Single Hung Tilt and Double Hung Tilt Window Installation Instructions
|
|
- Emil Gibbs
- 5 years ago
- Views:
Transcription
1 Single Hung Tilt and Double Hung Tilt Window Installation Instructions IMPORTANT: Please read before you begin installation.
2 Table of Contents & Tool Material Requirements START PAGE Collections Single and Double Hung General Information iii Safety Alert Symbol; A Special Note About Masonry iv Unit Preparation Before Installation v Wood Sealer or Finishing Supplies, Installation Clips (#6 x 1/2" Phillips Pan Head Screws, and Power Screwdriver With Phillips Head Bits) Rough Opening Preparation Weather Barrier Self-Adhering Tape, Utility Knife, Measuring Tape, Rubber Roller, Clear Silicone Sealant, Caulking Gun, Cloth Tape, Staples, Staple Gun Window Installation Measuring Tape, Hammer, Galvanized Casing Nails (long enough to penetrate framing material at least 1-1/2"), Electric Drill w/screwdriver & Drill Bits, Pry, Bar, Shims, Straightedge, Level Window Installation Using Installation Clips Measuring Tape, Hammer, #6 x 1/2" Phillips Pan Head Screws, Stainless Steel Screws (long enough to penetrate framing material by at least 1-1/2" or roofing nails long enough to penetrate framing material by at least 1-1/2"), Electric Drill w/screwdriver & Drill Bits, Pry, Bar, Shims, Level Drip Cap Installation Measuring Tape, Hammer, Roofing Nails (long enough to penetrate framing material at least 1-1/2") Drip Cap (long enough for each window unit), Tin Snips, Silicone Sealant, Hacksaw, Caulking Gun, Utility Knife Finishing Touches Putty Knife, Fiberglass Insulation, Interior Trim, Exterior Grade Color Matched Wood Filler Window Lock and Unlock & Sash Operation Sash Removal Sash Reinstall Screen Removal Retractable Screen Collections Recommended Finishing Instructions Collections Care and Maintenance Products With Synthetic Stucco Back Cover ii
3 Collections Single & Double Hung General Information IMPORTANT: Thoroughly read and follow these instructions. Failure to install as recommended will void any warranty, expressed or implied. Before installation check building codes for the area in which the windows are being installed to ensure proper compliance. The installation instructions that follow are based on typical frame construction. Specific applications may differ. The window manufacturer recommends that you consult a qualified installation professional. The window manufacturer is not responsible for installation. IMPORTANT: A number of jurisdictions have adopted building code design pressure (DP) requirements that require window and door products be installed in the same way they were installed for laboratory testing. To comply with these requirements, see Part No Standardized Window Installation Instructions For Maintaining Design Pressure Ratings. FOR ALL NON-DP INSTALLATIONS: Sealant must be applied in all installations. There must be continuous contact with a generous bead of sealant between the window unit s exterior casing and the face of the wall around the window s entire perimeter. The following additional steps must be taken as appropriate. A generous, continuous bead of silicone sealant must be applied to the exterior face of the rough opening before installing the window unit. The exterior casing must contact the sealant continuously along the head and both sides of the unit. Do not caulk the sill area of the rough opening. The exterior casing must fully contact the exterior face of the wall around the window s entire perimeter. A shim space is required around all sides of the window to allow for structure movement, seasonal expansion and contraction, and to provide space for insulation. The shim space cannot exceed: For wood exterior casing windows 1/2" on all sides (1" total for either width or height). Accessories, such as jamb extension, may alter unit width and height. Check rough opening size vs. unit size accordingly. If a shim space greater than listed above exists on the interior or exterior of the unit, use solid continuous furring material to fill this space until the maximum 1/2" shim allowance is achieved. Furring material must be solid, continuous, and run the full height and/or width of the rough opening. Furring strip depth must be at least equal to window jamb depth. Furring material must be securely fastened to rough opening framing. ADDITIONAL NOTES FOR ALL INSTALLATIONS: For any installation that has exposed fasteners, it is recommended to use fasteners made of 300 series stainless steel. Follow your local codes if they specify a different series of stainless steel. Certain options, accessories, and warranty considerations require the unit be installed using installation clips. Instructions for their use start on Page 8. Weather Shield Mfg., Inc. reserves the right, as necessary, to change product specifications, installation procedures, materials, prices and terms of purchase without notice. iii
4 Recognize this symbol. This is the Safety-Alert symbol. When you see this symbol be alert to the potential for personal injury or product damage. Falling from window opening may result in serious injury or death. DO NOT leave openings unattended when children are present. Weight of window and accessories will vary. Use a reasonable number of people with sufficient strength to lift, carry and install window unit(s) and accessories. Always consider site conditions and use appropriate techniques when installing. CUT HAZARD *Non-safety Glass. *May cause serious injuries if broken. *Do not install where tempered safety glass is required. Screen will not stop children, any one or anything from falling out window. Keep children and objects away from open window. Improper use of hand and power tools could result in personal injury and/or product damage. Follow equipment manufacturers instructions for safe operation. Always wear safety glasses. A Special Note About Masonry SPACE FOR SEALANT MIN. 3/8" MAX. 1/2" WEATHER BARRIER TAPE SPACE FOR SEALANT MIN. 3/8" MAX. 1/2" WEATHER BARRIER TAPE The perimeter joint between window exterior and the exterior building material must conform to siding manufacturers recommendations. All masonry, stucco, or synthetic stucco systems require an expansion joint around the window perimeter that must be filled with sealant compatible with the building material and window components. Expansion joint space should be no less than 3/8" and not greater than 1/2" unless stated otherwise by your siding manufacturer. If there is a conflict, follow siding manufacturer s guidelines. Failure of this joint will cause structural damage unrelated to window performance. iv
5 Unit Preparation Before Installation FIGURE 1 FIGURE 2 SEAL BEFORE INSTALLATION SEAL BEFORE INSTALLATION Collections is a premium all wood window designed for years of enjoyment. Additional years of service can be obtained by ensuring that all wood surfaces that will become inaccessible after installation are sealed against moisture before the unit is installed. The following should be sealed before installation (FIGURES 1 & 2): Top of Head Jamb Bottom of Sill Outside Surfaces of Side Jambs Sides and Top of Exterior Casing After installation, all exposed raw wood surfaces must be sealed. See the Collections Recommended Finishing Instructions starting on Page 23. Normal installation calls for fastening through the exterior casing into the rough opening framing. An alternative method is to use installation clips (FIGURES 3 & 4) to avoid fastening through exterior components. Clip installation procedures start on Page 8. IMPORTANT: If installation clips will be used, they must be attached to the window unit before starting installation. There is a 5 1 /2" long clip (Part No ) or an 11" long clip (Part No ) available. FIGURE 3 5-½" STANDARD Part # FIGURE 4 11" Part # v
