RELEVANT ELECTRICAL STANDARDS

Similar documents
RELEVANT ELECTRICAL STANDARDS

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007.

TS RES - OUTSTANDING ISSUES

SYNCHRONISING AND VOLTAGE SELECTION

RELEVANT ELECTRICAL STANDARDS

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS

LIMITS FOR TEMPORARY OVERVOLTAGES IN ENGLAND AND WALES NETWORK

Key DRAFT EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 13/12/17

ECP HV INSULATION TESTING

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code)

SYSTEM MONITORING FAULT RECORDING

each time the Frequency is above 51Hz. Continuous operation is required

ECP HV INSULATION TESTING

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES

EI HIGH VOLTAGE INSULATION TESTING POLICY

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

Australian Standard. Switchgear assemblies and ancillary equipment for alternating voltages above 1 kv AS

EUROPEAN COMPLIANCE PROCESSES (post RfG Implementation) CONTENTS. (This contents page does not form part of the Grid Code) Paragraph No/Title

National Grid s commitments when undertaking works in the UK. Our stakeholder, community and amenity policy

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it.

Requirements for Generators European Network Code High Level Implementation Issues

SUBJECT HEADING: Switching Programmes ISSUE: 18

Energy Networks Association

Distribution transformers Part 2 Ground mounted transformers not closecoupled

NETS SQSS Modification Proposal

Insulation co-ordination Part 1: Definitions, principales and rules. IEC 2006 Copyright - all rights reserved

OPERATING CODE NO. 5 (OC5)

Identification and recording of 'hot' sites - joint procedure for Electricity Industry and Communications Network Providers

INTERNATIONAL STANDARD

SSE Offices, Glasgow and Teleconference

EUROPEAN COMPLIANCE PROCESSES (post RfG Implementation) CONTENTS. (This contents page does not form part of the Grid Code) Paragraph No/Title

Appendix D Fault Levels

Click to edit Master title style. Click to edit Master title style. Northern Powergrid Asset Recording Guidance

Guidance for UK Fire and Rescue Services. Dealing with incidents on or near National Grid high voltage overhead lines

Policy guidance regarding authorisation for Earth Stations on Vessels (ESVs)

Herts Valleys Clinical Commissioning Group. Review of NHS Herts Valleys CCG Constitution

Capacity Market Prequalification

REPORT OF DIRECTOR OF CITY OPERATIONS AGENDA ITEM: 7 PORTFOLIO: TRANSPORT, PLANNING & SUSTAINABILITY (COUNCILLOR RAMESH PATEL)

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Distribution Code. Approved by CER. Version: 5.0 Date: April Distribution System Operator ESB Networks Limited

Draft Kenya Standard for Balloting Not to be Cited as Kenya Standard

INTERNATIONAL STANDARD

IET Standards Committee. Governance. IET Standards Committee Remit. IET Standards Committee Constitution

INTERNATIONAL STANDARD

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

VI 3 - i TABLE OF CONTENTS

NIC Project Medium Voltage Direct Current Link Technical Specification

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Revision 1 of Issue 4 of the Grid Code has been approved by the Authority for implementation on 10 th February 2010.

PROCEDURE FOR INSPECTION OF ELECTRICAL INSTALLATIONS ABOVE 250KVA

TECHNICAL SPECIFICATION

EDS FAULT LEVELS

Plain bearings Wrapped bushes

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

PSSI 27 Work or Testing On or Near to High Voltage Direct Current (HVDC) Plant and Apparatus

Continuous On-line Measurement of Water Content in Petroleum (Crude Oil and Condensate)

TECHNICAL REPORT. Insulation co-ordination

Recommended Practice for Wet and Dry Thermal Insulation of Subsea Flowlines and Equipment API RECOMMENDED PRACTICE 17U FIRST EDITION, FEBRUARY 2015

East Anglia TWO and East Anglia ONE North. Summary and Approach to Site Selection

This is a preview - click here to buy the full publication. IEC 2006 Copyright - all rights reserved

