Max voltage in 400 kv Networks

Similar documents
Parameters related to voltage issues

ENTSO-E Draft Network Code on High Voltage Direct Current Connections and DCconnected

SELECTING NATIONAL MW BOUNDARIES

INCIDENTS CLASSIFICATION SCALE METHODOLOGY

FREQUENCY and VOLTAGE, ranges and durations

FNN comments on NC HVDC submitted to ENTSO E

Automatic connection/reconnection and admissible rate of change of active power

Requirements for Generators European Network Code High Level Implementation Issues

FREQUENTLY ASKED QUESTIONS

The EU Network Code on Requirements for Generators A Summary

INITIAL RfG FREQUENCY PARAMETER SELECTION. BASED ON DRAFT RfG VALUES. Requirement Range Suggested GB Value Comments

Publishing date: 23/07/2015 Document title: We appreciate your feedback. Share this document

Mid-term Adequacy Forecast July 2016

(EC) ), 11(8) 347/ /2009, (EC)

each time the Frequency is above 51Hz. Continuous operation is required

Work process proposal adaptation FTR. UG Belgian Grid 09/09/2013 Elia

Publishing date: 22/12/2014 Document title: ACER Opinion on the draft ENTSO-E Work Programme We appreciate your feedback

Network Code for HVDC Connections and DC-connected Power Park Modules Explanatory Note

Load-Frequency Control and Reserves Network Code. David Bunney JESG 19 March 2013

VGB / EURELECTRIC s generators RfG Network Code: Needs, Feasibility, Alternative Solutions and Costs

POWER QUALITY REPORT

North-West University, 2 Eskom SOC South Africa

Constant Terminal Voltage. Working Group 1 29 st January 2014

The development of the SA grid code on Power Quality emission. Dr. Gerhard Botha 2017/08/08

This is an unofficial translation. The legally binding text is the original Czech version.

EN 50160:2010 IMPROVEMENTS OF THE REVISED VERSION. TC8X System Aspects of Electricity Supply

DRAFT PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS

TABLE 1 COMPARISION OF ENTSO-E RfG TO GB GRID CODE

This is an unofficial translation. The legally binding text is the original Czech version.

Wind Requirements and Testing for Steady-State Voltage and Frequency Control

Key DRAFT EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 13/12/17

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Network Code for HVDC Connections and DC-connected Power Park Modules Requirement Outlines

Table of Contents. Introduction... 1

HVDC systems default parameters

European Update. 3 rd December 2015

GIE response to public consultation Interoperability NC of ENTSOG

GB FREQUENCY HVDC FREQUENCY RESPONSE PARAMTERS HVDC CONNECTIONS (TITLE II)

NETWORK CODE FOR REQUIREMENTS FOR DEMAND CONNECTION

Generation and Load Interconnection Standard

European Workgroup. 7th May 2015

Parameters related to frequency stability

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Deleted: 9 4 anuary ... [1] Deleted: much more. Formatted ... [2] Formatted Table. Formatted: Indent: Left: 0.06 cm

Energy Networks Association

Identification number : Jean-Louis MARTINAUD. 1, Place Samuel de Champlain PARIS LA DEFENSE Cedex. Address

DRAFT PROPOSAL FOR NC HVDC REQUIREMENTS OF GENERAL APPLICATION

Position Paper.

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management

Generation and Load Interconnection Standard

Fault Ride Through. Antony Johnson / Richard Ierna National Grid TNS Technical Policy

European Update. 5 th May 2016

The General Data Protection Regulation

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

NC HVDC User Group 1 st meeting MINUTES. Date: 12 March 2013 Time: 13h00 16h30 Place: Martins Central Park Hotel, Brussels

Short-Circuit Apparent Power of System Survey Comments

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007.

