PRE-INSPECTION CLEANING OF UNPIGGABLE SUBSEA OPERATIONAL PIPELINES

Similar documents
Challenging Inspections of Offshore Pipelines by Intelligent Pig

Challenging Inspections of Offshore Pipelines by Intelligent Pig

Deepwater Precommissioning Services

Pressurised Subsea Pipeline Repair Recent Case Studies

By: Derek Watson and Lee Robins, Tracerco, UK

Subsea Processing and Cold Flow Technology for Extended Oil and Gas Developments

BRENT BYPASS & FRAM Subsea Projects

Optimizing MEG Systems on Long Subsea Tiebacks. Patrick Wan DOT PERTH, Wednesday 28 Nov 2012

Pipeline Design & Installation Systems

Flow Assurance. Capability & Experience

MARS. Multiple application reinjection system

Implementing a Deepwater- Pipeline-Management System

Innovative Subsea Engineering

A marginal field (re-)development using several alternative methodologies 1

World First Pressurised Subsea Pipeline Repair Facilitated By A Combination Of Non-Piggable And Piggable Isolation Tools

In-line Subsea Sampling: Non-disruptive Subsea Intervention Technology for Production Assurance

REDUCING DEEPWATER PIPELINE INSPECTION COSTS

PIPELINE THROUGH-WALL COMMUNICATION CAPABILITIES By Gary Anderson, Offshore Market Development Director, T.D. Williamson, Inc.

Operating topsides or onshore. It s a lot easier to picture what is happening within the process..

Ring Pair Corrosion Monitor : RPCM

Seatooth Pipelogger. Ian Crowther Executive VP WFS Technologies

Subsea Production Water Management

Using Critical Zone Inspection and Response Monitoring To Prove Riser Condition. M Cerkovnik -2H Offshore

Offshore Development Concepts: Capabilities and Limitations. Kenneth E. (Ken) Arnold Sigma Explorations Holdings LTD April, 2013

A NOVEL APPROACH TO NON-PIGGABLE SUBSEA PIPELINE INSPECTION

INVESTIGATION OF SLUG FLOW IN DEEPWATER ARCHITECTURES. Y. OLANIYAN TOTAL S.A. France

Cathodic Protection & Monitoring

Pumps and Subsea Processing Systems. Increasing efficiencies of subsea developments

Marine Well Containment Company. Charlie Miller, Chief Technology Officer

Oil&Gas Subsea Subsea Technology and Equipments

Flexible solutions for your oil and gas needs

Background Why? What are the business drivers? Subsea, Surface or FLNG? Subsea Dehydration & The SubCool Hybrid Concept

Integrated Modeling of Complex Gas-Condensate Networks

DIFFICULT TO PIG AND TO INSPECT OFFSHORE PIPES

TURNKEY SOLUTIONS FOR NON-INTRUSIVE PIG MONITORING. By William Louden, Online Electronics Limited

Subsea Sampling on the Critical Path of Flow Assurance

Quad 204 Schiehallion Field Restarting a brownfield subsea development

Deepwater Subsea Tie-Back Flow Assurance Overview M U R P H Y S A B A H O I L C O M P A N Y L T D.

Active Heating Potential Benefits to Field Development

Ultrasonic sensors in subsea oil & gas production current use and opportunities

Subsea Pipeline IMR. PT Hallin Marine June 18 th, 2014!

Safety and Environment considerations override all other items and should be considered in all design aspects.

OneSubsea Pumps and Subsea Processing Systems

Subsea Technologies. For Asset and Pipeline Inspection

Speaker at the Americas: Decommissioning and Well Abandonment. September 23, 2015

Tony Owen, Subsea and Pipelines Decommissioning Delivery Manager AOG February 2017

Send your directly to

Case Study (GoM 2016): Enhanced Production Strategies Throughout Field Life Using Standardised Flow Access Modules (FAM) Ian Donald

Flexible Pipe Solutions a competitive approach for Shallow water development. Sylvain Cabalery

Riser & Flowline Intervention Using New Composite Coil Tubing Technology

Implementing FPSO Digital Twins in the Field. David Hartell Premier Oil

Pipeline & Specialty Services (P&SS)

DACON INSPECTION SERVICES I MFL INSPECTION OF PIPELINES

Evolution of Deepwater Subsea / Offshore Market

VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application

Intervention/Decommissioning

INTEGRATED SUBSEA PRODUCTION SYSTEMS Efficient Execution and Cost-Effective Technologies Deliver Project Success. Deepsea technologies

16/09/2014. Introduction to Subsea Production Systems. Module structure. 08 Production Control Systems

Deep offshore gas fields: a new challenge for the industry

Measuring Circumferential Metal Loss Rates in Subsea Pipelines

Increased Safety & Efficiency from a Dedicated Light Well Intervention Vessel on Deepwater Subsea Wells

BP SWOPS Single Well Oil Production System. Sandy Meldrum CEng, MIMechE

Explore & Discover. The future of pipeline inspection

Apache Subsea Projects NORTH SEA REGION. Richard Stark Paul Williams

James Fisher Offshore. Your specialist partner in the delivery of subsea and topside projects.

