Control and maintenance of the Superphenix knowledge and its specific sodium skills through an innovative partnership between EDF and AREVA

Similar documents
Innovative solutions in Engineering, Services and Products for nuclear and highly regulated environments

INPRO Dialogue Forum on Legal and Institutional Issues in the Global Deployment of SMRs

French sodium-cooled fast reactor Simulation Program

Brief to the. Senate Standing Committee on Social Affairs, Science and Technology. Dr. Eliot A. Phillipson President and CEO

GROUP OF SENIOR OFFICIALS ON GLOBAL RESEARCH INFRASTRUCTURES

Turning the wheels of your success

University of Massachusetts Amherst Libraries. Digital Preservation Policy, Version 1.3

Implementing the International Safety Framework for Space Nuclear Power Sources at ESA Options and Open Questions

Founding Manifesto Friends of Floating Offshore Wind 18 May 2016

Education and Training in Nuclear Decommissioning

Nuclear Infrastructure Support

Usage of any items from the University of Cumbria s institutional repository Insight must conform to the following fair usage guidelines.

TCP on Solar Power and Chemical Energy Systems (SolarPACES TCP)

CONTACT DETAILS. NNC s Leak Sealing Services. Greg Willetts, Head Of Leak Sealing Services. Phone: +44 (0)

Case Study of Socio economic Impact of Research Infrastructures: ITER Korean Project

Oil & Gas. GST Engineering

i-tech SERVICES DELIVERING INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE

NUGENIA position paper. Ageing of Low Voltage Cable in Nuclear Environment. 12 February 2015

Hard Drilling, Made Easier.

Standard MOD Area Interchange Methodology

Valinox Nucléaire: the first choice for the Chinese customers

THE USE OF A SAFETY CASE APPROACH TO SUPPORT DECISION MAKING IN DESIGN

TERMS OF REFERENCE FOR CONSULTANTS

Rosatom Approach to IPR Management in Collaborative Projects on Innovations

LICENSING THE PALLAS-REACTOR USING THE CONCEPTUAL SAFETY DOCUMENT

Harmonization of Nuclear Codes & Standards Pacific Nuclear Council Working and Task Group Report

It all starts here. Format fermé : 9" x 12" Format ouvert : 18 x 12 Marges : 0,125" Couleurs : CMYK

Commission proposal for Horizon Europe. #HorizonEU THE NEXT EU RESEARCH & INNOVATION PROGRAMME ( )

INTEGRATED SUBSEA PRODUCTION SYSTEMS Efficient Execution and Cost-Effective Technologies Deliver Project Success. Deepsea technologies

RENEWABLE ENERGY SOLUTIONS. oceaneering.com

Wind Energy Technology Roadmap

Office for Nuclear Regulation

SUBSEA 7 AND GRANHERNE ALLIANCE. Engaging Early to Deliver Value

FP7-INFRASTRUCTURES

ERDF Stakeholder Workshop 4 th May 2016: Overview and Priorities

Contribution of civil society to industrial safety and safety culture: lessons from the ECCSSafe European research project

Co-operative Programme on Decommissioning Projects CPD. Jean-Guy Nokhamzon CEA/DEN/DPA

Nuclear decommissioning training by the SCK CEN Academy: transfer of knowledge and practical experience coming from various decommissioning projects

CITY OF BAYTOWN CENTRAL DISTRICT WASTEWATER TREATMENT PLANT GRIT, SECURITY, AND SCADA IMPROVEMENTS SCOPE OF SERVICES

Technical Assistance. Programme of Activities

Trade of Metal Fabrication. Module 5: Pipe Fabrication Unit 3: Flanges Phase 2

Decommissioning conduct Working Group

EGS-CC. System Engineering Team. Commonality of Ground Systems. Executive Summary

Construction Phase Project Management and Documentation

CUSTOMER APPLICATION

FY2013 Indicative Work Programme and Budget Co-regulatory Forum. 18 November 2011

