Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

Similar documents
Connection Impact Assessment Application Form

Connection Impact Assessment Application

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form

Form B. Connection Impact Assessment Application Form Distribution System

Embedded Generation Connection Application Form

Impact Assessment Generator Form

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

GENERATOR INTERCONNECTION APPLICATION Category 3 For All Projects with Aggregate Generator Output of More Than 150 kw but Less Than or Equal to 550 kw

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 150 KW BUT LESS THAN OR EQUAL TO 550 KW

Table of Contents. Introduction... 1

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System

APPLICATION FOR INTERCONNECTION & OPERATIONS OF MEMBER-OWNED GENERATION

Owner/Customer Name: Mailing Address: City: County: State: Zip Code: Phone Number: Representative: Address: Fax Number:

APPENDIX B: Generation Interconnection Application Form

EASTERN ILLINI ELECTRIC COOPERATIVE Application for Operation of Member-Owned Generation

Settlements & Revenue Metering SLD Requirements INTERCONNECTIONS AT VOLTAGES 50KV

State of North Dakota Engineering data submittal Page 1 For interconnection of distributed generation to Otter Tail Power Company

SOUTH CENTRAL INDIANA REMC Application for Operation of Member-Owned Small Power Generation Systems

PART 1 OWNER/APPLICANT INFORMATION

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

Capstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:

Distributed Generation Application Form (Generation of Greater than 20 kw to 15 MW)

Generation Interconnection Requirements at Voltages 34.5 kv and Below

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

BED INTERCONNECTION TECHNICAL REQUIREMENTS

INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

APPENDIX 1 to LGIP INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

E N G I N E E R I N G M A N U A L

QUESTIONNAIRE for Wind Farm Power Stations only

Initial Application Form for Connection of Distributed Generation (>10kW)

Southern Company Interconnection Requirements for Inverter-Based Generation

Generation Interconnection Study Data Sheet Synchronous Machines

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

TABLE OF CONTENT

Information and Technical Requirements For the Interconnection of Distributed Energy Resources (DER)

The Connecticut Light and Power Company

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

IEEE sion/1547revision_index.html

DRAFT. City of Lethbridge Electric ENGINEERING STANDARDS GUIDELINE FOR GENERATOR INTERCONNECTION THE CITY OF LETHBRIDGE ELECTRIC DISTRIBUTION SYSTEM

Impacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering

Grid Code 2015 for Small Scale Distributed Generation (SSDG) Net Metering Scheme Version June 2017 Central Electricity Board

TECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

Functional Specification Revision History

Renewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

Tasmanian Networks Pty Ltd Guideline. Technical Requirements for the Connection of Embedded Generation

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

Babak Enayati National Grid Thursday, April 17

CONTENTS. 1. Introduction Generating Stations 9 40

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces

Customer Standard. Standard for Embedded Generation (5MW and above)

Embedded Generation Information Package

This document covers common questions concerning the design of an effectively grounded system.

MV network design & devices selection EXERCISE BOOK

Transmission Interconnection Requirements for Inverter-Based Generation

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management

Revision Control. 0 18/07/2012 Initial Document Creation. STAKEHOLDERS The following positions shall be consulted if an update or review is required:

ELECTRICAL POWER ENGINEERING

2012 Grid of the Future Symposium. Impacts of the Decentralized Photovoltaic Energy Resources on the Grid

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

Earth Fault Protection

Industrial Electrician Level 3

Appendix C-1. Protection Requirements & Guidelines Non-Utility Generator Connection to Okanogan PUD

Connection of Embedded Generating Plant up to 5MW

ACS 1000 Transformer Failure Investigation. Nathan Schachter, Peng

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.

If any queries arise ESB Networks DAC can be contacted at or

Demand Customer Connection Connection Application Form to the Transmission System

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

ECE 528 Understanding Power Quality

WDG 61 - Technical Data Sheet

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

Modelling Parameters. Affect on DER Impact Study Results

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007.