Deleted: 9 4 anuary ... [1] Deleted: much more. Formatted ... [2] Formatted Table. Formatted: Indent: Left: 0.06 cm

This document is a preview generated by EVS

UK Broadband Limited Company Reg No: Spectrum Access 3.5 GHz Licence First Issued: 28/02/17 Licence Number: Rev 1: 11/01/18

TECHNICAL SPECIFICATION

INTEGRATED TRANSMISSION PLAN Glossary

Geoff Brown & Associates Ltd

WORKING GROUP REPORT. Frequency and voltage operating range. Prepared by the Working Group for submission to the Grid Code Review Panel

Revision 32 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 8 th December 2008.

INTERNATIONAL. Medical device software Software life cycle processes

Herefordshire CCG Patient Choice and Resource Allocation Policy

Functional Specification Revision History

GE/GN8648. Guidance on Positioning of Lineside Telephones. Rail Industry Guidance Note for GE/RT8048

TECHNICAL SPECIFICATION

Siemens ST950 & ST900 Statement of Compliance Against TR 2513 Issue A, September 2005 Performance Specification for Wig Wag Signal Control Equipment

Company Directive STANDARD TECHNIQUE: TP14C. Distribution Business Provided Metering Facilities

NEMA Standards Publication ICS Adjustable Speed Electrical Power Drive Systems

INTERNATIONAL STANDARD

SYSTEM MONITORING FAULT RECORDING

INTERNATIONAL STANDARD

Bats and the Law An overview for planning, building and maintenance works

Table of Contents. Introduction... 1

Network Standard NS

CHAPTER ELECTRIC AND MAGNETIC FIELDS

AGREEMENT on UnifiedPrinciples and Rules of Technical Regulation in the Republic of Belarus, Republic of Kazakhstan and the Russian Federation

GK/GN0653. Guidance on Control of Unwanted Voltages on Telecommunications. Equipment at Stations. Rail Industry Guidance Note for GK/RT0053

This document is a preview generated by EVS

INTERNATIONAL STANDARD

Patient Choice and Resource Allocation Policy. NHS South Warwickshire Clinical Commissioning Group (the CCG)

MESP TECHNICAL SPECIFICATION FOR AN ESSENTIAL SERVICES SUPPLY STEP UP TRANSFORMER

Steel wire for general fencing purposes

Adoption of pipe systems by a GT management of UIP activities

High Wind Speed Shutdown / Power Available

UK Broadband Ltd - Spectrum Access 28 GHz Licence Company Registration no: First Issued 22 July Licence Number: /01/18

Wind. Farms. Purpose. recording Offshore. wind farms. the Transmission. the flows of voltages. the onshore. measuree and record. Agents.

Principles and Operation of Three-phase Systems

Terms of Business for ICICI Bank Investment Services (effective from October, 2013)

American National Standard. For Wet Process Porcelain Insulators Indoor Apparatus Type ANSI/NEMA C (R2002, R2012)

DEP 2008 ELECTRIC AND MAGNETIC FIELDS CHAPTER ELECTRIC AND MAGNETIC FIELDS

April 30, Andreas Bergman Chair International Public Sector Accounting Standards Board 529 Fifth Avenue, 6th Floor New York, NY USA

INTERNATIONAL STANDARD

Transcription:

RELEVANT ELECTRICAL STANDARDS Issue 2 February 2014

National Grid 2014 No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means electronic, mechanical, photocopying, recording or otherwise, without the written permission of National Grid s obtained from the issuing location. The contents of National Grid engineering documents are based on the needs of National Grid and the conditions under which it operates. It should not therefore be assumed that the specifications and requirements stated therein necessarily meet the particular circumstances and requirements of other organisations. The principles set out in this document are for information only and to the extent permitted by law. National Grid does not accept any liability to customers / suppliers for any loss or damage resulting from reliance on the contents. It is the responsibility of such external organisations to check that the document is the latest version and is appropriate for their purposes. (National Grid Legal Services. February (2014) Registered Office Registered in 1-3 Strand England and Wales London No. 2366977 WC2N 5EH Published by: National Grid Warwick Technology Park Gallows Hill Warwick CV34 6DA This document has been prepared by the following User Group: Tony Westmorland Mark Waldron Leigh Fraser Antony Johnson Asset Policy Asset Policy Asset Policy Technical Policy Uncontrolled When Printed