Use of application-optimised type 1 combined arresters in low-voltage installations

IEEE sion/1547revision_index.html

IEEE Major Revision of Interconnection Standard

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

LIMITS FOR TEMPORARY OVERVOLTAGES IN ENGLAND AND WALES NETWORK

WORKING GROUP REPORT. Frequency and voltage operating range. Prepared by the Working Group for submission to the Grid Code Review Panel

Final draft ETSI EN V2.1.1( )

Proposal for a COUNCIL REGULATION. on denominations and technical specifications of euro coins intended for circulation. (recast)

RADIO SPECTRUM POLICY GROUP. Commission activities related to radio spectrum policy

TS RES - OUTSTANDING ISSUES

BEFORE THE ALBERTA ELECTRIC SYSTEM OPERATOR

We appreciate your feedback

Having regard to the Treaty establishing the European Community, and in particular its Article 286,

CENELEC Guide n 24 Electromagnetic Compatibility (EMC) Standardization for Product Committees

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code)

USING DAMPED AC VOLTAGES

IEEE sion/1547revision_index.html

Official Journal of the European Union L 21/15 COMMISSION

SAUDI STANDARD NO. SASO IEC : 2007 SWITCHES FOR HOUSEHOLD AND SIMILAR FIXED ELECTRICAL INSTALLATIONS

ECC. Doc. ECC(08)038 CEPT. 20 th Meeting Kristiansand, June Date issued: 23 rd May Subject: Password protection required?

MEASUREMENT METHODS OF THE CHARACTERISTICS AND TARGET VALUES OF THE VOLTAGE QUALITY SUPPLIED BY HYDRO-QUEBEC SYSTEM

Participants Affiliation Present Excused. Stakeholders

TECHNICAL SPECIFICATION

Unofficial Comment Form Project Geomagnetic Disturbance Mitigation

6 TH CEER BENCHMARKING REPORT ON THE QUALITY OF ELECTRICITY AND GAS SUPPLY 2016 ELECTRICITY VOLTAGE QUALITY

Trends in the European electricity sector and outlook on the Greek market European Federation of Energy Traders

PROPOSAL FOR NC RFG REQUIREMENTS OF GENERAL APPLICATION

Update on relevant points discussed at 27 th Madrid Forum. Walter Boltz

DERIVATIVES UNDER THE EU ABS REGULATION: THE CONTINUITY CONCEPT

LFC/AGC Nordic and European perspective. Exchange of balancing services international workshop Jan 2011 Whitley Gjerde

POWER QUALITY AND SAFETY

RfG Implementation Fault Ride Through

EFRAG s Draft letter to the European Commission regarding endorsement of Definition of Material (Amendments to IAS 1 and IAS 8)

Considerations and Recommendations for the Harmonisation of Under Frequency Loadshedding Schemes in Multi Zone Meshed Grids

EUROPEAN CENTRAL BANK

This document is a preview generated by EVS

Recommended code of good practice for the interpretation of Directive 2006/42/EC on machinery concerning air handling units Second Edition

COMMISSION REGULATION (EU) No /.. of XXX

Modeling insulation in high-voltage substations

NEMA Standards Publication ICS Adjustable Speed Electrical Power Drive Systems

Wind Power Plants and future Power System Frequency Stability

IMPLEMENTATION PLAN : CONSULTATION PROCESS AND

MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT

Transcription:

Max voltage in 400 kv Networks ENTSO-E GC ESC, 08, Brussels 1

Summary NEED TO WITHSTAND WIDE VOLTAGE RANGE 3 EXISTING CONNECTION RULES 4 KEMA REPORT ON RFG 5 STUDIES ABOUT TOV 6 REFERENCE TO EU NC REGULATIONS ON VOLTAGE RANGES 7 EURELECTRIC QUESTION ON VIOLATION OF RFG S ART.1 8 EURELECTRIC QUESTION ABOUT STANDARDS 9 CONCLUSIONS 11 REFERENCES 12 2

Need to withstand wide voltage range RfG requirements have been written taking into account power system needs. Some examples of such needs are reported below (extracts from the final NC RfG package submitted to ACER in July 2012): 120626 - NC RfG - Justification outlines, p. 35 [1]: Voltage ranges are critical to secure planning and operation of a power system within a synchronous area. These need to be coordinated between adjacent interconnected networks. This can often be a cross border issue. Alternative solutions identified was to: Have no defined voltage ranges. but: However, this would lead to widespread uncertainty in planning and operation of the system with respect to operation beyond normal operating conditions. 120626 - NC RfG Frequently Asked Question, p. 29 [2]: Q: Why do you need the wide voltage ranges for operation? A: Indeed, most of the large-scale disturbances to electricity transmission system in the recent years were caused by a loss of voltage stability 3

