Application Example Document ID: SA Rev. - September 24, 2004

Similar documents
System Protection Schemes in Power Network based on New Principles

Power System Stability. Course Notes PART-1

EH2741 Communication and Control in Electric Power Systems Lecture 2

Wide Area Monitoring with Phasor Measurement Data

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

Tor Rolv Time, Øystein Kirkeluten STATNETT Oslo, Norway

Power System Reliability and Transfer Capability Improvement by VSC- HVDC (HVDC Light )

ESB National Grid Transmission Planning Criteria

Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link.

Integration of Variable Renewable Energy

ABB Inc. April 1, 2016 Slide 1

Fuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1)

Real-time Monitoring of Power Oscillations and Modal Damping in the European ENTSO-E System

Use of the Power System Outlook (PSO) and SMART 1 Programs to View PSLF Dynamic Simulation Data Files

ELEMENTS OF FACTS CONTROLLERS

POWER SYSTEM OSCILLATIONS

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Fault Ride Through Principles. and. Grid Code Proposed Changes

Phasor-based wide area monitoring in the South African power system

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

Sarma (NDR) Nuthalapati, PhD

Adamantios Marinakis, Scientist, 12 th IEEE SB Power Engineering Symposium, Leuven, Enhancing Power System Operation with WAMS

Synchrophasor Technology PMU Use Case Examples

Control of Reactive Shunts- Voltage Stability and Restoration Mohammad Reza Safari Tirtashi

Wide-Area Monitoring and Control of Power Systems using Real-Time Hardware-in-the-Loop Simulations

POWER systems are being operated closer to the stability

SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011

Doãn Văn Đông, College of technology _ Danang University. 2. Local Techniques a. Passive Techniques

Coordinating Power Oscillation Damping Control using Wide Area Measurements

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers

Operationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0

Eigenvalue Analysis All Information on Power System Oscillation Behavior Rapidly Analyzed

ADVANCED VECTOR SHIFT ALGORITHM FOR ISLANDING DETECTION

Stability Improvement for Central China System

Measurement tools at heart of Smart Grid need calibration to ensure reliability

Arvind Pahade and Nitin Saxena Department of Electrical Engineering, Jabalpur Engineering College, Jabalpur, (MP), India

USING SUPERIMPOSED PRINCIPLES (DELTA) IN PROTECTION TECHNIQUES IN AN INCREASINGLY CHALLENGING POWER NETWORK

Low Frequency Local mode Oscillations in NER Grid, Validation using Model based analysis and Mitigation

Analysis of a 405 km transmission line with series compensation

LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

NVESTIGATIONS OF RECENT BLACK-

Islanding and Detection of Distributed Generation Islanding using Negative Sequence Component of Current

COMPARATIVE PERFORMANCE OF SMART WIRES SMARTVALVE WITH EHV SERIES CAPACITOR: IMPLICATIONS FOR SUB-SYNCHRONOUS RESONANCE (SSR)

Use of Synchronized Phasor Measurements for Model Validation in ERCOT

Testing model data usability Excitation Systems PSS Limiters

Fault Location Using Sparse Wide Area Measurements

The Baltic Ring Study Transmission System Simulations in the Baltic Sea Region

Zambezi (previously Caprivi) Link HVDC Interconnector: Review of Operational Performance in the First Five Years

A. df/dt Measurement principle by relays

C1-207 TRANSMISSION CAPACITY INCREASE BY RETURNING POWER SYSTEM STABILIZERS

Initial Application Form for Connection of Distributed Generation (>10kW)

Combination of Adaptive and Intelligent Load Shedding Techniques for Distribution Network

AORC Technical meeting 2014

Accurate Synchrophasor Estimation to Support the Islanding Maneuver of Active Distribution Networks

Experiences of Using Synchrophasors at Duke Energy

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

IJSER. Fig-1: Interconnection diagram in the vicinity of the RajWest power plant

Hydro-Québec s Defense Plan: Present and Future

Transmission System Phase Backup Protection

ELECTRICAL POWER ENGINEERING

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

Testing and Implementation of a Source Locating method at ISO New England

Frequency Analysis for Planned Islanding Operation in the Danish Distribution System Bornholm