PIPELINE PIGGING TECHNOLOGY DOWNLOAD

Marine Well Containment Company Response Overview New Orleans Area Committee

PREDICTION OF INTERACTIONS BETWEEN FPSO AND SUBSEA CATHODIC PROTECTION SYSTEMS

Matt Wilson Global Subsea Business Development Manager

MSV Seawell. The vessel that pioneered subsea light well intervention

Richard Rickett, General Manager Engineering and Procurement - March Case Study

PERFORM CHEMISTRY TO ACHIEVE FULL FIELD POTENTIAL

TKP4170(1) PROCESS DESIGN PROJECT

Learn more at

Subsea Structural Engineering Services. Capability & Experience

Offshore Pipelines. Capability & Experience

Bespoke ROV Tooling..The story behind the Subsea Bumble Bee

Advanced Technologies Diversified Solutions

Capability Presentation. Subsea Sampling Richard Barr Thursday 8 February

Subsea Chemical Storage and Injection collaboration project

ENGINEERING SOLUTIONS AND CAPABILITIES. Capacity enhancement for deep water operations THE CHALLENGE THE SOLUTION

FLANGE INTEGRITY MANAGEMENT

High Pressure Intensifier Application on subsea HFL The Dalia Case

INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE

Kuala Lumpur 3 October 2012 State of the Industry of Riserless Light Well Interventions (RLWI)

i-tech SERVICES DELIVERING INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE

Nils J. Vågen Framo Engineering

Dagang Zhang China-America Frontiers of Engineering Symposium San Diego, USA

Subsea Developments Status and Trends. Tore Halvorsen Senior Vice President

BP s deepwater technologies

MOORING SOLUTIONS IN ASIA PACIFIC A SINGLE, LOCAL SOURCE OF MOORING, POSITIONING AND RIG MOVING SERVICES

Marine Well Containment Company. Charlie Miller, Chief Technology Officer

SAFER, SMARTER, GREENER

The intent of this guideline is to assist the Drilling Engineer in his preparation of the deepwater drill stem test design and procedure.

Review of Joint Industry Projects: Delivering Subsea Well Intervention Capability James Burroughs SWIS Operations Manager

ADCHEM International Symposium on Advanced Control of Chemical Processes Gramado, Brazil April 2-5, 2006

Brae Area Pre Decommissioning MARATHON BRAE. Brae Area Decommissioning Programme. June Revision 1.0

Gulfstar One FPS. Nathan Davidson. February 26, 2015

Flow Assurance Services

Multiphase Technology

Transcription:

PRE-INSPECTION CLEANING OF UNPIGGABLE SUBSEA OPERATIONAL PIPELINES By: Jakub Budzowski and Robert Davidson, Halliburton Pipeline and Process Services Europe Abstract Subsequent to risk based inspection (RBI) and corrosion assessment, it was highlighted that several operator pipelines in the North Sea required internal inspection to verify line conditions and to ensure that the pipelines were fit for purpose. It was recognised that some of these pipelines were not readily equipped for pigging operations and challenges existed to enable inspection of the lines. The most feasible means of obtaining detailed inspection data was to perform intelligent pigging (IP) operations, requiring the installation of temporary subsea launch/receive facilities, which were also used to allow pipeline cleaning using a combination of chemical applications, progressive pigging, and pipeline gauging before the IP tools were run. Introduction Aging subsea infrastructure coupled with extended field life has led us to an era where in-line inspection (ILI) of pipelines has become a necessary requirement. Periodic checks on pipe wall quality give credence to continued use or highlight areas in need of remediation. Installation of existing flowlines however have not always taken into account this requirement and, as such, the UK North Sea has many lines deemed unpiggable in their current configuration. To redress this balance on several infield flowlines, one North Sea operator embarked upon a campaign to make the un-piggable piggable. This required the cleaning of multiple lines over individual projects to allow pigging facilities to be incorporated and intelligent tools run. A service company was chosen to provide cleaning and pigging services to these projects as well as pump support for the ILI runs themselves where necessary. Early collaboration was a key component of project success and several methods for cleaning were considered and evaluated for each flowline dependent upon system conditions, such as: Type of deposit(s) expected in the line Volume of deposit(s) expected in the line Pipeline geometry Level of cleanliness required Technical difficulty Existing facilities and cost of refurbishing/replacing equipment to perform cleaning/inspection operations Cost of temporary equipment to perform cleaning/inspection operations Cost of consumables (pigs/chemicals) to perform cleaning/inspection operations Physical constraints, such as platform based fluid handling capabilities and solids handling facilities, were also considered. These had an impact on the method and aggressiveness of the cleaning performed and influenced pumping/pigging speeds. In turn, pigging speed would define the flow regimens within each line, which in turn would impact the chosen cleaning methodology. Copyright 2017 Pigging Products & Services Association

