Upper Divertor Cryopump Quarterly Progress Report Presented by B. LaBombard for the Cryopump Team July 26, 2007

Similar documents
Alcator C-Mod Second Quarter FY07 DoE Review

Advanced Tokamak Program and Lower Hybrid Experiment. Ron Parker MIT Plasma Science and Fusion Center

Status Alcator C-Mod Engineering Systems. DoE Quarterly Review October 27, 2005

Lower Hybrid. Ron Parker Alcator C-Mod PAC Meeting January January 2006 Alcator C-Mod PAC Meeting 1

Overview of ICRF Experiments on Alcator C-Mod*

First Results From the Alcator C-Mod Lower Hybrid Experiment.

System Upgrades to the DIII-D Facility

C-Mod ICRF Research Program

Status of C-Mod Diagnostics. Presented by Jim Irby For the C-Mod Group

Facilities and Upgrades PAC Presented by Jim Irby for the C-Mod Group

ICRF Physics in KSTAR Steady State

Facilities and Diagnostics. Jim Irby MIT-PSFC

C-Mod/PSFC MFE DoE Quarterly Review August 10, 2015

Poloidal Transport Asymmetries, Edge Plasma Flows and Toroidal Rotation in Alcator C-Mod

3D modeling of toroidal asymmetry due to localized divertor nitrogen puffing on Alcator C-Mod

Technical Readiness Level For Plasma Control

Development of C-Mod FIR Polarimeter*

Abstract. G.D. Garstka 47 th APS-DPP Denver October 27, Pegasus Toroidal Experiment University of Wisconsin-Madison

Varying Electron Cyclotron Resonance Heating to Modify Confinement on the Levitated Dipole Experiment

Novel Vacuum Vessel & Coil System Design for the Advanced Divertor Experiment (ADX)

Development Status of KSTAR LHCD System

Design and commissioning of a novel LHCD launcher on Alcator C-Mod

Diagnostic development to measure parallel wavenumber of lower hybrid waves on Alcator C-Mod

Initial Results from the C-Mod Prototype Polarimeter/Interferometer

Structural Analysis of High-field-Side RF antennas during a disruption on the Advanced Divertor experiment (ADX)

RF Physics: Status and Plans

FY11 FES Joint Research Target: C-Mod Highlights

P. Koert, P. MacGibbon, R. Vieira, D. Terry, R.Leccacorvi, J. Doody, W. Beck. October 2008

2. Composing and characteristics of EAST

Observation of Electron Bernstein Wave Heating in the RFP

C-Mod ICRF Program. Alcator C-Mod PAC Meeting January 25-27, 2006 MIT Cambridge MA. Presented by S.J. Wukitch

Evaluation of a Field Aligned ICRF Antenna in Alcator C-Mod

Recent progress of 170 GHz Gyrotron in KSTAR

INITIAL RESULTS FROM THE MULTI-MEGAWATT 110 GHz ECH SYSTEM FOR THE DIII D TOKAMAK

High Power Antenna Design for Lower Hybrid Current Drive in MST

Status of the rf Current Drive Systems on MST

Field Aligned ICRF Antenna Design for EAST *

High Field Side Lower Hybrid Current Drive Launcher Design for DIII-D

ICRF Mode Conversion Flow Drive Studies with Improved Wave Measurement by Phase Contrast Imaging

Locked-mode avoidance and recovery without external momentum input using Ion Cyclotron Resonance Heating

Dust Measurements With The DIII-D Thomson system

Detection and application of Doppler and motional Stark features in the DNB emission spectrum in the high magnetic field of the Alcator C-Mod tokamak

Initial Active MHD Spectroscopy Experiments Exciting Stable Alfvén Eigenmodes in Alcator C-Mod

Operational progress of 170GHz 1MW ECH system in KSTAR

High Density LHRF Experiments in Alcator C-Mod and Implications for Reactor Scale Devices

Investigation of RF-enhanced Plasma Potentials on Alcator C-Mod

Measurement of Mode Converted ICRF Waves with Phase Contrast Imaging and Comparison with Full-wave Simulations on Alcator C-Mod

RF Heating and Current Drive in the JT-60U Tokamak

SOL Reflectometer for Alcator C-Mod

Alcator C-Mod ICRF Research Program

External Stimulation of Edge Modes

Ion Heating Arising from the Damping of Short Wavelength Fluctuations at the Edge of a Helicon Plasma Source