Utility Interconnection and System Protection

Guide and Requirements for Service. at 69,000 to 287,000 Volts R 0.2

AGN 165 Parallel Operation with Mains Grid Systems

WDG 83 - Technical Data Sheet

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)

Wind Power Facility Technical Requirements CHANGE HISTORY

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Transcription:

General Application Information Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application Hydro One Remote Communities Inc. Lori.Rice@hydroone.com 1-807-474-2828 This Application Form is for Generators with a project size, based on the generator nameplate, which is greater than the 10 kw: New Generators applying for Connection Impact Assessment ( CIA ) New Generators applying for revision(s) to their original CIA This form is NOT for generation sizes of the 10 kw or less. Please fill out and submit the Remotes Case 1 Form (REINDEER Case 1 -Connection Impact Assessment (CIA) Application) unless otherwise specified. For technical requirements of Hydro One Remote s REINDEER projects, refer to the Distributed Generation Technical Interconnection Requirements Interconnections at Voltages 50kV and Below available at: http://www.hydroone.com/generators/pages/technicalrequirements.aspx. Application Submission Instructions: Please return the completed form, fees and other required documents by email, FAX, or mail: Email: RemotesCustomerService@HydroOne.com Telephone: 1-888-825-8707 FAX: 1-807-475-3127 Address: Hydro One Remote Communities Inc. Attn: RemotesCustomerService Case 2 & 3 Form 680 Beaverhall Place Thunder Bay, Ontario P7E 6G9 Important Notes Hydro One Remote Communities Inc. shall be hereafter referred to as Remotes Applicants are cautioned NOT to incur major expenses until Remotes approves to connect the proposed generation facility. All technical submissions (Case 2&3 Form, single line diagrams, etc.) must be signed and sealed by a licensed Ontario Professional Engineer (P.Eng.). All fields below are mandatory, except where noted. Incomplete applications will be returned by Remotes Section A Administrative Information (Completed By Remotes) Date: / / (dd / mm / yyyy) Project Name: Location: REINDEER Reference Number: Section B.1 Project Information (ONLY if there have been changes since Remotes Form A) 1. Type of connection: Single phase OR Three phase 2. Project Size: Total requested DG output capacity (maximum DG power output): kw (Note: The project size must be in agreement with your REINDEER contract) 3. Equipment Capacity: Nameplate capacity (equipment rating as per manufacturer s stamp): kw (Note: See section 2.1.2 of Hydro one s Technical Interconnection Requirements)

4. Fuel / Renewable Energy Type: Biomass Solar (PV) Gas Turbine Wind Diesel Engine Other (please specify) Water (for water projects please answer (a) and (b) below): a) Is water your primary energy source? Yes No b) Is your generation facility located on provincial Crown or federally-regulated lands? Yes No 5. Project Location: Community Lot/ID Number(s) Meter Number(s) (If applicable) Common Name (e.g Water Treatment Plant ) 6. Project Contact Information: The Single Point of Contact for the project will be the (choose ONE): Owner Consultant Company/ Person Contact Person Mailing Address (Street #) Mailing Address (Suite, Unit #) Work Tel. # Cell Fax E-mail Owner (Mandatory) Consultant (Optional) Preferred method of communication with Remotes (check ONE): E-mail Telephone Mail Fax Section B.2 Project Information 7. Customer Status: Is there an existing Remotes customer account at the project location? Yes No If yes, what is the Remotes 10 OR 12-digit account number of the property: Customer name registered on existing Account: Are you the existing account owner? Yes No Are you an HST registrant? Yes No If yes, provide your HST registration number: - RT Barcode of nearest Hydro pole serving project location: 8. Ontario Corporate Number: OR Business Identification Number: 9. Proposed In- Service Date: / / (dd / mm / yyyy) Page 2 of 11

