NIC Project Medium Voltage Direct Current Link Technical Specification

Similar documents
VI 3 - i TABLE OF CONTENTS

TS RES - OUTSTANDING ISSUES

Table of Contents. Introduction... 1

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ECP HV INSULATION TESTING

EI HIGH VOLTAGE INSULATION TESTING POLICY

ECP HV INSULATION TESTING

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it.

Generation and Load Interconnection Standard

Zambezi (previously Caprivi) Link HVDC Interconnector: Review of Operational Performance in the First Five Years

RELEVANT ELECTRICAL STANDARDS

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Standard Prices for Generators 2010

Insulation Co-ordination For HVDC Station

LIMITS FOR TEMPORARY OVERVOLTAGES IN ENGLAND AND WALES NETWORK

Connection of Embedded Generating Plant up to 5MW

each time the Frequency is above 51Hz. Continuous operation is required

Wind Power Facility Technical Requirements CHANGE HISTORY

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

Generation and Load Interconnection Standard

Multimeter 500CVD21 RTU500 series

RELEVANT ELECTRICAL STANDARDS

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

Southern Company Interconnection Requirements for Inverter-Based Generation

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code)

Technical recommendation for the purchase of Real Time Thermal Rating for transformers

69 kv to 500 kv INTERCONNECTION REQUIREMENTS FOR TRANSMISSION FACILITIES

Generation Interconnection Requirements at Voltages 34.5 kv and Below

SYNCHRONISING AND VOLTAGE SELECTION

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Key DRAFT EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 13/12/17

ESB National Grid Transmission Planning Criteria

Customer Standard. Standard for Embedded Generation (5MW and above)

Transformers connected via a cable Overvoltage protection

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

E N G I N E E R I N G M A N U A L

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

SYSTEM MONITORING FAULT RECORDING

Company Directive POLICY DOCUMENT: SD4/7. Relating to 11kV and 6.6kV System Design

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Single Line Diagram of Substations

TECHNICAL SPECIFICATION

Power System Studies

NETWORK INNOVATION COMPETITION ANGLE-DC PROJECT HOLISTIC CIRCUIT CONDITION MONITORING SYSTEM REPORT

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS

RELEVANT ELECTRICAL STANDARDS

Guidance and Declaration - Electromagnetic Compatibility (EMC) for the Delfi PTS ii Portable Tourniquet System

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter

Company Directive STANDARD TECHNIQUE: TP6F/1. Power Measurement Conventions

INTEGRATED TRANSMISSION PLAN Glossary

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

NT & NQ CLASS II TRANSFORMERS FOR SIGNALLING SYSTEMS. A Balfour Beatty and Alstom Company

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

Company Directive STANDARD TECHNIQUE: SD5F. Relating to connecting multiple small low voltage connections with limited network analysis

A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation Equipment

Smart Termination TECHNICAL SPECIFICATIONS CURRENT VOLTAGE INSTRUMENTRANSFORMER

PSSI 27 Work or Testing On or Near to High Voltage Direct Current (HVDC) Plant and Apparatus

Fixed Series Compensation

High-set undervoltage stage with definitetime. or inverse definite minimum time (IDMT) characteristic. Low-set undervoltage stage with definitetime

Centrale de mesure Power Meter PM500 Merlin Gerin

Harmonizing the ANSI-C12.1(2008) EMC Tests. Harmonizing the ANSI-C12.1(2008) EMC Tests

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks

NPRG860 NPRG870 REGULATION. Automatic Synchronizer for Generator

Unit 2. Single Line Diagram of Substations

UMG 103. UMG 103 Universal measurement device for DIN rails. GridVis Analysis software. Harmonics. Measurement accuracy 0.5.

