INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM

Similar documents
LLRF Operation and Performance of the European XFEL. An overview

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY

SNS LLRF Design Experience and its Possible Adoption for the ILC

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

Borut Baricevic. Libera LLRF. 17 September 2009

R.Bachimanchi, IPAC, May 2015, Richmond, VA

Software Requirements Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 06, 2009

Beam Diagnostics, Low Level RF and Feedback for Room Temperature FELs. Josef Frisch Pohang, March 14, 2011

3.9 GHz System (AH1) XFEL WP46

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium

Status of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008

LLRF Plans for SMTF. Ruben Carcagno (Fermilab) Nigel Lockyer (University of Pennsylvania) Thanks to DESY, PISA, KEK, Fermilab, SLAC Colleagues

FLASH Operation at DESY From a Test Accelerator to a User Facility

FLASH at DESY. FLASH. Free-Electron Laser in Hamburg. The first soft X-ray FEL operating two undulator beamlines simultaneously

High Power Couplers for TTF - FEL

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory

The TESLA Linear Collider. Winfried Decking (DESY) for the TESLA Collaboration

Software Design Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 16, 2009

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University

FLASH. FLASH Training: RF Gun. FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously. Siegfried Schreiber, DESY

Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY

Demonstration of exponential growth and saturation at VUV wavelengths at the TESLA Test Facility Free-Electron Laser. P. Castro for the TTF-FEL team

State of the Art in RF Control

THE CRYOGENIC SYSTEM OF TESLA

Using Higher Order Modes in the Superconducting TESLA Cavities for Diagnostics at DESY

Calibrating the Cavity Voltage. Presentation of an idea

Design & Implementation of the LLRF System for LCLS-II. Andy Benwell (SLAC Spokesperson) LLRF 2017 October 16, 2017

Femtosecond-stability delivery of synchronized RFsignals to the klystron gallery over 1-km optical fibers

Cavity Field Control - RF Field Controller. LLRF Lecture Part3.3 S. Simrock, Z. Geng DESY, Hamburg, Germany

Does the short pulse mode need energy recovery?

Advance on High Power Couplers for SC Accelerators

Review on Progress in RF Control Systems. Cornell University. Matthias Liepe. M. Liepe, Cornell U. SRF 2005, July 14

Design considerations for the RF phase reference distribution system for X-ray FEL and TESLA

To produce more powerful and high-efficiency particle accelerator, efforts have

3 General layout of the XFEL Facility

FLASH II. FLASH II: a second undulator line and future test bed for FEL development.

Superstructures; First Cold Test and Future Applications

Report of working group 5

TECHNICAL CHALLENGES OF THE LCLS-II CW X-RAY FEL *

Status of superconducting module development suitable for cw operation: ELBE cryostats

Frank Schmidt-Föhre, DESY

RF System LSD Work. William Merz

RF-based Synchronization of the Seed and Pump-Probe Lasers to the Optical Synchronization System at FLASH

H. Weise, Deutsches Elektronen-Synchrotron, Hamburg, Germany for the XFEL Group

The European Spallation Source. Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013

Behavior of the TTF2 RF Gun with long pulses and high repetition rates

Third Harmonic Superconducting passive cavities in ELETTRA and SLS

REVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES. S. Belomestnykh

Status, perspectives, and lessons from FLASH and European XFEL

Digital LLRF Test on the Renascence Cryomodule

RF Design of Normal Conducting Deflecting Cavity

Grounding for EMC at the European XFEL

The ILC Accelerator Complex

Vibration studies of a superconducting accelerating

Performance Evaluation of the Upgraded BAMs at FLASH

Acceleration of High-Intensity Protons in the J-PARC Synchrotrons. KEK/J-PARC M. Yoshii

OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW*

TESLA RF POWER COUPLERS DEVELOPMENT AT DESY.

FLASH performance after the upgrade. Josef Feldhaus

- RF Master-Reference Update (F.Ludwig, H.Weddig - DESY, K.Czuba - TU Warsaw) - Beam Stability Update (C.Gerth, F.Ludwig, G.