A NEW MULTI-POINT, MULTI-PULSE THOMSON SCATTERING SYSTEM FOR THE MST RFP

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY

Alcator C-Mod Ion Cyclotron Antenna Performance

Study of Plasma Equilibrium during the AC Current Reversal Phase on the STOR-M Tokamak

Measurements of Mode Converted ICRF Waves with Phase Contrast Imaging in Alcator C-Mod

Progress in High Gradient Accelerator Research at MIT

Instrumentation Development for a Novel Local Electric and Magnetic Field Fluctuation Diagnostic

ICRF antenna matching systems with ferrite tuners for the Alcator C-Mod tokamak

3.10 Lower Hybrid Current Drive (LHCD) System

FREIA Facility for Research Instrumentation and Accelerator Development Infrastructure and Control Architecture

Wall Conditioning Strategy for Wendelstein7-X. H.P. Laqua, D. Hartmann, M. Otte, D. Aßmus

Experimental results and Upgrade plan of ECH/CD system in KSTAR

Task on the evaluation of the plasma response to the ITER ELM stabilization coils in ITER H- mode operational scenarios. Technical Specifications

GA A25836 PRE-IONIZATION EXPERIMENTS IN THE DIII-D TOKAMAK USING X-MODE SECOND HARMONIC ELECTRON CYCLOTRON HEATING

Active Control for Stabilization of Neoclassical Tearing Modes

Abstract. PEGASUS Toroidal Experiment University of Wisconsin-Madison

Gyung-Su Lee National Fusion R & D Center Korea Basic Science Institute

Investigation of ion toroidal rotation induced by Lower Hybrid waves in Alcator C-Mod * using integrated numerical codes

Present status of the SST-1 project

Structure and Characteristics of the Quasi-Coherent Mode

Field-Aligned ICRF Antenna Characterization and Performance in Alcator C-Mod*

Status and Plan for VEST

GA A24030 ECE RADIOMETER UPGRADE ON THE DIII D TOKAMAK

Contributions of Advanced Design Activities to Fusion Research

Advanced Density Profile Reflectometry; the State-of-the-Art and Measurement Prospects for ITER

Toroidal Rotation and Ion Temperature Validations in KSTAR Plasmas

GA A24691 STATUS OF THE ELECTRON CYCLOTRON HEATING SYSTEM ON DIII D

Profile Scan Studies on the Levitated Dipole Experiment

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University

Magnetic Reconnection and Ion Flows During Point Source Helicity Injection on the Pegasus Toroidal Experiment

Resonant and Non-resonant type Pre-ionization and Current Ramp-up Experiments on Tokamak Aditya in the Ion Cyclotron Frequency Range

Disruption mitigation experiments with one and two gas jets on Alcator C-Mod

Launcher Study for KSTAR 5 GHz LHCD System*

Non-inductive Production of Extremely Overdense Spherical Tokamak Plasma by Electron Bernstein Wave Excited via O-X-B Method in LATE

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS

H. Y. Lee, J. W. Lee, J. G. Jo, J. Y. Park, S. C. Kim, J. I. Wang, J. Y. Jang, S. H. Kim, Y. S. Na, Y. S. Hwang

Whistlers, Helicons, Lower Hybrid Waves: the Physics of RF Wave Absorption for Current Drive Without Cyclotron Resonances

Overview of ICRF Experiments in Alcator C-Mod

ECRH on the Levitated Dipole Experiment

Effect of ICRF Mode Conversion at the Ion-Ion Hybrid Resonance on Plasma Confinement in JET

ICRF Mode Conversion Physics in Alcator C-Mod: Experimental Measurements and Modeling

Real-time Fast Ferrite ICRF Tuning System on the Alcator C-Mod Tokamak

Design of the COMPASS Upgrade Tokamak

Novel Reactor Relevant RF Actuator Schemes for the Lower Hybrid and the Ion Cyclotron Range of Frequencies