6 IMPORTANT: When accessories have been ordered, check their directions BEFORE you install the unit OR prep the rough opening. Rough Opening Preparation FIGURE 1 FIGURE 2 W H FIGURE 3 FIGURE 4 ROUGH OPENING WIDTH JAMB WIDTH JAMB HEIGHT ROUGH OPENING HEIGHT Wear gloves, safety glasses, goggles or eye-shields as appropriate. Read installation instructions completely before beginning procedure. Wire brushed finishes are rough and may produce splinters and slivers while handling. Wear protective gloves. IMPORTANT: BEFORE starting installation. Ensure you have the correct window type (casement, tilt, etc.) Ensure you have the correct size window (Width and Height) for your rough opening (FIGURE 1). Check that your rough opening is 1/2" wider on all sides (1" total for either width or height). Accessories, such as jamb extension, may alter unit width and height. Check rough opening size vs. unit size accordingly. If using a sill pan, be sure rough opening size will accommodate both the window unit and the sill pan. Perform a complete unit inspection checking for shipping damage, broken glass, or other physical damage. Fix whatever is wrong before installation or start appropriate claim procedures. When accessories such as jamb extension have been ordered, apply according to the directions BEFORE you install the unit OR prep the rough opening. 1. Measure the rough opening to ensure it meets the guidelines listed above. Check the rough opening dimensions against the units actual Jamb Height and Jamb Width (FIGURES 1, 2, & 3). 2. Make sure walls are plumb and not twisted. Check rough opening for squareness by measuring diagonally from corner to corner in both directions. Diagonal measurements cannot differ from each other by more than 1/4" (FIGURE 4). IMPORTANT: Fix problems with plumb, level or squareness before proceeding. 1
7 Rough Opening Preparation (cont.) FIGURE 5 The following instructions are for structures with weather resistant barrier (WRB) applied before the windows are installed. 9" 45 CUT WEATHER RESISTANT BARRIER AS SHOWN BY SOLID LINES. 5 Improper use of hand and power tools could result in personal injury and/or product damage. Follow equipment manufacturers instructions for safe operation. Always wear safety glasses. 9" WEATHER RESISTANT BARRIER INSTALLED OVER SHEATHING AND FRAMING DASHED LINES SHOW ROUGH OPENING. DO NOT CUT HERE. 3. Cut weather resistant barrier (WRB) in sequence as shown by the circled numerals in (FIGURE 5). 4. Fold sill and side jamb WRB into the rough opening (FIGURE 6). Lift head WRB up and tape to face of wall (FIGURE 6). 5. Secure WRB to interior framing with staples placed every 12" to 16" apart (FIGURE 7). FIGURE 6 FIGURE 7 VIEWED FROM INTERIOR FOLD FLAP UP TAPE TO WRB FOLD WRB INTO ROUGH OPENING AFTER CUTTING FOLD WEATHER RESISTANT BARRIER TO INTERIOR AND STAPLE TO FRAMING. PLACE STAPLES EVERY 12" TO 16". 2
8 Rough Opening Preparation (cont.) FIGURE 8 9" 9" 1" MIN. 9" 8A 6. Cut a piece of weather barrier self-adhering tape 10" tall and as long as the opening width plus 18". Apply to face of exterior wall so 1" extends above the opening and 9" extends beyond each side of the opening (FIGURE 8). Cut along the corners of rough opening and fold down onto the sill (FIGURE 8A). Use a rubber roller to apply. 7. Apply a second continuous piece of weather barrier self-adhering tape on the top surface of the rough opening sill (FIGURE 9). 8. Cut the second piece of weather barrier tape the thickness of the wall plus 1". Make the tape 18" longer than the width of the opening. 9. Align flush with interior of the wall and extend edge of the tape 1" past the exterior wall surface (FIGURE 9). Start the piece 9" up the side of the rough opening and run it to the bottom of the opening, to the other side of the opening, and 9" up the other side (FIGURE 9). 10. Use a utility knife to cut the sill piece on both corners of the rough opening, and fold along the outside wall (FIGURE 9A). FIGURE 9 1" MIN. 9" 9A 3
9 Rough Opening Preparation (cont.) FIGURE 10 FLUSH WITH EDGE OF ROUGH OPENING 8-1/2" 9" 1" MIN. 11. After completing all instructions on Pages 1, 2, and 3, cut two side pieces of weather barrier self-adhering tape to length and width as shown (FIGURE 10). Length starts 8-1/2" above top of rough opening and extends 1" below sill wrap weather barrier. Make tape width 9". 12. Apply side weather barrier tape to the exterior of the wall with the tape s edge flush with the rough opening. Start 8-1/2" above the top of the rough opening and run tape down so that it goes over the sill wrap weather barrier tape. Use a rubber roller to apply. 13. Cut an 8-1/2" tall piece of weather barrier tape for the head that is as long as the rough opening plus 20" (FIGURE 11). 14. Apply the head piece to the sheathing. Start one end so it overlaps a side piece of weather barrier tape by 1". Work toward opposite side and overlap other side piece by 1". Keep bottom edge of the head weather barrier tape flush with the horizontal edge of the rough opening header (FIGURE 11). FIGURE /2" 1" MIN. FLUSH WITH TOP OF ROUGH OPENING 9" 4
10 Rough Opening Prep (cont.) FIGURE Check the rough opening sill for level (FIGURE 12). If sill plate is not level or straight place a 1-1/2" x 4-1/2" shim under the low side. Adjust shim until level is achieved. NOTE: If level isn t long enough to reach across entire sill use a straightedge with the level. IMPORTANT: To ensure that the sash operate smoothly, make sure that the sill is level and straight. 16. Measure the opening diagonally from corner-tocorner (FIGURE 13). The measurements should not differ more than 1/4". Fix problems before continuing. FIGURE 13 FIGURE 14 IMPORTANT: If you are going to install with installation clips, be sure clips are attached to unit (see Page 8) before applying sealant as called for in Step 17 below. If too much time passes between sealant application and window installation, sealant may start to cure preventing a good seal between window and wall. 17. Apply a continuous 3/8" bead of high-quality, exterior, neutral-cure, clear, silicone sealant (compatible with window and exterior face of the wall) to the exterior face of the wall, located 1/2" (FIGURE 14) from the rough opening edge. Caulk around the head and sides of the rough opening. Do not caulk the sill. When the window is installed the caulk bead must contact the exterior casing continuously so it seals the exterior casing against the face of the wall. Normal installation is to nail the unit in place through the exterior casing. See Pages 6 & 7. An alternate method is to use installation clips as described starting on Page 8. SILICONE SEALANT APPLIED ON WEATHER BARRIER SELF-ADHERING TAPE FOR BRICKMOULD UNITS Do not nail or screw through factory-applied finish. Breaking exterior finish coating voids warranty. (Does not apply to factory applied primer paint). Install with interior installation clips. See instructions starting on Page 8. 5
11 Window Installation FIGURE 1 Weight of window unit(s) and accessories will vary. Use a reasonable number of people with sufficient strength to lift, carry and install window unit(s) and accessories. Always consider site conditions and use appropriate techniques when installing. FIGURE 2 IMPORTANT: When accessories such as jamb extension are going to be installed, apply according to the directions BEFORE you install the unit OR prep the rough opening. Before you begin, make sure sash is closed and locked. Remove all shipping and packing material from the unit. 1. Immediately after applying caulk around rough opening, lift and center window in the opening from the exterior (FIGURE 1). 2. Check unit level and plumb from the interior or exterior across the side and head (FIGURES 2 & 3). 3. From the interior, shim as necessary to obtain level (FIGURE 4). IMPORTANT: If unit is mulled it must be supported with shims at the sill under each mull joint. FIGURE 3 FIGURE 4 6