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE

MIMO-LTI Feedback Controller Design -Status report-

Available online at ScienceDirect. Physics Procedia 84 (2016 )

The European X-Ray Free-Electron-Laser Facility

Functional block diagram for SIS8300. Christian Schmidt for the LLRF team Collaboration workshop

FLASH II: an Overview

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute

R100 Microphonics. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton

FLASH 2. FEL seminar. Charge: 0.5 nc. Juliane Rönsch-Schulenburg Overview of FLASH 2 Hamburg,

Performance of the Prototype NLC RF Phase and Timing Distribution System *

Electro-Optical Measurements at the Swiss Light Source (SLS) Linac at the PSI. First Results

Update 5/19/11. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton

Performance of the TTF Photoinjector Laser System

LC Technology Hans Weise / DESY

BCS UPDATE. j. welch 2/9/17

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT

Feedback Requirements for SASE FELS. Henrik Loos, SLAC IPAC 2010, Kyoto, Japan

COMPLEX ENVELOPE CONTROL OF PULSED ACCELERATING FIELD

FLASH: Status and upgrade

Digital Signal Processing in RF Applications

Energy Recovering Linac Issues

Superconducting RF System. Heung-Sik Kang

Status of the ESS Accelerator Workpackage

Cryogenics for Large Accelerators

Engineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team

Superconducting RF for Energy-Recovery Linacs

An Iterative Learning Algorithm for Control of an Accelerator Based Free Electron Laser

SNS CRYOMODULE PERFORMANCE*

CEBAF Overview June 4, 2010

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY

Cavity BPM Activities at PSI

Superconducting 1.3 GHz Cavities for European XFEL

Transcription:

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM FOR THE EUROPEAN XFEL Julien Branlard, for the LLRF team

TALK OVERVIEW 2 Introduction Brief reminder about the XFEL LLRF system Commissioning goals Commissioning Planning Steps description + automation Results: some statistics Assessment What went well, what didn t What s done, what s left

European XFEL Hamburg DE 3.4 km The European X-ray Free Electron Laser 17.5 GeV light source user facility TESLA superconducting 1.3 GHz RF cavities 1.4 msec RF pulses at 10 Hz e- beam 1.35 ma nom. - 4.5 ma max Dec. 18 th 2015: first beam in injector 2015-2016: main tunnel installation Q1 of 2017: main linac commissioning May 4 th 2017 : first lasing! End of 2017: first user operation Experimental hall source: http://www.xfel.eu Undulator lines IT FR (5,9%) (6.4%) RU (7,7%) DE (72.7%) access particle shaft acceleratort tunnel access shaft modulator hall cryogenic plant source: http://www.fis-landschaft.de watch online: injector tunnel https://www.youtube.com/watch?v=p3g90p4glqa injector building

INTRODUCTION: the XFEL LLRF system 4 CM1 (8 cav.) CM2 (8 cav.) CM3 (8 cav.) CM4 (8cav.) KLYSTRON LLRF master LLRF slave Drift compensation Reference synchr. + distr. Clocks + local oscillator Main controller crate (MicroTCA) Technical commissioning represents >50% of the commissioning time Piezo* Power supplies Intersystem commissioning is a key factor of the commissioning time * not installed yet

INTRODUCTION: goals 5 INJ (GUN, A1, AH1) Already commissioned and in operation (cold) throughout 2016 Recommissioning necessary due to warm up/cool down + installation of new components L1 (A2) First time commissioning of a complete RF station (4 cryomodules) Commissioning of the commissioning plan First time 32 cavity vector sum feedback control L2 (A3, A4, A5) 3 times L1 Validation of the commissioning plan L3 (A6 A20) 15 times L1 Hardware slightly different Change strategy : horizontal commissioning (step 1 for all stations, then step 2, etc..)