PPSA Seminar 2017 Stratified 0.25 m/s Stratified wavy Stratified mixing Dispersion > 0.6 m/s Fig. 1 Examples of Pipeline Flow Regimens Operations were performed on three fields, as detailed below, each bringing their own challenges and tailored solutions. Field 1 Field 2 Field 3 22 km / 22 km Loop 3.5 km Pipeline Length 44 km Loop Note: One 10 line was 14.5 km 65 km common to both loops. Pipeline Duty and Nominal Diameter 8 Test to 10 Oil Production Dual Diameter 8 Oil Production 10 Oil Production 10 Oil Production 16 Oil Production Subsea Launch Subsea Launch PLR Setup Subsea Receive Subsea Launch Subsea Launch Susbea Receive Subsea Receive Subsea Launch Subsea Receive Topside Receive Disposal of Cleaning Fluid Reused Via Pigging Loop Pumped into Topside Process Disposed to Platform Storage Cells Figure 1 Field Overview Before construction activities for the addition of pig launchers and receivers, all pipelines were required to be deoiled and cleaned to a level of less than 30 ppm oil in water. In addition, barrier checks were necessary to confirm satisfactory primary and secondary barrier from the wells before disconnecting subsea flanges. 2-2

Field 1 Pre-Construction De-Oiling/Flushing PPSA Seminar 2017 Flushing of the pigging loops proved to be relatively simplistic. Both loops were flushed and cleaned to the required cleanliness level using the existing FPSO water injection system. Oil in water was measured at 8 ppm at the end of the flushing operation. The flowlines were disconnected from their risers and temporary spools and subsea pig launchers and receivers were fitted in the system configuration as below. This allowed cleaning and ILI to be performed. Fig. 2 Field 1 Pigging Configuration Progressive Pigging Mechanical Pigging of 10 to 10 Pipeline Loop Although flushed to the required standard, it was essential that the pigging loop met an acceptable cleanliness criterion before running the in-line-inspection tool. As such, the following mechanical cleaning train was run. Mechanical Pig Train: The first mechanical pig train consisted of: Pig 1: Calliper foam pig Pig 2: Low aggression pig Launched and received as two pig train Pig 3: Medium aggression pig Launched and received as single run Pig 4: High aggression pig Launched and received as single run Pig 5: High aggression pig Pig 6: High aggression gauge pig Launched and received as two pig train Pigs were propelled through the pipeline system at speed of 0.8 ms -1. ILI Tool ILI tool was propelled through the pipeline at an average speed of 0.5ms -1. On recovery of the ILI tool, it was in good condition and very little debris was recovered in the bunded area. Mechanical Pigging of 8 to 10 Pipeline Loop Similar to the 10 /10 loop it was essential that the pigging loop meet an acceptable cleanness criterion prior to running In-Line-Inspection Tool. As such, the following mechanical cleaning pigs were run. 2-3

PPSA Seminar 2017 Mechanical Cleaning Pigs: The first mechanical cleaning run consisted of: Pig 1: Low aggression pig Launched and received as single run Pig 2: Low aggression gauge pig Launched and received as single run Pig 3: Medium aggression pig Launched and received as single run Pig 4: High aggression pig Launched and received as single run Pigs were propelled through the pipeline system at speed of 0.8 ms -1. ILI Tool The ILI tool was propelled through the pipeline at an average speed of 0.5ms -1. Upon recovery of the ILI tool, it was observed to be in good condition and very little debris was recovered in the bunded area. Subsea temporary spools and pig traps were removed, risers were refitted, and the field was returned to operation. Field 2 Pre-Construction De-Oiling/Flushing A chemical cleaning/de-oiling train was injected into the pipeline by means of a temporary pumping spread located on a dive support vessel (DSV) and propelled through the pipeline at a speed of 0.5m/s. This allowed a contact time between the wax dissolver and wax deposit of 48 minutes. Following the chemical cleaning train, the pipeline was high velocity flushed with inhibited filtered seawater. Based on the debris assessment supplied by the operator, the following chemical/de-oiling trail was designed: Slug 1: 40m 3 of Wax dissolver Slug 2: 3.2m 3 of X-linked gel Slug 3: 14m 3 of Debris pick-up gel Slug 4: 3.2m 3 of X-linked gel Slug 5: 120% of Pipeline line volume of seawater c/w corrosion inhibitor and chemical cocktail Fig 3. Field 2 De-Oiling and Flushing Train After the chemical train was run, a total of 3.55 tonnes of sand was recovered from the separator on the operator platform as a result of the chemical cleaning. Progressive Pigging Upon completion of the chemical cleaning, the 8 production pipeline had temporary subsea pig traps fitted to facilitate mechanical cleaning before being intelligently pigged. 2-4

