TECHNICAL SPECIFICATION FOR ANNUBAR (DELTA TUBE)

Similar documents
NEYVELI LIGNITE CORPORATION LIMITED (NLC LTD.)

TECHNICAL SPECIFICATION FOR LEVEL CONTROL VALVE HANDLING WATER

Heat Exchanger Construction Checklist

Operating instructions OI/FPD350-EN Rev. H. FPD350 Torbar Averaging pitot tubes

Bharat Heavy Electricals Limited (High Pressure Boiler Plant) Tiruchirappalli , TAMIL NADU, INDIA MATERIALS MANAGEMENT / CAPITAL EQUIPMENT

OIL INDIA LIMITED (A Govt. of India Enterprise) P.O. Duliajan , Assam. Fax No ,

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PRESSURE GAUGES, Section 15130

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

REVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty

Plant Client Contract Code Document ID Contract No. TECHNICAL SPECIFICATIONS DC SHUNT Rev 00 Page 1 of 2

5.1 MUELLER CORPORATION VALVES. MUELLER 300 Ball Type Corporation Valves

2.14 Main Cable Type HO7RN-F4G10-15 Metres each Chiller Tank Capacity- 75 Litres Compressor- 3.5 Tons Refrigeration type

WESTERN UNDERGROUND COMMITTEE GUIDE 2.6 (2.6/00/0868)

PURCHASE SPECIFICATIONS 500KVA DRY TYPE TRANSFORMER FOR OIL RIG APPLICATIONS

INSERTION paddle wheel flowmeter for continuous flow measurement

CONNOLS-AIR. AIR TERMINAL UNITS Engineered for Versatile Application and Energy Conservation

Specifications for EA31002 U Tube Bundle for CDU 3

Digital flow ELEMENT transmitter for continuous flow measurement

Digital flow ELEMENT transmitter for continuous flow measurement

TECHNICAL SPECIFICATIONS for 300KV CONSTANT POTENTIAL X RAY EQUIPMENT (for industrial applications) S. No. PARTICULARS BHEL SPECIFICATIONS

TECHNICAL SPECIFICATIONS OF STORES AND DRAWINGS.

MUELLER GAS. DH-5 Drilling Machine. For use on 1 1 /2 & 2 Line Stopper Fittings. Reliable Connections. General Information 2

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal

Precision Thermistor Sensors

ph or ORP Transmitter

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

SensyTemp TSBA (BA R) Resistance thermometer for building automation, machine construction and environmental engineering

36kV VOLTAGE TRANSFORMERS (OUTDOOR TYPE)

012: 2015 CEB SPECIFICATION GALVANIZED STEEL WIRE (EXCEPT SHIELDING WIRE FOR TOWER LINE APPLICATION)

INLINE flowmeter for continuous flow measurement

TECHNICAL SPECIFICATION & DRAWINGS

Annexure - V. Specifications, Typical Drawing & Data Sheet for Split TEE (Hot Tapping Material)

SECTION WIREWAYS FOR RADIOLOGY EQUIPMENT

NON-PENETRATING ROOFTOP HANGERS AND SUPPORTS

Single-Phase Mini Pad-Mounted Transformer Specification: Energy+ MPDL

RTD Temperature Sensor omnigrad T -TSM 480, TR 480. Hygienic RTD sensor with Pt 100, class A TSM 480 with electronics programmable via PC

WATERFLUX 3000 Quick Start

SPECIFICATION FOR RUBBER INSULATING GLOVES FOR LOW VOLTAGE 500V

Consideration of External Pressure in the Design and Pressure Rating of Subsea Equipment API TECHNICAL REPORT 17TR12 FIRST EDITION, MARCH 2015

WATERFLUX 3000 Quick Start

VARIABLE FREQUENCY DRIVE SPECIFICATION

Fluid Sealing Association

Conductivity Transmitter

QUALITY ASSURANCE SPECIFICATION

Assmann Corporation of America TANK INSTALLATION AND USE GUIDELINES FOR BULK STORAGE TANKS

Insertion Transducer On-line Install Instruction

Digital flow transmitter for continuous flow measurement

Programmable transmitter of temperature, relative humidity and other derived humidity values with 4-20 ma outputs Instruction Manual

11-SDMS-03 REV. 02 SPECIFICATIONS FOR

The RSM shall be extensively used in field & laboratory for verification of the accuracy of all types of single-phase energy meters.