CONTENTS PART 1 - INTRODUCTION... 1 PART 2 - ADMINISTRATION... 3 PART 3 - GENERAL REQUIREMENTS... 5 PART 4 SPECIFIC REQUIREMENTS... 6 Uncontrolled When Printed

PART 1 - INTRODUCTION This document defines the relevant technical specifications, policies and procedures that must be complied with by all Users connected to or seeking connection to the Transmission System as set out under CC.6.2.1.2 of the Grid Code Connection Conditions and pursuant to the terms of the Bilateral Connection Agreement. This document applies only in accordance with the existing provisions of CC.6.2.1.2. Equipment which was commissioned prior to the implementation date of this RES will continue to be subject to the standards applicable at the time of commissioning of that equipment. The Relevant Electric Standards seek to maintain an appropriate level of reliability and security for the Transmission System in England and Wales. Ensuring that User equipment connected to the System at least meets the same standard of construction, manufacturing and installation quality as that employed by NGET where such equipment has a material impact on the overall reliability and security of the System. The User shall demonstrate that its equipment connected to the Transmission System in England and Wales is fit for purpose, complies with both statutory and Grid Code requirements, it meets the manufacturers stated performance characteristics and the requirements of the Specific Requirements contained within these. For the avoidance of doubt this includes evidence of commissioning processes and procedures that ensure that the above requirements are met. In accepting the Connection Conditions, Users connecting to the Transmission System are required to comply with these requirements pursuant to the terms of the Bilateral Connection Agreement. This document applies only to connection agreements where the User is connected /connecting to an extant NGET substation or where the connection will be to a new substation that is being constructed by NGET. Where the User elects to construct the substation to which it will connect and subsequently transfer the assets to NGET the substation construction as a minimum shall meet in its entirety the National Grid Technical Specifications used by NGET. The Relevant Electric Standard document comprises of Introduction, Administration, User Policy, User Specification in respect of each category of Plant and Apparatus and Guidance Notes. Administration covers roles and responsibilities with respect to issue, maintenance and administration of the document including the governance of changes to the document contents and/or requirements. General Requirements cover NGET s intentions with respect to the use of particular asset types on its System. Policies being based on, inter alia, safety, environmental implications, International policy, legislation and supplier market. Specific Requirements covers the functional requirements of equipment connected to the Transmission System in England and Wales. Guidance Notes provide advice and guidance on how the General Requirements may be applied or the Specific Requirements are used, referencing the General Requirements, Specific Requirements or other relevant documents as appropriate. These contain the technical specifications that NGET currently requires Users to meet. However the requirements contained herein cannot be completely exhaustive and, in certain circumstances, there may still be specific scheme related reasons that will result in NGET requiring a User to meet further requirements that are not set out within these Relevant Electrical Standards. The detail, along with the Grid Code, certain of NGET s requirements with respect to User equipment that is connected within the zone of the substation busbar protection Uncontrolled When Printed Page 1 of 6

system. Its scope does not extend to detailing requirements for User equipment outside the zone of the busbar protection that could nonetheless be subject to various electrical phenomena due to their connection to the Transmission System in England and Wales (e.g. voltage transients). The User is responsible for ensuring that its equipment is capable of withstanding the effects of such system phenomena. Details of the technical and operational characteristics of the Transmission System in England and Wales are given in NGET report CI01 Technical and Operational Characteristics of the Transmission System. For the avoidance of doubt the term Transmission System in England and Wales used in conjunction with this document relates to those transmission assets owned by NGET. Uncontrolled When Printed Page 2 of 6

