Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Similar documents
R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

In Class Examples (ICE)

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2016

PAPER-II (Subjective)

Rajasthan Technical University, Kota

IGEE 402 Power System Analysis. FINAL EXAMINATION Fall 2004

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)

Conventional Paper-II-2013

Exercises on overhead power lines (and underground cables)

Var Control. Adding a transformer and transformer voltage regulation. engineers loadflow program. The control system engineers loadflow.

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Electrical Engineering. Power Systems. Comprehensive Theory with Solved Examples and Practice Questions. Publications

, ,54 A

Impact Assessment Generator Form

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Initial Application Form for Connection of Distributed Generation (>10kW)

SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS)

Conventional Paper-II-2011 Part-1A

Electrical Power Systems

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

Beskrivelse av simuleringsmodell ==> Description of simulation model

ETAP PowerStation. Electrical Transient Analyzer Program. ETAP PowerStation. Short Circuit Analysis. ANSI Standard 3-Phase Fault Currents

Hours / 100 Marks Seat No.

PROTECTION APPLICATION HANDBOOK

POWER SYSTEM II LAB MANUAL

Rajasthan Technical University, Kota

Chapter 10: Compensation of Power Transmission Systems

Influence of Wind Generators in Voltage Dips

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers

Embedded Generation Connection Application Form

Modle 6 : Preventive, Emergency and Restorative Control. Lecture 29 : Emergency Control : An example. Objectives. A simple 2 machine example

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

SRI VIDYA COLLEGE OF ENGG AND TECH

Embedded Generation Connection Application Form

Stability Enhancement for Transmission Lines using Static Synchronous Series Compensator

COURSE PLANNER SUBJECT: ELECTRICAL POWER SYSTEM II

3. (a) List out the advantages and disadvantages of HRC fuse (b) Explain fuse Characteristics in detail. [8+8]

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Transmission Line Models Part 1

Embedded Generation Connection Application Form

Transient stability improvement by using shunt FACT device (STATCOM) with Reference Voltage Compensation (RVC) control scheme

Power Quality enhancement of a distribution line with DSTATCOM

EH2741 Communication and Control in Electric Power Systems Lecture 2

Chapter 2: Transformers

EL 403 MODEL TEST PAPER - 1 POWER SYSTEMS. Time: Three Hours Maximum Marks: 100

1 Introduction General Background The New Computer Environment Transmission System Developments Theoretical Models and Computer Programs

Owner/Customer Name: Mailing Address: City: County: State: Zip Code: Phone Number: Representative: Address: Fax Number:

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering)

Connection Impact Assessment Application Form

QUESTIONNAIRE for Wind Farm Power Stations only

Power System Stability. Course Notes PART-1

ELECTRICAL POWER TRANSMISSION TRAINER

Form B. Connection Impact Assessment Application Form Distribution System

Analysis of a 405 km transmission line with series compensation

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur

Fatima Michael college of Engineering and Technology

ELECTRICAL POWER ENGINEERING

EE 340L EXPERIMENT # 5.1 SYNCHRONOUS GENERATOR (STAND-ALONE OPERATION)

1

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System

Short-Circuit Analysis IEC Standard Operation Technology, Inc. Workshop Notes: Short-Circuit IEC

SYNCHRONOUS MACHINES

State of North Dakota Engineering data submittal Page 1 For interconnection of distributed generation to Otter Tail Power Company

Dynamic Model Of 400 Kv Line With Distance Relay. Director Research, The MRPC Company, Hyderabad, India 2

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009

SCHEME OF COURSE WORK ( ) Electrical & Electronics Engineering. Electrical machines-i, II and power transmission engineering

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations

PART 1 OWNER/APPLICANT INFORMATION

Analysis of Temporary Over-Voltages from Self-Excited Large Induction Motors in the Presence of Resonance - Case Studies

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

Arvind Pahade and Nitin Saxena Department of Electrical Engineering, Jabalpur Engineering College, Jabalpur, (MP), India

Exercises. 6 Exercises

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

EE 740 Transmission Lines

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT CODE & NAME : EE 1402 HIGH VOLTAGE ENGINEERING UNIT I

Single Line Diagram of Substations

SIMPLE SOLUTIONS FOR IMPROVING LIFE OF BREAKERS USED IN TRANSMISSION AND DISTRIBUTION SYSTEMS

Impact of Thyristor Controlled Series Capacitor on Voltage Profile of Transmission Lines using PSAT