MINISTRY OF ELECTRICITY

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Transmission Interconnection Requirements for Inverter-Based Generation

2620 Modular Measurement and Control System

Reference Number PDS 04 (RIC Standard: EP SP)

TEST SUMMARY. Prüfbericht - Nr.: Test Report No.: Seite 2 von 25. Page 2 of 25

Power quality Harmonics up to 40th harmonic Unbalance, rotary field indication Distortion factor THD-U / THD-I

RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana

Capstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:

Distribution/Substation Transformer

Power Quality Requirements for Connection to the Transmission System

Embedded Generation Connection Application Form

Company Replaces previous document Document ID Issue E.ON Elnät Sverige AB Ny engelsk utgåva D

Education & Training

BED INTERCONNECTION TECHNICAL REQUIREMENTS

Device Under Test: ALTEA VS- 24-I VS-24-I. 0 24/09/12 First issue A. Peretto L. Peretto 1 24/06/16 All text review E. Scala L. Peretto J. L.

NPRG860 & NPRG870 perform synchronization and paralleling of generators with electrical network. NPRG860 features a speed adjustment function.

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER

High voltage engineering

P.O (November 2009) This is an unofficial translation of the latest draft of the Spanish grid code. Source: Jason MacDowell, GE Energy

POWER QUALITY AND SAFETY

Utility Interconnection and System Protection

SolidGround TM grid stability and harmonics mitigation system Geomagnetic Storm Induced Current (GIC) and Electromagnetic Pulse (EMP) protection

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter

ABB 1. Multifunctional three-phase monitoring relays. CM-MPN.52, CM-MPN.62 and CM-MPN.72 Data sheet. Features. Approvals. Marks.

Curso de Transmissão em Corrente Continua Rio de Janeiro, de Junho, 2007

TSX Series. Modicon Manuals. Presented by: Modicon PLC. Schneider Electric Quantum Modicon Gould Gettys

Standard Development Timeline

Title Substation Auxiliary Transformer from Rectifier Transformer Secondary. Reference Number PDS 01 (RIC Standard: EP SP)

Types CDG 11 and CDG 16 Inverse Time Overcurrent and Earth Fault Relay

Substation HV Cables. Document Number: 1-11-FR-07

Transcription:

1 SCOPE This Specification details SP Energy Networks (SPEN) requirements for a bidirectional Medium Voltage Direct Current (MVDC) Link for the Angle-DC project, being carried out in conjunction with Ofgem s Network Innovation Competition (NIC). 2 ISSUE RECORD This document is controlled Date Issue No Author(s) Amendment Details June 2015 1.0 James Yu/ Norman Macleod Original NIC submission document functional specification. Feb 2017 2.0 Andrew Moon Reorganised and amended to SPEN specification format. Additional functional requirements added from supplier tender process. 3 ISSUE AUTHORITY CHANGE BACK Author(s) Owner Issue Authority James Yu, Norman Macleod, Kevin Smith and Andrew Moon. James Yu Ochil House, Technology Avenue, Hamilton Intnl Technology Park, Blantyre, Glasgow James Yu Ochil House, Technology Avenue, Hamilton Intnl Technology Park, Blantyre, Glasgow Page 1 of 13

4 CONTENTS Table of Contents 1 Scope... 1 2 Issue Record... 1 3 Issue Authority change back... 1 4 Contents... 2 5 Introduction... 4 6 Existing Circuits... 4 7 Conversion to DC operation... 4 8 Ratings... 5 8.1. Power Rating... 5 8.2. DC voltage rating... 6 8.2.1 Voltage Reduction Capability... 6 8.2.2 DC Creepage... 6 9 DC Circuit Protection... 6 10 Scheme operation... 7 10.1. Polarity Reversal... 7 11 Control Modes... 8 11.1. Power... 8 11.2. DC voltage... 8 11.3. Reactive power... 8 11.4. AC bus voltage... 9 11.5. STATCOM operation... 9 11.6. Power run-back... 9 11.7. Black start... 9 11.8. Power oscillation damping... 9 11.9. Control Interface... 10 12 Relocation Capability and Building Detail... 10 13 Operating Temperature... 10 14 Noise Levels... 11 15 Reliability and Availability... 11 16 Operating Losses... 11 17 Harmonic distortion... 12 Page 2 of 13

18 Auxiliary power... 12 19 Network Dynamic Performance... 12 20 Pre-Insatllation Testing... 12 21 EMC... 12 22 Safety... 13 Page 3 of 13