12 Window Installation (cont.) FIGURE 5 FIGURE 6 FIGURE 7 4. Drill a pilot hole in the exterior casing at one top corner. Secure top corner with a rust-proof casing nail long enough to penetrate framing material by at least 1-1/2". Drive first nail far enough in so it bites into the framing but do not drive the nail all the way in just yet. 5. While holding unit in place, square and plumb jambs. Check both side-to-side and inside-to-outside. Measure unit from corner-to-corner to check for square (FIGURES 5 & 6). Measurements must be exactly the same. To plumb, level and square, use a pry bar to shift unit and shim from the interior as needed (FIGURE 7). 6. Check again for level, plumb and square. Use shims and a level to straighten the side and top jambs. When unit is straight, level, and true; drill pilot holes through head and side exterior casing and fasten through pilot holes with rust-proof casing nails long enough to penetrate the framing material by at least 1-1/2". Place nails every 8 to 10 inches on center along side and head exterior casing. Do not nail at the sill. 7. Continue to check level and square as unit is nailed in place. Make adjustments as you proceed. 8. When unit is nailed-in, set nail heads below the surface with a nail set (FIGURE 9). FIGURE 8 FIGURE 9 7
13 Window Installation Using Installation Clips FIGURE 1 FIGURE 2 Installation clips can be ordered in two lengths, 5-1/2" or 11", to accommodate varying wall depth. 1. Before installing unit in rough opening, install installation clips on head and side jambs using five (5) #6 x 1/2" Phillips pan head sheet metal screws (FIGURE 1) on each clip. Square end of clip faces the interior. Locate first clip 4" from corner and screw into jamb. Be sure clips are at right angles to the jambs and will be long enough to extend into the interior with enough clip left to secure to the framing. Locate additional clips 12" to 16" apart along side jambs and head jamb. Keep clips at least 4" from any corner. 2. Immediately after applying caulk around rough opening (see Page 5), lift and center window in the opening from the exterior. 3. Check unit level and plumb from the interior or exterior across the side and head (FIGURES 2 & 3). 4. From the interior, shim as necessary to obtain level (FIGURE 4). IMPORTANT: If unit is mulled it must be supported with shims at the sill under each mull joint. FIGURE 3 FIGURE 4 8
14 Window Installation Using Installation Clips (cont.) FIGURE 5 FIGURE 6 FIGURE 7 Ensure the unit is held firmly in place while performing the following steps. 5. Measure the entire window assembly diagonally in both directions (FIGURES 5 & 6). 6. Shim as necessary (FIGURE 7) to get the diagonal measurements of the entire window assembly exactly the same. 7. With the unit shimmed securely in place, add a shim near each installation clip (FIGURE 8). 8. Start at one corner and bend the installation clip against the rough opening framing and secure it to the framing with at least two (2) stainless steel screws or roofing nails long enough to penetrate framing material by at least 1-1/2". 9. Continue checking level, plumb and square as clips are bent and fastened. Make adjustments with shims to maintain all alignments. Continue around the window bending and fastening each installation clip until all clips are secured to the framing. FIGURE 8 4" SHIM INSTALLATION CLIP STAINLESS STEEL SCREW 9
15 Drip Cap Installation FIGURE 1 FIGURE 2 All installations require a drip cap. 1. Measure and cut a drip cap that is as long as the top exterior casing. 2. Apply a continuous 1/4" bead of high-quality, exterior, neutral-cure clear silicone sealant (compatible with wood aluminum and the exterior face of the wall) to the exterior face of the wall, located above the exterior casing such that the drip cap s vertical leg will seal against the caulk. Continue caulk bead along top surface of exterior casing. Caulk bead must be as long as the drip cap (FIGURE 1). 3. Place drip cap on top of exterior casing and center its length on the exterior casing. Push tightly down against exterior casing and embed the vertical leg into the bead of caulk. 4. Nail drip cap in place through vertical leg with galvanized roofing nails long enough to penetrate framing members by at least 1-1/2". Place nails every 12 to 16 inches along drip cap s length. 5. Fold down head flap of weather resistant barrier and trim it flush with the top of the drip cap (FIGURE 2). After trimming fold the flap back up and tape it out of the way. 6. Cut pieces of self-adhesive weather barrier tape to fit each corner of the drip cap and wall (FIGURE 3). Set aside for later installation. Continued on next page. FIGURE 3 10
16 Drip Cap Installation (cont.) FIGURE 4 7. Apply a generous bead of silicone sealant along the full length of the drip cap s vertical leg (FIGURE 4). 8. Untape and fold down the head flap of weather resistant barrier so its bottom edge is sealed by the caulk applied in Step 7 (FIGURE 5). 9. Apply self-adhesive weather barrier corner cover pieces created in Step 6, to each corner (FIGURE 6). Use a rubber roller to get a good seal between the corner cover and the face of the wall. FIGURE 5 FIGURE 6 11
17 Finishing Touches FIGURE 1 1. To finish the window installation, use fiberglass insulation and loosely insulate the gap between the window frame and rough opening (FIGURE 1). IMPORTANT: Do not over pack insulation. IMPORTANT: Do not use expandable foam. Installation is ready for interior wall finish and trim. 2. If unit is nailed in through the exterior casing, set nails below the surface with a nail set (FIGURE 2) and fill the nail holes with color-matched exterior grade wood filler. FIGURE 2 12
18 Window Lock and Unlock & Sash Operation FIGURE 1 SASH LOCK UNLOCKED ROTATE TO LOCK FIGURE 2 SASH LOCK LOCKED ROTATE TO UNLOCK FIGURE 3 Sash Lock and Unlock Bottom sash tilt latches are integral with the sash lock(s). If sash lock(s) are rotated beyond 1/4 turn toward the unlocked position, the sash may unlatch and inadvertently remain in the tilt in position. After unlocking sash gently push the meeting rail toward the exterior to ensure tilt latches are fully engaged before opening sash. NOTE: On a single hung units only the bottom sash operates. On a double hung units, both top and bottom sash operate and can be positioned independently. SINGLE HUNG TILT 1. To lock unit, lower bottom sash and rotate sash lock lever as far as it will go toward the window glass (FIGURE 1). The lock s cam must engage the keeper in the upper sash (FIGURE 2). 2. Unit is unlocked when sash lock lever is moved 1/4 rotation away from the glass (FIGURE 2). DOUBLE HUNG TILT 1. To lock unit, raise upper sash as far as it will go making sure it fully seats in the head jamb. 2. Completely lower bottom sash and move sash lock lever as far as it will go toward the glass (FIGURE 1). The lock s cam must engage the keeper in the upper sash (FIGURE 2). 3. Unit is unlocked when sash lock lever is moved as far as it will go away from the glass (FIGURE 2). Both single hung and double hung units have two sash locks as in (FIGURE 3). The locks are shown unlocked. FIGURE 4 Sash Operation To open or close sash, turn sash lock(s) to the unlocked position. Then grasp handles and raise or lower bottom sash as desired (FIGURE 4). Upper sash on a double hung unit can be opened and slid down independently of the top sash once the sash lock(s) are moved to the unlocked position. 13
19 Sash Removal If removing or tilting sash in and returning to closed position while standing on a ladder or step stool, be careful not to lose your balance. Sash can be heavy and caution should be used when removing. It is recommended that the sash be removed with adequate number of persons. Use care when working on ladders and scaffold, falls could occur. Follow all safety procedures recommended by ladder, scaffold and tool manufacturers. Use care when working around window openings, a fall could occur. FIGURE 1 FIGURE 2 ROTATE TO UNLATCH TILT SASH IN NOTE: SINGLE HUNT TILT Only the bottom sash is removable. DOUBLE HUNG TILT Both the bottom and top sash are removable Single and Double Hung Bottom Sash Removal 1. Unlock and raise bottom sash approximately 6". Rotate latch levers 1/4 turn toward center of window (FIGURE 1). NOTE: This 1/4 turn of the latch levers withdraws the tilt latches from each side jamb liner. 2. While holding latches in retracted position, tilt top of sash in toward you (FIGURE 2). Once meeting rail clears the side jambs, the tilt latches may be released. Sash now tilts in while remaining hinged at the bottom. 14
