TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS

Similar documents
TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Wind Power Facility Technical Requirements CHANGE HISTORY

E N G I N E E R I N G M A N U A L

BED INTERCONNECTION TECHNICAL REQUIREMENTS

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

Southern Company Interconnection Requirements for Inverter-Based Generation

FACILITY CONNECTION REQUIREMENTS

Transmission Interconnection Requirements for Inverter-Based Generation

The Connecticut Light and Power Company

HOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System

Generation Interconnection Requirements at Voltages 34.5 kv and Below

69 kv to 500 kv INTERCONNECTION REQUIREMENTS FOR TRANSMISSION FACILITIES

I WP Asset # I ~:2 3. I Review Annual. ~c~~ Date: 'l/j(j/! ZL>IJ,...

Generation and Load Interconnection Standard

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

Table of Contents. Introduction... 1

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

Oklahoma Gas and Electric Co. Facility Connection Requirements MAINTAINED BY. Transmission Planning Engineering Department

Technical Requirements For Generation Connected to The ODEC System

Generation and Load Interconnection Standard

HUTCHINSON UTILITIES COMMISSION TRANSMISSION INTERCONNECTION GUIDELINES

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

Embedded Generation Connection Application Form

1

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Technical Interconnection Requirements For Transmission Voltage Customers for Service at 60,000 to 287,000 Volts R XX

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

ESB National Grid Transmission Planning Criteria

SECTION LOW VOLTAGE ACTIVE HARMONIC FILTER SYSTEM NEMA 1 ENCLOSED

Facility Interconnection Requirements for Colorado Springs Utilities Version 03 TABLE OF CONTENTS

Protective Relaying for DER

each time the Frequency is above 51Hz. Continuous operation is required

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Information and Technical Requirements For the Interconnection of Distributed Energy Resources (DER)

60 kv to 500 kv Technical Interconnection Requirements For Power Generators

DRAFT. City of Lethbridge Electric ENGINEERING STANDARDS GUIDELINE FOR GENERATOR INTERCONNECTION THE CITY OF LETHBRIDGE ELECTRIC DISTRIBUTION SYSTEM

Impact Assessment Generator Form

Appendix C-1. Protection Requirements & Guidelines Non-Utility Generator Connection to Okanogan PUD

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

GREAT RIVER ENERGY GREAT RIVER ENERGY GENERATION INTERCONNECTION GUIDELINES. Revision 4

Section 11: Power Quality Considerations Bill Brown, P.E., Square D Engineering Services

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Southern Company Power Quality Policy

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

GENERAL REQUIREMENTS FOR TRANSMISSION INTERCONNECTION

Embedded Generation Connection Application Form

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin

TECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM

Protection of Electrical Networks. Christophe Prévé

Table of Contents. 1.0 Intent and Limitations Intent Limitations Contact Information General Requirements...

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

PQ for Industrial Benchmarking with various methods to improve. Tushar Mogre.

Final ballot January BOT adoption February 2015

OPERATING PROCEDURE. Table of Contents

IEEE sion/1547revision_index.html

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

Connection Impact Assessment Application

Education & Training

GENERATOR INTERCONNECTION APPLICATION Category 3 For All Projects with Aggregate Generator Output of More Than 150 kw but Less Than or Equal to 550 kw

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Voltage and Reactive Procedures CMP-VAR-01

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

Generator Protection GENERATOR CONTROL AND PROTECTION

Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014

Guide and Requirements for Service. at 69,000 to 287,000 Volts R 0.2

Embedded Generation Connection Application Form

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

EH2741 Communication and Control in Electric Power Systems Lecture 2

System Protection and Control Subcommittee

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

FACILITY RATINGS METHOD TABLE OF CONTENTS

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

HOOSIER ENERGY REC, INC. Requirements for Connection of Non Generation Facilities

METERING REQUIREMENTS FOR INTERCONNECTION POINTS OF SERVICE

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Dairyland Power Cooperative June Transmission to Transmission (T-T) Interconnection Guidelines

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

TABLE OF CONTENT

Transmission Interconnection Handbooks For NERC Reliability Compliance Program. Pacific Gas and Electric Company. Combined Version

Transmission to Distribution/ End-User Interconnection Guidelines for the Dairyland Power Cooperative Transmission System

Transcription:

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS Puget Sound Energy, Inc. PSE-ET-160.60 October 30, 2007

TABLE OF CONTENTS 1. INTRODUCTION...1 1.1 GENERAL POLICY...1 1.2 COMPLIANCE WITH NERC INTERCONNECTION STANDARDS...1 2. PSE SYSTEM INFORMATION...5 2.1 VOLTAGE...5 2.2 FREQUENCY...5 2.3 PSE EFFECTIVE GROUNDING...5 3. SYSTEM INTEGRITY...7 3.1 HARMONICS...7 3.2 VOLTAGE - DISTRIBUTION LEVEL...9 3.3 VOLTAGE - TRANSMISSION LEVEL...10 3.3.1 Voltage Control...11 3.3.2 Wind Power Induction Generating Facilities...12 4. GENERAL DESIGN REQUIREMENTS...13 4.1 DISCONNECTING DEVICES...13 4.2 INTERRUPTING DEVICES...13 4.3 STEP AND TOUCH POTENTIAL...13 4.4 INSULATION COORDINATION...13 4.5 CONTROL REQUIREMENTS...13 4.6 EFFECTIVE GROUNDING...14 4.7 EXCITATION EQUIPMENT, INCLUDING POWER SYSTEM STABILIZERS - TRANSMISSION CONNECTED GENERATING FACILITIES...14 4.8 GOVERNOR REQUIREMENTS - TRANSMISSION CONNECTED GENERATING FACILITIES...15 4.9 INDUCTION GENERATORS...15 4.10 INVERTER SYSTEMS...16 4.11 WIND POWER GENERATING FACILITIES...16 4.11.1 Production Control...16 5. MINIMUM INTERCONNECTION PROTECTION REQUIREMENTS...17 5.1 TYPICAL INTERCONNECTION REQUIREMENTS...17 5.2 MINIMUM SYSTEM REQUIREMENTS...18 i