5 INTRODUCTION This specification details the requirements for a Medium Voltage Direct Current (MVDC) Link, originally required for the SPEN Angle-DC project trial, involving the AC to DC conversion on Medium Voltage AC circuit. The features of a bidirectional MVDC link should include: Enhancing the power flow between two network groups; Providing more control of the power flow; Providing control of reactive power flows, hence influencing wider area voltage profile; Reducing operating losses in the wider distribution area; Providing additional ancillary services from the link; and The conversion of existing AC assets to DC operation. This specification provides the functional requirements of the MVDC scheme which will be required to achieve the above. General electrical and environmental requirements for a costal MVDC link are provided in this specification. 6 EXISTING CIRCUITS The route may consist of a mix of land cables and sections of overhead line. Each circuit can have multiple sections, with several designs of cables (e.g. 3-core, 1-core, copper, aluminium etc.). The existing circuits must have a minimum of two phase conductors to make up DC a circuit. The DC resistance of the existing two circuits may not be the same. 7 CONVERSION TO DC OPERATION The MVDC scheme should operate as a symmetrical monopole, i.e. with one positive MV terminal and one negative MV terminal, or as a bi-pole, with positive and negative MV terminals and a neutral point. In the latter case, a neutral connection between the converter stations is not required, but the neutral at one station shall be grounded. The supplier should indicate if and how they intend to provide a ground reference for a symmetrical monopole scheme. The conductors of one existing AC circuit can be parallel connected to form one pole conductor and the same for the other circuit. For two 3-phase circuits, the scheme topology would be as shown in Figure 3. Page 4 of 13

Figure 1. Conversion of three phases to two poles, with 2 position 3-phase DC disconnector earth switch allowing earthed isolation of the DC circuit. The impact on this arrangement could lead to unbalance in the resistances of the pole conductors. The MVDC equipment supplier should comment on the impact the unbalance in the pole conductor resistances would have on the operation of the scheme. Where 6-phase conductors are present and a prolonged loss of one conductor on one pole occurs (i.e. due to a cable fault), it is proposed that a complimentary conductor on the other pole is taken out of service by mechanical isolation. This should maintain, as close as possible, the resistance balance between circuits. This can be achieved using 2-position 3 - phase disconnector earth switch with a moulded termination for each phase conductor. The scheme would operate at approximately 67% of normal power, with one termination per pole open, once the disconnector is reclosed. 8 RATINGS 8.1. Power Rating The notional power rating of the scheme shall be calculated as follows. =2 3, ( ), ( 1 ) where is the number of conductors per pole,, is the peak line to ground voltage and ( ) is the current carrying capacity of the weakest of circuit section, according to ER P17 or ER P27, for a maximum insulation temperature,. The maximum insulation temperature will be determined by SP Energy Networks taking into account the age and condition of the cable. The supplier should assume that the scheme may operate continuously at, with a power factor of lead/lag 0.9, i.e. a scheme rated capacity of = /0.9. The power rating will be confirmed by detailed evaluation early in the project execution phase and the supplier should comment on how higher power levels could be achieved from their designs. Bi-directional power transfer capability is required, i.e. the rated power is required in both directions. Page 5 of 13

