Precast Concrete Panels for Rapid Pavement Repair

Similar documents
Jointed Precast Concrete Pavement

Project No.: VTRC 06-R22 March Period Covered: Contract No.

POSTPRINT UNITED STATES AIR FORCE RESEARCH ON AIRFIELD PAVEMENT REPAIRS USING PRECAST PORTLAND CEMENT CONCRETE (PCC) SLABS (BRIEFING SLIDES)

TechBrief. Precast Concrete Panels for Repair and Rehabilitation of Jointed Concrete Pavements

Precast Concrete Pavement Background Concepts. Project 1517 FHWA, CTR & TxDOT Gary Graham November 15, 2001

Table 5G-2.01: Transverse Joint Requirements. Transverse Joint Type 6 C 12 7 C 15 8 CD CD CD 1 20

PERFORMANCE OF PRECAST CONCRETE PAVEMENTS

Design and Construction of Highway Pavement Joint Systems

PCCP Preservation Steps to Take to Extend Pavement Life and Performance of Your Concrete Pavements

Jointing Rural Intersections

Precast Concrete Pavement

AMENDMENTS Manual of STANDARD SPECIFICATIONS. Adopted by Standard Specifications Committee. Amendment. No. 6. Published by

4.1. Foremen 4.2. Concrete plant manager 4.3. Concrete plant operator 4.4. Personnel performing saw cutting and joint sealing

IGGA Guide Specification: Dowel Bar Retrofit (DBR) Introduction

Chapter 3: APPLICATIONS FOR JOINTED PRECAST PAVEMENT SYSTEMS

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION

Fast Track Precast Concrete Pavement Rehabilitation Pilot Project

AFRL-RX-TY-TR

This brochure is provided by:

Plan Preparation Checklist

Research. Maria Masten, P.E and Gordy Bruhn MnDOT Concrete Engineering Unit CPAM Concrete Paving Workshop March 9, 2017

SECTION 58 PRECAST CONCRETE BOX CULVERT. This work consists of furnishing and installing Pre-cast Concrete Box Culverts.

SECTION 39 - MANHOLES TABLE OF CONTENTS

Dowel Bar Alignment and Location for Placement by Mechanical Dowel Bar Insertion

PART 4 STANDARD DRAWINGS FOR CONSTRUCTION

PERFORM WITH PRECISION WELDED DOWEL ASSEMBLY LOAD TRANSFER PRODUCTS CONCRETE CONSTRUCTION SOLUTIONS BROCHURE

To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved:

Session 8: Load Transfer Restoration. (Dowel Bar Retrofit, Cross-Stitching, and Slot Stitching)

Demolition of Ramp C (SN ): Westbound Ontario Street to Eastbound I-90/94) over I-90/94 (JF Kennedy Expressway)

Full-Depth Concrete Pavement Repairs on the Ohio Turnpike

Deep Creek Canyon US Highway 12

Concrete Pavement Preservation

ABCDE. TechBrief. Best Practices for Dowel Placement Tolerances

Chapter 6: SHOP DRAWINGS AND OTHER SUBMITTALS

PRECAST CONCRETE BRIDGE SUBSTRUCTURE COMPONENTS. Presented by: Matthew Youngblood, PE, SE Scott Noyer, PE Janssen & Spaans Engineering

Responses to Concrete Specifications Survey with Summary (2011)

B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following.

A Solution to Cracking and Stresses Caused by Dowels and Tie Bars

Update: July 20, 2012

Chapter 8 PRE-INSTALLATION PROCEDURES COMMON TO ALL SYSTEMS

Non-Destructive Bridge Deck Assessment using Image Processing and Infrared Thermography. Masato Matsumoto 1

SECTION MANHOLES

EXCAVATION AND BACKFILL

Section 914. JOINT AND WATERPROOFING MATERIALS

Pave-IR Scan TM Primer

SPECIFICATIONS FOR THE INSTALLATION OF CONDUIT SYSTEMS IN RESIDENTIAL SUBDIVISIONS. Notification of Completed Conduit Sections

SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS

ABC and Innovative Bridge Construction for Minnesota Local Roads

Large Scale CalArc Pavers for Sand-Set Pedestrian Use Installations

Prefabricated Elements Case Study

Precast Concrete Pavement Panels on Minnesota Trunk Highway 62 - First Year Performance Report

TxDOT Project : Evaluation of Pavement Rutting and Distress Measurements

DATE: April 22, 2016 (CPR Details Revised & Dated April 22, 2016)

The $13.2 billion Central Artery/Tunnel Project (CA/

LIFE CYCLE COST ANALYSIS OF PRECAST CONCRETE PAVEMENT

AASHTO TIG Promoting the use of Precast Concrete Pavement Systems. Highways for Life PCPS Showcase NJDOT, Mt. Arlington NJ Timothy J.