5.3 PROTECTION SYSTEM MODIFICATIONS...18 5.3.1 Modifications for Distribution Interconnections...18 5.3.2 Modifications for Substation Interconnections...19 5.3.3 Modifications for Transmission Interconnections...19 6. METERING: PSE REVENUE, OPERATIONS AND SCHEDULING REQUIREMENTS...21 6.1 GENERAL...21 6.2 REVENUE METERING...21 6.3 RTU (REMOTE TERMINAL UNIT) AND TELEMETRY METERING...23 6.3.1 Generator Sites With A Combined Output Less Than 2 MW...23 6.3.2 Generator Sites With A Combined Output of 2 MW or Greater...23 6.4 GENERATION SCHEDULING REQUIREMENTS...24 6.5 EXPORTING ENERGY...24 6.6 SCADA, RTU AND TELEMETRY REQUIREMENTS...24 7. PROTECTION SETTINGS...27 7.1 INTERCONNECTION PROTECTION...27 7.2 GENERATION PROTECTION...28 7.2.1 Underfrequency / Overfrequency (81 O/U)...28 7.2.2 Alternative to Meeting Underfrequency WECC Requirements...29 8. DEMONSTRATION OF INTERCONNECTION CUSTOMER S PROTECTIVE DEVICES...31 8.1 GENERAL...31 8.2 CALIBRATION...31 8.2.1 Current Transformer (CT)...31 8.2.2 Voltage Transformer (VT), Potential Device (PD), Capacitor Voltage Transformer (CVT), and Coupling-Capacitor Voltage Transformer (CCVT)...32 8.2.3 Relays...32 8.2.4 Testing and Calibration...32 8.3 TRIP AND CIRCUIT CHECKS...32 9. DEMONSTRATION OF GENERATING SYSTEM FUNCTIONALITY...35 9.1 ON-LINE START-UP TESTING...35 9.1.1 Synchronous Generators...36 9.1.2 Induction Generators...36 9.2 POWER FACTOR (PF) CONTROLLER TEST...36 ii

9.3 VAR CAPACITY TESTS...37 9.3.1 Distribution Connected Generators...37 9.3.2 Transmission Connected Generators...37 9.3.3 Transmission Connected Wind Power Generating Facilities...38 9.4 AUTOMATIC GENERATION CONTROL DISPATCHABILITY TESTING...38 9.5 POWER SYSTEM STABILIZER TESTS AND TUNING...38 9.6 WECC-REQUIRED INITIAL AND PERIODIC TESTING...38 10. GENERAL MAINTENANCE REQUIREMENTS...41 10.1 INSPECTION...41 10.2 ANNUAL DEMONSTRATION...41 10.3 CALIBRATION DEMONSTRATION (EVERY 3 YEARS)...42 10.4 DESIGN CHANGES AFTER COMMERCIAL OPERATION...42 11. OPERATING REQUIREMENTS...43 11.1 SWITCHING AND TAGGING RULES...43 11.2 DE-ENERGIZED CIRCUITS...43 11.3 OPERATING LOG...43 11.4 COMMUNICATIONS FACILITIES 2 MW AND GREATER...43 11.5 DISCONTINUANCE OF OPERATIONS...44 ATTACHMENTS 1 through 6...45 INTERCONNECTION PROTECTION AND METERING DIAGRAMS...45 DISTRIBUTION SECONDARY CONNECTIONS > 25 KW TO 300 KW...46 DISTRIBUTION SECONDARY CONNECTIONS > 300 KW TO 5 MW...47 DISTRIBUTION SECONDARY CONNECTIONS > 5 MW TO 10 MW...48 TRANSMISSION CONNECTIONS...49 METERING OPTION A...50 METERING OPTION B...51 APPENDIX A... A-1 TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS... A-1 APPENDIX B...B-1 TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS...B-1 iii

1. INTRODUCTION 1.1 GENERAL POLICY This document is issued in connection with the Federal Energy Regulatory Commission s (FERC) order, Standardization of Generator Interconnection Agreements and Procedures, Final Rule, Order No. 2003, Fed. Reg. 49,846 (Aug. 19, 2003), 104 FERC 61,103 (issued July 24, 2003) (the Order ) and the Standard Small Generator Interconnection Agreement (SGIA) set forth in the Order. All capitalized terms used in this document are used with same meanings given to them in the Order and the SGIA. The requirements stated in this document are intended to ensure, pursuant to Section 5.10.2 of the SGIA, that the Interconnection Customer's Interconnection Facilities (ICIF) are compatible with the telemetry, communications and safety requirements of PSE. In addition, the requirements stated in this document are intended to provide, pursuant to Section 9.3 of the SGIA, operating instructions to the Interconnection Customer consistent with the SGIA and these operating protocols and procedures. To those ends, the requirements cover the necessary interconnection equipment (relays, breakers, etc.) to be installed, owned, and maintained by the Interconnection Customer and the ICIF needed to disconnect parallel generation from PSE s electric system whenever a fault or abnormality occurs. Any modifications to this document will be provided to applicable Interconnection Customers. For purposes of this document and the SGIA, Applicable Reliability Council means the Western Electricity Coordinating Council (WECC). Interconnection Customers and PSE personnel shall apply this document and the system reliability performance requirements of the North American Electric Reliability Corporation (NERC), WECC, Northwest Power Pool (NWPP) and PSE when planning installations of independently owned or controlled generation throughout the planning horizon. 1.2 COMPLIANCE WITH NERC INTERCONNECTION STANDARDS NERC Standard FAC-001-0 Facility Connection Requirements, in requirement R2.1, states the Transmission Owner shall, Provide a written summary of its plans to achieve the required system performance...throughout the planning horizon. This document represents such a written summary of PSE s plans to achieve the required system performance of requirement 2.1. Additionally, Requirement R2.1.1 states the written summary will address, Procedures for coordinated joint studies of new facilities and their impacts on the interconnected transmission systems. To meet this requirement, studies performed by the Interconnection Customer and PSE to achieve the required system performance may include, but are not limited to, short circuit, power flow, transient stability, and 1