Section C Project Connection Information In the following section: Point of Connection or POC means the point where the new Generator s connection assets or new line expansion assets will be connected to the existing Remotes distribution system. Point of Common Coupling or PCC or Point of Supply means the point where the Generation facility is to connect to Remotes distribution system. The POC and the PCC may be the same, especially if the Generation facility lies along the existing Remotes distribution system; or the PCC may be located somewhere between the POC and the Generation facility if the new line will be owned by Remotes. For illustration of the POC and the PCC, refer to Appendix A attached. 10. Connection to Remotes Distribution System: a. Community: b. GPS coordinates of the following: (GPS Format: Latitude, Longitude - Degree Decimal e.g. 49.392, -75.570) POC: PCC: Generation Facility: c. Please select ONE applicable connection figure from Appendix A: A-1 A-2 A-3 d. Length of line distance from the POC to the PCC: km e. Length of line distance from the PCC to the Generation Facility (refer to Appendix A): km Conductor type/size: / f. Fault contribution from the Generator s Facilities, with the fault location at the PCC: Three-phase generators: 3-phase short circuit current: Single-phase generators: 1-phase short circuit current: NOTES: If this project requires line expansion work between the POC and PCC, Remotes will provide a cost estimate to construct any line located on public road right-of-way. The cost estimate will include a breakdown of Uncontestable work (i.e. overbuild to existing line) that can only be performed by Remotes, as well as Contestable work (i.e. new construction/green-field) that can be performed by the Generator/their contractor or Remotes. (Both Uncontestable work and Contestable work requires the design to Remotes specifications). Remotes will become the owner of the line expansion. 11. Single Line Diagram ( SLD ): Provide an SLD of the Generator s facilities including the PCC, transformer(s) and connecting station, feeder, supply voltage, inverters, and all protection and control devices. The SLD should be as detailed as possible. SLD must be signed and sealed by a Professional Engineer in Ontario. SLD Drawing No., Rev. A A Page 3 of 11

Section D Generation Characteristics 12. Generation Characteristics a. Existing Generation: Are there any existing generators at the PCC? Yes No b. Indicate annual generation projection (kw) with at least a 15 minute resolution. (i.e. projected annual kw output every 15 minutes for a whole year.) This should be attached as another document. Preferably an Excel document. (See Item 7 in Appendix B) c. Maximum projected dynamic generation response of the renewable resource over two (2) minutes at a resolution one (1) second. This should be attached as another document. (See Item 8 in Appendix B) d. Characteristics of Proposed Generation NOTE for facilities with multiple generators: Provide the manufacturer s technical data (electrical) for the generator or inverter. If your generators have different characteristics, please provide the characteristics for each generator on an additional sheet(s). Number of generating unit(s): Manufacturer / Type or Model No: / Rated capacity of each unit: kw kva Generator Output Voltage kv Generator Type: Rotating Static (PV, fuel cell, battery) Generator phasing: Single phase Single phase connecting to three phase system Three phase Power conversion technologies: Synchronous Induction Full inverter interfaced Other (Please Specify) (If the machine type is Other, please provide values equivalent to a Synchronous or Induction type Generator) Limits of range of reactive power at the machine output: i. Lagging (over-excited): kvar power factor ii. Leading (under-excited) kvar power factor Limits of range of reactive power at the PCC: iii. Lagging (over-excited): kvar power factor iv. Leading (under-excited) kvar power factor Maximum Starting inrush current: pu (multiple of full load current) Generator winding connection: delta star Neutral grounding method of star connected generator: Solid Ungrounded Impedance: R: ohms X: ohms Page 4 of 11