20 Sash Removal (cont.) FIGURE 3 FIGURE 4 3. To remove the bottom sash, tilt sash in so it is at right angles to the window frame (FIGURE 3). 4. Grasp the sash firmly on both sides and lift one side straight up to disengage the sash pivot pin (FIGURE 4). Lift the opposite side up and out of the side jamb. Top Sash Removal Double Hung Tilt 5. To tilt or remove top sash, the bottom sash must be first tilted in or removed. Lower the top sash to about 12" from the bottom of the unit. 6. Slide tilt latches, on top of sash, toward middle to retract the latches (FIGURE 5). 7. While holding tilt latches retracted, tilt sash in until the latches clear the side jambs (FIGURE 6). 8. To remove the top sash, tilt sash in so it is at right angles to the window frame (FIGURE 7). 9. Grasp the sash firmly on both sides and lift one side straight up to disengage the sash pivot pin (FIGURE 8). Lift the opposite side up and out of the side jamb. FIGURE 7 FIGURE 5 FIGURE 8 FIGURE 6 15
21 Sash Reinstall FIGURE 1 DOUBLE HUNG TILT EXTERIOR FIGURE 2 PIVOT PIN TOP SASH (outer track) TOP SASH BALANCE SHOE BOTTOM SASH (inner track) If pivot pins are placed below balance shoes the pivot pins will not be supported. Sash will have no counter balance and could fall rapidly possibly causing personal injury or property damage. When inserting sash in frame, pivot pins MUST BE ABOVE the balance shoes. NOTE: DOUBLE HUNG TILT Install top sash first. Top sash is placed into the outer track. Bottom sash is placed into the inner track (FIGURE 1). IMPORTANT: If your unit is a double hung tilt, the top sash must be completely installed in the side jamb s outer tracks before the bottom sash can be installed. IMPORTANT: When placing sash into side jambs, the sash pivot pins MUST BE ABOVE the balance shoes so the latching mechanism in the shoe will engage the pivot pins when the sash is lowered into the balance shoes. Double Hung Top Sash 1. Grasp the top sash so that the exterior surface is up and the bottom edge of the sash faces the window. Pivot pins are located at the bottom of the sash (FIGURE 1). 2. With one side of sash angled up (FIGURE 2), place pivot pin so it sits on the top of the balance shoe in the outer track of the jamb liner (FIGURE 1). Lower opposite side of the sash, so that its pivot pin is above opposite side balance shoe in the outer track. 3. Slide sash down until each pivot pin fully engages the balance shoe slots. Continued on next page. 16
22 Sash Re-Install (cont.) FIGURE 3 FIGURE 4 FIGURE 5 TOP SASH EXTERIOR FIGURE 6 INNER TRACK PIVOT PIN BOTTOM SASH To prevent damaging wood side jamb liners, hold tilt latches in retracted position as window is tilted up into side jambs. Keep latches retracted until sash is fully seated in the side jambs. 4. After pivot pins are fully engaged in balance shoes, tilt or push the top of the sash up and away from you (FIGURE 3). Hold the tilt latches retracted until the latches can be released into BOTH side jambs (FIGURE 4). Tug gently inward on sash to check tilt latch engagement. Be sure tilt latches on BOTH sides are fully seated to keep window from unintentionally falling inward. 5. Fully raise top sash to make working room for bottom sash installation. Install Bottom Sash Double Hung Tilt 1. Grasp the bottom sash so that the exterior surface is up and the bottom edge of the sash faces the window. Pivot pins are located at the bottom of the sash (FIGURE 5). 2. With one side of sash angled up (FIGURE 6), place pivot pin so it sits on the top of the balance shoe in the inner track of the jamb liner. Lower opposite side of the sash, so that its pivot pin is above the opposite side balance shoe in the inner track. 3. Slide sash down until each pivot pin fully engages the balance shoe slots. 17
23 Sash Re-Install (cont.) FIGURE 7 ROTATE TO RETRACT TILT LATCHES TILT SASH OUT Install Bottom Sash Double Hung Tilt (cont.) To prevent damaging wood side jamb liners, hold tilt latches in retracted position as window is tilted up into side jambs. Keep latches retracted until sash is fully seated in the side jambs. 4. After pivot pins are fully engaged in balance shoes, tilt or push the top of the sash up and away from you (FIGURE 7). Hold the tilt latches retracted until the latches can be released into BOTH side jambs (FIGURE 8). Tug gently inward on sash to check tilt latch engagement. Be sure tilt latches on BOTH sides are fully seated to keep window from unintentionally falling inward. FIGURE 8 18
24 Screen Removal About Children: The consumer Product Safety Commission, in its pamphlet Protect your Child, advises: Keep children away from open windows to prevent falls. Don t depend on screens to keep the child from falling out the window. They are designed to keep insects out, not children in. Avoid placing furniture near windows to keep children from climbing to a window seat and sill. Prevent injury or death from falling screen. Maintain secure grip on screen until it is safely back inside the structure. FIGURE 1 SINGLE HUNG Screen will not stop children, any one or anything from falling out window. Keep children and objects away from open window. There are three screen types available on the Collections tilt window. The single hung unit has a half screen covering the bottom sash (FIGURE 1). The double hung has a full screen covering both sash (FIGURE 2). A retractable screen, mounted to the interior, is optional. Half Screen Removal Single Hung 1. Remove bottom sash. See previous instructions. 2. Pull down on screen plungers in top of screen frame (FIGURE 3) and pull top of screen in slightly. 3. Pull side screen plungers away from side jamb and rotate screen out of its frame in the window (FIGURE 4). Bring screen inside. FIGURE 3 FIGURE 2 DOUBLE HUNG FIGURE 4 19
25 Screen Removal (cont.) FIGURE 1 Full Screen Removal Double Hung 1. Remove both sash. See previous instructions. 2. Pull and hold the spring-loaded plungers (FIGURE 1), located on either side of the screen, towards the center of the window unit and then tilt the screen slightly away from the side jamb (FIGURE 1). 3. Pull down on screen plungers in top of screen frame and pull top of screen inward (FIGURE 2). 4. Rotate screen and bring inside (FIGURE 3). Screen Re-Install Reverse above steps to reinstall screen in either a a single or double hung unit with a standard screen. FIGURE 2 FIGURE 3 20
26 Retractable Screen FIGURE 1 The optional retractable screen is housed in a cassette at the top of the window (FIGURE 1). To lower the screen, grasp the built-in handle and pull it straight down to the sill (FIGURE 2). FIGURE 2 FIGURE 3 SCREEN LATCH LATCHED The screen must be fully extended or completely retracted. There are no intermediate latching points. The screen track, mounted on each side jamb, has a latch that will hold the screen fully extended at the sill (FIGURE 3). IMPORTANT: Whenever extending or retracting the screen keep a firm grip on the handle. Do not allow screen to fly up into the cassette. There is a recoil spring built into the screen cassette to help raise the screen and its pull must be controlled by hanging on to the handle when operating the screen. 21
27 Retractable Screen (cont.) FIGURE 4 SCREEN LATCH LATCHED 1. To latch the screen fully extended, bring screen completely down to the sill and push down on the screen handle. Visually check that the latches on each side have engaged the screen pull bar (FIGURE 4). NOTE: It may be necessary to push down on the screen pull bar at each corner to ensure the pull bar fully engages each screen latch. 2. To retract (raise) the screen, push gently toward the outside, on the handle to release the latches (FIGURES 5 & 6). Keep a grip on the screen handle and guide the screen upwards until it retracts into the cassette at the top of the window (FIGURE 7). FIGURE 5 PUSH OUTWARD AND UPWARD ON HANDLE TO RELEASE SCREEN LATCHES FIGURE 6 SCREEN LATCH UNLATCHED FIGURE 7 22