National Fusion Research Institute a. Princeton Plasma Physics Laboratory

Radiofrequency Current Drive Experiments in MST

HIGH-POWER CORRUGATED WAVEGUIDE COMPONENTS FOR mm-wave FUSION HEATING SYSTEMS

CRITICAL PROBLEMS IN PLASMA HEATING/ CD IN LARGE FUSION DEVICES AND ITER

Transcription:

Alcator C-Mod Upper Divertor Cryopump Quarterly Progress Report Presented by B. LaBombard for the Cryopump Team July 6, 7

Recent Accomplishments Alcator C-Mod Pumping Slots Gas Baffle Gas Cuffs (for laser access) Periscope Cryopump is Operational Cool-down to LHe attained on May 5 => factor of reduction in base pressure Cryogenic control system works well Easy to operate - technician Seamless integration of cryopump operation with C-Mod shot cycle cool-down, pumping, regen ~ min. Only 6-9 liters of LHe consumed for a run heat exchanger LHe line stepper control valve LN line LHe Dewar PLC Rack

Recent Accomplishments Alcator C-Mod Cryopump Startup Experiments Performed (MP#475) - Cryopump meets D Pumping Speed Benchmark Torr-l/s 6 4 D Injection Rate - D injection at ~35 torr-l/s mtorr Torus Pressure - Chamber ~ 3.5 mtorr liters/s.5 4. 4 5. 3 System Pumping Speed Pumping speed = 9.6E+3 liters/s - Pumping speed ~ 9,6 liters/s 3 4 seconds

Recent Accomplishments Alcator C-Mod - Pumping slot/baffles work as planned USN upper divertor pressures ~ LSN lower divertor pressures. Upper Null - Red Lower Null - Blue MA.5 Plasma Current. m - mtorr mtorr.8.4. NL4 Upper Divertor Pressure Similar neutral pressures Lower Divertor Pressure..5..5. seconds

Recent Accomplishments Alcator C-Mod - Pumping slot/baffles work as planned USN upper divertor pressures ~ LSN lower divertor pressures. Forward Field Direction Upper Null - Red Lower Null - Blue. Reversed Field Direction MA.5 Plasma Current MA.5 Plasma Current m - mtorr mtorr..8.4. NL4 Upper Divertor Pressure Lower Divertor Pressure Similar neutral pressures..5..5. seconds m - mtorr mtorr..8.4. 5 NL4 NL4 Upper Divertor Pressure Lower Divertor Pressure Similar neutral pressures 5..5. seconds.5. - Divertor pressures and pumping throughputs are found sensitive to magnetic field direction

..5 seconds..5...5 seconds..5...5 seconds..5...5 seconds..5. Recent Accomplishments Alcator C-Mod - Effect of SSEP on pumping throughput explored SSEP jog from LSN to USN is being used as a tool to promptly turn on cryopumping - Excellent L-mode density control has been demonstrated Example of SS operation with large pump & puff throughputs: m - Torr-l/s..8.6.4. mtorr 8 6 4 NL4 UDIV Pressure Injection Rate 7556..5..5. seconds - Very flat NL4 trace = density control - Steady state fueling rate of ~ 4 torr-l/s ~, liters/s pumping speed at pump entrance

Remaining Activities Alcator C-Mod Semi-Automatic Cryopump Control - Cool-down & regen initiation based on C-Mod states Continued Development of Cryopump as an Operational Tool MP#498 Density peaking at low collisionality MP#56 H-Mode with cryopumping in upper single null topology...

..5 seconds..5...5 seconds..5...5 seconds..5. Remaining Activities Alcator C-Mod Semi-Automatic Cryopump Control - Cool-down & regen initiation based on C-Mod states Continued Development of Cryopump as an Operational Tool MP#498 Density peaking at low collisionality MP#56 H-Mode with cryopumping in upper single null topology... m - mm Challenge: H-mode density control..5..5. NL4 3 SSEP 3 763 & 9 L-H density rise L-mode reference plasma NL4 9 SSEP 9..5..5. seconds..5..5. - L-H density rise is faster than pumpout - Jog in SSEP controls pumping rate Potential remedy: Evolve H-mode into ELMy regime, apply cryopumping...