harmonics. With respect to coordination, the planning of Interconnection installations will be coordinated through phone calls and conference calls, meetings, possible site visits, and sharing study results and data with affected transmission owners. WECC policies, procedure and guidelines governing the coordination of plans include WECC Progress Report Policies and Procedures, and WECC Policies and Procedures for Regional Planning Project Review, Project Rating Review, and Progress Reports. Requirement 2.1.2 further states that the written summary will address, Procedures for notification of new or modified facilities to others (those responsible for the reliability of the interconnected transmission systems) as soon as feasible. To comply with this requirement, plans for new or modified facilities will be provided to PSE s interconnection customer as governed by PSE s tariff. Additionally, plans for new or modified facilities will be provided to WECC when they can be made publicly available, which involves announcing such plans on OASIS. Documents governing the notification of plans, and providing models for modification of new or modified facilities include WECC Progress Report Policies and Procedures, WECC Policies and Procedures for Regional Planning Project Review, Project Rating Review, and Progress Reports, WECC Data Preparation Procedural Manual for Power Flow and Stability Studies, WECC Dynamic Modeling Procedure, and WECC Approved Dynamic Model Library. Requirement R3 states that PSE shall maintain and update these facility connection requirements as required. These facility connection requirements shall be maintained and updated from time to time as required. Requirement R3 further states that PSE shall make documentation of these requirements available to the users of the transmission system, WECC, and NERC on request (five business days). Documents of these requirements shall be made available to the users of the transmission system, WECC, and NERC on request (five business days). This document provides for compliance for PSE with NERC Standard FAC-001. This section provides direction to find compliance with the requirements in FAC-001. The following Table 1.2 gives the location in this document where each requirement of FAC- 001 R1 and R2 is met. Some requirements are general and are addressed in many locations, but at least some of the locations are listed. 2

Table 1.2. NERC Standard FAC-001 Facility Connection Requirements NERC Standard FAC-001 Requirement R1. The Transmission Owner shall ensure compliance with NERC Reliability Standards and applicable Regional Reliability Organization, subregional, Power Pool, and individual Transmission Owner planning criteria and facility connection requirements. R2.1. Provide a written summary of its plans to achieve the required system performance as described above throughout the planning horizon: R2.1.1. Procedures for coordinated joint studies of new facilities and their impacts on the interconnected transmission systems. R2.1.2. Procedures for notification of new or modified facilities to others (those responsible for the reliability of the interconnected transmission systems) as soon as feasible. R2.1.3. Voltage level and MW and MVAR capacity or demand at point of connection. R2.1.4. Breaker duty and surge protection. R2.1.5. System protection and coordination. R2.1.6. Metering and telecommunications. R2.1.7. Grounding and safety issues. R2.1.8. Insulation and insulation coordination. R2.1.9. Voltage, Reactive Power, and power factor control. R2.1.10. Power quality impacts. R2.1.11. Equipment ratings. 1 R2.1.12. Synchronizing of facilities. R2.1.13. Maintenance coordination. R2.1.14. Operational issues (abnormal frequency and voltages). R2.1.15. Inspection requirements for existing or new facilities. Section/Page 1.1/p.1, para.4 1.2/p.1, para.1 1.2/p.1, para.2 1.2/p.2, para.2 2.1/p.5; 3.2/p.9-12; 4.11.1/p.16; 9.3/p.37-38; Appendix/p.A1-B5 duty 4.2/p.13 surge 4.4/p.13; 5.1/p.18, bullet 1 5./p.17-19; 7./p.27-29 6./p.21-25 2.3/p.5; 4.1/p.13; 4.3/p.13; 4.6/p.14 4.4/p.13 3.2/p.9-10; 3.3/p.10-12; 4.7/p.14-15 3./p.7-12 Appendix/p.A1-B5 7.1/p.28, para.3; 9.1/p.35, para.1 10./p.41-42 freq. 7.2/p.28-29 volt. 3.2/p.9-10; 3.3/p.10-12 existing 10./p.41-42 new prot. 8./p.31-33 new other 9/p.35-39 11./p.43-44 R2.1.16. Communications and procedures during normal and emergency operating conditions. R3. The Transmission Owner shall maintain, update, and make available 1.1/p.2, para.3 1 PSE does not specify equipment ratings to Interconnection Customer. 3

2. PSE SYSTEM INFORMATION 2.1 VOLTAGE PSE s most common primary local distribution voltage is 12.47 kv. Other local distribution voltages are sometimes used in specific areas (example 4.16 kv or 34.5 kv). The majority of the distribution circuits are effectively grounded (see Section 2.3) and are used for four-wire distribution (phase to neutral) connected loads. Other voltages of PSE s electrical system are 57.5 kv, 115 kv and 230 kv. 115 kv and 230 kv are the most typical transmission facility voltages. 2.2 FREQUENCY The frequency for connection to the PSE s system must be 60 Hz sinusoidal alternating current at a standard voltage (see Section 2.1) and phase rotation. 2.3 PSE EFFECTIVE GROUNDING PSE maintains effective grounding on its distribution and transmission systems as defined by IEEE Std. 142. 5

3. SYSTEM INTEGRITY 3.1 HARMONICS The Total Harmonic Distortion (THD) from the facility will be measured at the facility s metering point or point of interconnection. Harmonics on the power system from all sources must be kept to a minimum. Under no circumstances will the harmonic current and voltage flicker be greater than the values listed in Tables 10.3, 10.4, 10.5 and 11.1 reprinted from the most current version of IEEE Std. 519. Table 10.3 Current Distortion Limits for General Distribution Systems (120 V Through 69,000 V) Maximum Harmonic Current Distortion in Percent of I L Individual Harmonic Order (Odd Harmonics) I sc /I L <11 11 h<17 17 h<23 23 h<35 35 h TDD <20 4.0 2.0 1.5 0.6 0.3 5.0 20<50 7.0 3.5 2.5 1.0 0.5 8.0 50<100 10.0 4.5 4.0 1.5 0.7 12.0 100<1000 12.0 5.5 5.0 2.0 1.0 15.0 >1000 15.0 7.0 6.0 2.5 1.4 20.0 Even harmonics are limited to 25% of the odd harmonic limits above. Current distortions that result in a dc offset, e.g., half-wave converters, are not allowed. *All power generation equipment is limited to these values of current distortion, regardless of actual I sc /I L. I sc = maximum short-circuit current at Point of Interconnection. I L = maximum demand load current(fundamental frequency component) at Point of Interconnection. 7

