Contents. 1 Introduction Assessment criteria Assessment Recommendations References... 8

Similar documents
Goals, progress and difficulties with regard to the development of German nuclear standards on the example of KTA 2000

ELECTRICAL POWER ENGINEERING

TABLE OF CONTENT

Table 6.1 Fault Code List Code indication (Note 3)

COOPERATIVE PATENT CLASSIFICATION

OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES

AGN 005 Fault Currents and Short Circuit Decrement Curves

ESB National Grid Transmission Planning Criteria

Survey of Operational Events

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

Company Replaces previous document Document ID Issue E.ON Elnät Sverige AB Ny engelsk utgåva D

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

CONTENTS. 1. Introduction Generating Stations 9 40

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter

Protective Relaying for DER

INCIDENTS CLASSIFICATION SCALE METHODOLOGY

Residual Current Operated Circuit-Breakers (RCCBs)

Protection of Electrical Networks. Christophe Prévé

Alternative Approaches and Dynamic Analysis Considerations for Detecting Open Phase Conductors in Three Phase Power Systems

TN, TT & IT Earthing Arrangements

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code)

Hamdy Faramawy Senior Application Specialist ABB Sweden

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

This document covers common questions concerning the design of an effectively grounded system.

SYNCHRONISING AND VOLTAGE SELECTION

NIPSCO Energy Symposium

SECTION AUTOMATIC TRANSFER SWITCH

CHAPTER 5 DESIGN OF DSTATCOM CONTROLLER FOR COMPENSATING UNBALANCES

Microgrid Protection

Digital Fault Recorder Deployment at HVDC Converter Stations

RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements

Transmission Interconnection Requirements for Inverter-Based Generation

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Impacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering

Current monitor Type C 551

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

Excitation Systems THYRIPART. Compound-Excitation System for Synchronous Generators. Power Generation

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Curso de Transmissão em Corrente Continua Rio de Janeiro, de Junho, 2007

Miniature circuit-breakers S 280 UC series. System pro M. Technical data

VOLTAGE OPTIMIZATION FOR INDUSTRY, TRADE, BUSINESS AND LOCAL NETWORKS

Voltage Sags Evaluating Methods, Power Quality and Voltage Sags Assessment regarding Voltage Dip Immunity of Equipment

Transformer energisation after network blackout

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

SUBJECT HEADING: Switching Programmes ISSUE: 18

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers

EH2741 Communication and Control in Electric Power Systems Lecture 2

Energy Networks Association

PARAMETER LIST PARAMETER LIST

We take care of it. Special Publication. Power Quality PQ-Box 100/200. Expert opinions: Emergency power supply for hospitals and computer centres.

Table of Contents. Introduction... 1

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Generation Interconnection Requirements at Voltages 34.5 kv and Below

Babak Enayati National Grid Thursday, April 17

BED INTERCONNECTION TECHNICAL REQUIREMENTS

Power systems Protection course

Power System Stability. Course Notes PART-1

PROTECTION of electricity distribution networks

PSV3St _ Phase-Sequence Voltage Protection Stage1 (PSV3St1) Stage2 (PSV3St2)

XUA1 AC Voltage and phase balance relay. (August 1996) Manual XUA1 (Revision New)

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

BUS2000 Busbar Differential Protection System

E N G I N E E R I N G M A N U A L

XUA1 - AC Voltage and phase balance relay

CROSS Chassis from 160 A to 450 A

1

TECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM

TS RES - OUTSTANDING ISSUES

Electronic relays. Monitoring. Monitoring

Utility Interconnection and System Protection

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP

RELEVANT ELECTRICAL STANDARDS

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Embedded Generation Connection Application Form

TEST REPORT DIN V VDE V :2006 Automatic disconnecting device

CHAPTER 2 ELECTRICAL POWER SYSTEM OVERCURRENTS

Power Quality Basics. Presented by. Scott Peele PE

SECTION PANELBOARDS

UNO-PS/1AC/24DC/150W. Primary-switched power supply unit. Data sheet. 1 Description

SIPROTEC 5 Application Note

FREQUENCY and VOLTAGE, ranges and durations

VI 3 - i TABLE OF CONTENTS

ISO INTERNATIONAL STANDARD. Safety of machinery Basic concepts, general principles for design Part 1: Basic terminology, methodology

RELEVANT ELECTRICAL STANDARDS

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

Appendix D Fault Levels

Installation and start up instructions. Detection of vector shift. Detection of over- and underfrequency. Generator disconnection on mains failure

Renewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

P.O (November 2009) This is an unofficial translation of the latest draft of the Spanish grid code. Source: Jason MacDowell, GE Energy