28 Collections Recommended Finishing Instructions Always follow chemical manufacturers safety instructions when using chemicals to avoid injury or illness. Do NOT clean any surface with gasoline, diesel fuel, solvent based, or petroleum based products. Do NOT use abrasive materials or strong acidic solutions against vinyl, wood, glass, or factory-applied finishes. Do NOT scrape or use tools that might damage the surface. Do NOT use mastic-type tapes such as Duct Tape. NOTE: If masking tape is used on any surface to aid in painting or staining, remove tape as soon as possible after use. Tape must be removed within 24 hours of application. For long term use, such as stucco applications; use tape that will release, even when exposed to high temperatures for an extended period of time. (Examples include 3M #2080 and #2090 tapes.) Before Starting Remove all hardware so finish can be applied more easily. IMPORTANT: With hardware removed, seal all raw wood in the hardware routs. For Bare Wood Surfaces For best results, wood should be sealed immediately upon installation or upon receipt, especially if unit is being stored for ANY length of time. 1. Remove all construction and adhesive label residue with mineral spirits before finishing. IMPORTANT: Do not sand special surfaces such as wire brushed finishes. Sanding will damage the characteristics of this type surface. Wire brushed finishes are rough and may produce splinters and slivers while handling. Wear protective gloves. A water-proof, ultra-violet resistant, clear penetrating finish is more appropriate for the fine woods used in creating the Collections windows. IMPORTANT: If staining will be done in conjunction with a clear finish, stain first! You will not be able to stain on top of a clear, penetrating sealer. Follow the stain and sealer manufacturer s instructions. -If a stained surface is desired: If no sealer is applied over stain, the wood will weather very rapidly and defects will occur. If applying varnish as a sealer, apply at least two (2) coats. If using a clear penetrating sealer, follow manufacturer s instructions. In all cases, test any stain and sealer combination in an inconspicuous spot, before applying the stain/sealer combination to the whole unit. 1. Use a high-quality oil or water based stain. A gel stain is easier to apply as it does not easily run or drip. The clear top coats may be oil or water-based. Apply at least two top coats of varnish or sealer. For a Varnish Finish 2. Apply one (1) coat of varnish to the stained surface and let dry. Use an exterior, UV inhibiting varnish as a sealer to provide extra protection against sunlight and moisture. Let varnish dry completely. 3. Before applying the next finish coat, make sure the previous coat is completely dry. Then lightly buff previous finish coat with #000 steel wool. Clean off all sanding dust and wipe surfaces with a tack cloth. 4. Apply next coat of desired finish to surface and let dry. Apply only one coat at a time. 5. For any additional coats of finish, repeat steps 3 and 4. If a clear, unstained finish is desired, either treat with a penetrating sealer or varnish as explained above, but eliminate the staining procedures. -If a painted surface is desired: 1. An unprimed wood unit requires priming. Use a high-quality oil or water based primer. Use compatible oil or water-based finish coats. Refer to the primer and paint manufacturers instructions. 2. When priming bare wood or repriming, cover all exposed wood surfaces. Priming all exposed surfaces helps prevent end splitting, warping and/or checking. 3. Once primed, apply two (2) coats of paint (on all exposed sides) to each item. 23
29 Collections Care and Maintenance Maintaining your Collections Casement Keep the glass clean with any household glass cleaning product. Keep the wood surfaces clean by using a soft brush or vacuum cleaner with a brush attachment. Keep the friction hinges clean by removing dirt and grime with a household cleaner and soft rag. Periodically apply a silicone lubricant to the top and bottom hinges. Do not use petroleum based lubricants as these will attract and hold dust and dirt. Depending on sealer applied, common household wood cleaning products can be used to clean the wood surfaces. Do not use these cleaning products if wood has been left unsealed as they may produce stains or blotches. HARDWARE MAINTENANCE IMPORTANT: Do not use any brass or bronze cleaning agents that contain petroleum distillates. The Stone River Bronze hardware is offered in two finishes, dark antique and natural nickel. To clean, wipe hardware with a soft cloth dampened with mild household cleaner. Do not use any abrasive products to clean Stone River Bronze hardware. Once soiled spots are removed, use a soft clean cloth to gently wipe surface completely dry. See instructions below for products and techniques to maintain this fine hardware. For Natural Nickel Finishes These finishes can be restored to their natural luster by periodically applying Flitz Metal Polish and then sealing with Stone River Bronze Clear Wax. Read and follow the complete instructions on the Flitz product label. In general, the metal polish is applied with a soft, clean, moist or dry cloth do not let polish dry on hardware. Use a soft, clean, dry cloth to buff hardware and polish before polish dries. After applying and buffing the Flitz Metal Polish, apply a coat of Stone River Bronze Clear Wax. Apply wax with a clean soft cloth. Let stand for 5 to 10 minutes then buff excess wax off surface with a clean soft cloth. For Dark Antique Finishes This finish can be restored to its original luster by periodically applying Stone River Bronze Rubbing Oil. Apply a small amount of bronze rubbing oil to a clean, soft cotton cloth until damp. Gently rub bronze surface with oil dampened cloth. Allow bronze surface to absorb rubbing oil before lightly buffing with a soft, clean dry cloth. MATERIAL SOURCES Flitz Metal Polish is available at hardware stores and home centers. It is made by: Prime Time Solutions, Inc. 23 Garfield St Torrington, CT Telephone: They also sell direct through their web site at: Stone River Bronze can be reached at: P.O. Box 3513 Logan, UT Telephone:
30 NOTES 25
31 NOTES 26
32 Weather Shield Products With Synthetic Stucco Serious concerns have been raised about excessive moisture problems in homes and other buildings that have Exterior Insulation Finish Systems, commonly referred to as EIFS or Synthetic Stucco. Many experts agree that a certain amount of water or moisture can be expected to enter almost any building exterior system. The building system should allow such water and moisture to escape or weep to the exterior, so no damage occurs. However, some EIFS systems may not allow water or moisture that penetrates the wall system to weep to the exterior. This can cause excessive moisture to accumulate within the wall system, which can cause serious damage to wall and other building components. It has been reported that so-called barrier EIFS systems are particularly prone to this problem. Moisture problems in any type of building structure can be reduced by proper design and construction with appropriate moisture control considerations, taking into account prevailing climate conditions. Examples of moisture control considerations include flashing and/or sealing of all building exterior penetration points, use of appropriate materials and construction techniques, adherence to applicable building codes, and general attention to proper design and workmanship of the entire building system, including allowances for management of moisture within the wall system. Determination of proper building design, components and construction, including moisture management, are the responsibility of the design architect, the contractors, and the manufacturer of the exterior wall finish products. Questions and concerns about moisture management issues should be taken up with these professionals. Weather Shield Mfg., Inc. is not responsible for problems or damages caused by deficiencies in building design, construction or maintenance, failure to install our products properly, or use of our products in systems that do not allow for proper management of moisture within the wall system. Part No /07 Printed in U.S.A Weather Shield Mfg., Inc.