Table 10.4 Current Distortion Limits for General Transmission Systems (69,001 V Through 161,000 V) Maximum Harmonic Current Distortion in Percent of I L Individual Harmonic Order (Odd Harmonics) I sc /I L <11 11 h<17 17 h<23 23 h<35 35 h TDD <20 2.0 1.0 0.75 0.3 0.15 2.5 20<50 3.5 1.75 1.25 0.5 0.25 4.0 50<100 5.0 2.25 2.0 0.75 0.35 6.0 100<1000 6.0 2.75 2.5 1.0 0.5 7.5 >1000 7.5 3.5 3.0 1.25 0.7 10.0 Even harmonics are limited to 25% of the odd harmonic limits above. Current distortions that result in a dc offset, e.g., half-wave converters, are not allowed. *All power generation equipment is limited to these values of current distortion, regardless of actual I sc /I L. I sc = maximum short-circuit current at Point of Interconnection. I L = maximum demand load current (fundamental frequency component) at Point of Interconnection. Table 10.5 Current Distortion Limits for Generation Transmission Systems (>161 kv) Dispersed Generation and Cogeneration Individual Harmonic Order (Odd Harmonics) I sc /I L <11 11 h<17 17 h<23 23 h<35 35 h TDD <50 2.0 1.0 0.75 0.3 0.15 2.5 >50 3.0 1.5 1.15 0.45 0.22 3.75 >50 3.0 1.5 1.15 0.45 0.22 3.75 Even harmonics are limited to 25% of the odd harmonic limits above. Current distortions that result in a dc offset, e.g., half-wave converters, are not allowed. *All power generation equipment is limited to these values of current distortion, regardless of actual I sc /I L. I sc = maximum short-circuit current at Point of Interconnection. I L = maximum demand load current (fundamental frequency component) at Point of Interconnection. Bus Voltage at Point of Interconnection Table 11.1 Voltage Distortion Limits Individual Voltage Distortion (%) Total Voltage Distortion THD (%) 69 kv and below 3.00 5.0 69001 kv through 161 kv 1.5 2.5 161,001 kv and above 1.0 1.5 NOTE: High-voltage systems can have up to 2.0% THD where the cause is an HVDC terminal that will attenuate by the time it is tapped for a user. 8

3.2 VOLTAGE - DISTRIBUTION LEVEL The Interconnection Customer shall ensure that operation of the ICIF does not adversely affect the voltage stability of PSE s system. Adequate voltage control shall be provided by all Interconnection Customers to minimize voltage deviations on the PSE system caused by changing generator loading conditions. Automatic power factor or VAR controllers must be provided for installations utilizing synchronous generators. Generator installations over 5 kw must maintain power factor between 0.95 bucking or leading (VARS into the generator) and 0.95 boosting or lagging (VARS out of the generator), inclusive, over an operating range of 25% to 100% of maximum rated power during all hours of operation. However, if the Interconnection Customer's Generating Facility is operating with a power factor less than 0.98 bucking or leading, the Interconnection Customer will be responsible for installing some type of reactive power compensation to bring the overall power factor up to the 0.98 bucking or leading minimum level. These power factor requirements are to be met at the point of delivery and/or metering point, during all hours of operation and over all operating conditions. The Interconnection Customer's generator(s) shall be capable at all times of continuous operation at 0.95 to 1.05 per unit voltage, as measured at the Point of Interconnection. The Interconnection Customer's generator(s) shall be capable during electric system disturbances of short term operation at voltages (as measured at the Point of Interconnection), and for durations as provided in the most current version of NERC/WECC Planning Standards, Section I.A, WECC Disturbance-Performance Table. For synchronous generators, sufficient generator reactive power capability shall be provided to withstand normal voltage changes on the PSE system. The generator voltage- VAR schedule, voltage regulator, and transformer ratings (including taps if applicable) will be jointly determined by PSE and the Interconnection Customer to ensure proper coordination of voltages and regulator action. For induction generators, where starting will have an adverse impact on PSE system voltage, step-switched capacitors or other techniques may be required to limit the voltage changes and bring the unit to synchronous speed before connection to PSE. The magnitude and frequency of the voltage flicker (i.e., sudden momentary voltage change) caused by the Interconnection Customer shall not exceed the values given in the most current version of PSE s Standard Practice 0650.4100, Voltage Flicker, (see Figure 3.2). Voltage flicker percentage shall be referenced to generator pre-synchronize or motor pre-start conditions. Some PSE customers have voltage sensitive loads and, if PSE receives complaints from customers affected by the Interconnection Customer, the Interconnection Customer will be responsible for reducing voltage variations even if they are within the parameters stated in the voltage flicker chart in the above referenced PSE Voltage Flicker standard. Voltage flicker will normally be measured at the Point of Interconnection between the Interconnection Customer and PSE. However, at PSE s discretion, if voltage flicker 9

problems are found, the measurement may be taken at the nearest possible present or future PSE customer. The voltage flicker chart does not address the time duration of the voltage drop. For the purposes of this section, a drop of any duration shall be considered as a single occurrence. Such a voltage drop may be acceptable after consultation with PSE, but the Interconnection Customer is responsible for any associated damage caused to the equipment or lost productivity of other PSE customers. It is advised that Interconnection Customers review the most current version of IEEE/ANSI Standard 141 (Red Book) for typical computer sensitivity to very short voltage disturbances. Figure 3.2. Range of observable and objectionable voltage flicker versus time, from PSE Standard 0650.4100 3.3 VOLTAGE - TRANSMISSION LEVEL The Interconnection Customer shall ensure that operation of the ICIF does not adversely affect the voltage stability of PSE s system. Adequate voltage control shall be provided by all Interconnection Customers to minimize voltage deviations on the PSE system caused by changing generator loading conditions. For synchronous generators, sufficient generator reactive power capability shall be provided to withstand normal voltage changes on the PSE system. The generator 10