Existing connection rules The following table shows existing operational voltage ranges, as used in respective countries, before EU s NC RfG (extracts from the document: 120626 NC RfG - Requirements in the context of present practices [3]). Every voltage range is related to a time period in minutes ( = unlimited operating time): Country Fig. 1 range 2 range 3 range Romania 10 0.90 pu 1.1 pu = Hungary 11 0.925 pu 0.95 pu = 120 0.95 pu 1.05 pu = 1.05 pu 1.1 pu = 30 Poland 12 0.8 pu 0.85 pu = 30 0.85 pu 1 pu = Italy 13 0.875 pu 1.075 pu = Germany 14 0.875 pu 0.9 pu = 120 0.9 pu 1.05 pu = 1.05 pu 1.1 pu = 30 Spain 15 0.90 pu 1.0875 pu = Such values show the need for the operating voltage range high threshold to be not limited to 1.05 pu 4

KEMA report on RfG The KEMA report on RfG [4] (requested by the EC during comitology) further justified the need to have wide voltage withstand capability for the power system: Drafting should be introduced permitting the reinstatement of the additional overvoltage range of 1.0875 pu 1.10 pu for the Type D power generating modules in Article 11, Table 6.2 for parts of the networks of individual TSOs in Continental Europe where it is required for network configuration reasons, as approved by the NRA, provided it is neither detrimental to the operation of the power system nor to the operation of the internal market. The above proposal (as in the paragraph 5.2.1 of the KEMA report about Voltage Ranges) was the conclusion of the analysis and the reply to the comment from the Stakeholders on the values of the voltage ranges proposed during the drafting phase of the RfG. 5

Studies about TOV Several works [5] [6] from Cigrè Working Group 33.10 assess the need for High Voltage equipment to be capable of withstand to Temporary over voltage. Temporary over voltage definition (from Cigrè Electra 185-5 [6]): Temporary over voltages (TOV) are undamped or weakly damped oscillatory overvoltages. Frequencies of TOV range from a few Hz to a few hundreds Hz and TOV duration varies from one period of power frequency to hours. As an example, following figure shows voltage withstand capability related to some HV equipment (from Cigrè Electra 179-3 [5]) Withstand TOV characteristics for power equipment 6

Reference to Voltage Ranges in EU NCs and GLs Art. 16.2(a)(i) of NC RfG: power-generating module shall be capable of staying connected to the network and operating within the ranges of the network voltage at the connection point, expressed by the voltage at the connection point related to the reference 1 pu voltage, and for the time periods specified in Tables 6.1 and 6.2; Table 6.2 applies to networks from 300 kv to 400 kv (for Continental Europe, following ranges are admitted): Voltage Ranges Time period for operation 0,85 pu 0,90 pu 60 minutes 0,90 pu - 1,05 pu Unlimited 1,05 pu 1,10 pu 20 < time period in minutes <= 60 (to be specified by each TSO) Thus, this RfG s article refers to voltage withstand capability in all operating conditions. Art. 27.1 of SO GL: In accordance with Article 18, each TSO shall endeavour to ensure that during the normal state the voltage remains in steady-state at the connection points of the transmission system within the ranges specified in the Tables 1 and 2 of Annex II Annex II - Table 2 applies to networks from 300 kv to 400 kv (for Continental Europe): Continental Europe Synchronous area Voltage Range 0,90 pu 1,05 pu Thus, this SO-GL s article refers to voltage withstand capability in normal operating conditions. 7