INLINE flowmeter for continuous flow measurement

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

079 : 2000 CEB STANDARD ALUMINIUM BINDING WIRE

Ambient Conditions. Operating Conditions. Pressure

SECTION EQUIPMENT WIRING

REVISIONS. App Thom. App Sud. App PC IG 2014/09/19

Ford Water Meter Couplings & Accessories

Technical Specifications: Supply of Seamless Grade TP304L Pipe and Grade WP304L Pipework Fittings to the ITER Organization (IO).

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.:

SECTION EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

Temperature Sensor Tri-Clamp

Electromagnetic Flow Transmitter

Physical Properties Measurement System (PPMS): Detailed specifications: Basic unit cryogen- free

INTEX Millwork Solutions SECTION EXTERIOR PVC PERGOLAS (IBC Compliant)

001: 2007 CEB STANDARD

ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO.

The surveillance test is a physical inspection of the product and a comparison with the specifications of the original type tested sample.

mass flowmeter for compressed air

JB/T Translated English of Chinese Standard: JB/T

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.

Customer Drawings Product Selection

TECHNICAL SPECIFICATIONS NO. EMT 6689(REV. 00) WITH INDENT NO. E/6743/5/5954

ANSI ORIFICE FLANGES METAL-KOREA

Flush pressure transmitter For viscous and solids-containing media Model S-11

Accutech DP20. Wireless differential pressure field unit


TENDER COVER PAGE (CHECK LIST)

For crossing under a railroad, contact the specific railroad company's engineering department.

Digital inductive conductivity transmitter

Thin Film Deposition

The transducer component converts the measured signal and displays the actual value.

Thin Film Deposition

INSUL-FLUE is used to reduce the danger of radiant heat from smoke pipe, flue pipe, gas vents, etc. igniting combustibles.

INSTALLATION INSTRUCTIONS for INSIGHT FIBER OPTIC FLAME SCANNERS

RF, COAXIAL. HYBRID COUPLERS POWER DIVIDERS and DIRECTIONAL COUPLERS GENERIC SPECIFICATION

INLINE flowmeter for continuous flow measurement

A. Compatibility: Products shall be suitable for piping service fluids, materials, working pressures, and temperatures.

Section Meetings Section Material and Equipment. None Required

The MUELLER method of making a main to service connection using the MUELLER E-5 Small Drilling Machine. Hand or power. kpa/34.

COMPLETE REVISION October Process Industry Practices Piping. PIP PNFJ8000 Jacketed Piping Fabrication and Installation Details

Flow Measurement SITRANS F US Inline

SPECIFICATION SS-140/9. 0.6/1 (1.2) kv CONTROL AND POWER UNDERGROUND CABLES WITH PVC OR XLPE INSULATION AND PVC JACKET

University of Houston Master Construction Specifications Insert Project Name SECTION MECHANICAL SCOPE OF WORK PART 1 - GENERAL

Construction Phase Project Management and Documentation

The MUELLER method of making a main to service connection using the MUELLER E-5 Small Drilling Machine. The main is drilled out under pressure.

General Information. Ball Curb Valve

JUMO Dtrans T100 Screw-in RTD Temperature Probe with/without Transmitter

Reliance SG800 Series Steel Water Gage Valves

JIS G3465 Seamless Steel Tubes for Drilling

DOLPHIN SHELL & TUBE MARINE CONDENSERS (DSTMC)

Transcription:

TECHNICAL SPECIFICATION FOR ANNUBAR (DELTA TUBE) SPEC NO.: PE-SS-999-145-I009 REV. NO. 01 DATE : 20.04.2012 SHEET 1 OF 4 1.0 SCOPE This specification covers the Design, Manufacture, Inspection and Testing at the manufacturer s works, proper packing for transportation and delivery to site of Annubar (Delta Tube) for use in Utility/Captive Power Station/Combined Cycle Station. 2.0 CODES AND STANDARDS 2.1 All the equipments specified herein shall comply with the requirements of the latest issue of the relevant National and International standards. 2.2 The Design and Materials used for the components shall also comply with the relevant National and International standards. 3.0 TECHNICAL REQUIREMENT The annubar and the accessories shall be suitable for continuous operation under an ambient temperature of 0-55 C and Relative Humidity of 0-95% unless specified otherwise in volume IIB Section-B or Section-C. 3.1 DP flow measurement Element shall be tubular, insert type with minimum four impact ports facing upstream direction, located precisely for measurement of average flow velocity. The sensor shall be supplied with complete mounting hardware and support plugs and valves for DP transmitter connection. The flow devices producing a differential pressure signal having a high accuracy & reliability with rigid structure & shall be suitable for larger diameter pipe. The sensor comprises of a signal outer tube & an inner tube. The inner tube conveys the high pressure signal & outer conveys the low press signal. The sensor can also be provided with dual averaging chambers, which will convey the high pressure & low pressure signal. This shall be suitable for online mounting. 3.2 Element / Probe This shall be constructed of stainless steel, SS-316/SS316L. 3.3 Assembly Flow devices shall be complete with stub, flanged end with counter flanges, isolating valves, nipple, elbow, packing, etc. and shall be terminated with root valves for remote measurement. Each device shall also be provided with SS nameplate with tag number. 4.0 GUARANTEE AND PERFORMANCE The guarantee of flow measuring assembly shall be 18 months from the date of despatch or 12 months from commissioning which ever is earlier. 5.0 TEST & INSPECTION 5.1 The bidder shall adopt suitable quality assurance plan to ensure that the equipments offered will meet the specification requirements in full. 5.2 The Quality Plan shall be discussed and finalized with the technically accepted bidders before opening the price bid. The stages where the purchaser would like to be associated for witnessing or verification would be indicated by the purchaser in the Quality Plan before approval.