For Synchronous Units (If applicable): a) Nominal machine voltage: kv (LL) b) Unsaturated reactances on: kva base kv base Direct axis subtransient reactance, Xd pu Direct axis transient reactance, Xd pu Direct axis synchronous reactance, Xd pu Subtransient time, Td ms Transient time, Td ms Zero sequence reactance, X0 pu For Induction Units (If applicable): a) Nominal machine voltage: kv b) Unsaturated reactances on: kva base kv base Direct axis subtransient reactance, Xd pu For Inverter Characteristics (if applicable): a. Inverter Output rating (AC): kw b. Nameplate voltage of AC output: kv c. Nameplate voltage of DC input: kv d. Number of Phases: single phase three phase e. Type of Inverter: Line-Commutated Self-Commutated Other: f. Inverters meet UL 1741: Yes No g. Inverters meet CSA C22.2 No.107.1-01: Yes No I. Any other standards met by Inverters: h. Method of synchronizing to system: Automatic Manual NOTES: Inverters MUST meet UL 1741 and CSA C22.2 No.107.1-01. 13. Interface Step-Up Transformer Characteristics: a. Transformer ownership: Customer / Remotes If transformer Remotes owned, provide the Remotes Account No. (b) to (h) below: b. Transformer rating: kva c. Nominal voltage of high voltage winding: kv d. Nominal voltage of low voltage winding: kv e. Transformer type: single phase three phase f. Impedances on: kva base kv base R: pu, X: pu g. High voltage winding connection: delta star OR complete Page 5 of 11

Grounding method of star connected high voltage winding neutral: Solid Ungrounded Impedance: R: ohms X: ohms h. Low voltage winding connection: delta star Grounding method of star connected low voltage winding neutral: Solid Ungrounded Impedance: R: ohms X: ohms NOTES: At the Generator s expense, and, if requested, Remotes may provide transformation up to a maximum of 75 kva single phase and 300 KVA three-phase, as described in the Hydro One Remote Communities Conditions of Service (Section 2.1.1.9). The term High Voltage refers to the connection voltage to Remotes distribution system and Low Voltage refers to the generation or any other intermediate voltage. 14. Intermediate Transformer Characteristics (if applicable): a. Transformer rating: kva b. Nominal voltage of high voltage winding: kv c. Nominal voltage of low voltage winding: kv d. Transformer type: single phase three phase e. Impedances on: kva base kv base R pu X pu f. High voltage winding connection: delta star Grounding method of star connected high voltage winding neutral: Solid Ungrounded Impedance: R ohms X ohms g. Low voltage winding connection: delta star Grounding method of star connected low voltage winding neutral: Solid Ungrounded Impedance: R ohms X ohms NOTE: The term High Voltage refers to the intermediate voltage that is input to the interface step-up transformer and the Low Voltage refers to the generation voltage. 15. High-Voltage Grounding Transformer Characteristics (if applicable): Type: Zig-zag star-delta Zig-zag Grounding Transformer zero sequence impedance (Z0): R ohms X ohms Star-delta Grounding Transformer zero sequence impedance (Z0): R ohms X ohms 16. Load information: a. Maximum load of generating facility: kva kw b. Maximum load current (referred to the nominal voltage at the connection point to Remotes system): A c. Maximum inrush current to loads (referred to the nominal voltage at the connection point to Remotes system): A Page 6 of 11

Attached Documents: Item No. 1 2 3 4 Description Document No. No. of Pages Attached Drawings: Item No. 1 2 3 4 Description Document No. No. of Pages Section E Checklist Please ensure the following items are completed prior to submission. The application will be returned if Remotes determines it is incomplete: Completed Remotes Case 2&3 Form stamped by a Professional Engineer Payment in full including applicable taxes by cheque, payable to Hydro One Remote Communities Inc. (As indicated on the Agreement for Services for Engineering Fees) Signed Agreement for Services for Engineering Fees (original signature is required) Detailed Single Line Diagram (SLD) of the Generator s facilities, must be stamped by a Professional Engineer. SLD must follow the Hydro One Embedded Generation Single Line Diagram Requirements. See here for more details: http://www.hydroone.com/generators/documents/feed- In%20Tariff/Embedded%20Generation%20SLD%20Requirements.pdf Photos of nameplate data of all inverters and transformers Ensure that all applicable items in Appendix B are complete and attached to this Form. Page 7 of 11