voltage-var schedule, voltage regulator, and transformer ratings (including taps if applicable) will be jointly determined by PSE and the Interconnection Customer to ensure proper coordination of voltages and regulator action. During electric system disturbances, the Interconnection Customer s generator(s) shall be capable of short term operation at voltages (as measured at the Point of Interconnection), and for durations as provided in the most current version of NERC and WECC voltage ride-through standards for high and low voltage, and the NERC/WECC Planning Standards, Section I.A, WECC Disturbance-Performance Table. The Interconnection Customer s generators shall operate to fulfill this requirement by selecting the appropriate generator main power transformer tap setting. In general, a generator must be designed to remain connected to the PSE system under the following voltage conditions: Normal Conditions. Under normal conditions, the voltage at the Point of Interconnection may range between 95% and 105%. Voltage Disturbance. For a fault on the interconnection transmission bus or a fault on the transmission system that are cleared with normal clearing times. And, following fault clearing, for transient and post-transient voltages remain within the following ranges: Disturbance Transient Voltage Dip Standard Post Transient Voltage Deviation Standard N-1 (Single Contingency) Not to exceed 25% at load buses. Not to exceed 20% for more than 20 cycles at load buses. Not to exceed 5% at any bus. N-2 (Double Contingency) Not to exceed 30% at any bus. Not to exceed 20% for more than 40 cycles at load buses. Not to exceed 10% at any bus. 3.3.1 Voltage Control The Interconnection Customer s synchronous generator(s) shall be designed to be able to operate in such a manner as to provide and deliver, at the Point of Interconnection, for voltage or power factor requested by PSE operators, enough VAR output to obtain a net 0.95 power factor boosting or lagging (VARS are supplied to PSE s system by the Generating Facility) minimum at the maximum rated (MW) generator capacity. Note that if the Point of Interconnection is on the transmission voltage side of the step-up transformer(s), the VARS absorbed by the step-up transformer(s) must be provided by the Interconnection Customer and the net 0.95 power factor at the Point of Interconnection is determined after transformer VARS are absorbed. Additionally, the Interconnection Customer s synchronous generator(s) shall be designed to be able to operate in such a manner as to provide and deliver, at the Point of Interconnection, for voltages or power factor requested by PSE operators, enough VAR absorption to obtain a net 0.95 power factor bucking or leading (VARS are absorbed from PSE s system by the Generating Facility) minimum at the maximum rated (MW) generator capacity. 11

3.3.2 Wind Power Induction Generating Facilities Under certain conditions, a self-excited induction generator can produce abnormally high voltages that can cause damage to the equipment of other Interconnection Customers and other customers. Overvoltage relays can limit the duration of such overvoltages but cannot control their magnitude. Because of these problems, the reactive power supply for large induction generators must be studied on an individual basis. In general, self-excitation problems are most likely in rural areas where the PSE system capacity and load density are low. Where self-excitation problems appear likely, special service arrangements will be required. PSE requires the following power factors for wind power Generating Facilities: 1. At the Point of Interconnection of the wind power Generating Facility to the PSE system: The wind power Generating Facility shall have a reactive power compensation scheme, sized to provide and control between a net 0.98 power factor bucking or leading and a net 0.95 power factor boosting or lagging at maximum generation output at the Point of Interconnection to the PSE system. The switching and control of the reactive power shall be done in small enough increments to limit the change in reactive power production or absorption in steady state to steps of no more than 10% of the generated power. 2. Capacitors shall be installed to maintain a power factor of at least 0.98 over a range of 25% to 100% of output rating. The following capacitor banks will be required to compensate the large reactive loads created by wind induction generators: Several steps of capacitor banks for each generator at generator voltage, and Capacitor banks at the collector feeder voltage and located at the substation to compensate the reactive losses in the substation transformers connected at the Point of Interconnection to the PSE system, and for transmission voltage regulation. 3. To ensure adherence to the power factor correction criteria, the wind power Generating Facility developer will be required to perform VAR accounting for all generator loading levels to determine size of capacitor bank at the collector feeder voltage at the substation connected to the PSE System in order to ensure that the wind power Generating Facility meets the power factor criteria defined above. 12

4. GENERAL DESIGN REQUIREMENTS 4.1 DISCONNECTING DEVICES Any switch or other disconnecting device installed by the Interconnection Customer pursuant to Section 9.7.5 of the SGIA must be operable by PSE, must be accessible to PSE at all times, and must be lockable in the open position with PSE s standard padlock. For three-phase installations, gang-operated three pole switches must be installed. Each switch or other disconnecting device shall comply with the most current versions of PSE Standard Specifications 1300.2100 and 1300.2300. Any interconnection breaker shall comply with the most current version of PSE Standard Specification 1300.4000. 4.2 INTERRUPTING DEVICES Any interrupting device installed by the Interconnection Customer must be adequately rated for the available short circuit current. PSE will provide short-circuit data to the customer for use in calculating the required interrupting rating as part of the System Impact Study. 4.3 STEP AND TOUCH POTENTIAL It is the Interconnection Customer s responsibility to ensure that the step and touch potentials meet the most current version of IEEE Std. 80 and that construction complies with National Electrical Safety Code (NESC). 4.4 INSULATION COORDINATION In general, stations with equipment operated at 15 kv and above, as well as all transformers and reactors, shall be protected against lightning and switching surges. Typically this includes station shielding against direct lightning strokes, surge arresters on all transformers, reactors, and surge protection with rod gaps (or arresters) on the incoming lines. 4.5 CONTROL REQUIREMENTS Outputs or interposing relays controlled by programmable logic controls shall not be in series with the interconnection tripping relays and breaker trip coils. All interconnection protection relays shall be capable of tripping the breakers. All interconnection protection shall be powered by station battery DC voltage and must include a DC undervoltage detection device and alarm. The station battery design shall be in compliance with the most current version of IEEE Std. 485. 13

