SECTION ADMINISTRATIVE REQUIREMENTS

Similar documents
SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.

SECTION SUBMITTAL PROCEDURES

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

East Central College

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

SECTION SUBMITTAL PROCEDURES

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION SUBMITTAL PROCEDURES

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

Answer: Qualification statement should be provided with the bid.

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

SECTION PROJECT MANAGEMENT AND COORDINATION

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

Jacksonville District Master

2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS

A. Section includes administrative and procedural requirements for project record documents, including the following:

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

Section Meetings Section Material and Equipment. None Required

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018

SUBMITTAL PROCEDURES

Construction Phase Project Management and Documentation

Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer

INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS:

Working Drawing Manual

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

SUBCONTRACTORS PROCEDURES MANUAL EXHIBIT A.15 SAMPLE MANUAL ONLY FINAL MANUAL WILL BE CUSTOMIZED FOR GREAT WOLF LODGE

DWG, Inc. Coastal Carolina University State Project No. Consulting Engineers HTC Arena Lighting H17-N112-JM

WTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) CITY OF CARTERSVILLE

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

What Are Submittals?

UNIFIED FACILITIES GUIDE SPECIFICATIONS *************************************************************************** SECTION

SECTION OPERATION AND MAINTENANCE DATA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

Working Drawing Procedure

Vanderbilt University Standard Specification Revised 2/6/08

01100 SUMMARY OF WORK

835 Gil Harbin Industrial Blvd Valdosta, GA 31601

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.:

SECTION PHOTOGRAPHIC DOCUMENTATION

City of Aspen Electronic File Preparation Standards September 2018

Bidders for the Oak Brook Park District Family Locker Room Renovation

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Scope of Services. Project management tasks are estimated based upon anticipated project duration of 52 weeks.

PROCEDURE FOR PROCESSING WORKING DRAWINGS

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

UNIFIED FACILITIES GUIDE SPECIFICATIONS

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]

Section Project Closeout

SPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work

Signs, Canopies & Awnings City of Oshkosh Department of Community Development

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document.

TABLE OF CONTENTS. 1.0 Scope. 2.0 References. 3.0 Definitions. 4.0 Submission and Design Requirements. 5.0 Materials 5.1 General 5.

1. Land survey Work. 2. Civil and Structural engineering services.

Recommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7)

DESIGN REVIEW PROCESS AND APPLICATION

SECTION 2 GENERAL REQUIREMENTS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

SECTION SUBMITTALS

SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

REMARKS: The A.F.F. dimension noted on the drawings to the bottom of the grid is 15 0, this dimension should be 16 0.

Solid Surface Countertops

SECTION III SUBMITTALS AND APPROVALS

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.

List of Figures. List of Forms

FTEV Repair Mezzanine Bldg Hurlburt Field, Florida SECTION DESIGN AFTER AWARD

SECTION PROJECT COORDINATION VIA BIM

ADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

Spec Section: Concrete Mix Design psi - Review Form Concrete Mix Design psi Data Sheets GCAN

This specification describes the general requirements for Engineering Services provided to Vale.

APPLICATION FOR CERTIFICATE OF APPROPRIATENESS IN THE HISTORIC DESIGN REVIEW DISTRICT

TABLE OF CONTENTS ALL OTHER SPECIFICATION SECTIONS ARE ON THE CONSTRUCTION DRAWINGS

Booster Pumping Station 115 Booster Pump Procurement

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

TAB B-9 RECORD DRAWINGS

MnDOT Contract Exhibit A - Scope of Services

SUBMITTAL LIST Note: See tab below for Samples and Instructions. Attach to end of Specification Section when complete.

Stanford University-Facilities Design Guideline SECTION Plans Review Submission Guidelines

May 15, 2012 Hugh Anderson Legal Counsel to the Engineers Joint Contract Documents Committee

Transcription:

PART 1 GENERAL 1.01 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Progress meetings. D. Construction progress schedule. E. Coordination drawings. SECTION 013000 ADMINISTRATIVE REQUIREMENTS F. Submittals for review, information, and project closeout. G. Number of copies of submittals. H. Submittal procedures. 1.02 RELATED REQUIREMENTS A. Section 007000 - Special Conditions. B. Section 011000 - Summary: occupancy,. C. Section 013216 - Construction Progress Schedule: Form, content, and administration of schedules. D. Section 013010 - Internet-Based Collaboration System E. Section 017000 - Execution and Closeout Requirements: Additional coordination requirements. F. Section 017800 - Closeout Submittals: Project record documents. 1.03 PROJECT COORDINATION A. Project Coordinator: Owner. B. During construction, coordinate use of site and facilities through the Project Coordinator. C. Comply with Project Coordinator's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts. D. Comply with instructions of the Project Coordinator for use of temporary utilities and construction facilities. E. Coordinate field engineering and layout work under instructions of the Project Coordinator. F. Make the following types of submittals to PhiloWilke Partnership through the Project Coordinator: 1. Requests for information. 2. Requests for substitution. 3. Shop drawings, product data, and samples. 4. Test and inspection reports. 5. Manufacturer's instructions and field reports. 6. Applications for payment and change order requests. 7. Progress schedules. 8. Coordination drawings. 9. Closeout submittals. 211-012R / MHMP Level 29 Oncology Clinic 013000-1 ADMINISTRATIVE REQUIREMENTS