C-Mod FY7 Campaign Status presented by R. Granetz Alcator C-Mod quarterly review 6 July 7

C-Mod JOULE target is 5 weeks of research operation in FY7 Budgeted for 6 research days plus 4 startup & conditioning days So far we have completed about 75% of the planned weeks of operation, and we anticipate meeting the 5 week research target around the end of August. We are currently running two run weeks in reversed B T and reversed I p configuration. Remainder of campaign is heavily oversubscribed, as always. It will include operation at several different ICRF frequencies.

C-Mod 7 run utilization through 5 July (in run days) Topic/Group Run Days Original Allocation Pre-Physics* ----------- ------------ -------------------- ------------- LH.3 9.6 H-mode Scenarios 3.33 6 MHD. 6 Divertor/Edge 4.65 6 Transport 5.38 AT Scenarios.5 7 ICRF.9 6 Operations 7.38 6.63 Diagnostics 6.63 4.3 Total Research 44.6 6 5.8 Startup/Condition 8.5 4 6.63 Total Operating 5.76 (~ weeks) 74.44 *Note that some of the research runs, especially under the LH and Diagnostics topics, were actually done during the pre-physics time (tentatively before 74), so these aren't really overrun. We have actually used 8.5 days for official "Startup and Conditioning" activities, out of 4 budgeted, so at this point we get about six bonus days available for research and/or operations (i.e. frequency switches, etc.)

Facility Status and Plans DoE Quarterly Review 7/6/7

Status Alcator C-Mod is currently in operation (details from Bob Granetz) 5 plasma discharges thus far 77% startup reliability Operational activities thus far include Excellent performance of the new upper chamber cryopump Tests of the prototype FFT system Improvements in MSE diagnostic performance Commissioning of new diagnostics and diagnostic upgrades Routine operation of Long Pulse DNB

Updates: Lower Hybrid Systems Lower Hybrid Control and Protection Systems Continuing to work with vendor of high speed CPCI data acquisition card to provide programming area for coupler protection upgrade interlock signals Phase I SBIR awarded to design transmitter protection system upgrade (Rockfield Research, Inc.) Lower Hybrid Stainless Steel Couplers Detailed analysis of brazing process is now complete New brazing fixture being fabricated A 4-window braze test will be performed New couplers and windows are in-house 3

Updates: Lower Hybrid Systems Design of nd launcher continues New 4-way splitter design may reduce complexity of the jungle gym (8-way systems also under investigation) Prototype splitter fabricated and successfully tested at low power Detailed layouts of E-Plane design underway 4 th Cart Fabrication work also continues Klystrons are being refurbished Circulators on order and on schedule for Fall delivery 4-way splitter 8-way splitter 4

Updates: ICRF Systems Continued fast-ferrite-tuner work The power reflection on the match side has been dynamically kept below % for sudden plasma variations, such as L-H transition and pellet injection. For a slowly varying plasma, the power reflection is usually < 3% under feedback control. Low power drivers for transmitters #3 and #4 replaced No saturation Less harmonic generation Reduced performance of J-Port antenna under investigation 5

Updates: Diagnostics Upgrades and additions to CXRS, fast scanning probes, x-ray spectrometers, Thomson scattering, bolometry, Penning gauges, and plasma video system are all operational and providing new data Science Surface Station (S 3 ) is providing important new data on boronization deposition profiles as function of fill pressure and vertical field Dual FIR laser for polarimetry diagnostic expected Feb 8 Single chord rotation measurement during next run campaign Quotes being received for detectors Collaborations with PPPL and UTexas underway Beam position feedback system being tested this run campaign (direct application to ITER) 6

Boronization Boronization is critical to high performance operation of C-Mod Boronization has previously been done with toroidal field only, using an electron cyclotron discharge to produce the plasma --- particles drift out radially; very little localization The addition of a vertical field can improve the localization of the deposited boron Coat proper surfaces Protect outboard components S 3 has been used to study the deposition profiles as a function of vertical field, diborane pressure 7

NSTAR On June st NSTAR reconfigured our 3.8 kv line that supplies power for our LH HV supply, ICRF, DNB, several power supplies, and the alternator drive motor Power was no longer supplied from two stations but just one Remaining station had.5 Ω current limiting reactor in the line that resulted in up to a 35% drop in voltage under load We have reconfigured some of our power systems to use house power (another 3.8 kv source) NSTAR has completed a review and is scheduling removal of the reactor Configuration w/o the reactor will result in acceptable voltage drops 8