Unsymmetrical Fault Analysis & Protection Of The Existing Power System

HIGH VOLTAGE CIRCUIT BREAKERS

Analysis and Design of Low-Power Systems

Electrical Power Systems

Power Quality Symptoms What Is Normal? Power Quality Approach. Other Power Quality Solutions

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Transcription:

Note: This is a translation of the RSK recommendation entitled Ein- oder zweiphasiger Ausfall des Haupt-, Reserve- oder Notstromnetzanschlusses. In case of discrepancies between the English translation and the German original, the original shall prevail. RSK recommendation (467 th meeting of the Reactor Safety Commission (RSK) on 26.06.2014) Faults in one or two phases of the main, standby or emergency grid connection Contents 1 Introduction... 2 2 Assessment criteria... 3 3 Assessment... 3 4 Recommendations... 5 5 References... 8 at the Federal Office for Radiation Protection Page 1 of 8

1 Introduction In the years 2012 and 2013, events from several nuclear power plants outside Germany were reported that were due to the faults in one or two phases of the high-voltage grid connection and involved the unavailability and several failures of components of the operational systems and the safety system, as described in GRS Information Notice 2013/05 [1]. On 30.01.2012, an insulator on the high-voltage side (345 kv) of the auxiliary power transformers failed in the Byron-2 plant (Illinois, USA) during full power operation, which resulted in the loss of one phase. This caused an asymmetric voltage situation in two redundancies in the plant s auxiliary power supply, which in turn, led to switch-off by overcurrent protection and unavailability of various consumers, some of them with safety significance. The installed measuring and monitoring devices were not capable of detecting the actual loss of the auxiliary power supply and thus did not trigger the necessary actions (initiation of grid disconnection and activation of the emergency diesel generators). The plant could only be restored to normal condition by manual actions. On 30.05.2013, the Swedish nuclear power plant Forsmark, Unit 3, was in an outage for refuelling and maintenance, auxiliary power was supplied from the main grid, and the standby grid was disconnected. During maintenance work, the electrical protection was actuated so that the high-voltage circuit breaker received an OPEN command. In two of three phases, the breaker on the high-voltage side of the generator transformer then opened on demand, but one phase remained connected with the main offsite power supply. As in Byron, the resulting asymmetric conditions in the plant s auxiliary power supply resulted in the unavailability of various safety-related consumers due to switch-off by overcurrent protection. Some nonsafety-related consumers were destroyed by thermal overload. The installed measuring devices also did not detect the instability in this case and thus the unavailability of the auxiliary power supply and did not trigger any automatic protective actions; normalisation was again only possible by means of manual actions. Despite the sometimes considerable differences in the auxiliary power supply systems between the affected and the German nuclear power plants, transferability of the observed phenomena and failure mechanisms to German plants is given. A more detailed description of both events as well as four additional events under the aspect of open phase condition (OPC) can be found in [1]. For all events, the difficulties were related to the detection of these open phase conditions (OPCs), i.e. the resulting asymmetric voltage conditions. Due to the magnetic coupling of the three phases within transformers, there is a voltage on the low-voltage side for all three phases although asymmetrical up to the level of the nominal voltage (depending on the consumer load) despite the failure in one or two phases on the high-voltage side, but also on the high-voltage side there might only be a slightly changed voltage at all phases due to the aforementioned magnetic coupling effect within the transformer. The magnitude of these voltages depends on the load of the transformer. This applies, in particular, to transformers in a star-delta connection. A reliable detection of such situations therefore depends on the load of the transformer and, in addition, of its neutral treatment (grounded or non-grounded neutral). The voltage measurements currently installed in German NPPs are not capable of ensuring reliable detection and control of an OPC in all phases of operation and at all power levels. at the Federal Office for Radiation Protection Page 2 of 8