Toronto Reference Library Premium Rental Space Renovation Award of Tender

7 Briefing. Responsible investor

CHAPTER 3 NOVEL TECHNOLOGIES FOR THE DETECTION OF UNDECLARED NUCLEAR ACTIVITIES* Nikolai Khlebnikov, Davide Parise, and Julian Whichello

SECTION PROJECT MANAGEMENT AND COORDINATION

New Realities Facing the Mining and Metals Industry

Experienced project management Total flexibility of the workforce Modern drydocking facilities

Gerald G. Boyd, Tom D. Anderson, David W. Geiser

4 Briefing. Responsible investor

COMPREHENSIVE SOLUTIONS

University of Houston System. System-wide Public Art Committee (SPAC) Operating Procedures Manual

Collaboration Agreement

European Research Infrastructures Framework Programme 7

Leader in Pharmaceutical Films

each time the Frequency is above 51Hz. Continuous operation is required

Item 4.2 of the Draft Provisional Agenda COMMISSION ON GENETIC RESOURCES FOR FOOD AND AGRICULTURE

Technology Transfer: An Integrated Culture-Friendly Approach

National Standard of the People s Republic of China

Facility Services Subgroup Preface for Divisions 21` through 28

Metrology at NRC Canada: An NMI in an RTO Context

Using a third-party cementing laboratory to generate value for your company

Food Product Standards to Support Exports

Follow the Yellow Brick Road

EPPEI status and way forward for Phase 2

PGNiG. Code. of Responsible Gas and Oil Production

Our Acquisition Challenges Moving Forward

Digital Oil Recovery TM Questions and answers

Horizon 2020 and Photonics

The Policy Content and Process in an SDG Context: Objectives, Instruments, Capabilities and Stages

ENGINEERING SHORT COURSES

Joint Industry Programme on E&P Sound and Marine Life - Phase III

MARITIME MANAGEMENT MASTER S DEGREE (ONLINE) Train for a leading role in maritime-based organizations.

ETSU V/06/00187//REP; DTI Pub/URN 01/799 (for Ove Arup reference:

Committee on Development and Intellectual Property (CDIP)

Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management

National BIM Standard - United States Version 3

Chemionix Solutions. Outsourcing. Engineering. Drafting

OFFSHORE FABRICATION

Innovative Approaches in Collaborative Planning

Maverick Inspection Ltd. has been pioneering specialized non-destructive testing in Western Canada

Innovation for Materials Degradation Challenges

University-University and University-Industry alliances and networks promoting European integration and growth

Maasvlakte CCS Project - ROAD

LAW ON TECHNOLOGY TRANSFER 1998

Planning of Knowledge Management System for Decommissioning of Nuclear Facilities

ONR Strategy 2015 to 2020

The use of technical readiness levels in planning the fusion energy development

A. BACKGROUND B. GENERAL TERMS OF REFERENCE

Strategic Partnerships in Offshore Project Installations and Wind Farm Operation

Project: ACT Acorn Feasibility Study

High Performance Engineering

Mining and Petroleum Services Centre of Excellence

International Cooperation in Strengthening Nuclear Security Capacities within Public Company Nuclear Facilities of Serbia

FoundOcean All-Energy Presentation May The experts in subsea grouting for the offshore energy construction industry

Verification and monitoring in the Islamic Republic of Iran in light of United Nations Security Council resolution 2231 (2015)

Transcription:

Control and maintenance of the Superphenix knowledge and its specific sodium skills through an innovative partnership between EDF and AREVA Thomas CALAIS a*, Jean-Claude RAUBER b a AREVA NP, 10, rue Juliette Récamier, 69006 Lyon, France b EDF DP2D, 154 avenue Thiers, 69009 Lyon, France *corresponding author: thomas.calais@areva.com Keywords: decommissioning, Superphenix, sodium, partnership, alliancing. 1) Background Superphenix is a 1200 MWe sodium cooled Fast Breeder Reactor (FBR) located in Creys-Malville (France). Its grid coupling occurred in 1986 and its final shutdown pronounced through a decree, 12 years later, in 1998. Figure 1: General view of Superphenix nuclear plant (EDF) This Superphenix final shutdown decision marked a new stage in the life of the nuclear plant. Decommissioning activities were highly challenging due to the following: Non recurrent and first-of-a-kind (FOAK) characteristics Environment constraints: radiation level, high temperatures, presence of argon, sodium, NaK, soda, hydrogen, etc. Complexity of the primary vessel internal structures Numerous interfaces to manage 1 Full paper #...

Numerous technical uncertainties due to the difficulty in anticipating the effective state of components (sodium and aerosols retentions, tritium concentration, NaK alteration, etc.) 2) Approach At the end of 1998, exchanges took place between EDF as «Superphenix nuclear operator» and AREVA as «Superphenix Nuclear Steam System Supply (NSSS) designer» in order to find the best way to meet the new challenge of decommissioning Superphenix. A key ingredient to achieving success was to ensure that existing local and specific sodium skills were controlled and maintained. AREVA was selected by EDF as its industrial partner for the sodium activities on this project being entrusted with the following missions: Maintaining and adapting a strong EDF / AREVA partnership within the project duration Supplying support as the «NSSS Designer» Rolling-out multidisciplinary skills from the design to the on-site operations Relying on its best technical experts to solve each technical challenge Developing and adapting durable specific skills of its technical team (sodium, mechanical, process, I&C, statutory, etc.) following each stage of the decommissioning 3) Development of the Works This EDF / AREVA partnership on the sodium activities has taken different forms according to the different stages of the project. From 1998 to 2005, AREVA was involved in strategic and feasibility studies on various technical subjects. EDF identified these subjects and AREVA was entrusted with the preliminary studies relying on a dedicated engineering team located in its Lyon office. An initial dismantling plan was drawn up on the basis of these studies results. Initial status No sodium risk No radiological risk Final status Preliminary operations (Defueling, Turbine hall, MHSD) * *MHSD = Decommissioning STAGE 2 Sodium treatment - Design and realization of TNA (Na hydrolysis plant) - Treatment of primary, secondary and auxiliary sodium components - Primary vessel and secondary loops sodium treatment (mechanical and chemical operations) - in 2016 STAGE 3 Dismantling of primary vessel internal structures Reactor building remediation STAGE 4 Demolition and site restoration Figure 2: Superphenix decommissioning schedule in 4 stages Full paper #... 2

From 2006 to 2012, the partnership consisted of a common structure, combining skills from both parties into an integrated team located in the EDF offices in Lyon. This team conducted the high level strategic engineering studies and managed the support workforce, while relying on the technical skills of specialists. The purpose of this organization was to efficiently develop the general decommissioning strategy and the main technical guidelines which would be adopted during these seven years. At the same time, in 2009, volume of field work exceeded the one of engineering activities due to the physical progress of the project. The center of gravity of these activities shifted from Lyon to Creys- Malville, where the nuclear plant is located. Then, the partnership was complemented with an integrated team office located on plant site from 2009 to 2014. This team followed up operations studies and associated operations and managed technical and operational exchanges between the onsite EDF and AREVA teams. The development plan for primary sodium draining is an example of the integrated team outpost coordination activities. Figure 3: Convergence plan for primary sodium draining The success of this partnership can be illustrated at each stage of the project; a number of technical challenges were addressed while maintaining the project deadlines. This includes, for example: TNA sodium hydrolysis plant from design to the start of operations Primary vessel internal structures drilling Four secondary loops sodium carbonation Gas transfer lock dismantling Eighteen large components sodium carbonation 3 Full paper #...