Liquid Helium There is a shortage of helium (nation wide) Numerous problems at processing plants Suppliers are reducing allocations We have had to carefully work availability of LHe into our operational planning (cryopump, DNB, diagnostics) Now working with multiple vendors We already had plans to reclaim helium gas for reprocessing at the MIT Cryogenics Lab This effort has been moved up in the schedule and will be available before the next run campaign Exhaust gas will be pressurized and returned via an underground line directly to the Cryolab 9

Plans Complete 5 week operation (approx run days remaining) Continue design of new E-plane launcher and fabrication of new klystron cart (4 klystrons) Complete brazing of 4 new couplers Preparations underway for up-to-air period. A few items from the work list include Improve high voltage performance of J-Port antenna Add gas puff capability to lower hybrid launcher Refurbishment of LH launcher Numerous diagnostic upgrades Additional marker tiles Magnetics refurbishment

Lower Hybrid Experiment Completion of non-joule Milestone: Operate LHRF into L-Mode and H-Mode plasmas, and investigate combined LHRF and ICRF. (June 3, 7) Ron Parker Alcator C-Mod Quarterly Review 6 July 7

Coupling of LHRF into ICRH-heated and H-Mode plasmas depends on density at grill no special problems as long as density maintained x 8 m -3 Operation up to MW with E- and J- port antennae and in ohmic H-mode D- and E-port antennae decrease density at LH antenna Magnetically well connected to LH antenna at C-port Less dramatic effect from E- port, especially following boronization Γ.8.6.4. Short Pulse Coupling Data 6 o 9 o Solid curves: Brambilla coupling code n grill = 4x 7 m -3 o 4 6 8 n [m 3 ] probe x 8

Boronization apparently has beneficial effect on n grill ICRF Power RF Power (MW) [kw] [MW] 7698 Post boronization.6.8..4 ICRF RF Power (MW) [kw] 7474 Pre boronization.8.9.. I sat [A].. I sat [A].. Top Mid Bot.6.8..4.8.9.. n e bar [m 3 ] x 9 8 6.6.8..4 n e bar [m 3 ].5 x.8.9...75.75 I p [MA].8 I p [MA].8.85.6.8..4.85.8.9..

Shot 7695: ICRH-heated L-Mode discharge with LHRF n e bar [m 3 ].5 x.5.6.7.8.9...3.4 I p [MA].75.8.85.6.7.8.9...3.4 Mid n e [m 3 ].5 x.5.6.7.8.9...3.4 V loop [V].5.5.6.7.8.9...3.4 LH Bot n LH Mid n LH Top n e [m 3 e [m 3 ] e [m 3 ] ] Mid T e [kev] 4.6.7.8.9...3.4 4 x 8.6.7.8.9...3.4 x 8 5.6.7.8.9...3.4 4 x 8.6.7.8.9...3.4 Time [s] LH Net [kw] GPC ICRF Net [MW] LH Ref Co [%] 5.6.7.8.9...3.4 5.6.7.8.9...3.4.6.7.8.9...3.4.5.6.7.8.9...3.4 Time [s]

Shot 7673 : ICRH-heated H-Mode discharge with LHRF n e bar [m 3 ].5 x.6.7.8.9...3.4 I p [MA].95.5.6.7.8.9...3.4 Mid n e [m 3 ] 3 x.6.7.8.9...3.4 V loop [V].5.5.6.7.8.9...3.4 Mid T e [kev] LH Top n e [m 3 ] LH Mid n e [m 3 ] 4.6.7.8.9...3.4 4 x 8.6.7.8.9...3.4 4 x 8.6.7.8.9...3.4 GPC LH Net [kw] ICRF Net [MW].5.6.7.8.9...3.4 4.6.7.8.9...3.4.6.7.8.9...3.4 LH Bot n e [m 3 ] x 8 5.6.7.8.9...3.4 Time [s] LH Ref Co [%].5.6.7.8.9...3.4 Time [s]