Construction Tolerances - The following tolerances apply to cast-in-place structures:

AFRL-RX-TY-TR

Dowel Alignment: Measurement and Impacts on Pavement Performance

R&T UPDATE. An Alternative to Traditional Round Dowel Bars Plate Dowel Innovations Driven by Industrial Concrete Paving

Texas Transportation Institute The Texas A&M University System College Station, Texas

Retrofit Dowel Bars in Jointed Concrete Pavement Long-Term Performance and Best Practices

Appendix D Answers To Chapter Review Questions

INSTRUCTIONS *= RECOMMENDED += ACCEPTABLE N/A= NOT AN APPROVER INSTALLATION METHOD

Glass Fiber Reinforced Polymer (GFRP) Dowel Bars - Aslan 600

In Denver, a recently completed flyover

King Mill Lambert DRI# 2035 Henry County, Georgia

Precast Bridge. in only Eight Days. profile. Minimizing construction-related traffic delays and improving workzone

Value Engineering Design Build MODULAR INFRASTRUCTURE

Precast Bendable Concrete Paving Slab for Speedy Road Construction

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT SUBMITTAL AND APPLICATION REQUIREMENTS FOR ProVAL PAVEMENT SMOOTHNESS SOFTWARE

Plate Dowels. An Innovation Driven by Industrial Concrete Paving. Introduction

Tire/Pavement Noise 1

CITY OF LA MARQUE CHAPTER GRAPHIC REQUIREMENTS CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS

Washington County Road Engineering Plan Submittal/Review Checklist

Automated Machine Guidance

SECTION III STANDARD DRAWINGS ROYSE CITY GENERAL CONSTRUCTION NOTES & DETAILS

CHAPTER 9: SYSTEM-SPECIFIC INSTALLATION PROCEDURES

PAVEMENT SURFACE CONDITION RATING MANUAL

CHAPTER 5 PREFORMED THERMOPLASTIC

The Need for Improved Specifications on Dowel Bar Placement Tolerance

Innovative Dewax Method Unlocks Potential for Investment Casters

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

Flanged Dowel Box. Load Transfer System INDUSTRIAL SLAB ON GROUND

A. Extent of structural precast concrete work is shown on drawings and in schedules.

Dowel. Design. Performance-Based World of Concrete Official Show Issue. Lift-truck design changes require a new look at joint durability

Update on Bridge Deck Fastener Performance on the FAST Steel Bridge. By Duane Otter and Brian Doe ABSTRACT

PROPOSED FIBER OPTIC CONDUIT INSTALLATION E. 50TH ST. AND S. COTTAGE GROVE AV. CHICAGO, ILLINOIS

Effect of Dowel Bar Embedment Length on Joint Load Transfer Efficiency of MnROAD Concrete Pavement Test Cells

DESIGN GUIDELINES (SD) COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 399 ELMHURST STREET HAYWARD, CA

SECTION 1085 PRECAST REINFORCED CONCRETE BOX CULVERT

Designer s NOTEBOOK CORNERS AND RETURNS

EVALUATING AN ADAPTIVE SIGNAL CONTROL SYSTEM IN GRESHAM. James M. Peters, P.E., P.T.O.E., Jay McCoy, P.E., Robert Bertini, Ph.D., P.E.