Appendix A: Illustrations of PCC and Point of Connection Figure A-1: Remotes Owns Entire Tap Line Figure A-2: Generator Owns Entire Tap Line Page 8 of 11

Figure A-3: Remotes Owns a Portion and Generator Owns a Portion of Tap Line Page 9 of 11

Appendix B: List of Documents Connection of Generation Facilities to the Hydro One Remote Communities (Remotes) Distribution System LIST OF REQUIRED DOCUMENTS Instructions: Please review the table below and return ALL required portions together with the rest of Remotes Case 2&3 Form 1. Description Case 2 and Case 3 Remarks Detailed Single Line Diagram (SLD) of the Generation Facility Show ratings of electrical components, generator & transformer neutral grounding, protection, metering, synchronizing schemes, inverters, etc. Refer to the following link for guidance: http://www.hydroone.com/generators/documents/f eed- In%20Tariff/Embedded%20Generation%20SLD%2 0Requirements.pdf 2. Site Plan Showing General Arrangement of the Generation Facility Include location - street address, lot nos. etc. (include the location of lockable, visible-break isolating device) 3. Interface Electrical Equipment Technical Information / Data Sheets / Manufacturer s Nameplate Information transformers, CTs, VTs, isolating / disconnect device, HV circuit breaker, fuses, surge arresters and other interface equipment 4. Description of Protection Scheme Philosophy of Tripping for Internal & External Faults, Islanding and Other Abnormal Conditions 5. Description of Synchronizing Scheme (Synchronous & Inverter Units) & Connection Scheme for Induction Units 6. Description of Power Factor Control for Induction Generators (& Inverter Units, if applicable) Include details of capacitor switching and control, if applicable. Highlight: method, steps, safety features, interlocks with generator breaker etc. 7. Annual Power Generation Projection Indicate annual generation projection (kw) with at least a 15 minute resolution. (i.e. projected annual kw output every 15 minutes for a whole year.) 8. Maximum projected dynamic generation response 9. Protection AC and DC EWD 10. 11. 12. 13. Protection Three Line Diagrams Breaker (HV & Generator) and Isolating Device / Disconnect Control Schematics Tele-protection AC and DC EWD Breaker Failure Protection AC and DC EWD Maximum projected dynamic generation response of the renewable resource over two minutes at a resolution one (1) second Page 10 of 11

14. 15. 16. 17. 18. Interface Protection Relay / Fuse Co-ordination Study, Curves & Settings Relay Logic Diagrams / Tripping Matrix Verification of End to End Testing, Registration for Generator License (If applicable) Commissioning & Verification Procedure & Schedule Signed Band Council Resolution (BCR) if Applicable Generation Facility interface protection relay / fuse must co-ordinate with upstream Remotes protection relay / device For Proponents hoping to install generation capacity in on a First Nation Reserve. Notes: 1. The above list includes drawings that would generally be required for Generation Facility projects. Additional drawings / information may be required for certain projects. In such cases, Remotes will duly inform the Generation Facility. 2. For very small generation facility projects, some drawings / information may not be required. For example, those relating to tele-protection, GPR study, breaker failure, etc. 3. Remotes review of Generation Facility drawing / data / protection settings & witnessing of commissioning tests etc. shall be limited only to those portions of the Generation Facility that interests Remotes and which interfaces with its distribution system. 4. The Generator shall be responsible to coordinate the design, installation, testing, operation and maintenance of its facilities in conformance with applicable codes, standards, Remotes connection requirements, service performance requirements and all relevant laws and regulations. The Generator shall obtain, at its expense, any and all authorizations, permits and licenses required for the construction and operation of its Generation Facilities. Page 11 of 11