TALK OVERVIEW 6 Introduction Brief reminder about the XFEL LLRF system Commissioning goals Commissioning Planning and milestones Steps description + automation Results: some statistics Assessment What went well, what didn t What s done, what s left

COMMISSIONING: planning 7 Commissioning team 8 LLRF experts 6 trained colleagues from DESY Christian Mariusz Mathieu Matthias 6 colleagues from external facilities Commissioning team of 20 people Commissioning shifts Two 8-hours shifts / day Following DESY s operator shift program Sven Uros Valeri Wojtek Procedure Parallel work (station-wise) Follow detailed commissioning checklist Gather issues. Investigate/fix on maintenance day (once a week)

COMMISSIONING: LLRF milestones (1/2) Initial checks LLRF system ready for commissioning? Cold coupler conditioning RF signal checks: Forward and Reflected Cabling issues? Signal saturation? Frequency tuning From parking position to resonance RF signal checks: Probe Cabling issues? Signal saturation? Coupler tuning Target Q L = 4.6e6 Power-based gradient calibration Coarse Closed-loop operation Feedback, learning feedforward, RF ONLY READY FOR BEAM 8

COMMISSIONING: LLRF milestones (2/2) Establish beam transport 30 bunches, 0.5nC Cavity phasing Using waveguide phase shifters Beam-based gradient calibration Fine relative calibration Absolute validation using energy server BEAM REQUIRIED 9 Estimated schedule Injector (gun, A1, AH1) 2 weeks L1 (1 RF station) 2 weeks L2 (3 RF stations) 2 weeks L3 (15 RF stations) 2 months

COMMISSIONING: tool automation 10 Cavity tuning 1. Perform initial check (1 motor turn ~ 15 khz) Check that the detuning changes in the correct direction, in the proper amount and for the correct cavity resonance mode parking position 2. if successful, tune to resonance (coarse) 200-400kHz Based on step-to-resonance measured at AMTF 3. If successful, tune to resonance (fine) Example: A3.L3 1 RF station (32 cavities) tuned from parking position to resonance in 1h.

COMMISSIONING: tool automation 11 Cavity tuning

COMMISSIONING: tool automation 12 Cavity tuning

COMMISSIONING: tool automation 13 RF signal checks (1/2) what s wrong with this picture?

COMMISSIONING: tool automation 14 RF signal checks (2/2) 3-4 mins per RF station Verify phase shifter functionality (32x) Identify cabling errors: FORW REFL C1 C2 Reminder: LLRF has 2500+ RF signals (Probe, forward, reflected) x2 counting int/ext cabling

COMMISSIONING: tool automation 15 Power-based calibration 1. Dynamic range optimization Adjust attenuation so that available signal uses the optimal range of the digitizers 2. Forward power calibration Scale forward power signals so they read actual kw, based on the power meter measurements 3. Probe and Reflected signal calibration Scale reflected and probe signals so that Probe = Forward Reflected

COMMISSIONING: some statistics 16 Cabling issues 15 cabling issues (outer rack) identified before cool down 11 cabling issues (outer rack) identified after cool down 0 cabling issues (inner rack) identified so far < 1% Multipacting Observed on nearly all stations Start appearing around 550-600 MV (i.e. ~17-18 MV/m) Up to 50% of cavities / cryomodule required conditioning (worse case) Conditionable on all stations Required couple of hours per station (@10 Hz) 3 GeV additional energy after conditioning

COMMISSIONING: multipacting commissioning 17

COMMISSIONING: some statistics 18 4 out of 616 couplers shorted after test in XTL A4.M4.C4 coupler problem: T70K [shorted] A12.M4.C1 coupler problem: T70K [shorted] A16.M2.C1 coupler problem: T70K [shorted] A20.M4.C1 coupler problem: T70K [shorted] 5 out of 616 cavities not used due to AMTF results A5.M1.C5 temporary, shorted pick up A6.M3.C1 high FE/X-ray (10 MV/m limit) A7.M2.C7 high FE/X-ray (11 MV/m limit) A10.M1.C3 low Eacc BD (no FE) (13 MV/m limit) A18.M4.C4 high FE/X-ray (23 MV/m limit + wrong P FORW ) 10 out of 19 RF stations actually have all cavities tuned i.e only 50% of the RF stations have a 32-cavity vector sum