ROSE - Real Time Analysis Tool for Enhanced Situational Awareness

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Transient stability improvement by using shunt FACT device (STATCOM) with Reference Voltage Compensation (RVC) control scheme

Application of Synchrophasors in Power Plants Incorporated with Condition Monitoring Systems K P C L

Hamdy Faramawy Senior Application Specialist ABB Sweden

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Simulation Programs for Load Shedding Studies: Expermintal Results

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Under-Frequency Load Shedding based on PMU Estimates of Frequency and ROCOF

Generation Interconnection Study Data Sheet Synchronous Machines

A Software Tool for Real-Time Prediction of Potential Transient Instabilities using Synchrophasors

Use of Synchrophasors to Detect Control System and Circuit Breaker Reclosing Issues

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC

THE ROLE OF SYNCHROPHASORS IN THE INTEGRATION OF DISTRIBUTED ENERGY RESOURCES

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Controlled Islanding Followed by Load Shedding Based on Rate of Frequency Decline

Oscillatory Stability: Extended Range & Enhanced Source Location

Relay Performance During Major System Disturbances

Generator Parameter Validation (GPV)

RECENT developments have seen lot of power system

Practical PMU Applications for Utilities

GRID CODE COMPATIBLE PROTECTION SCHEME FOR SMART GRIDS

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Performance of Relaying During Wide-area Stressed Conditions

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

1. An Introduction to Transient Stability

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

How to maximize reliability using an alternative distribution system for critical loads

Extensive LV cable network. Figure 1: Simplified SLD of the transformer and associated LV network

SDG&E Transmission Synchrophasor Project Update

Test Cases Library and Real-life Oscillation Examples

Power Quality enhancement of a distribution line with DSTATCOM

Voltage Sag and Swell Mitigation Using Dynamic Voltage Restore (DVR)

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

Authors and affiliations. Introduction. Approach

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES

Transcription:

Application Example Rev. - September 24, 2004 1 Summary Phasor based control of braking resistors A case study applied to large power oscillations experienced in the Swedish grid 1997 Phasor measurement, i.e. AC voltages and currents represented as magnitude and phase angle from all over any power system, is now a reality. Based on GPS (Global Positioning System) time synchronization, phase angles at different geographical locations can be directly measured and compared. So far power oscillations in electric power grids have been detected only at their point of appearance, and damping control criteria have been based solely on local input quantities. PMUs (Phasor Measurement Units), located at strategic nodes in the power system, provide all necessary data for damping algorithms. In the present paper a disturbance in Sweden, January 1, 1997, when two large nuclear units suddenly faced a large increase in transmission reactance, due to network split up, caused by clearance of a busbar fault, is studied. The generators started to oscillate with poor or negative damping, and after 6-8 seconds they tripped. The purpose of this Application Newsletter is to study the possibilities of the new phasor based technology applied to the disturbance from 1997. Initially the pre-disturbance load flow is re-created in the simulation tool ARISTO [1], then the disturbance and fault clearance scenario is added, and finally different phasor based control algorithms for braking resistors, to counteract the oscillations, are tested, and compared. The results show that the dynamic angle difference between the voltage vector of the center of the power system and an oscillating generator is a very suitable criteria for damping control. The disconnection of the two units (about 900 MW each) could probably be avoided with PMU-based on/off control of a 50 MW braking resistor. The braking resistor was in the study energized 6 times for a total time of 8 s. 2 Background The aim of the present study is to investigate the benefit of power system voltage phase angle as input to a damping control algorithm. For this purpose a real, experienced disturbance is simulated and different control strategies are applied. 2.1 Synchronized Measurement Technology Development The recent development in measurement technology and time synchronization accuracy has dramatically changed the possibilities for monitoring, control and protection of electric power systems. Development of PMUs and WAMS (Wide Area Measurement Systems) has been going on for some ten years now and quite reliable systems are in operation today. This technology is mostly applied in western US and Canada and in Mexico, but smaller systems are emerging all over the world today. So far phasor measurements have been used for monitoring and post fault analysis only. The PMU data were extremely useful, and speeded up the analysis and restoration process considerably, after the disturbances in western US in 1996 [2]. Nowadays discussions have started not to just store enormous amounts of data for post-fault activities, but also take the step to use these unique high quality phasor data for on-line control and protection. Therefore the ABB PMU RES 521 is based on protection technology and quality, i.e. all hardware and software components fulfill extremely high requirements on reliability and accuracy. This design makes RES 521 suitable not only for monitoring, but also for wide area control and protection. 2.2 Description of the Disturbance The disturbance occurred late in the evening in the southwest of Sweden, when load was dropping and hydro power plants were about to be disconnected. The spinning reserve was large and the power system was well prepared to survive a major loss of generation. The Nordel network is shown in Figure 1. The totally installed Page 1 (9)