NAVSEA STANDARD ITEM. 2.2 MIL-STD-1689, Fabrication, Welding, and Inspection of Ships Structure

Case Study: Roofing Shingle Scrap in Hot Mix Asphalt, TxDOT Dallas District. Project Overview

DYNAMIC CHARACTERISTICS OF A BRIDGE ESTIMATED WITH NEW BOLT-TYPE SENSOR, AMBIENT VIBRATION MEASUREMENTS AND FINITE ELEMENT ANALYSIS

SECTION PRECAST CONCRETE SECTIONAL MANHOLES

Seal Coats and Surface Treatments Fred J. Benson, Dean of Engineering A. and M. College of Texas College Station, Texas The construction, as here

Edgerail Aluminum Bridge Railing System Specification & Installation Instructions

Memorandum 1.0 Highway Traffic Noise

Transcription:

Precast Concrete Panels for Rapid Pavement Repair Scott Shuler, Ph. D., P. E. Colorado State University Ft. Collins, CO 80523-1584 Gary Dewitt, P. E. Colorado Department of Transportation Evans, Colorado 80620 Closing a major interstate highway for extended periods of time for pavement rehabilitation is becoming increasingly difficult. As a result, night paving is becoming a routine practice for most highway agencies facing rehabilitation on major routes. However, concrete pavement rehabilitation often requires significantly more time than an over night repair can provide. Conventional repairs to I-25 north of Denver, Colorado were estimated to require a minimum of 48 hours to complete, requiring closure of the facility. Closing this major interstate for this length of time would have created significant traffic congestion and was judged unacceptable. Therefore, a rehabilitation method requiring only an twelve hour closure of the interstate was evaluated. This research describes the use of precast concrete panels to replace the deteriorated concrete pavement in lieu of conventional cast-in-place techniques or asphalt concrete patches. Results of the experiment indicate that not only can the process be completed in the time frame desired, it can be used where non-uniform cross sections exist, installed in adverse weather conditions and at a cost that is lower than competing techniques and saves significantly on user costs. After this research was completed several additional locations have used the precast process with success. Keywords: Concrete pavement repair, precast pavement panels, rapid pavement repair Introduction Rehabilitation of roadways is rapidly replacing original construction as the primary mode of construction activity for most public agencies. Rapid repair of these facilities is becoming increasingly important as reduction of traffic congestion becomes a higher priority (Mohsen, et al, 1998, Merritt, et al, 2001). Therefore, methods for expediting rehabilitation time have been suggested to minimize this congestion. Michigan (Buck, et al, 2003), Texas (Elkins, 1979), and Colorado (Public Works, 2001) have experimented with the use of precast concrete panels for expediting the rehabilitation of portland concrete pavement. Objective The objective of this research was to demonstrate whether repairing concrete pavement using precast concrete panels could be accomplished successfully in under twelve hours. The first trial pavement was on US287 north of Ft. Collins, Colorado. The success of this small-scale trial lead to further evaluation on a high traffic segment of I-25 north of Denver. This pavement consisted of ten inches of plain concrete over twelve inches of aggregate base course. Traffic was between 23,000 to 60,000 vehicles per day with 10 percent heavy trucks. A condition survey conducted prior to rehabilitation indicated that over 500 thirty by twelve foot panels existed with at least three full depth longitudinal cracks and significant spalling. As the concrete continued to deteriorate around the cracks it was typical for loose concrete pieces to dislodge under traffic and

become airborne. Rapid repair of the slabs became a high priority as these hazards became more common. Experiment This experiment was conducted on US287 north of Ft. Collins, Colorado near the intersection with Larimer County Road 19. The trial pavement had repeated pavement failures due to an unstable base course. The proposed pavement section was on a super elevated curve of approximately 4 percent. This location was chosen to test the feasibility of placing precast panels over unlevel substrates in addition to: 1. a complete panel of the same shape and size as the original with matching transverse and longitudinal joints, 2. a smaller portion of a panel, 3. an irregularly shaped panel. Constraints for constructing the precast panels were: 1. Maintaining two-way traffic 2. 8 hour time limitation for conducting work 3. Acceptable ride required 4. All debris to be removed during the 8 hour work period 5. Base repair had to occur prior to the pre-cast slab placement 6. Widths of joints could not exceed ½ inch for longitudinal joints and 5/8 inch for transverse joints Typical panels were 12 feet by 12 feet by 10 inches thick. Connection of the panels to the existing pavement was with fiberglass joint ties measuring ¼ inch thick by 5 inches wide by 36 inches long as shown in the detail in Figure 1.