TECHNICAL SPECIFICATION FOR ANNUBAR (DELTA TUBE) SPEC NO.: PE-SS-999-145-I009 REV. NO. 01 DATE : 20.04.2012 SHEET 2 OF 4 5.3 Quality Plan/Quality Assurance programme shall be submitted for owner approval. The following tests are to be included & test certificate/report shall be furnished. 1. Material Test Certificate 2. Hardness Testing 3. Hydro Test 4. Visual/Dimensional inspection report. 5.4 Inspection will be conducted by BHEL and/or their authorized representatives as per the agreed inspection schedule. The inspection schedule will be submitted by the bidder for BHEL s approval at contract stage. The cost of all tests and inspections will be deemed to have been included in the bid. For all the type tests Type Test Certificates as per agreed Quality Plan shall be furnished. In the absence of the same, such Type Tests shall be arranged at the Vendor s works in the presence of BHEL and/or their authorized representatives or in independent Test House/Laboratory approved by BHEL. 6.0 SPARES AND CONSUMABLES 6.1 Commissioning Spares and consumables As part of the main equipment supply, the bidder shall supply all commissioning spares and consumables required during Start-up, 6.2 Recommended Spares The bidder shall furnish a list of Recommended Spares along with the normal service expectancy period and frequency of replacement; quantities recommended for 3 years operation along with unit rate against each item to enable BHEL/BHEL s Customer to place a separate order later, if required. 6.3 Special Tools & Tackles The bidder shall furnish a list of Special Tools & Tackles included in the bid. 7.0 DRAWINGS & DOCUMENTS. 7.1 The offer shall include the following in 4 copies each. i. Technical data sheet for each flow measuring device assembly in the Pro forma enclosed under Data Sheet-B. ii. Catalogue/Technical Literature. iii. List of installation for similar equipment supplied in Thermal Power Station application. iv. Assembly drawing with dimensional details. 7.2 4 copies each of the following alongwith 2 CDs to be furnished after award of contract for owner approval. i. Technical Data Sheet-C. ii. Sizing Calculations. iii. Assembly drawing with dimensions. iv. Installation drawing. v. Flow Vs DP Curve.

8.0 FOR INFORMATION TECHNICAL SPECIFICATION FOR ANNUBAR (DELTA TUBE) 8.1 Storage and Commissioning Instruction 8.2 O&M are to be supplied as specified. 9.0 PACKING & MARKING SPEC NO.: PE-SS-999-145-I009 REV. NO. 01 DATE : 20.04.2012 SHEET 3 OF 4 9.1 Each item shall be properly packed with adequate protection against friction, stresses, vibration & shock during transportation. Each packing box shall have marking as per Purchase Order. 9.2 Each assembly shall be identified with the following information. - Tag No. - Service. - Line size & thickness. - Direction of flow. 10.0 APPLICABLE DATA SHEETS This document shall be read in conjunction with following data sheets. 1. Data Sheet - A & B : Data sheet no. PES-145-09-DS1-0 2. Data Sheet - C. : Data sheet no. PES-145-09-DS2-0