Eurelectric question on violation of RfG s Art.1 Statement by Eurelectric: We are convinced that the requirement to withstand 440 kv during 20 minutes or more is a violation of Art. 1 of NC RfG requiring that system operators make appropriate use of the power generating facilities capabilities because the voltage will never be above 420 kv during more than 20 minutes. However RfG, Art. 1 states that: This Regulation establishes a network code which lays down the requirements for grid connection of power-generating facilities, namely synchronous power-generating modules, power park modules and offshore power park modules, to the interconnected system. It, therefore, helps to ensure fair conditions of competition in the internal electricity market, to ensure system security and the integration of renewable electricity sources, and to facilitate Union-wide trade in electricity. This regulation also lays down the obligations for ensuring that system operators make appropriate use of the power- generating facilities' capabilities in a transparent and non-discriminatory manner to provide a level playing field throughout the Union. The whole reading of Art. 1, clarifies that the following sentence: system operators make appropriate use of the power- generating facilities' capabilities is referred to the competition for the European Energy Market and not to the technical capabilities of the power generating modules. 8

Eurelectric question about technical standards 1/2 On the same topic, Eurelectric claims: o o The value of 420 kv is also the upper limit specified in the IEC established technical standard to be taken into particular consideration according to the NC RfG recital 27. A similar requirement for the installations of the grid operators does not exist. moreover, a table on product specification about a GIS switchgear was also shown: ELK-3 C, 420 kv Rated Voltage kv 420 Power-frequency withstand voltage, 1min. kv 650 To further discuss on this topic, we need to show previous terms as defined on Electropedia.org [7]: Term Definition IEV ref Rated voltage Power-frequency withstand voltage Rated value of the voltage assigned by the manufacturer to a component, device or equipment and to which operation and performance characteristics are referred rms value of sinusoidal power frequency voltage that the insulation of the given equipment can withstand during tests made under specified conditions and for a specified duration 442-09-10 614-03-22 9

Eurelectric question about technical standards 2/2 According to previous Electropedia definitions, these values do not refer to voltage withstand capabilities requirement of the NC RfG, but to: Rated voltage Power-frequency withstand voltage the nominal voltage of the switchgear a compliance test which product should withstand thus, this compliance test does not explicitly limit the voltage operational range to a maximum value of 420 kv. About current technical standards on equipment tests, WG-CNC/ENTSO-E agrees with Eurelectric that they do not adequately cover some aspects of RfG requirements. This gap, however, should not affect the validity of the connection requirements, which should instead lead to review or update such standards 10

Conclusions There is no violation of Art.1 of RfG because: Fair use of power generating facilities refers to energy market The voltage limit of 420 kv from Art. 27(1) GL SO is related to Normal Operating Conditions Regarding NC RfG recital 27 about Technical Standards: The voltage limit of 420 kv from IEC standard is a reference to the equipment characteristics The time limit of 1 minute is related to a specific compliance test which equipment should withstand About current technical standards on equipment tests: They don't adequately cover some aspects of RfG requirements This shortcoming, however, should not affect the validity of the connection requirements Equipment testing procedures should be amended according to NC RfG Requirements About applying upper compliance standards: The intent is not to require compliance to 550 kv standard, but to continue using 420 kv standard 11

References [1] 120626 - NC RfG - Justification outlines https://www.entsoe.eu/fileadmin/user_upload/_library/consultations/network_code_rfg/120626_-_nc_rfg_-_justification_outlines.pdf [2] 120626 - NC RfG Frequently Asked Question https://www.entsoe.eu/fileadmin/user_upload/_library/consultations/network_code_rfg/120626_-_nc_rfg_-_frequently_asked_questions.pdf [3] 120626 - NC RfG Requirements in the context of present practice https://www.entsoe.eu/fileadmin/user_upload/_library/consultations/network_code_rfg/120626_-_nc_rfg_-_requirements_in_the_context_of_present_practices.pdf [4] KEMA final Report of November 2013 on the ENTSO-E Network Code: Requirements for Generators https://ec.europa.eu/energy/sites/ener/files/documents/kema_final%20report_rfg%20nc.pdf [5] Temporary overvoltage withstand characteristics of extra high voltage equipment https://e-cigre.org/publication/elt_179_3-temporary-overvoltage-withstand-characteristics-of-extra-high-voltage-equipment [6] Temporary overvoltages. System aspects. Part 1 https://e-cigre.org/publication/elt_185_5-temporary-overvoltages-system-aspects-part-1 [7] Electropedia: The World's Online Electrotechnical Vocabulary (by IEC) http://www.electropedia.org/ 12