PART 2 PRODUCTS - NOT USED PART 3 EXECUTION 3.01 ELECTRONIC DOCUMENT SUBMITTAL SERVICE A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF) format and transmitted via an Internet-based submittal service that receives, logs and stores documents, provides electronic stamping and signatures, and notifies addressees via email. 1. Besides submittals for review, information, and closeout, this procedure applies to requests for information (RFIs), progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, and any other document any participant wishes to make part of the project record. 2. The General Contractor and PhiloWilke Partnership are required to use this service. 3. It is the General Contractor's responsibility to submit documents in PDF format. 4. Subcontractors, suppliers, and PhiloWilke Partnership's consultants will be permitted to use the service at no extra charge. 5. Users of the service need an email address, Internet access, and PDF review software that includes ability to mark up and apply electronic stamps (such as Adobe Acrobat, www.adobe.com, or Bluebeam PDF Revu, www.bluebeam.com), unless such software capability is provided by the service provider. 6. Paper document transmittals will not be reviewed; emailed PDF documents will not be reviewed. 7. All other specified submittal and document transmission procedures apply, except that electronic document requirements to not apply to samples or color selection charts. B. Submittal Service: The selected service is: PhiloWilke's ProjeXtranet. C. Project Closeout: PhiloWilke Partnership will determine when to terminate the service for the project and is responsible for obtaining archive copies of files for Memorial Hermann. 3.02 PRECONSTRUCTION MEETING A. Memorial Hermann will schedule a meeting after Notice of Award. B. Attendance Required: 1. Memorial Hermann. 2. PhiloWilke Partnership. 3. General Contractor C. Agenda: 1. Execution of Memorial Hermann- Agreement. 2. Submission of executed bonds and insurance certificates. 3. Distribution of Contract Documents. 4. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule. 5. Designation of personnel representing the parties to Contract, General Contractor and PhiloWilke Partnership. 6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures. 7. Scheduling. 211-012R / MHMP Level 29 Oncology Clinic 013000-2 ADMINISTRATIVE REQUIREMENTS

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to PhiloWilke Partnership, Memorial Hermann, participants, and those affected by decisions made. 3.03 PROGRESS MEETINGS A. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals. B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings. C. Attendance Required: Job superintendent, major Subcontractors and suppliers, Memorial Hermann, PhiloWilke Partnership, as appropriate to agenda topics for each meeting. D. Agenda: 1. Review minutes of previous meetings. 2. Review of Work progress. 3. Field observations, problems, and decisions. 4. Identification of problems that impede, or will impede, planned progress. 5. Review of submittals schedule and status of submittals. 6. Maintenance of progress schedule. 7. Corrective measures to regain projected schedules. 8. Planned progress during succeeding work period. 9. Maintenance of quality and work standards. 10. Effect of proposed changes on progress schedule and coordination. 11. Other business relating to Work. E. Record minutes and distribute copies within two days after meeting to participants, with two copies to PhiloWilke Partnership, Memorial Hermann, participants, and those affected by decisions made. 3.04 CONSTRUCTION PROGRESS SCHEDULE A. If preliminary schedule requires revision after review, submit revised schedule within 10 days. B. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review. 1. Include written certification that major contractors have reviewed and accepted proposed schedule. C. Within 10 days after joint review, submit complete schedule. D. Submit updated schedule with each Application for Payment. 3.05 COORDINATION DRAWINGS A. Provide information required by Project Coordinator for preparation of coordination drawings. B. Review drawings prior to submission to PhiloWilke Partnership. 3.06 SUBMITTALS FOR REVIEW A. When the following are specified in individual sections, submit them for review: 1. Product data. 2. Shop drawings. 3. Samples for selection. 4. Samples for verification. B. Submit to PhiloWilke Partnership for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents. 211-012R / MHMP Level 29 Oncology Clinic 013000-3 ADMINISTRATIVE REQUIREMENTS

C. Samples will be reviewed only for aesthetic, color, or finish selection. D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 017800 - CLOSEOUT SUBMITTALS. 3.07 SUBMITTALS FOR INFORMATION A. When the following are specified in individual sections, submit them for information: 1. Design data. 2. Certificates. 3. Test reports. 4. Inspection reports. 5. Manufacturer's instructions. 6. Manufacturer's field reports. 7. Other types indicated. B. Submit for PhiloWilke Partnership's knowledge as contract administrator or for Memorial Hermann. No action will be taken. 3.08 SUBMITTALS FOR PROJECT CLOSEOUT A. When the following are specified in individual sections, submit them at project closeout: 1. Project record documents. 2. Operation and maintenance data. 3. Training sign-in sheets. 4. Warranties. 5. Bonds. 6. Other types as indicated. B. Submit for Memorial Hermann's benefit during and after project completion. 3.09 NUMBER OF COPIES OF SUBMITTALS A. Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected. B. Samples: Submit the number specified in individual specification sections; two of which will be retained by PhiloWilke Partnership. 1. After review, produce duplicates. 2. Retained samples will not be returned to unless specifically so stated. 3.10 SUBMITTAL PROCEDURES A. Transmit each submittal with approved form. B. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix. C. Identify Project,, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate on each copy. D. Apply General Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents. E. Schedule submittals to expedite the Project, and coordinate submission of related items. F. For each submittal for review, allow 15 days excluding delivery time to and from the Architect. 211-012R / MHMP Level 29 Oncology Clinic 013000-4 ADMINISTRATIVE REQUIREMENTS

G. Identify variations from Contract Documents and Product or system limitations that may be detrimental to successful performance of the completed Work. H. Provide space for Design Engineer and PhiloWilke Partnership review stamps. I. When revised for resubmission, identify all changes made since previous submission. J. Distribute reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements. K. Submittals not requested will not be recognized or processed. END OF SECTION 211-012R / MHMP Level 29 Oncology Clinic 013000-5 ADMINISTRATIVE REQUIREMENTS