HR175 Sash Replacement Kit Installation Instructions
HR175 Sash Replacement Kit Installation Instructions IMPORTANT: Please read before you begin. Weather Shield HR175 Sash Replacement Kits Important: Thoroughly read and follow these instructions, failure
More informationIMPORTANT: Please read completely before you begin.
Standardized Window Installation Instructions For Maintaining Design Pressure Ratings For Aluminum or Vinyl Clad & All-Vinyl Window Units With Nailing Fin Structure With Weather Resistant Barrier Applied
More informationIMPORTANT: Please read this supplement and your unit installation instructions before you begin.
Installation Supplement For All Window and Door Products Utilizing Interior Installation Clips This document must be used in conjunction with the installation instructions packed with your specific window
More informationWood Hinged Patio Door Installation Instructions
Wood Hinged Patio Door Installation Instructions #1029970 / 1029971 / 1182557 (12/05) Rev 4 IMPORTANT: Please read before you begin installation. Wood Hinged Patio Door Door Installation Instructions IMPORTANT:
More informationAluminum Clad Wood Window Field Mulling and Stacking Instructions
Aluminum Clad Wood Window Field Mulling and Stacking Instructions Mulling Stacking Mulling and Stacking IMPORTANT: Please read before you begin. TABLE OF CONTENTS AND TOOL / MATERIAL REQUIREMENTS START
More informationIMPORTANT: Please read before you begin installation.
ProShield Single-Slide & Double-Slide Window Installation Instructions [Includes Instructions to Maintain Design Pressure Test Ratings] Including Installation of Jamb Extension Option See Separate Instructions
More informationVinyl Hinged Door Installation Instructions Structure With Weather Resistant Barrier Applied Before Door Installation
Vinyl Hinged Door Installation Instructions Structure With Weather Resistant Barrier Applied Before Door Installation IMPORTANT: Please read before you begin. Part No. 1221586 Install 262 02/08 Printed
More informationTilt and Slider Replacement Window Installation Instructions
Tilt and Slider Replacement Window Installation Instructions Installer Please leave this booklet for the homeowner after the install is completed. IMPORTANT: Please read completely before you begin. Part
More informationAll Window Installation Instruction
1 All Window Installation Instruction Hurd Window Installation Instructions for Nail Fin & Wood Brick Mould Units Nail Fin Windows See Pages 2-11 Wood Brick Mould Windows See Pages 2-6, 8 & 12BM - 14BM
More informationIMPORTANT: Please read before you begin.
Visions ELS Single-Hung Tilt, Single-Hung Picture Center and Direct-Set Window Replacement Window Installation Instructions Including Installation of: Jamb Extensions (ordered separately) (For Non-Replacement
More informationCasement Replacement Window Installation Instructions
Installation Instructions Installer Please leave this booklet for the homeowner after the install is completed. CAUTION - IMPORTANT Lead-based paint may be present in older homes, and the removal of windows
More informationRead guide from beginning to end before starting installation. Read all warnings and cautions during unit installation.
Installation Guide for E-Series/Eagle High-Performance Mullion Windows with LVL Reinforcement and Installed Using Type B Clips Thank you for choosing Andersen. Instructions are for typical, new wood-framed
More informationFixed Upper Sash Replacement Guide for Andersen 400 Series Woodwright Springline Single-Hung Windows
Fixed Upper Sash Replacement Guide for Andersen 400 Series Woodwright Springline Single-Hung Windows Manufactured Between September 2005 and October 2006 Read all instructions carefully before attempting
More informationTools required by installer: Materials required by installer:
Installation Guidelines For Quaker Window Products Vinyl product line (Single Hung, Double Hung, Sliding Window, Fixed Window, Casement, Awning, and Hopper) Installer: Read these instructions completely
More informationInstaller Please leave this booklet for the homeowner after the install is completed. IMPORTANT: Please read before you begin.
Hinged Patio Door Standardized Installation Instructions Aluminum Clad, Vinyl Clad, Fiberglass Clad, and Units With Wood Exterior Casings Structure With Weather Resistant Barrier Applied Before Door Installation
More informationInstallation Instructions For Vinyl Sliding Patio Door & French Sliding Patio Door 1-Wide, 2-Wide and 4-Wide
Installation Instructions For Vinyl Sliding Patio Door & French Sliding Patio Door 1-Wide, 2-Wide and 4-Wide Includes Instructions For Door and Frame Reversal For 2-Wide Doors and Jamb Extension Option
More informationInstallation Guidelines. Next Dimension. Single Hung / Single Hung Fixed / Double Hung / Sliding Window / Fixed Window
Installation Guidelines Next Dimension Single Hung / Single Hung Fixed / Double Hung / Sliding Window / Fixed Window Windsor Windows & Doors Windsor Windows & Doors 900 S. 19 th St. 2210 Stafford St. Extn
More informationWINDOW REPLACEMENT INSTRUCTIONS FOR CASEMENT, DOUBLE-HUNG AND CLAD FRAME WINDOWS USING FRAME SCREWS
WINDOW REPLACEMENT INSTRUCTIONS FOR CASEMENT, DOUBLE-HUNG AND CLAD FRAME WINDOWS USING FRAME SCREWS These instructions were tested developed for replacing windows in wood-frame wall construction systems
More informationInstallation Guide. for E-Series/Eagle Clad Hinged Inswing French Door
Installation Guide for E-Series/Eagle Clad Hinged Inswing French Door Thank you for choosing Andersen. Instructions are for typical, new wood-framed wall construction with weather protection in place.