The target minimum power transfer level of the scheme shall be 0MW. The supplier shall comment on any difficulty in achieving this level and if not possible, the minimum continuous power level which can be achieved. Over-load rating of the scheme, i.e. operating at higher DC current, is not required. However, the supplier should comment on which items of equipment in their supply would be the limiting factor for short time overload. 8.2. DC voltage rating The DC voltage is constrained by the insulation capability of the existing cables. The age of the cables is also a factor in the consideration of the DC voltage. The notional DC voltage for the scheme is ±27kV for 33 kv networks. For other voltage levels the dc voltage shall be, = 2,!" / 3, ( 2 ) where,!" is the RMS line to line voltage. The voltage rating should confirmed by detailed evaluation early in the project execution phase and the supplier is requested to comment on how higher voltage levels could be achieved from their designs. 8.2.1 Voltage Reduction Capability A voltage reduction capability, to clear a transient fault or allow for changing pollution levels, is desirable. Suppliers shall declare their base voltage reduction capability and any cost options of an enhanced voltage reduction capability over the base value declared. e.g. a base voltage reduction capability could be 80% of nominal, with an enhanced voltage reduction capability of 60%. 8.2.2 DC Creepage The creepage distance of insulators should be at least 33.3 mm/kv for coastal environments and may be increased to 50mm/kV should the nominal DC voltage cause issues during the commissioning stage. Where the proximity of the overhead line to the coast introduces the possibility of saline pollution on the insulators, enhanced measures, such as the application of grease, the use of additional sheds or replacement with units of longer creepage distance or by polymeric insulators may be required. 9 DC CIRCUIT PROTECTION Suppliers should consider the cables and cables and OHL sections capable of withstanding short periods operating at 2 #$ during transient faults. To ensure the safety of the cable, it is proposed that the supplier installs a surge arrester on the DC terminals (+ve and ve) at either end of the DC link. As a provisional approach, the surge arrestors should have a protective level set at 1.5pu of the nominal DC voltage. This figure will be revised during the post tender design stage. Page 6 of 13

Protection Current Transformers (CTs) will be required at the MVDC converter connection points for the interconnection cable protection scheme. In the event of a transient fault, the MVDC converters are expected to recover after a fault and allow DC cable re-energisation provided the circuit has reclosed. The MVDC link auto-reclose policy shall be in line with the SPEN 33kV Protection and Control Application Policy. Suppliers should reference PROT-01-006 section 13, which states that the operating mode for all auto reclose equipment shall be delayed single-shot auto reclose only, with a minimum dead time setting of between 4 and 10 seconds. Where automatic reclosing systems are connected in series, the minimum grading between each dead time interval shall be 1-second. Suppliers are responsible for carrying out and providing results from a transient analysis study and recommending pre-insertion resistance values and circuit breaker capacities, so that SP Energy Networks can supply the correct AC side equipment. The insulation strength of equipment for lightning and switching stresses shall be chosen on basis of calculated over-voltages. The minimum margins used for determination of withstand levels for each piece of equipment should be chosen in accordance to practice on conventional HVDC schemes and to IEC 60071-5. 10 SCHEME OPERATION SP Energy Networks operators should be able to dispatch power through the link, either as, Pre-set power transfer levels, e.g. 100%, 80%, 60%, etc.; Vernier control from full load to minimum power. The power ramp rate shall be adjustable by design, but the operator would implement a fixed rate anticipated to be MW/minute. This ramp rate would apply to steps between pre-set power levels and to Vernier control. This ramp rate should be confirmed by detailed evaluation early in the project execution phase and the supplier is requested to comment on what limits on ramp rate could be achieved from their designs. 10.1. Polarity Reversal Due to concerns over XLPE cable insulation, SPEN view DC polarity reversal as a nonbeneficial feature of reducing DC cable re-energisation times. Suppliers can include this as a cost option provided its use can be avoided. Page 7 of 13

11 CONTROL MODES 11.1. Power The primary control mode for the scheme will be power control, i.e. the scheme is able to operate from minimum power to maximum power, transferring power in either direction through the link. By operator selection, each terminal may function as a rectifier (exporting power) or an inverter (importing power). 11.2. DC voltage The inverter terminal should control the DC voltage and the rectifier terminal should control the DC current and hence power flow. 11.3. Reactive power The scheme should be able to control reactive power absorption and generation at each terminal independently and also independent from the direction of power flow. Thus a full 4 quadrant capability is required for real and reactive power, as illustrated in Figure 1. It is anticipated that the voltage or and/or current ratings of the equipment may introduce a limitation on the full 4 quadrant operation of the converter, as indicated by the inner shape in Figure 1. The supplier is requested to confirm the converter operating capability at the points indicated in Table 1. A +P(pu) B C D -Q (pu) J E +Q(pu) I H G -P(pu) F Figure 1. Real/reactive power capability diagram. In the following table operating points B, E, G and J are requested To Be Confirmed (TBC) by the supplier. All other operating points are a mandatory requirement of this specification. Page 8 of 13