OPC has not been taken into account in the designs of nuclear power plants worldwide so far, even though it has the potential that all safety systems may be affected simultaneously. Accordingly, the RSK derives a need for action from it. At its 467 th meeting on 26.06.2014, the RSK discussed the draft recommendation submitted by the RSK Committee on ELECTRIC INSTALLATIONS (EE) and approved it after amendments. 2 Assessment criteria The RSK investigated which requirements exist in international and national regulations for the management of OPCs. It was concluded that phase faults have to be postulated, identified and controlled (see [2], Section 3.9 (1)). Specific requirements detailed on a technical level, in particular regarding their implementation, are not included in the regulations. 3 Assessment The investigations of the RSK focus on OPCs in the grid connections due to the fact that several redundancies can only be affected simultaneously from the grid during power supply. Of particular importance for the impacts of asymmetries are transformers since magnetic coupling of the individual phases occur in the transformers. Consumers on the low-voltage side, such as solenoid valves, pumps, drives and controller drives, may be affected by asymmetric voltage conditions, i.e. they may either be switched off through protective devices or even damaged by load unbalances. An OPC as an initiating event or in connection with a transient as an independent additional failure or due to a certain probability results from a failure of operational installations that may also be located outside the nuclear facility. The RSK derives the requirements regarding the detection of the OPC and for the measures to be taken from the safety requirements for nuclear power plants (Sicherheitsanforderungen an Kernkraftwerke) [2] in combination with the reference values for the frequency of occurrence of events according to the RSK s understanding of safety philosophy (RSK-Verständnis der Sicherheitsphilosophie) [3]. Due to the frequency observed, the RSK assigns an OPC as an initiating event to the second level of defence. The requirements for installations to detect and control the effects are to be specified according to the safety requirements for nuclear power plants [2]. In this context, it has to be checked whether the event sequence OPC in combination with failure of the monitoring system provided is to be assigned to the third level of defence due to the effects. Events where the OPC is postulated as an additional fault independently or conditionally with a certain probability are to be assigned to the respective level of defence according to the frequency of the event itself and under consideration of the additional OPC. The RSK considers the probability to be very low that at the Federal Office for Radiation Protection Page 3 of 8

independently an OPC occurs simultaneously in addition to any initiating event of the second or third level of defence due to a random failure of conductors. There are no reliable figures for OPCs during switching operations (e.g. resulting from reactor trip/turbine trip). The RSK currently assumes that there will be scenarios with frequencies that would have to be classified as level of defence 3. The RSK therefore holds the view that for equipment for detection and control of OPCs the requirements according to [2] for level of defence 3 are to be met, unless it is demonstrated by the operator that less stringent requirements may be applied due to the frequency or permissible effects. First of all, a distinction can be made between single- and two-phase faults. A single-phase fault results in the interruption in one phase of the three-phase grid connection (main, standby or emergency grid connection (third grid connection)). In the event of a two-phase fault, only one phase remains connected to the grid. From operating experience, different causes are known for such asymmetric faults: single- or two-phase faults may be due to a failure of passive components (conductor rupture, insulator breakage) as well as of active components (failure of individual switch poles of circuit breakers). Both types of fault are to be treated equally with regard to the potential effects. In its recommendation, the RSK considers the following: Single- and two-phase fault resulting from conductor rupture, insulator breakage switch pole failure OPC as initiating event plant in power operation plant in non-power operation mode, supply from the main grid (400/220 kv), or standby grid connection (110/220 kv) OPC as an independent additional failure OPC in the time sequence subsequent to reactor trip/turbine trip OPC in the standby grid connection in standby These scenarios are of a general character and do not refer to a specific failure analysis taking into account all possible plant configurations (i.a. transformer neutral treatment, location of the failure, failure type, grid connection concept). Furthermore, the RSK generically compiled the possibilities already available in the plants for detection and control of phase failures and discussed their effectiveness. The following issues were considered: Synchronisation monitoring (monitoring of the synchronous behaviour of all switch poles of a three-phase breaker) at the Federal Office for Radiation Protection Page 4 of 8

Trigger communication (simultaneous automatic opening of the high-voltage- and low-voltage-side breaker of a grid transformer) Generator load unbalance protection Auxiliary power changeover Overvoltage protection Voltage monitoring of the auxiliary power and emergency busbars Signalling in the reactor protection system Undervoltage protection Voltage monitoring for static or rotating inverters Despite the large number of existing monitoring capabilities, an OPC cannot be detected reliably in all cases. For the derivation of recommendations, the RSK formulates basic requirements for the identification and control of asymmetric conditions with respect to current or voltage. On this basis, recommendations are made, taking into account the following operational states: Generator connected to the main grid (400/220 kv) during power operation Refuelling and maintenance outage with supply from the main or standby grid connection Standby transformer in idle mode (standby operation) Emergency grid connection in idle mode (standby operation) Main grid connection in idle mode (standby operation) Power plants in standstill operation mode/post-operational mode/residual operation mode Furthermore, recommendations are made for interim measures. 4 Recommendations The effects of OPCs on the auxiliary power and emergency power supply depend on the plant-specific conditions (transformer parameters, neutral treatment, short-circuit power at the grid node, cable lengths, busbar load, etc.). The plant-specific conditions must therefore be considered in the implementation of recommendations E_2 to E_8. The RSK notes that, for example, methods based on symmetric components (evaluation of positive, negative and zero sequence) are suitable to detect asymmetries due to phase failures. E_1 In the KTA safety standards, the issue of phase asymmetry is only dealt with indirectly. To meet the requirements based on the safety requirements for nuclear power plants, Section 3.9 (1) and their interpretations, it is necessary to reliably detect and control OPCs. After final clarification of the technical details, the relevant standards should be revised accordingly (e.g. KTA 3701, Section 4.1.2 (3), supplement to include OPCs). at the Federal Office for Radiation Protection Page 5 of 8