4.6 EFFECTIVE GROUNDING It is the Interconnection Customer s responsibility to ensure that its system is effectively grounded at the point of interconnection. As defined by IEEE Std. 142, an effectively grounded system requires that X0/X1 <3 and R0/X1 < 1. 4.7 EXCITATION EQUIPMENT, INCLUDING POWER SYSTEM STABILIZERS - TRANSMISSION CONNECTED GENERATING FACILITIES Excitation equipment includes the exciter, automatic voltage regulator, power system stabilizer and over-excitation limiter. The following NERC/WECC Planning Standards, Section III.C, shall be observed: S1 - All synchronous generators connected to the interconnected transmission systems shall be operated with their excitation system in the automatic voltage control mode unless approved otherwise by the transmission system operator. (The intent is that continuous automatic voltage control not be overridden by supplementary power factor or reactive power controls.) S2 - Generators shall maintain a network voltage or reactive power output as required by the transmission system operator within the reactive capability of the units. Generator step-up and auxiliary transformers shall have their tap settings coordinated with the electric system voltage requirements. S4 - Voltage regulator controls and limit functions (such as over and under excitation and volts/hertz limiters) shall coordinate with the generator s short duration capabilities and protective relays. The excitation system ceiling voltage shall be at least 150 percent of the rated field voltage. The excitation system must be capable of maintaining no less than 150% of rated field voltage at 70% synchronous machine terminal voltage. The excitation system ceiling current shall have a short time capability no less than the short time thermal overload capability of the synchronous machine field winding. Automatic voltage regulators (AVRs) should be continuously acting solid state analog or digital. Tuning should be in accordance with NERC/WECC Planning Standard Section II.C, G8 reproduced below. Tuning results should be included in commissioning test reports provided to PSE. G8 - Generator voltage regulators to extent practical should be tuned for fast response to step changes in terminal voltage or voltage reference. It is preferable to run the step change in voltage tests with the generator not connected to the system so as to eliminate the system effects on the generator voltage. Terminal voltage overshoot should generally not exceed 10% for an open circuit step change in voltage test. 14

New generators that are connected by a generator step-up transformer to the PSE system at a voltage of 60 kv or higher shall have power system stabilizers, and shall tune and operate them according to the requirements of WECC Policy Statement on Power System Stabilizers. The Policy defines exceptions and suitability requirements. Generating Facilities that are less than or equal to 30 MVA are exempt from such requirements, unless they are part of a complex with an aggregate capacity larger than 75 MVA. Every power system stabilizer shall operate in-service at all times the Interconnection Customer s Generating Facility is connected to the PSE system, except for reasons given in the WECC Policy Statement on Power System Stabilizers. The voltage regulator shall include an overexcitation limiter. The overexcitation limiter shall be of the inverse-time type adjusted to coordinate with the generator field circuit time-overcurrent capability. Operation of the limiter shall cause a reduction of field current from the continuous field current capability. Full automatic voltage regulation shall automatically be restored when system conditions allow field current within the continuous rating. 4.8 GOVERNOR REQUIREMENTS - TRANSMISSION CONNECTED GENERATING FACILITIES All unit governors shall be operated in automatic with droop set as stated in the WECC, Part III, Minimum Operating Reliability Criteria, December 2000, Section 1.C.2 Frequency, Response and Bias, Governors (or as otherwise provided in its most current standard). Governor deadbands shall meet the requirements of NERC/WECC Operating Standard Policy 1, which states: Governors should, as a minimum, be fully responsive to frequency deviations exceeding +/- 0.036 Hz (+/-36mHz). 4.9 INDUCTION GENERATORS Installations over 5 kw capacity will require capacitors to be installed to maintain a power factor of at least 0.95 over a range of 25% to 100% of output rating (see Section 3.3). Such capacitor installation will be at the expense of the Interconnection Customer. Under certain conditions, a self-excited induction generator can produce abnormally high voltages that can cause damage to the equipment of other Interconnection Customers and other customers. Overvoltage relays can limit the duration of such overvoltages but cannot control their magnitude. Because of these problems, the reactive power supply for large induction generators must be studied on an individual basis. In general, selfexcitation problems are most likely in rural areas where the PSE system capacity and load density are low. 15

It is particularly important for the Interconnection Customer to contact PSE to determine if an induction generator can be connected to an existing distribution line. Where selfexcitation problems appear likely, special service arrangements will be required. 4.10 INVERTER SYSTEMS Since inverters can be a harmonic source, the Interconnection Customer shall strictly comply with Section 3.1. 4.11 WIND POWER GENERATING FACILITIES Wind power Generating Facility developers must follow the Utility Interconnection requirements defined in IEEE Standard 1094-1991 (IEEE Recommended Practice for the Electrical Design and Operation of Windfarm Generating Stations). Developers must provide wind turbine detailed technical data for each wind turbine type to be installed at the wind power Generating Facility. 4.11.1 Production Control The control for wind power Generating Facilities must limit production as follows: The production, determined as a one-minute average value, must not at any time exceed the production limit by more than five percent of the maximum power of the wind power Generating Facility. The production limit must be able to be controlled by a single central signal. The control shall be arranged individually for each wind power Generating Facility and control algorithms must be capable of being changed at a later time. The control shall take place at the individual wind turbine, and production control must be capable of reduction to below 20 percent of the maximum power in less than two seconds. High wind speed must not cause more than 20 percent of the Generating Facilities turbines to stop simultaneously. Each generating unit must be capable of controlling power changes to 1 percent or less of the rated power per minute across the entire range between minimum power and maximum power. 16

5. MINIMUM INTERCONNECTION PROTECTION REQUIREMENTS To ensure that all proposed interconnections are handled uniformly, this section outlines the minimum protection requirements for the interconnection to protect PSE s system. 5.1 TYPICAL INTERCONNECTION REQUIREMENTS See Attachment 1 for a one-line diagram of typical interconnection requirements. Project design shall, in accordance with Good Utility Practice, include redundancy and backup protection. For all Generating Facilities > 25 kw, connection to the PSE system through a dedicated service transformer is required. For all non-inverter technology > 25 kw, the interconnection protection shall be utility grade, and shall conform to the most current version of ANSI Standard C37.90. Frequency relays must be solid-state or microprocessor technology. All Generating Facilities > 50 kw require three-phase connections. If generation < 300 kw connects to PSE s system through an inverter or static power converter which complies with UL1741 for non-islanding operation, then no further interconnection protection is required. The design of the interconnection protection shall be based upon a single failure philosophy. Discrete relays may act as a back-up to one another. For multifunction microprocessor based relays, two separate redundant relays are required. For installations < 300 kw, a single microprocessor-based relay is permissible if its alarm will automatically isolate the generation from the PSE system. The microprocessorbased alarm must be of the normally held-open type that closes upon alarm or loss of power. Microprocessor relays provide event recording. Event recording is recommended for all Generating Facilities > 300 kw and may later be required if needed for unresolved operational or fault events. PSE will specify transformer connections for projects greater than 1 MW. Overcurrent protection and breaker failure detection and tripping are required on all generation >300 kw. Failure of the interconnection breaker must initiate secondary action to isolate the generation from PSE s system. If adequate sensitivity of interconnection relays is not achievable with aggregated generation, phase overcurrent relaying will be required on each generator. Any protective relay not equipped with an internal isolation device must be connected through an external test device, such as the ABB FT-1 switch or equivalent. 17