Increasing Dynamic Stability of the Network Using Unified Power Flow Controller (UPFC)

Improving the Transient and Dynamic stability of the Network by Unified Power Flow Controller (UPFC)

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

EE 340L EXPERIMENT # 3 SYNCHRONOUS GENERATORS

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström

LOAD BEHAVIOUR DURING VOLTAGE DIPS: A VOLTAGE QUALITY STUDY IN LOW VOLTAGE DISTRIBUTION SYSTEM

University of Rajshahi Department of Electrical & Electronic Engineering B.Sc. Engineering Part-IV Odd Semester Examination- 2017

CHAPTER 2 ELECTRICAL POWER SYSTEM OVERCURRENTS

EASTERN ILLINI ELECTRIC COOPERATIVE Application for Operation of Member-Owned Generation

Wind Power Facility Technical Requirements CHANGE HISTORY

APPENDIX A MATLAB CODE FOR CALCULATION OF MOTOR TORQUE

APPLICATION FOR INTERCONNECTION & OPERATIONS OF MEMBER-OWNED GENERATION

COMPARATIVE PERFORMANCE OF SMART WIRES SMARTVALVE WITH EHV SERIES CAPACITOR: IMPLICATIONS FOR SUB-SYNCHRONOUS RESONANCE (SSR)

IJSER. Fig-1: Interconnection diagram in the vicinity of the RajWest power plant

Transcription:

9210-114 Level 6 Graduate Diploma in Engineering Electrical Energy Systems Sample Paper You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler, drawing instruments No additional data is attached General instructions This examination paper is of three hours duration. This examination paper contains nine questions. Answer any five questions. All questions carry equal marks. The maximum marks for each section within a question are given against that section. An electronic, non-programmable calculator may be used, but the candidate must show clearly the steps prior to obtaining final numerical values. Drawings should be clear, in good proportion and in pencil. Do not use red ink.

1 a) A 66 kv overhead distribution line, having a length of 60 km delivers power to a load centre. During peak hours, the load centre serves a load of 15 + j8 MVA. Per unit length, resistance and reactance of the line are 0.249 Ωkm 1 and 0.414 Ωkm 1 respectively. The effect of shunt capacitance of the line is neglected. Voltage at the sending end is maintained at its rated value. i) Calculate the approximate value of voltage at the load centre during the peak hours. (10 marks) ii) Express the voltage drop of the line as a percentage. (2 marks) b) It is proposed to install series capacitors to each phase of the line to reduce the line drop to 5%. The rated voltage and power of the available capacitors are 0.66 kv and 40 kvar respectively. i) Calculate the number of capacitors that are to be connected in series in each phase of the line to achieve above requirement. (8 marks) 2 A 750 kv, 50 Hz, 315 km overhead transmission line delivers power to a grid substation. Series impedance and shunt susceptance of the line are 0.025 + j0.3 Ωkm 1 and j6 x 10 6 Skm 1. During peak hours, the grid substation receives 800 MW at 0.8 power factor lagging. Voltage at the receiving end is to be maintained at the rated value. a) Calculate surge impedance, wavelength and propagation constant. (5 marks) b) Determine A, B, C, D parameters of the line. (6 marks) c) Calculate sending end voltage, current and power factor of the line during peak hours. (6 marks) d) Now the line is opened at the far end. Without any calculation, state giving reasons whether the voltage at the far end is increased or decreased. 2

3 Consider the power system shown in Figure Q3. Branch data and bus data of the system are given in Table 3.1 and Table 3.2 respectively. Initial estimates of respective buses are given in the voltage column of the Table 3.2. Line reactance is given on 100 MVA base. Figure Q3 Bus number Bus number Series impedance p.u. 1 2 j0.025 1 3 j0.04 2 3 j0.06 Table 3.1 Bus number P MW Q MVar Table 3.2 a) Construct bus admittance matrix. (4 marks) b) Use Gauss-Seidel method to calculate voltages at nodes after one iteration. (10 marks) c) Determine swing bus power and power factor. (6 marks) V p.u. 1 1.05 0 2 400 1.02 0 3 500 200 1.0 0 Voltage angle 3 See next page