PART 2 - ADMINISTRATION NGET is responsible for the issue, maintenance and administration of this document. Changes to this document are subject to the provisions of the Grid Code Governance process - Governance of Electrical Standards as detailed in GC.11 of the Grid Code and shall apply where NGET or a User:- a) proposes a change to a technical requirement; b) proposes to add a new technical requirement; c) proposes to delete a technical requirement. d) The document amendment process is shown in Figure 1 below. Uncontrolled When Printed Page 3 of 6

User or NGET submits Amendment Proposal Form to GCRP NGET circulate Amendment Proposal immediately to Grid Code signatories Objections Received within 20 Business Days Amendment Proposal taken to next GCRP Meeting by Grid Code Panel Secretary and appropriate route forward determined GCRP unable to reach consensus to implement/reject No objections Received within 20 Business Days NGET establish a Working Group to consider Amendment Working Group writes Working Group Report for submission to GCRP. Report published on NGET Website Amendment proceeds to wider Industry Consultation (Grid Code signatories) National Grid prepares a Consultation Report and submit to GCRP. Consultation Report placed on NGET website GCRP remain unable to reach consensus to implement/reject Amendment referred to OFGEM/ DECC GCRP reach consensus to implement/reject Amendment Rejected Amendment Implemented Figure 1 - Governance of Electrical Standards- Amendment Process Uncontrolled When Printed Page 4 of 6

PART 3 - GENERAL REQUIREMENTS Engineering Policy statements included in this document relate to particular types of technology assets and are a clear and unambiguous statement of need or intent, based on safety and/or environmental implications, business needs, international policy, legislation and supplier market. Policy statements reference standards, NGET Transmission engineering policy and other relevant documents as appropriate. User equipment installed within the busbar protection zone shall be proven fit for its intended purpose through demonstration of its strength and capability via compliance with the General and Specific Requirements of these. Uncontrolled When Printed Page 5 of 6

PART 4 SPECIFIC REQUIREMENTS The documents listed below, which form part of the, are not reproduced here but are available separately via access to the National Grid UK website. Management of Rise of Earth Potential at New and Refurbished Towers Back-Up Protection Grading across NGET's and other Network Operator Interfaces Ratings and General Requirements for Plant, Equipment, Apparatus and Services for the National Grid System and Connections Points to it. Substations Switchgear Earthing Requirements Substation Auxiliary Supplies Ancillary Light Current Equipment Substation Interlocking Schemes Synchronising Circuit-Breakers Disconnectors and Earthing Switches Current Transformers for Protection and General Use on the 132 kv, 275 kv and 400 kv Systems Bushings Solid Core Post Insulators for Substations Busbar Protection Circuit Breaker Fail Protection Environmental and Test Requirements for Electronic Equipment Gas Insulated Switchgear System Monitor - Dynamic System Monitoring (DSM) Ancillary Services Business Monitoring Protection & Control for HVDC Systems Guidance for Working in Proximity to Live Conductors - Reducing the Risks Guidance for Conductor Jointing in Substations PS(T)045(RES) PS(T)044(RES) TS 1(RES) TS 2.01(RES) TS 2.02 (RES) TS 3.01.02 (RES) TS 2.12 (RES) TS 2.19 (RES) TS 3.01.01(RES) TS 3.24.60 (RES) TS 3.02.01 (RES) TS 3.02.02 (RES) TS 3.02.04 (RES) TS 3.02.07 (RES) TS 3.02.09 (RES) TS 3.24.34 (RES) TS 3.24.39 (RES) TS 3.24.15 (RES) TS 3.02.14 (RES) TS 3.24.70 (RES) TS 3.24.95 (RES) TS 3.24.90 (RES) TGN(E)186 (RES) TGN(E)187 (RES) NOTE The guidance documents referenced in the above table support the NGET Policy Statements contained in the but do not form part of the RES document. Uncontrolled When Printed Page 6 of 6