If lightning arresters are installed, they must be properly rated for the system, and must be within the protective zone of the interconnection relays. Because of feeder relay desensitization, connection to the distribution substation by a dedicated feeder is required. At 12 kv projects > 5 MW or < 10 MW require a dedicated feeder. Project sizes are proportional at other voltages. Generation over 10 MW must connect to facilities having a voltage of greater than 35 kv. Table 5.1 List of One-Line Diagrams Generation Capability See Attachment 25 kw Schedule 150 >25 kva requires a dedicated transformer > 25 to 300 kw Attachment 1 > 300 kw to 5MW Attachment 2 > 5 to 10 MW Attachment 3 > 10 MW Attachment 4 5.2 MINIMUM SYSTEM REQUIREMENTS In all cases, the IFIC must isolate the generation from the PSE system when power is disconnected from its PSE source, including, but not limited to, before any reclosing (automatic or manual) takes place. The Interconnection Customer shall prevent the IFIC from automatically re-energizing the PSE system. For all generation added to the PSE distribution system, the total symmetrical three-phase fault current shall not exceed 10,000 amps rms and the total symmetrical single-phase-toground fault current shall not exceed 7,100 amps rms. This total includes the proposed generation and the existing system, which includes all aggregate generation as calculated by PSE. 5.3 PROTECTION SYSTEM MODIFICATIONS The following PSE protection system modifications may be required: 5.3.1 Modifications for Distribution Interconnections For a Generating Facility whose total capacity is 50% of the Interconnection Customer s minimum load, system modifications to PSE s system may be required to detect and clear certain faults. Depending upon the location of the Generating Facility along the distribution circuit, smaller generation may require further protection and system changes when its capacity is a high percentage of the PSE s system load. 18

For a Generating Facility greater than 1 MW connected to a 15 kv distribution line (size of facility is proportional for other voltages), all existing single-phase fault interrupting devices between the generator and PSE s substation shall be replaced with three-phase interrupting devices. This will prevent possible single-phasing of other PSE customers. When special system modifications are required on the normal feed to a Generating Facility, the generator will not be allowed to operate when fed from an alternate source, unless the alternate source has been similarly modified. The interconnection equipment is to be located as close as possible to the Point of Interconnection between the Interconnection Customer s Generating Facility and PSE s system. Typical distances are within one span of overhead line or 200 feet of unspliced cable. PSE will use prudent engineering judgement to determine when additional protective devices are required at the Point of Interconnection to limit exposure to the PSE system. 5.3.2 Modifications for Substation Interconnections When the generation capacity is 50% or more of the minimum load of the substation feeding the Generating Facility, and if the substation transformer feeding the Generating Facility is protected by fuses on the primary, then the fuses must be replaced with a three-phase interrupting device that will also trip the interconnection breaker when opened. Certain conditions may dictate use of direct transfer trip from PSE s substation to the Generation Facility. These conditions include unacceptably slow clearing for PSE end-of-line faults, the Generation Facility being capable of carrying the minimum feeder load with the PSE source disconnected, or other undesirable operations (such as extended overvoltages or ferroresonance) that cannot be resolved by local protection measures. The communication medium for direct transfer trip is typically dedicated optical fiber. 5.3.3 Modifications for Transmission Interconnections When the generation is 50% of the minimum load of the transmission line feeding the substation, the generation must be disconnected for transmission system faults, in order to prevent islanding. Additional protection devices shall be required. Any generation connected to the transmission system will require overlapping zones of protection. 19

6. METERING: PSE REVENUE, OPERATIONS AND SCHEDULING REQUIREMENTS 6.1 GENERAL Metering may be required for revenue purposes, System Operations purposes, or both, depending on the specifics of the project. Revenue metering is required for the measurement of any function that will be billed under a PSE Scheduled Tariff. The Washington Administrative Code (WAC) requires that revenue metering be owned and operated by PSE, and that it meets stringent accuracy requirements. Even if revenue metering is not required on a project initially, it is often advisable, during the planning and construction of interconnection facilities, to include all the provisions for the possibility of future installation of PSE-owned revenue metering as retrofit installation at a later date can be extremely costly and complicated compared to the incremental cost of including those provisions during the initial construction. Systems Operation metering is used for dispatching, reserves, accounting, and control of the PSE Transmission and Distribution systems. Whether or not System Operations metering is required is the sole discretion of PSE. Often, the revenue metering can also be used to provide meter data for system operations, which is the most cost effective solution when both metering systems are necessary. If System Operations metering is required but revenue metering is not required, it may be possible for the System Operation metering to be customer-owned as Systems Operation metering does not fall under the WAC. Systems Operation metering that is customer-owned must be reviewed in advance by the PSE Electric Meter Engineering Department for function and accuracy. Accuracy must be within +/- 1.0%. 6.2 REVENUE METERING In general, Revenue Metering installation requirements for the different categories of the Interconnection Customer-owned parallel generators are the same as those outlined in PSE s Electric Service Handbook for Commercial/Industrial/Multifamily & Manufactured Housing Developments (PSE Standards 6325.3000-3360). In addition to the PSE Handbook, metering installations shall comply with the requirements of the Electric Utility Service Entrance Requirement Committee (EUSERC), Section 300 or 400, as appropriate. PSE will provide a current one page EUSERC acceptability summary. Preferably, the metering will be located on PSE's side of ownership of the electric facilities and the metering voltage shall normally be the same voltage as the Point of Interconnection for the Generating Facility output. If the voltage at the Point of Interconnection exceeds 15 kv, metering may be installed at the low side of the step-up transformer. In this case, loss compensation shall be applied at the meter to adjust for 21