COMMISSIONING: some statistics 19 RF regulation (in-loop) Intra-pulse Pulse-to-pulse Intra-pulse Pulse-to-pulse Specifications: Courtesy S. Pfeiffer

TALK OVERVIEW 20 Introduction Brief reminder about the XFEL LLRF system Commissioning goals Commissioning Planning Steps description + automation Results: some statistics Assessment What went well, what didn t What s done, what s left

ASSESSMENT: what went well 21 Install / test as much as possible, as early as possible Individual component tests Crate installation Rack installation Automation Simple scripts Broken down into single, modular tasks Availability of cryomodule test data Results from individual cryomodule tests Cavity gradient limits, phase shifter limits, What to pay attention to (tune / don t tune)

ASSESSMENT: what went well 22 Checklists + documentation Prepare the checklist Test the checklist Iterate the checklist Stick to it Machine operation Handed over to machine operators after couple of months Regular operator trainings On-call LLRF experts FSM: ramp up / down stations Man power Large machine large commissioning team Beware of the installation burn out (2 years ) External support (fresh eyes + enthusiasm)

ASSESSMENT: what didn t go so well 23 Initial checks of tuners drivers More than 40% initial checks failed Several iterations required time consuming Triggered one cryo incident Multipacting: working here but quenching there Repeating same tasks several times Procedures not always well understood / documented Phase jumps Intricate combination of timing + reset + clocks resulting in 240 deg. phase jumps (single boards) after a crate reboot Too long recovery time after shut down Piezo driver Piezo driver production was delayed > 2 years To be installed and commissioned during maintenance this year

CONCLUSIONS / OUTLOOK 24 The baseline commissioning phase went relatively well Strong commissioning team Automation Still a few milestones on our to do list Max energy? Piezo Performance assessment, stability, drifts (i.e. advanced commissioning) Improved diagnostics (aging, radiation, system health) Data from 10.04.2017 5am 12 GeV exp. Further higher-level development Inter-RF station communication + automation Multi-beamline operation

THANK YOU FOR YOUR ATTENTION! 25 Photo Dirk Noelle

BACKUP SLIDES 26

COMMISSIONING: pre-commissioning 27 System integration Warm (parasitically during warm coupler conditioning) Cold (parasitically during cool down) Master oscillator Module tests Module integration Noise suppression Reference line distribution Power / spectrum measurement point by point

COMMISSIONING: tool automation 28 Coupler tuning Target Q L Measured Q L 32 couplers adjusted to target Q L in a couple of minutes

COMMISSIONING: tool automation 29 Cavity phasing M1 M2 initial spread < +/- 8 degrees final spread < +/- 2 degrees M3 2 minutes M4

ASSESSMENT: what went well 30 Experience from FLASH Similar system (HW, SW, FW) Expertise Cabling Use professional cabling companies Cable labeling (both sides!), custom length, pre-assembly

ASSESSMENT: what went well 31 Availability of cryomodule test data Browseable, easy to use Cavity gradient limits, phase shifter limits, What to pay attention to (tune / don t tune) Easy navigation from an internet browser Maximum theoretical energy gain for an RF station Phase shifters position and range Cavities to pay attention to (not tune / Xrays) Cavities tuner steps from parking to resonance (expected)

ASSESSMENT: what s left 32 Evaluate the present max energy Data from 10.04.2017 5am 12 GeV exp. Many studies & projects in the pipeline Optimal Q L Higher-level machine automation Energy management Radiation / health monitoring

ASSESSMENT: what s left 33 System performance: beam energy stability 09.05.2017, 19:06, 600shot, 10Hz BC0 BC2 Preliminary energy measurements: BC0: y = 97.5 m, D y = -218.5mm E /E = 3.6e-4 too large! BC1: y = 56.4 m, D y = -490.3mm E /E = 1.1e-4 ok BC2: y = 57.4 m, D y = -379.9mm E /E = 1.5e-4 why worse? BC1 Courtesy: L. Fröhlich