capacity in the system is about 90 GW. At the moment of the disturbance the power flow, around 1800 MW, was from south to north along the Swedish west coast. Figure 1: The Nordel main grid, with the location for the disturbance marked. In a major substation, close to Ringhals nuclear power station, water from a cooling equipment dripped to the ground and formed a growing icicle. The icicle finally caused a flashover to one phase and caused an earth-fault. The fault was located between the CT and the circuit-breaker, according to Figure 2, and was correctly cleared by the busbar protection, and later also by the transformer under-impedance protection. Page 2 (9)

Kilanda T1 Bus Protection (sectionalized) B Objects connected to bus B A Trip of objects connected to bus A CT inputs T2 Strömma Timmersdala Underimpedance protection G Runvik 97-01-17 Figure 2: Busbar fault in Stenkullen substation 1997-01-01. A number of 400 kv transmission lines were lost as a consequence of the clearance of the busbar fault. Reduction of transmission capacity on the main grid moved the power flow to the underlying sub-transmission grid, and one line was tripped due to overload. The sudden change in 400 kv network topology, when the fault was cleared, caused two units in Ringhals to suddenly be very weakly connected to the rest of the system. Before the disturbance Ringhals 1&2 were connected to the main grid via substations Strömma and Stenkullen, see Figure 3. After the fault clearance the two units were connected to the main grid via substations Strömma, Breared, Söderåsen and Horred a substantial increase in impedance! Page 3 (9)

Kilanda Stenkullen Timmersdala Kontiskan 1 Kontiskan 2 +350 MW 400 kv Fault Strömma Ringhals 1 Ringhals 2 Horred Ringhals 3 Ringhals 4 Lahall Breared Söderåsen Baltic Cable +370 MW Själland +1270 MW Barsebäck G Runvik 97 01 17 Figure 3: Topology change of transmission grid due to fault clearance. The generation was about 900 MW per unit, and heavy oscillations were observed in the power system, sees Figure 4. The two units in Ringhals were tripped after 6.5 and 8.5 seconds, and the oscillations were damped. Loosing 1800 MW is more severe than the dimensioning loss of production. Due to the late evening, load dropping and a large spinning reserve, no load shedding was activated. The frequency dropped to 49.4 Hz, which initiated automatic start up of gas turbines. Page 4 (9)

Line Trip RHS 1 RHS 2 Line Trip RHS 1 RHS 2 Voltage [kv] Time [s] Reactive Power [Mvar] Frequency [Hz] Active Power [MW] Time [s] Line Trip RHS 1 RHS 2 Line Trip RHS 1 RHS 2 Time [s] Time [s] Figure 4: Oscillations in the power system due to topology change and generator trip (Sydkraft Recordings). Upper left:400 kv active power Barsebäck-Söderåsen. Upper right:400 kv voltage at Söderåsen substation. Lower left:400 kv reactive power Barsebäck-Söderåsen. Lower right:400 kv frequency at Söderåsen substation. 3 Power System Model Setup and Simulations The power system model used for this study includes the entire synchronized Nordel network, according to Figure 1. The model is quite detailed in the neighborhood of the disturbance, i.e. southwestern part of Sweden, while equivalents are used for more peripheral parts of the grid. The real-time simulator ARISTO [1] was used for the study, which was carried out in three steps: 1) set up the pre-disturbance load flow; 2) apply the disturbance and the fault clearance scenario, and 3) add damping actions to ensure that the Ringhals units stay synchronized. The aim of the two first steps is to calibrate the model and the fault clearance scenario to recordings from the event. Most large generators are equipped with PSS (Power System Stabilizers), which act on the generator voltage control in such a way that the voltage set-point is altered a little with respect to power oscillations. Locally measured generator output power or frequency is usually used as input signal to the PSS. The PSS is very efficient to handle small signal oscillations, but since the PSS acts on the voltage controller, its capacity to handle larger oscillations is limited. 3.1 Comparison with Recordings The simulation model was tuned by comparing ARISTO simulations of the disturbance scenario with recordings from the disturbance. Figure 5 shows the corresponding simulation results to the recordings in Figure 4. Page 5 (9)