Table 1. Scheme operating points. Operating point Power (pu) Power factor (pu) Comment A 1.0-0.9 Required B TBC 0 Requested C 1.0 0 Required D 1.0 0.9 Required E 0 TBC Requested F -1.0 0.9 Required G TBC 0 Requested H -1.0 0 Required I -1.0-0.9 Required J 0 TBC Requested 11.4. AC bus voltage The scheme should be able to operate in a voltage control mode, such that the operator may select an AC bus voltage and the converter will automatically adjust converter reactive power absorption or generation to achieve the desired voltage. Normal operating range of the 33kV distribution system is ±6%. 11.5. STATCOM operation In the event that the DC circuit is unavailable, e.g. due to a major cable fault, each converter station should be capable of operating as a STATCOM, i.e. providing reactive power output at points E and J in Figure 1. This will require that any equipment required for initial energisation, e.g. pre-insertion resistors, is installed at both terminals. 11.6. Power run-back Under certain contingencies on the distribution system, e.g. the loss of a key circuit or generator, there may be the need to instigate a power run-back from the present operating power transfer level to a pre-defined operating level. Studies in the early project execution phase will determine if this facility is required and to what levels power run-back would be set. Note that run-back can imply power reduction and power increase, the latter limited by the rating of the scheme. 11.7. Black start Not required. 11.8. Power oscillation damping Not required. Page 9 of 13

11.9. Control Interface The scheme should be designed for un-manned operation, with remote control via a SCADA system from SP Energy Networks operation centre. The MVDC converters shall have the following interfaces: 1 A HMI interface with remote access; and 2 A hardwired SCADA interface accepting remote and local control commands. Suppliers shall describe any input parameters required to configure and operate the solution (fixed and time-variant) and also the full list of parameters to be monitored during live operation of the flexible power link. The MVDC control system should be capable of interfacing with SCADA Remote Terminal Units (RTUs); including digital I/O at 48 V and analogue inputs at 0-10 ma DC and SCADA systems using industry standard SCADA protocols IEC 61850. 12 RELOCATION CAPABILITY AND BUILDING DETAIL MVDC link converters will be housed in buildings sympathetic to building aesthetics of similar building types in the local vicinity. The volume and height of the MVDC converters stations should be as small as is reasonably practicable. A re-locatable MVDC housing solution is not an essential requirement. However, in the unlikely event that the MVDC converters cannot operate the DC circuit as designed, the converter may be required to be relocated to a different site. The incremental cost and any space and height variation of this feature should be listed as optional, with variation details provided. The supplier should also give cost consideration to external cladding/finish, which would be sympathetic to local building aesthetics, if recommending the containerised variation. Where site civils preparation work will be carried out by a SP Energy Network s contractor, ground surveys do not need to be taken into account. The site preparation works will include concrete bases, power cabling, embedded earthing tape and auxiliary cables for the MVDC apparatus. The earthing arrangements for the MVDC converters, the housing, in conjunction with the existing substation earthing system will need to be assessed and designed by the MVDC converter supplier. 13 OPERATING TEMPERATURE For low lying and costal locations of both converter stations, converters must be capable of normal operation between the following ambient temperatures: Maximum - For equipment rating purposes = +40 C Maximum - For rated power transfer capability = +35 C Minimum - For rated power transfer capability = -20 C Minimum - For equipment rating purposes = -20 C Page 10 of 13