Primary vessel main and complementary sodium draining Laser cuttings of several primary vessel internal sodium retentions as LIPOSO, primary pump skirt, primary vessel penetrations, Bellows seal 13L (+ 300L) Pipe 11L Casing 16L Figure 4: Primary pump transfer to MDG workshop for dismantling after its sodium carbonation Figure 5: Laser cutting of the LIPOSO primary vessel internal structures with the «CHARLI» ROV However, it was also necessary to tighten budget control as the field activities were ramping up, while keeping in mind, and coping with, the high level of uncertainties of such project, which is quite unusual in traditional reactors dismantling activities. Thus, from the end of 2012, EDF and AREVA jointly developed and adapted specific contractual rules for this project in order to: Adopt virtuous contractual measures (Win/Win), encourage both parties to reduce costs and delivery time, work in total technical and financial transparency, limit contractual conflicts, allow a quick and open negotiation on all technical issues occurring during the project (in a partnership spirit). Full paper #... 4

This «alliance» contractual model is now based on a «Target State» achievement for a «Target Amount». The «Target State» matches the end of the sodium activities on site. The «Target Amount» is composed of: A target price without risks, a risks amount based on a risk-analysis approach shared by EDF and AREVA for each work order, a budget envelope covering technical scope variation needed to reach the «Target State». Such contractual mechanism encouraged EDF and AREVA to find optimization of funding allocations thus resulting in simplified technical solutions when possible in order to set more funds aside to cover contingencies. This contractual mechanism fosters a better and easier control on the final project cost. These contractual arrangements include the financial incentives on: The labour cost of each work order, subcontracting cost of each work order, effective labour cost risks of each work order, project milestones and final project cost. Finally, EDF has committed to share the potential savings on this project with AREVA in the form of adjustment activities. This last contractual mechanism is essential because it ensures a stable workload enabling the contractor to mobilize and manage specific skills in the best possible way until the end of the project. 4) Main results Thanks to this strong partnership around the sodium activities, the Superphenix decommissioning project deadlines were met and the budget kept well under control from the beginning of the primary vessel sodium draining in November 2010 until today (i.e. 4,5 years), in spite of all the numerous issues and difficulties encountered which is quite unusual on decommissioning activities. 5 Full paper #...

EMP Bottom Na level Initial sodium level Figure 6: Primary vessel main sodium draining with electromagnetic pump This successful result is based on an efficient optimization strategy shared by the stakeholders and a contract model focused on work site problem-solving, ontime delivery, and budget compliance. These contractual rules are appropriate for: «FOAK» activities with high uncertainties (unsellable) and in an agreement and partnership context, introducing a commitment to achieving technical and commercial transparency. This innovative contractual model, developed by EDF and AREVA for the Creys-Malville decommissioning project, is based on: A common interest for both parties to perform under the target price while sharing gain and pain and an improvement in stakeholder relations and flexibility. 5) Future works The next steps in the Superphenix decommissioning program are the orbital laser cutting of 27 primary vessel penetrations from November, 2015, to March, 2016, and then the primary vessel carbonation, flooding and venting expected before the end of March, 2017. This last operation will mark the end of the sodium risk on site. Full paper #... 6

6) Conclusion Figure 7: «Target State» of the Superphenix primary vessel This partnership-based contractual model is most relevant with projects featuring complex operations and higher-than-usual risks and uncertainties. It is particularly adapted to situations where the project faces significant unknowns. In this case, traditional contracting models, such as lump-sum or costplus-fee could lead to significant overall overruns as both parties are not sufficiently incentivized to sharing the same goal. Equitably sharing the risks and opportunities as implemented with this partnership-based approach provides better control of the project through an increased understanding of the detailed situation and the actual risks. Finally, it facilitates the maintenance of key skills required for the project in the long term, in case of potential shortage (ex: technical expertise, engineering and fabrication, operation, specific knowledge including facilities configuration and history of past operations). 7 Full paper #...