More informationEagle clad double-hung window installation instructions
Eagle clad double-hung window installation instructions These instructions are for typical installation in new typical wood frame wall construction. These instructions and methods are not intended for
More informationInstallation Guide for Andersen 400 Series Tilt-Wash Transom and 200 Series Narroline Transom Windows
for Andersen 400 Series Tilt-Wash Transom and 200 Series Narroline Transom Windows Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance
More informationNEW CONSTRUCTION PATIO DOOR INSTALLATION INSTRUCTIONS (WITH NAILING FLANGE)
NEW CONSTRUCTION PATIO DOOR INSTALLATION INSTRUCTIONS (WITH NAILING FLANGE) Slim Line & Classic French Style Patio Doors Materials included: (2) #10 x 2-1/2" Phillips Pan head keeper s (2) 3/8" Hole plugs
More informationIMPORTANT: Please read completely before you begin.
Standardized Installation Instructions For Windows With Exterior Casings or Nailing Fins For Wood Brickmould Units, PVC Casing Trim Units For Aluminum Clad, Fiberglass Clad, Vinyl Clad, and All-Vinyl Units
More informationInstallation Guidelines For ALUMINUM M-SERIES 3 PANEL SLIDING DOOR
www.quakerwindows.comv www.quakercommercialwindows.com PO Box 128 504 Highway 63 South Freeburg, MO 65035 800-347-0438 573-469-4151 (fax) Installation Guidelines For ALUMINUM M-SERIES 3 PANEL SLIDING DOOR
More informationSash Replacement Guide for Andersen 400 Series Tilt-Wash Transom Windows
for Andersen 400 Series Tilt-Wash Transom Windows Read all instructions carefully before attempting this procedure. If you have any questions about your ability to complete this procedure, call Andersen
More informationFOLDING DOOR - FOR FACTORY ASSEMBLED JAMBS WITH APPLIED SILL
FOLDING DOOR - FOR FACTORY ASSEMBLED JAMBS WITH APPLIED SILL READ SPECIFIC INSTALLATION INSTRUCTIONS COMPLETELY BEFORE STARTING ANY INSTALLATION Failure to install and maintain our product according to
More informationSun Windows General Information New Construction Sliding Door Installation Instructions H F
A G B D C H F H E H A. Apply Weather Resistive Barrier B. Apply Bottom Flashing Tape C. Install Sill Pan End Caps & Pan D. Caulk Sides & Top Nailing Surface, Set Door, Fasten E. Apply Side Flashing Tape
More informationInstallation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows americancraftsmanwindows.com Project Requirements: Read
More informationInstallation Guidelines For Quaker Window Products Aluminum flange fin sub sill & receptor system using a T mulled twin window unit.
Installation Guidelines For Quaker Window Products Aluminum flange fin sub sill & receptor system using a T mulled twin window unit. Installer: Read these instructions completely before starting any installation.
More informationSTACKING MULTI-SLIDE DOOR SYSTEM INSTALLATION INSTRUCTIONS
STACKING MULTI-SLIDE DOOR SYSTEM INSTALLATION INSTRUCTIONS 1290363 Revision 1 12/16 Page 1 Weather Shield Mfg., Inc. NOTICE CAUTION! Failure to install and maintain our product according to these instructions
More informationSun Windows General Information New Construction Hinged Door Installation Instructions
A G H F H H A. Apply Weather Resistive Barrier B. Apply Bottom Flashing Tape C. Install Sill Pan End Caps & Pan D. Caulk Sides & Top Nailing Surface, Set Door, Fasten E. Apply Side Flashing Tape F. Apply
More informationInstallation Guide for Architectural Wood Hinged Windows
Guide for Architectural Wood Hinged Windows Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance are essential if the benefits
More informationVinyl Windows and Doors
Vinyl Windows and Doors Part Number: V983571 2011 Pella Corporation INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION 350 SERIES WINDOW INTO EXISTING WOOD FRAME WINDOW Lea las instrucciones en español
More informationInstallation Guide for Andersen 400 Series Tilt-Wash Transom Windows with Stormwatch Protection (PG Upgrade) Manufactured After 2006
for Andersen 400 Series Tilt-Wash Transom Windows with Stormwatch Protection (PG Upgrade) Manufactured After 2006 Thank you for choosing Andersen. Instructions are for typical, new wood-framed wall construction
More informationINSTALLATION GUIDE WOOD PIVOTING CIRCLE/ OVAL
WOOD PIVOTING CIRCLE/ OVAL READ SPECIFIC INSTALLATION INSTRUCTIONS COMPLETELY BEFORE STARTING ANY INSTALLATION Failure to install and maintain our product according to these instructions will VOID any
More informationCAUTION - IMPORTANT. IMPORTANT: Please read before you begin installation.
IMPORTANT: Please read before you begin installation. CAUTION - IMPORTANT Lead-based paint may be present in older homes, and the removal of windows & doors may cause this paint to be disturbed. To decrease
More informationTHERMO-FIT REPLACEMENT WINDOW INSTALLATION INSTRUCTIONS (BRICKMOULD / NO NAILING FLANGE)
THERMO-FIT REPLACEMENT WINDOW INSTALLATION INSTRUCTIONS (BRICKMOULD / NO NAILING FLANGE) fig.3 Casement, Awning, Fixed Casement, Direct-Set, Double-Hung, Single-Hung & Horizontal Slider Windows Materials
More informationInstallation Guide. for Andersen 400 Series Tilt-Wash Picture Windows with Stormwatch Protection (High-Performance Impact Resistant Glass)
for Andersen 400 Series Tilt-Wash Picture Windows with Stormwatch Protection (High-Performance Impact Resistant Glass) Installation Guide Congratulations! You have just purchased one of the many fine Andersen
More informationInstallation Guide for E-Series/Eagle Clad Mechanically Fastened Windows
Guide for E-Series/Eagle Clad Mechanically Fastened Windows Thank you for choosing Andersen. Instructions are for typical, new wood-framed wall construction with weather protection in place. Instructions
More informationVinyl Windows and Doors
Vinyl Windows and Doors Manufactured by Pella Corporation WINDOW REPLACEMENT INSTRUCTIONS FOR SINGLE-HUNG AND SLIDING WINDOWS INTO EXISTING CASEMENT FRAME Part Number: V981203 2009 Pella Corporation USING
More informationINSTALLATION INSTRUCTION FOR WOOD DOUBLE-HUNG AND CASEMENT WINDOWS USING WOOD BRICKMOULD OR FLAT CASING
2009 Pella Corporation Part Number: 80DZ0101 INSTALLATION INSTRUCTION FOR WOOD DOUBLE-HUNG AND CASEMENT WINDOWS USING WOOD BRICKMOULD OR FLAT CASING Brickmould/Flat Casing Aluminum Head Flashing Corner
More informationWOOD OUT SWING AWNING, CASEMENT, & HOPPER WINDOW
WOOD OUT SWING AWNING, CASEMENT, & HOPPER WINDOW INSTALLATION GUIDE READ SPECIFIC INSTALLATION INSTRUCTIONS COMPLETELY BEFORE STARTING ANY INSTALLATION Failure to install and maintain our product according
More informationAluminum Clad Wood Window 1/2 Reinforced Field Mulling and Stacking Supplement
Aluminum Clad Wood Window 1/2 Reinforced Field Mulling and Stacking Supplement 1 Aluminum Clad Wood Window 1/2 Reinforced Field Mulling and Stacking Supplement The following instructions are a supplement
More informationINSTALLATION INSTRUCTIONS - INSTRUCCIONES DE INSTALACION FOR HURRICANESHIELD IMPACT-RESISTANT DOUBLE-HUNG, SINGLE-HUNG AND SIMULATED-HUNG
2008 Pella Corporation Part Number: 80ED0101 INSTALLATION INSTRUCTIONS - INSTRUCCIONES DE INSTALACION FOR HURRICANESHIELD IMPACT-RESISTANT DOUBLE-HUNG, SINGLE-HUNG AND SIMULATED-HUNG Instrucciones en español
More informationFlashing Materials. Rough Opening Preparation
Installation Instructions for CertainTeed New Construction Windows Handling vinyl windows CAUTION: Always store vinyl windows and doors in an upright position on a slight angle. Never lay them flat or
More informationINSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS
2012 Pella Corporation Part Number: 80WH0101 INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS Installation Instructions for Typical Wood Frame Construction.