Mechanical Pig Train 1 PPSA Seminar 2017 The first mechanical cleaning pig train was to consist of the following: Pig 1: Calliper foam pig Pig 2: Calliper foam pig Launched and received as two pig train Pig 3: Low aggression bi-directional pig Pig 4: Medium aggression b-directional pig Pig 5: Low aggression bi-directional pig Pig 6: Medium aggression bi-directional pig Launched and received as four pig train 120% Line volume flush The calliper foam pigs were launched and recovered before the remaining pigs being launched. Upon recovery of the calliper foam pigs to the bunded area on the DSV, both appeared to be in a good state giving an early suggestion that the pipeline was in good condition. Data was received and downloaded from the dataloggers, allowing it to be sent to Aberdeen office for detailed analysis. During the first pig train runs, high ppm oil in water was measured. To overcome this problem, a total of 120% pipeline line volume of untreated seawater was flushed through the pipeline to try and reduce the volume of hydrocarbons in water. On completion of this pumping operation a decision was made by the operator representative that chemical injection was no longer necessary and the remaining pigs would be run through the pipeline using untreated seawater. The remaining pigs were then launched in turn; however, it was decided not to run the final pig because of positive results received on board the platform, indicating that the pipeline was relatively clean and ready for the second mechanical pig train. Mechanical Pig Train 2 The second mechanical pig train consisted of: Pig 1: High aggression bi-directional pig Pig 2: High aggression bi-directional pig Pig 3: High aggression bi-directional pig Pig 4: Gauge pig Pig 5: Gauge pig Pig 6: High aggression bi-directional pig On the basis of the data received from the calliper foam pig and the results of the first mechanical pig train, the second cleaning train was loaded as discussed previously. On recovery in the bunded area on the DSV, the pigs were found to be in good condition. Additionally, very little debris was recovered. As such, a decision was made to run the ILI tool. ILI Tool The ILI tool was propelled through the pipeline at an average speed of 0.3ms -1. On recovery, the ILI tool was in good condition and very little debris was recovered in the bunded area. Data was captured and sent off for analysis. Temporary pigging equipment was removed subsea and the system reconfigured to restart production. 2-5

Field 3 PPSA Seminar 2017 Pre-Construction De-Oiling/Flushing De-Oiling of 10 Pipeline The 10 pipeline was initially de-oiled using two off calliper foam pigs separated with a 100 linear metre MEG slug. The flushing medium was filtered and chemically treated seawater with 110% of line volume being pumped behind the last calliper foam pig. All of the products were diverted into the 16 pipeline by way of a temporary jumper hose connecting the 10 Receiver to the 16 flushing flange. On completion of de-oiling/flushing operations, the subsea pig launcher and receiver were fitted to facilitate cleaning and ILI operations. De-Oiling of 16 Pipeline Based on the debris assessment supplied by the operator, the following de-oiling train was designed: Slug 1: 50 Linear metres of wax dissolver Slug 2: Gel pig Slug 3: 100 Linear metres of 100% MEG Slug 4: Gel pig Slug 5: 105% of Pipeline line volume of seawater c/w corrosion inhibitor and chemical cocktail Fig 4. Field 3 16 De-Oiling Train An initial slug of 50 linear metres of wax dissolver was injected into the 16 pipeline to reduce potential wax buildup in front of the pig. An additional flush of downline volume plus 20% was necessary to clear downline of wax dissolver before change out of the flushing flange. Treated seawater was used as the flushing medium to fully displace the wax dissolver. Gel pigs were separated with 100 linear metres of MEG, which acted as an interface between treated seawater and hydrocarbon. Chemical Cleaning of 16 Pipeline During this stage all returns were being routed through a temporary debris handling spread located on the operator platform to platform storage cells. The seawater behind the chemical train was intended to aid the pick-up of solid debris based on liquid velocity and expected particle size and specific gravity. Based on the debris assessment supplied by the operator, the following chemical cleaning trail was designed: Slug 1: 6m 3 of X-linked gel Slug 2: 36m 3 of Debris pick-up gel Slug 3: 6m 3 of X-linked gel Slug 4: 105% of Pipeline line volume of seawater c/w corrosion inhibitor and chemical cocktail Fig 5. Field 3 16 Chemical Cleaning Train Note: The crosslinker was broken topside on the operator platform by injecting a suitable gel breaker into the topside pipework in front of the pig receiver. 2-6