Figure 5: Simulation results corresponding to Figure 4. Upper left: Upper right: Lower left: Lower right: 400 kv active power Barsebäck-Söderåsen. 400 kv reactive power Barsebäck-Söderåsen. 400 kv voltage at Söderåsen substation. 400 kv frequency at Söderåsen substation. 3.2 Simulation of Scenarios without Generator Tripping When the simulation model matched the recordings, actions aimed at keeping the two generators synchronized to the system could be studied. The well known KM-model for electromechanical oscillations was used to find the eigenfrequencies of the system [3]. It is also possible to use the eigenvectors in real-time, to find out how active each mode is. In a real power system the frequency, at each generator node participating in the oscillation, is compared to the system average frequency. The average frequency can be derived as the arithmetic mean value in a number of strategic nodes, weighted with respect to the inertia, controlling that frequency. Figure 6 shows the oscillations for the two units, if they were not tripped, and no damping actions were imposed. Each unit comprises two generators. In Figure 6, only the active power from one generator of each block is shown. Page 6 (9)

Figure 6: Simulation results for active power output, without tripping and without damping. Left: Both units kept synchronized. Right: One unit tripped. 4 PMU controlled Braking Resistors The main idea of this study is to find methods to damp the power oscillation and prevent the unit protection from disconnecting the generators from the grid. A simple controller according to Figure 7 and a 50 MW braking resistor for each generator seem to be sufficient. The input signal to the controller is the difference between the local frequency and the weighted average frequency of the power system. The output signal comprises square-waves of different duration, which connect the braking resistor, see Figure 8. Figure 7: Controller, based on frequency difference input, for the 50 MW braking resistor. To damp the power oscillations the braking resistor has to be switched in eight times for a total duration of about 8 seconds. For the two generators the braking energy corresponds to about 800 MWs. To be able to damp also the remaining minor oscillations, remaining after about 20-25 seconds, when the damping resistor is not used any more, smaller damping resistors have to be added, or, if small enough, the oscillations can be taken care of by the PSS on the AVR. Page 7 (9)

Figure 8: Controller output and input signals. Finally the simulation result for the generator active power output is shown in Figure 9, for the case when the controller and the braking resistor are activated. Figure 9: Generator active power output for the two units. Page 8 (9)

5 Conclusions This study shows that with a very simple controller and a modest braking resistor, even rather heavily undamped oscillations can be controlled and damped. In this case the control signal was based on the frequency at the center of the power system, or a weighted average, and the local frequency. 6 References [1] The training simulator ARISTO-design and experiences; Walve, K.; Edstrom, A.; Power Engineering Society 1999 Winter Meeting, IEEE, Volume: 1, 31 Jan.-4 Feb. 1999. [2] Recording and analyzing the July 2 cascading outage [Western USA power system]; Taylor, C.W.; Erickson, D.C.; Computer Applications in Power, IEEE, Volume: 10 Issue: 1, Jan. 1997 Page(s): 26 30. [3] Damping of electro-mechanical oscillations in a multimachine system by direct load control; Samuelsson, O.; Eliasson, B.; Power Systems, IEEE Transactions on, Volume: 12 Issue: 4, Nov. 1997 Page(s): 1604 1609. For more information please contact: ABB Power Technologies AB Substation Automation Products 721 59 Västerås, Sweden Phone: +46 21 342000, Fax: +46 21 324223 www.abb.com/substationautomation