Shot 7539 : ICRH-heated H-Mode discharge with LHRF n e bar [m 3 ] x..8.6.4.6.7.8.9...3.4 I p [MA].75.8.85.6.7.8.9...3.4 Mid n e [m 3 ] 3 x.6.7.8.9...3.4 V loop [V].5.5.6.7.8.9...3.4 Mid T e [kev] LH Top n e [m 3 ] LH Mid n e [m 3 ] 3.6.7.8.9...3.4 3 x 8.6.7.8.9...3.4 4 x 8.6.7.8.9...3.4 LH Net [kw] GPC ICRF Net [MW].6.7.8.9...3.4 5 4 x 4.6.7.8.9...3.4.6.7.8.9...3.4 LH Bot n e [m 3 ] x 8.6.7.8.9...3.4 Time [s] LH Ref Co [%].4..6.7.8.9...3.4 Time [s]

LH plus ICRH applied early in slow ramp discharge (Ip = 6 ka in ms) delays sawteeth Ohmic ICRH ICRH+LH,

LH plus ICRH applied early in slow ramp discharge (Ip = 6 ka in ms) delays sawteeth

Summary Coupling LHRF and ICRF in L- and H-Mode Plasmas LHRF has been successfully coupled into ICRF heated L-Mode and H- Mode plasmas. No special problem providing adequate density at grill is maintained. (LHRF has also been coupled into Ohmic H-modes and has also triggered them.) LHRF with ICRF has been used as a tool to delay onset of sawteeth during slow rampup discharges. Exploration of synergies between ICRF-heated H-Modes and LHRF will require density control (e.g., upper null, pumped) and higher LHRF power as expected from simulations.

Bremsstrahlung Profiles Broaden as n is Increased Dynamic development of Bremsstrahlung profiles obtained by square wave modulating RF with 5 ms period. Spectra averaged over ~ pulses. Count rate for 4 6 kev (s ) 8 x 4 7 6 5 4 3 HXR Profiles for 6 o Phasing Shots.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms Count rate for 4 6 kev (s ) 9 x 4 8 7 6 5 4 3 HXR Profiles for 9 o Phasing Shots.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms Count rate for 4 6 kev (s ) 8 x 4 7 6 5 4 3 HXR Profiles for o Phasing Shots.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms 5 5 5 3 Viewing Cord Channel 5 5 5 3 Viewing Cord Channel 5 5 5 3 Viewing Cord Channel n =.6 n =.3 n = 3.

Bremsstrahlung Emissivity Becomes Peaked Off-axis for Higher n 4 6 kev emissivity (counts/(mm 3 str s)) 8 7 6 5 4 3 x 4 Emissivity for 6 o Phasing Shots..3.4.5.6.7.8.9 r/a.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms 4 6 kev emissivity (counts/(mm 3 str s)) 8 7 6 5 4 3 x 4 Emissivity for 9 o Phasing Shots..3.4.5.6.7.8.9 r/a.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms 4 6 kev emissivity (counts/(mm 3 str s)) 8 7 6 5 4 3 x 4 Emissivity for o Phasing Shots..3.4.5.6.7.8.9 r/a.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms 5 7.5 ms 7.5 ms.5 ms.5 5 ms Absorption predicted to occur at lower temperature as n increases, T e ~ ( kev ) 3 n

Alcator C-Mod Contributions to ITER Design Review DoE 3 rd Quarter FY7 Review July 6, 7

C-Mod Personnel are Actively Involved in the ongoing ITER Design Review Paul Bonoli Coordinated and drafted the Physics Design Section of the Day Lower Hybrid Current Drive System proposal Currently being evaluated as part of the overall Review Amanda Hubbard and Joe Snipes Sensitivity study for L-H threshold for various proposed perturbations (particularly B T reduction) Recommended more general assessment of threshold, pedestal evolution, hysteresis Report submitted last week Ian Hutchinson, Steve Wolfe, Marco Ferrara Evaluation of vertical stability margins, particularly in light of C-Mod design and operational experience Analysis tools developed for C-Mod being applied Being combined with DIII-D and PPPL proposal to US-ITER for explicit funding Joe Snipes Evaluation of Alfven Eigenmode behavior changes with reduced B T Jim Terry and Jim Irby Evaluation of US credited diagnostics (spectroscopy, polarimetry, interferometry) Josh Stillerman and Tom Fredian Plans and design of the CODAC system for ITER Included participation in recent design review at Oak Ridge Earl Marmar Chairing Diagnostic Design Review for all ITER systems Review at Cadarache, July 9-3 Report is in preparation