PPSA Seminar 2017 Chemical Soak of 16 Pipeline Following the positive receipt of the chemical cleaning train, a chemical soak train was injected into the 16 pipeline. A total of 40 m 3 of wax dissolver was injected and pumped until the train was located over the expected area of wax buildup in the 16 pipeline. The wax dissolver in the 16 pipeline had the transit velocity between 0.21 and 0.42 m/s. The wax dissolver was left in place whilst the 10 mechanical pigging was performed. To make every effort to allow the wax dissolver to work effectively during the extended period of the 10 mechanical pigging operations, two supporting gel plugs (one each end of the chemical slug) were used. Based on the debris assessment supplied by the operator, the following chemical soak train was used: Slug 1: 6m 3 of X-linked gel Slug 2: 40m 3 of Wax dissolver Slug 3: 6m 3 of X-linked gel Slug 4: 110% of Pipeline line volume of seawater c/w corrosion inhibitor and chemical cocktail Fig 6. Field 3: 16 Chemical Soak Train Note: The crosslinked gel was broken on reaching the operator platform by injecting a suitable gel breaker into the topside pipework in front of the pig receiver. During this stage, a subsea pig launcher was fitted. Receipt of pigs/tools was handled on the receiving platform into an existing pig trap. Field 3 Progressive Pigging All pig loading and pig unloading took place on the back deck of a DSV using a hydraulic pig loading and handling tool with the pig launcher being deployed and recovered as necessary. Mechanical Pigging of 10 Pipeline The following pigs were propelled through the 10 line to prepare the system for ILI. Mechanical Pig Train: The first mechanical pig train consisted of: Pig 1: Low aggression pig Launched and received as single run Pig 2: Medium aggression pig Launched and received as single run Pig 3: High aggression pig Launched and received as single run Pig 4: High aggression pig Pig 5: High aggression gauge pig Launched and received as two pig train Pig 6: High aggression gauge pig Launched and received as single run All pigs were propelled through the pipeline system at an average speed of 0.5 m/s. 2-7

ILI Tool: PPSA Seminar 2017 The ILI tool was propelled through the 10 pipeline at an average speed of 0.5m/s and was recovered to the DSV for data download and analysis. Mechanical Pigging of 16 Pipeline The following pigs were propelled through the 10 line to prepare the system for ILI. Calliper Foam Pig Train: The first pig train consisted of: Pig 1: Calliper Foam Pig 1 Pig 2: Calliper Foam Pig 2 The pig train was propelled through the pipeline system at an average speed of 0.6ms -1. Pigs were recovered and data downloaded. During calliper data analysis, no significant bore restrictions were identified in the line, which allowed the cleaning to progress to the next stage. Mechanical Pig Train: The second pig train consisted of: Pig 3: Low aggression pig Launched and received as single run Pig 4: Low aggression gauge pig Pig 2: Medium aggression pig Pig 6: Medium aggression pig Launched and received as three pig train Pig 7: High aggression gauge pig Pig 8: High aggression pig Launched and received as two pig train The pig train was propelled through the pipeline system at an average speed of 0.6m/s with minimal debris received. ILI Tool: The ILI tool was launched subsea and propelled through the 16 pipeline at an average speed of 0.5m/s. The tool and was received topside on the platform and data retrieved for analysis. Summary and Conclusions As cited, the three projects described demonstrate how currently unpiggable systems can be adapted to allow pigging operations to be performed. The use of chemical cleaning in conjunction with gels has been validated as viable to allow subsea intervention for the retrofitting of temporary (or indeed permanent) pigging facilities. These, in-turn, allow more aggressive cleaning to be performed with a view to carrying out full in-line inspection operations. The data received can then be used to justify extension of useable life of existing infrastructure. Early collaboration between operators, construction companies, and pigging/cleaning specialists allows the best fit for purpose methodologies to be devised. Up front preparedness is only half the battle, however, and an ability to react to operational findings is key to timely delivery of project objectives. 2-8