E_2 E_3 To detect asymmetric voltages in the phases of the three-phase system, all phase-to-phase voltages are to be measured in all grid connections and monitored for deviations by alarm limits. The limit values are to be defined plant-specifically. To protect against impairment by asymmetries, additional protection is to be installed for the detection of an unbalanced load through a reliable current measurements on redundant high-power operational consumers of the 10 kv-power system (e.g. absolute measurement of the unbalanced load current), or current measurement on all supply breakers of the 10 kv busbars (e.g. ratio measurement negative to positive sequence current). For a PWR in operation, disconnection from the main grid is to be actuated by the signals derived from these measurements (e.g. resulting in load rejection to auxiliary power or actuation of auxiliary power changeover) and in case of supply by the standby grid, changeover to emergency diesel generator supply of the affected redundancy is to be actuated (i.e. opening of the section switch between auxiliary power and emergency busbar). For boiling water reactor SWR 72, opening of the section switch is to be actuated in case of operation by the main grid since standby grid connection is actuated by reactor protection signals via measurements of the low voltage and frequency at the emergency busbars. In case of supply by the standby grid, measurements are to be installed between standby grid bus bar and emergency busbar. For implementation of recommendation E_3, measures technically equivalent to the aforementioned current measures may also be applied as e.g. measurement of the negative sequence voltage. E_4 E_5 E_6 E_7 Unavailabilities of the standby grid connection in standby mode due to single- or two-phase faults must be detected by technical devices in order to initiate corrective measures. Unavailabilities of the emergency grid connection due to single- or two-phase faults must be detected by technical devices in order to initiate corrective measures. Unavailabilities of the main grid connection due to single- or two-phase faults before reconnecting the main grid transformers, e.g. after maintenance, must be detected by technical devices to ensure that there is no OPC before returning to main grid supply. For facilities in standstill operation mode/post-operational mode/residual operation mode, the same requirements apply as for power plants during outage mode. Should less requirements result regarding the availability of safety-relevant consumers considering different grace times for event control, less stringent requirements for the detection of OPCs and corresponding measures may be derived from it. This is to be documented and justified accordingly. at the Federal Office for Radiation Protection Page 6 of 8

E_8 Due to the potential for redundancy-wide failures of safety installations, the RSK considers it necessary that equipment is provided that reliably detects OPCs and initiates measures in time so that redundancy-wide failures of safety installations are not to be feared. To the RSK s knowledge, the equipment suitable for this purpose does not have a qualification according to the nuclear rules and regulations for reactor protection devices. Against this background, the RSK concludes that diverse operationally proven equipment should be used. It is to be demonstrated that this design will be appropriate in the long term with regard to effects on process-engineering systems or due to a very low frequency of occurrence of hazard states. As interim measures for the protection against simultaneous failure of safety installations by asymmetries, the following measures are recommended until implementation of the measures according to E_2 to E_8: E_9 E_10 It should be immediately ensured that in the event of an OPC at least one subsystem remains functional for coolant injection and residual heat removal. In order to prevent hazards initiated by OPCs, written procedures are immediately to be developed that describe the plant specific possibilities and criteria for detection of OPCs. In addition, the measures to be derived from it (manual switchover to the standby grid or opening of the section switch between auxiliary power and emergency busbar) are to be described (supplement to the operating manual). at the Federal Office for Radiation Protection Page 7 of 8

5 References [1] GRS, Information Notice (Weiterleitungsnachricht WLN) 2013/05 Unzureichend detektierte Ausfälle einzelner Phasen der Fremd- bzw. Reservenetzanbindung in mehreren ausländischen Anlagen ) [2] Sicherheitsanforderungen an Kernkraftwerke of 22 November 2012, published on 24.01.2013 in the Federal Gazette: BAnz AT 24.01.2013 B3 [3] RSK statement RSK-Verständnis der Sicherheitsphilosophie, 460 th meeting of the RSK on 29.08.2013, published in the Federal Gazette AT 05.12.2013 B4 at the Federal Office for Radiation Protection Page 8 of 8