transformer and line losses between the meter point and the Point of Interconnection. In this case, the Interconnection Customer shall provide PSE with a standard ANSI Power Transformer Test report to be used for transformer loss compensation calculations. For Interconnection Customers who have contracted to sell power to PSE, two metering schemes are available. 1. Metering Scheme Option A shall be used when the Interconnection Customer s load requirements are served directly by the Interconnection Customer s generator. Bi-directional metering shall be utilized for this option, with the delivered energy registers measuring power entering the facility when load exceeds generation, and the received energy registers measuring the power leaving the facility when generation exceeds load. Metering Scheme Option A is illustrated in Attachment 5. 2. Metering Scheme Option B shall be used when the Interconnection Customer has contracted to provide all generator output and PSE or another utility serves the Interconnection Customer s entire load requirements from a separate source. Two meters will be used for this option. At the first metering point, the generator meter, the received energy registers of a bi-directional meter will measure the net output of the generator that is the gross output of the generator minus the metered power consumed by the power production process. The delivered energy registers on the same bi-directional meter will measure the power consumed by the power production support equipment when the generator is off-line. The second metering point, the station service meter, will measure all other loads not associated with the power production process. Metering Scheme Option B is illustrated in Attachment 6. PSE shall provide current and potential transformers, test switches, and the meter(s). Instrument transformers shall be installed by the Interconnection Customer. The Interconnection Customer is responsible for furnishing, installing, and maintaining the meter sockets, switches, enclosures, conduit, protection equipment, and all necessary wiring and connections (except CT and VT secondary wiring). The Interconnection Customer is required to provide a phone line to the site for remote interrogation of the meter. If several meters are required, the Interconnection Customer shall provide a 1-1/2-inch conduit between meter cabinets for communication and control cables between the meters. The Interconnection Customer will provide an auxiliary single-phase 120-Volt source to all meter points. This will provide auxiliary power to the meter in the event the interconnection metering point is de-energized. All revenue and system operation metering installations must be reviewed and approved by the PSE Electric Meter Engineering Department. 22

6.3 RTU (REMOTE TERMINAL UNIT) AND TELEMETRY METERING Balancing Authorities, such as the one operated by PSE, are required to meet NERC, WECC and NWPP operating policies and to conform to Good Utility Practices. One such requirement is to have generating reserves per the WECC Minimum Operating Reliability Criteria and the NWPP Reserve Sharing Procedure. These reserves include regulating, contingency spinning, and contingency non-spinning. For System Operations generation RTU and telemetry metering is needed to manage reserves and to account for contingency load obligations. This section deals with those requirements. 6.3.1 Generator Sites With A Combined Output Less Than 2 MW Real time monitoring is not required for generator sites having a combined output of less than 2 MW. Also, real time monitoring is not required for generators that do not operate in parallel with PSE s system. For the purpose of this Standard, this includes standby generation intended for emergency use only, and generators connected to the system momentarily via closed transition switching (100 ms or less). 6.3.2 Generator Sites With A Combined Output of 2 MW or Greater Real-time monitoring data is required for generation sources with a combined output of 2 MW or greater. This data is sent from the generator site to PSE s Operating Center using RTU and telemetry equipment. A dedicated communication circuit (e.g., leased line) is required to transmit such data. Generation values are transmitted continuously from the source to the Operating Center and hourly accumulations are calculated at the end of each hour for Balancing Authority accounting purposes. These generation values are used for Automatic Generation Control ( AGC ), reserves calculations, forecasting, and for Balancing Authority energy accounting. If applicable, PSE may require indication of the spinning reserve available and for reserves under control. The following includes specific requirements: Meter values sent via RTU and telemetry include real power (MW), energy (MWh) and reactive power (kvar). Totalizing metering quantities from multiple generators at one site is desirable in most cases. PSE will determine telemetry requirements for temporary generators (12 months or less) on a case-by-case basis. Energy Pre-Scheduling may be used as an alternative to telemetry for temporary sites. Both RTU and telemetry require one or more dedicated communication circuits between the project and the PSE operating center. 23

Reasonable access must be provided by the Interconnection Customer to PSE for installation, testing, and repair of the RTU equipment, telemetry equipment, and circuits. The design, purchase, installation, testing, maintenance, and replacement of the remote generation RTU and telemetry equipment, and circuits from the Interconnection Customer s facility to PSE s AGC Dispatch Center, will be the responsibility of the Interconnection Customer. 6.4 GENERATION SCHEDULING REQUIREMENTS Interconnected generation that is either temporary or permanent and equal to or greater than 2 MW shall be prescheduled for each hour using PSE s normal scheduling procedures. The preschedule shows hourly generation plans on a 7-day (168-hour) advance time period, and is updated weekly or as conditions change. If prescheduled generation is taken off line for any reason, the Interconnection Customer shall notify PSE s 24-hour generation dispatcher with an updated generation schedule. 6.5 EXPORTING ENERGY All transmission or distribution arrangements for exporting energy off-site, either within, across, or out of the PSE Balancing Area, requires prescheduling along with metering and telemetry equipment. For applicable rules and procedures for transporting energy see PSE s Open Access Tariff (OATT). 6.6 SCADA, RTU AND TELEMETRY REQUIREMENTS The general RTU and telemetry requirements from the Interconnection Customer to PSE are provided for each generating unit greater than or equal to 2 MW in Table 6.6.1, and such requirements for the Point of Interconnection are provided in Table 6.6.2. SCADA for breaker status is required for the Point of Interconnection between PSE and the Interconnection Customer s generators when generators are dispatchable and connected to PSE s transmission system. PSE s 24-Hour Operating Center must have the ability to disconnect the Generating Facility from PSE s system via SCADA for sites that are 10 MW or greater. Switching procedures for disconnecting the Generating Facility will vary depending upon the bus configuration. Each wind power Generating Facility shall also provide a signal to PSE showing the status of the Generating Facility, such as whether power production has stopped due to lack of wind, too much wind, forced outage, or by external control. Together with signals from the PSE system operator and local measurements (for instance voltage, frequency and wind speed) these signals shall be part of a control system managing the release of the wind turbines for operation. 24