version 1.0


IEEE Project m as an IMT-Advanced Technology

PROGRAM UPDATEPDATE. Has anyone heard any good rumors lately? Steve Guilfoos AF SBIR/STTR Program Manager Spring 2007

14/05/02 20:48. Awards Entry Asia-pacific Conference Let's have a dream JCI JAPAN. 1/13

Climate Update March 2006 Meeting

Climate Update September 24, 2003 WATF meeting

Installing and Configuring SIV

Ministry of. Economic Development

TSC873 NPN Silicon Planar High Voltage Transistor

Innovative Approaches in Collaborative Planning

TS79M00 Series 3-Terminal 500mA Negative Voltage Regulator

Rod Larson President, Latin America. Houston, Texas March 9-10, 2011

Drought Update January 18, 2005 WATF Meeting

Load-Frequency Control and Reserves Network Code. David Bunney JESG 19 March 2013

Climate Update. Wendy Ryan Research Associate For Nolan Doesken, State Climatologist.

Climate Update. Nolan Doesken, State Climatologist Atmospheric Science Department Colorado State University.

UDW Technology Conference Dan McLeod / John Jacobson Lockheed Martin MS2 July 27, Secure Energy for America

NPN Silicon Planar High Voltage Transistor

SMART DUBAI INSPIRING NEW REALITIES

Climate Update May 2006 Meeting

Climate Update. Nolan Doesken State Climatologist Atmospheric Science Department Colorado State University.

Climate Update July 2006 Meeting

Matrix Composites & Engineering Ltd

Village of Glenview Appearance Commission

Software as a Medical Device (SaMD)

Holidays in United States, SEA Charter Master Calendar

NPN Silicon Planar High Voltage Transistor

TS79L00 Series 3-Terminal 100mA Negative Voltage Regulator

AGENDA. the giver's guide to greatness. the hidden DNA of the real estate business A MOTIVATIONAL MESSAGE FROM SPECIAL GUEST...

Low Power Low Offset Voltage Dual Comparators

2018 Spectrum Forum Topics. RSGB Spectrum Forum October 2018

WNA Survey on Licensing. Christian Raetzke WNA CORDEL Director of Licensing 2 nd MDEP Conference, Paris, 16 Sept 2011

Guide for Calculating Radio Licence Fees

Site Surveys for Offshore Windfarms: How to Spend your Money Wisely in an Age of Austerity

The Industrial Strategy Challenge Fund

SEQUATCHIE COUNTY TENNESSEE

3-Termal 500mA Negative Voltage Regulator

Source 2018 COURSE SCHEDULE SGT. MAJ. PHIL FASCETTI GIVES BACK UC SAN DIEGO EXTENSION CELEBRATES 25 YEARS OF MAKING SAFER WORK SPACES SAFETY FEST

Climate Update. Nolan Doesken, State Climatologist Atmospheric Science Department Colorado State University Presented by Reagan Waskom

BACCARAT: A LONGITUDINAL MICRO-STUDY

Single-Stage Buck Current Control LED Driver with High Voltage MOSFET Integrated

GLOBAL RIG AND OFFSHORE CONSTRUCTION MARKETS

Assessing the Feasibility of Wind Power Production for the University of Rhode Island s Bay Campus

C 2 B 1 E 1 E 2 B 2 C 1. Top View

3-Terminal 500mA Positive Voltage Regulator

Drought Update March 18, 2005 WATF Meeting

HPS Upgrade Proposal

Southeast Region Reserve Components. Conveyance Progress Report

Real Estate Trends and Outlook

SUCCESSFUL GOAL SETTING TO ACHIEVE A HEALTHY A presentation to

TSM2307CX 30V P-Channel MOSFET

Part Number Case Packaging SDM05U20CSP-7 X3-WLB ,000/Reel

Planetary Protection Subcommittee Mars Brief May 1, 2012 Doug McCuistion Director, Mars Exploration Program

FRONT HEATER VIEW BRACKET MOUNTING STYLES 2 1/8" B A W 1 3/4" W / 2 H / 2. 1/4" x 1/2" or 1/4" x 1" (12x12 & 12x24 Only) NOTES:

Release of new series of all-india IIP with base

TSM V P-Channel MOSFET

Top View BAT54T BAT54AT BAT54CT BAT54ST

TSM6866SD 20V Dual N-Channel MOSFET

Number patterns on a spreadsheet

Access to Infrastructure: A new approach for the North Sea

TSM V N-Channel MOSFET

Ultra Low Quiescent Current 5V/150mA Fixed-Voltage Ultra Low LDO

Future of the Ocean Economy

Yorkville Seasoned MLP Investment Team Recognized Experts

TSM V P-Channel MOSFET

Not Recommended. TSM V N-Channel MOSFET. PRODUCT SUMMARY V DS (V) R DS(on) (mω) I D (A) Features. Block Diagram. Application

BusinessHaldimand.ca. Haldimand County 2018 Community Profile

Resources and Energy Group (REZ) is pleased to enclose a brief presentation on the Radio Gold Mine Project.

THE COUNTDOWN TO KARLAWINDA Building a new mid-tier gold producer

Transcription:

GSOG suggestions on UNC Mod Proposal 373 Jacopo Vignola 18 th May 2011 UNC Transmission Workstream

Agenda Objectives Current arrangements Concerns Proposal

Objectives Map current arrangements What are the processes a storage developer must complete to ensure a connection to the NTS? How do they interact each other? Identify concerns Why current NTS connection arrangements are not optimal for developing new storage facilities? Proposal How does the proposed Straw-man help to address the identified concerns on current arrangements?

Current arrangements Map of processes Comparing the timeline of each process that any storage developer must face in order to secure a connection to the NTS Six processes Connection Land/seabed lease NTS ENTRY EXIT Storage developer licensing development Identify mismatches between timelines

Concerns (1) Information Transparency Need for additional clarity at earlier stages of the connection process (initial enquiry and feasibility study) Location, Ramp rates, Gas quality NGG Apr Initial enquiry Storage developer Jun Design & build agr. Jan - Jun Feasibility study Mar - Mar Jul - Feb negotiation Apr - Sep Conceptual Detailed design design Apr-Sep Construction work Mar SCA Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Designing facility and environmental assessment Permitting phase (18 months) Land negotiation Setting washing/drilling infrastructure Surface building Washing caverns / additional drilling Injecting cushion gas (6 months) START The trade association of choice for UK energy (18 months) & utility network companies

Concerns (2) Key milestones & FID Some key milestones are unlikely to be triggered before the FID Entry/Exit Capacity, DBA Storage developer Ofgem NGG Jul Application Window 38 months 42 months?? Mar QSEC auction Jun Design & build agr. Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Shipper Transportation NGG GT licence Designing facility and environmental assessment Permitting phase (18 months) FID Setting washing/drilling infrastructure Surface building Washing caverns / additional drilling (18 months) Injecting cushion gas (6 months) START

Proposal Addressing concern (1) The feasibility study shall be completed in advance, including: 1. Indicative tech details (including Ramp Rates, Capacity and gas quality) when NTS reinforcement is/isn t necessary 2. Timeline for applying to entry/exit capacity 3. Indicative location of connection (< few metres) 4. Indicative cost of the overall connection package 5. Indication of eventual reinforcement of NTS 6. Option for study to look at more than one connection location Addressing concern (2) The feasibility report shall include enough details to trigger the IPC, lease and licences processes developer will not make FID until certainty on ramp rates, capacity, costs

Proposal Enhancing and moving backward the feasibility study to trigger : pre-planning, land negotiations, permitting procedures to facilitate : FID NGG Apr Initial enquiry Storage developer Jun Design & build agr. Jan - Jun Feasibility study Mar-Mar Jul - Feb negotiation Apr-Sep Conceptual Detailed design design Apr - Sep Construction work Mar SCA Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Designing facility and environmental assessment Permitting phase (18 months) Land negotiation Setting washing/drilling infrastructure Surface building Washing caverns / additional drilling (18 months) Injecting cushion gas (6 months) START The trade association FID of choice for UK energy & utility network companies

Further concern Given a formal governance of NTS Connection Keeping current lead times for releasing NTS commercial capacity The overall timeline is too long + 3 years (NTS Capacity lead time) + 3 years (IPC process and other licensing) + 1 year of feasibility study = 7 years from the initial enquiry Need to consider shorter timescales for QSEQ auction from 42 months to 24-30 months for a min connection (NOT FULL CONNECTION) Capacity lead time shall be shorter All necessary studies (including indicative NTS reinforcements) have been carried out during the feasibility study All planning risks stand on the developer

Q & A