The system must deliver MW at +35 C and remain operational at +40 C, although power could be reduced if necessary. The system must be able to remain in operation at -20 C and achieve rated power. 14 NOISE LEVELS Allowable noise levels will largely be dictated by the distance from the MVDC converter site boundary to the nearest dwelling or place of business. A guidance maximum noise level in db Lar (15 minutes) at a location 3.5 metres from the façade of any nearby residential property will be agreed, between with local authority Environmental Health Officers and SP Energy Networks, following a 2-week site period of background noise monitoring in accordance to Section 11 of British Standard 4142:2014. The supplier shall provide noise emission data, including the number of noise sources and their locations within the MVDC substation compound, to allow SP energy networks to establish a combined noise limit, of the MVDC equipment, at 1 m from the substation boundary. 15 RELIABILITY AND AVAILABILITY As a single DC link will replace one existing AC link, the reliability of the scheme and the availability of energy are critical. The following target performance figures are requested: Forced outage rate (FOR) <3 trips per annum Scheduled energy unavailability (SEU) <1% Forced energy unavailability (FEU) <1% Energy availability (EA) >98% The supplier shall indicate what reliability and availability can be achieved from their design. Converter operation will be monitored for a period of 5 years after the start of commercial service. It is a requirement that the above conditions are met in each year of the 5 years. Outages of the converters, as a result of failures on the cable and overhead line distribution circuits, are excluded from the above limits, unless it is clear that such failures are a direct result of a mal-operation of the converters. Suppliers are to calculate the Mean Time Between Failure values of system components and include costs for enough spares to last 5-years. The supplier must demonstrate a replacement program that will enable the MVDC link to operate for a minimum of 20-years. 16 OPERATING LOSSES The following target operating losses are requested for each converter station and if not considered to be achievable the supplier should confirm what level of operating losses can be achieved. No-load losses < 0.25% of scheme rated power; and Load losses < 2.0% of scheme rated power. Page 11 of 13

The supplier shall provide a chart or range of loss values across various real and reactive power throughputs of the MVDC converter. 17 HARMONIC DISTORTION The contribution to the Total Harmonic Distortion (THD) and individual harmonic voltages, created by the MVDC link either side of the DC link, shall not exceed the 95% cumulative probability levels given in Engineering Recommendation G5/4. The effect of network segregation will be taken into account using monitoring data taken either side of the segregated AC network. 18 AUXILIARY POWER The supplier shall confirm the maximum level of auxiliary power required to operate each converter station. It is anticipated that the primary source of auxiliary power (at 415V) will be supplied by SP Energy Networks from the local distribution network. The supplier shall indicate what back-up power supplies are needed to allow the MVDC scheme to ridethrough momentary disturbances to the auxiliary power supply and the effect of auxiliary power loss on the MVDC converter operation. 19 NETWORK DYNAMIC PERFORMANCE MVDC Converter equipment should be designed to tolerate a 2% voltage unbalance as defined is ER P29. Within the voltage unbalance limit, levels of harmonic distortion should remain within those set out in Section 17. As the MVDC link does not connect to the transmission system, it does not need to adhere to the Grid Code but rather the Distribution Code which serves a similar purpose. However, unlike the Grid Code, the Distribution Code does not enforce Fault Ride Through upon its connected assets. The MVDC link should retain fault ride through capability as indicated in ENTSO-E Establishing a Network Code on Requirements for Grid Connection of Generators (p22, Table 3.1) so that the MVDC Link is capable of supporting system disturbances at the distribution level. 20 PRE-INSATLLATION TESTING The supplier shall test the equipment prior to delivery and provide an outline of the commission test procedure and requirements. 21 EMC Where secondary equipment is located within the control and relay building, or within separate relay rooms or within outdoor enclosures, it shall be designed to ensure adequate protection against electromagnetic interference and shall comply with ENA TS 48-05. Page 12 of 13

At the time of commissioning, the MVDC converter equipment, circuit-breaker and disconnector normal switching operations shall be performed to demonstrate that EMC has in fact been achieved within the substation environment. In addition, the MVDC equipment itself will need to achieve EMC compliance against third party interference. The emission levels at the substation perimeters will also need to be estimated at the design stage and assessed and measured during the MVDC burn-in period. General emissions standard BS EN 61000-6-3: 2007 Radiated Immunity Radiated Emissions Conducted Immunity Conducted Emissions BS EN61000-4-3 10V/m Criteria A BS EN55011 Class A BS EN6100-4-6 10V/m Criteria A BS EN55011 Class A 22 SAFETY Potential suppliers must comply with BS EN 61010 and with their statutory obligations under Construction (Design and Management) Regulations 2007. Manufacturers should provide method statements and risk assessments to the Network Operator. The Network Operator will use these documents to facilitate the assessment of safe installation procedures for energised and non-energised installations. Page 13 of 13