4 a) i) A power system consists of n1 number of PV buses and n2 number of load buses. Determine the order of the following blocks of Jakobian matrix. P P Q Q,,, δ V δ V ii) Describe the advantage of the fast-decoupled load flow calculation method over the Newton-Raphson method. b) Consider the power system shown in Figure Q4. Voltage at load bus to be calculated using the Newton-Raphson method. (4 marks) Figure Q4 i) Calculate active and reactive power mismatch at load bus B. (6 marks) ii) Determine the voltage at bus using the Newton-Raphson method after first round of iteration. (7 marks) 5 a) A 200 MVA, 50 Hz synchronous generator has inertia constant of 8 MJ/MVA. i) Calculate the kinetic energy stored when the generator is running at synchronous speed. (2 marks) ii) At the steady state condition, the generator delivers 150 MW. If the electrical load is suddenly dropped to100 MW determine the initial acceleration of the rotor. (2 marks) b) A three-phase, 50 Hz synchronous generator delivers power of 0.65 p.u. to a system via a transmission line. Sub-transient reactance of the generator and per- phase inductive reactance of the line are 1.25 p.u. and 0.38 p.u. respectively. Voltage magnitudes at the starting and ending points are equal to1.0 p.u. i) Determine the excitation voltage of the generator. (4 marks) ii) A three-phase short circuit occurred in the line and after a while, the fault was self-cleared. How long can the fault be continued without losing the synchronism (H = 4 MJ/MW)? (12 marks) 4

6 a) Describe briefly the importance of short circuit calculations. (5 marks) b) A synchronous generator G is connected via step-up transformer T1, transmission line L and step-down transformer T2 to a bus that supplies three identical induction motors (shown in Figure Q6). The ratings of all the equipment are given in the Table 4. Figure Q6 Equipment Rating G 50 MVA, 12.5 kv, 25% T1 75 MVA, 12.5 kv/132 kv, 11% T2 75 MVA,132 kv/6.6 kv M 12 MVA, 6.6 kv, 25% L Line reactance of 22% on the base of 50 MVA Table 4 A three-phase short circuit occurs at the motor terminal. Determine the current to be interrupted by the circuit breakers A and B. (15 marks) 7 A 100 MVA, 22 kv, 50 Hz synchronous generator is connected to a 100 MVA, 22 kv/132 kv step-up transformer. Both generator winding and transformer windings are Y-connected and their neutral points are solidly earthed. Reactance of generator and transformer in p.u. (On equipment base) are given in Table 7. A line-to-line fault occurs at the high voltage side of the transformer. G Xs = 1.50; x = 0.24, x = 0.10; X2 = 0.10; X0 = 0.05 T X1 = X2 = X0 = 0.11 Table 7 a) Calculate the current that flows to the point of fault during sub transient period and transient period separately. (12 marks) b) Determine voltage at generator terminals during each of the periods given above. (8 marks) 5 See next page

8 a) With suitable sketches, briefly explain the use of differential relays for the protection of the following equipment. i) Generator. (2 marks) ii) Bus Bar. (2 marks) iii) Transformer. (4 marks) b) Explain why distance protection is preferred compared to over current protection in transmission line protection. (2 marks) c) A 132 kv overhead transmission line having series impedance of 25 + j110 Ω is protected with the help of Mho relay. The Mho relay has a maximum reach of 5 Ω with an angle of 75. Voltage and current transformer ratio at the circuit breakers location are 132 kv: 120 V and 400 A: 5 A respectively. i) Sketch the operating diagram of the relay and clearly identify the operating and non-operating region of the relay. ii) Calculate the impedance of the line as seen by the relay. iii) Determine the fraction of the line that is protected by the relay. (4 marks) 9 a) i) With the help of a labelled diagram, explain what is meant by governor droop. ii) Explain why the power system is not allowed to operate beyond the permissible range of frequency. iii) Two 50 Hz synchronous generators A and B are feeding power to an isolated system. Generator ratings and their droop characteristics are given in Table 9. Both generators are operating at 50 Hz when generators A and B deliver 50% and 60 % (respectively) of their rated power. The synchronous speed of the both generators is 1500 rpm. Determine the synchronous speed of generators when they are disconnected from the system. (8 marks) Generator Rating (MW) Droop characteristic (%) A 200 4 B 350 8 Table 9 b) List three methods of voltage control and describe one of them briefly. (6 marks) 6