DATA SHEET FOR ANNUBAR (DELTA TUBE) SPEC NO.: REV. NO. DATE : SHEET 1 OF 2 Tag No. Data Sheet No. PES-145-09-DS1-0 DATA SHEET A & B DATA SHEET A (TO BE FILLED BY PURCHASER) DATA SHEET B (TO BE FILLED UP BY BIDDER) PROJECT GENERAL OFFER REFERENCE TAG NO. : QUANTITY SERVICE Bidder to indicate.. MAKE : MODEL Bidder to indicate.. ELEMENT TYPE PITOT ASSEMBLY PROBE DIAMETER & SHAPE MATERIAL ACCURACY REPEATABILTY No. OF TAP DELTA TUBE (AVERAGING PITOT TUBE) Bidder to indicate FLG SIZE & RATING Bidder to indicate SS 316 /SS316L + 1% OF ACTUAL VALUE + 0.1% OF ACTUAL VALUE ONE FLUID COOLING WATER RATE OF FLOW (T/HR) NORMAL : MAXIMUM : UPSTREAM WORKING PRESS (Kg/cm2g) PROCESS DATA DESIGN PRESS (Kg/cm2g) MAX. ALLOWABLE PRESS LOSS DIFF. PRESS AT MAX FLOW Bidder to indicate NORAML TEMP (Deg C) MAXIMUM TEMP (Deg C) PIPE SIZE (OD x THK) mm PIPE MATERIAL PIPE LINE DATA AVAILABLE PIPE STRAIGHT LENGTH UPSTREAM : DOWNSTREAM : RESTRICTION UPSTREAM : DOWNSTREAM :

DATA SHEET FOR ANNUBAR (DELTA TUBE) SPEC NO.: REV. NO. DATE : SHEET 2 OF 2 Tag No. Data Sheet No. PES-145-09-DS1-0 DATA SHEET A & B DATA SHEET A (TO BE FILLED BY PURCHASER) DATA SHEET B (TO BE FILLED UP BY BIDDER) STUB / NIPPLE SIZE : RATING : (Bidder to indicate).... END CONNECTION SPOOL PIECE WITH FLANGE ROOT VALVES SIZE : RATING : (Bidder to indicate) SIZE : RATING : END CONNECTION : QTY. :.......... FLUSHING ARRANGEMENT (REFER SHEET-3 OF SPEC) [] REQUIRED [] NOT REQUIRED ON-LINE RETRACTIBLE TYPE [] REQUIRED [] NOT REQUIRED INTERNAL BOTTOM SUPPORT OF SS 316 / SS316L MATERIAL SHALL BE PROVIDED IN PROCESS PIPE BIDDER TO SPECIFY HOLE SIZE TO BE DRILLED ON PROCESS PIPE FOR MOUNTING ANNUBAR PRPED BY CHKD BY APPD BY COMPANY SEAL NAME SIGN DATE NAME SIGN DATE

DATA SHEET FOR ANNUBAR (DELTA TUBE) SPEC NO.: VOLUME IIB REV. NO. DATE : SHEET 1 OF 2 Tag No. Data Sheet No. PES-145-09-DS2-0 DATA SHEET C DATA SHEET C FOR ANNUBAR (DELTA TUBE) (TO BE FILLED BY THE CONTRACTOR AFTER AWARD OF CONTRACT) PROJECT GENERAL TAG NO. : QUANTITY SERVICE MAKE : MODEL ELEMENT PROCESS DATA TYPE PITOT ASSEMBLY PROBE DIAMETER & SHAPE MATERIAL ACCURACY REPEATABILTY No. OF TAP FLUID RATE OF FLOW (T/HR) UPSTREAM WORKING PRESS (Kg/cm2g) DESIGN PRESS (Kg/cm2g) MAX. ALLOWABLE PRESS LOSS DIFF. PRESS AT MAX FLOW NORAML TEMP (Deg C) MAXIMUM TEMP (Deg C) DELTA TUBE (AVERAGING PITOT TUBE) FLG SIZE & RATING NORMAL : MAXIMUM : PIPE SIZE (OD x THK) mm PIPE MATERIAL PIPE LINE DATA AVAILABLE PIPE STRAIGHT LENGTH RESTRICTION UPSTREAM : DOWNSTREAM : UPSTREAM : DOWNSTREAM :

DATA SHEET FOR ANNUBAR (DELTA TUBE) SPEC NO.: VOLUME IIB REV. NO. DATE : SHEET 2 OF 2 Tag No. Data Sheet No. PES-145-09-DS1-0 DATA SHEET C DATA SHEET C FOR ANNUBAR (DELTA TUBE) (TO BE FILLED BY THE CONTRACTOR AFTER AWARD OF CONTRACT) STUB / NIPPLE SIZE : RATING : END CONNECTION SPOOL PIECE WITH FLANGE ROOT VALVES SIZE : RATING : SIZE : RATING : END CONNECTION : QTY. : FLUSHING ARRANGEMENT ON-LINE RETRACTIBLE TYPE INTERNAL BOTTOM SUPPORT OF SS 316 MATERIAL HOLE SIZE TO BE DRILLED ON PROCESS PIPE FOR MOUNTING ANNUBAR NAME COMPANY SEAL SIGN DATE