Figure 1: Precast Panel Details

Preconstruction In order to minimize construction time, obstacles were identified that could be addressed before panel installation including: 1. The size of the panel to be precast was accurately measured in advance so the panels could be cast to within plus-minus 1/4 inch. 3. The panels were cast 1 inch thinner than the surrounding pavement so polyurethane foam could be injected underneath to level the panels. This was a water blown formulation of high density polyurethane. 4. The total sequence of panel installation was reviewed and duties at 15 minute intervals were identified 5. Backup sequences were identified in case events did not go as planned, for example asphalt concrete was utilized as an alternate patch material. Trial Installation Several trial precast panels were installed on US287 for the first trial. However, one objective of this trial was to determine if the trial panels could be installed within a twelve hour period. Therefore, although the entire trial installation occurred from November 30, 2000 to December 7, 2000, the major activities required for installation of a single panel are summarized in Table 1 to show that installation within the twelve hour period is possible. Table 1: Major Activities and Time Requirements Day Time Cumulative Hrs Activity 11-30 0630 0 Traffic Control Established 0700 0.50 Saw Cutting 0745 1.25 Removed Old Slab 1000 3.50 Placed New Precast Slab 1030 4.00 Polyurethane Installation 1230 6.00 Final Leveling Completed 1500 8.50 Finished Cleaning Joints 12-1 1130 8.50 Traffic Control Established 1300 10.00 Dried Joints and Filled with Sealer

Performance After Six Years The precast panels have been in service for six years and are performing very well. There is no evidence of cracking or other distress in the precast panels. The fiberglass joint ties have remained in place, required only routine crack sealing, and show no evidence of distress. Ride quality when transitioning the panels is excellent. The only disadvantage of the process, to date, is due to the presence of crack filler in the perimeter joints and in the fiberglass ties which make the panels more obvious to motorists. Figure 2 shows the appearance after six years including corner cracks in the original pavement that were present at the time of panel installation.

Crack in Adjacent Slab Crack in Adjacent Slab Figure 2: Appearance of Trial Panels After Six Years

Costs An analysis was conducted to compare the relative costs of the precast panel repair technique and conventional cast-in-place repair and asphalt patching. Table 2 is a summary of the approximate costs for these procedures for projects using 12 foot by 15 foot concrete slabs 10 inches thick. Table 2: Cost Comparison for Three Concrete Pavement Repair Techniques QuickTime and a TIFF (LZW) decompressor are needed to see this picture. Summary Cost per Square Foot Cast-in-Place Concrete $5 to $17 Pre-cast Concrete $20 to $34 Asphalt Concrete $5 to $12 Although the initial cost of the precast concrete panels is significantly higher than competing methods, considering the advantages of long term performance and the relatively short time

required for installation, this method of rehabilitation of concrete pavements should be considered. Conclusions 1. Precast concrete slabs are effective as a repair technique for high traffic pavements when rapid repair is desirable and closing the facility for periods beyond twelve hours is not feasible. 2. Polyurethane foam was effective for lifting the precast panels into position initially and has remained in position for six years on the trial project. 3. Although the initial cost of the precast panels was three to four times the cost per unit area of asphalt patches and two to four times the cost of cast in place concrete, cost of this technique would decrease as experience is gained and more contractors are familiar with the process. 4. User costs associated with lane closures on high traffic roadways are significant and should be considered when rehabilitation strategies are selected. Precast concrete panels would help to significantly reduce this user cost. References Buck, N., Barnhart, V., and Kowli, R., Pre-cast Concrete Slabs as Full Depth Repairs (FDR) Michigan Experience. 82nd Annual Meeting of the Transportation Research Board, Washington D. C., 2003. Elkins, Gary Eugene, B. F. McCullough, and Ronald W. Hudson. Precast Repair of Continuously Reinforced Concrete Pavement, Research Report 177-15, Center for Transportation Research, The University of Texas at Austin, May 1979. Luh M. Chang, Using precast concrete panels for pavement construction in Indiana, No. C- 36-46X, File No. 5-11-24 SPR-2779, August, 2002. Merritt, D., McCullough, D. B., and Burns, N., Feasibility of Using Precast Concrete Panels to Expedite Construction on Portland Cement Concrete Pavements, Paper No. 01-2904, Transportation Research Board, 80th Annual Meeting, January 7-11, 2001, Washington, D.C, Transportation Research Record 1761, pp. 3-9. Mohsen A. Issa, Alfred A. Yousif, Mahmoud A. Issa, Iraj I. Kaspar, and Salah Y. Khayyat. Analysis of Full Depth Precast Concrete Bridge Deck Panels, PCI Journal, January- February 1998, pp. 74-85. Public Works, Colorado Uses Precast Concrete Panels for Interstate Highway Pavement Repair. August 2001.