More informationFold-A-Way Patio Door ASSEMBLY & INSTALLATION GUIDE
Fold-A-Way Patio Door ASSEMBLY & INSTALLATION GUIDE This instruction guide provides the minimum recommended procedures to correctly prepare the rough opening, install a fold-a-way patio door unit and apply
More informationInstallation Guide for Andersen Frenchwood Patio Door Sidelights and Transoms
for Andersen Frenchwood Patio Door Sidelights and Transoms Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance are essential if
More informationINSTALLATION INSTRUCTION INSTRUCCIONES DE INSTALACIÓN FOR CLAD HINGED PATIO DOOR PUERTA DE BISAGRA PARA PATIO
2008 Pella Corporation Part Number: 801V0101 INSTALLATION INSTRUCTION INSTRUCCIONES DE INSTALACIÓN FOR CLAD HINGED PATIO DOOR PUERTA DE BISAGRA PARA PATIO REMEMBER TO USE APPROPRIATE PERSONAL PROTECTIVE
More informationVinyl Windows and Doors
Vinyl Windows and Doors Manufactured by Pella Corporation Installation Instructions for Replacement of Aluminum Sliding Doors in Hard Coat Stucco Applications. Part Number: V981555 2009 Pella Corporation
More informationPanel Assembly and Installation
Assembly and Installation Assembly and Installation for Andersen 400 Series Frenchwood, 200 Series Narroline, 200 Series Perma-Shield Gliding Patio Doors and 400 Series Perma-Shield Gliding Patio Doors
More informationINSTALLATION INSTRUCTION FOR CLAD BOW WINDOWS WITHOUT HEAD AND SEAT BOARD
2008 Pella Corporation Part Number: 80KG0101 INSTALLATION INSTRUCTION FOR CLAD BOW WINDOWS WITHOUT HEAD AND SEAT BOARD Note: These instructions may be used for all Pella Bow windows that do not have a
More informationVinyl Windows Manufactured by VPI Quality Windows
Vinyl Windows Manufactured by VPI Quality Windows Part Number: 531&591 Installation 531 & 591 SERIES SLIDING AND HUNG WINDOW INSTALLATION INSTRUCTIONS Installation Instructions for Typical Construction.
More informationREMEMBER TO USE APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT.
Vinyl Windows and Doors Manufactured by Pella Corporation WINDOW REPLACEMENT INSTRUCTIONS FOR DOUBLE-HUNG VENT REPLACEMENT WINDOWS INTO EXISTING DOUBLE-HUNG FRAME USING FRAME SCREWS FROM THE EXTERIOR Part
More informationIntegrity Polygon and Round Top Installation and Finishing Instructions
Integrity Polygon and Round Top Installation and Finishing Instructions 08/20/2004 70852 BEFORE YOU BEGIN IMPORTANT: Read these instructions thoroughly before beginning to install your Integrity Polygon
More informationWeather Shield Telescoping Sliding Patio Door Installation Instructions
Weather Shield Telescoping Sliding Patio Door Installation Instructions The Telescoping Sliding Patio Door is shipped K.D. (Knocked Down) as shown above. IMPORTANT: Please read before you begin installation.
More informationINSTALLATION INSTRUCTIONS IMPERVIA SLIDING PATIO DOOR WITH FINS
2008 Pella Corporation Part Number: 803V0101 INSTALLATION INSTRUCTIONS IMPERVIA SLIDING PATIO DOOR WITH FINS Installation Instructions for Typical Wood Frame Construction. These instructions were developed
More informationINSTALLATION INSTRUCTIONS for Wood/Clad Wood Windows without Exterior Trim or Nailing Fin (JII025) ImpOrTaNT INFOrmaTION & GlOssary.
for Wood/Clad Wood Windows without Exterior Trim or Nailing Fin (JII025) Thank you for selecting JELD -WEN products. Attached are JELD-WEN s recommended installation instructions for metal clad wood windows
More informationInstallation Materials Required: Tools Required: 6" self-adhesive flashing. Shims. 3-foot level 6-foot level Tape measure 1/8" drill bit
installation instructions for CUSTOM WOOD & FIBERGLASS EXTERIOR FOLDING DOOR SYSTEMs (JII101) Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for
More informationINSTALLATION INSTRUCTION SINGLE PANEL, SINGLE PANEL WITH SIDELIGHT COMBINATION AND 20 MINUTE FIRE RATED WOOD FRAME ENTRY DOOR
2011 Pella Corporation Part Number: 818T0101 INSTALLATION INSTRUCTION SINGLE PANEL, SINGLE PANEL WITH SIDELIGHT COMBINATION AND 20 MINUTE FIRE RATED WOOD FRAME ENTRY DOOR Installation Instructions for
More informationINSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACIÓN FOR CLAD CASEMENT & AWNING WINDOW VENTANA DE DOS HOJAS CON REVESTIMIENTO
2008 Pella Corporation Part Number: 801P0101 INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACIÓN FOR CLAD CASEMENT & AWNING WINDOW VENTANA DE DOS HOJAS CON REVESTIMIENTO Corner Corner Top Fin Corner
More informationVinyl Windows and Doors Manufactured by Pella Corporation
Vinyl Windows and Doors Manufactured by Pella Corporation Part Number: V981255 2009 Pella Corporation INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACIÓN FOR BOW WINDOWS WITHOUT HEAD AND SEAT BOARD
More informationInstallation Guide for Andersen 200 Series Tilt-Wash Picture, Transom and Circle Top Windows
for Andersen 200 Series Tilt-Wash Picture, Transom and Circle Top Windows Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance
More informationINSTALLATION INSTRUCTIONS FOR REPLACEMENT FORGENT WOOD GLASTRA WINDOWS RECOMMENDATIONS FOR COMMON INSTALLATION OF ALL REPLACEMENT WINDOWS.
INSTALLATION INSTRUCTIONS FOR REPLACEMENT FORGENT WOOD GLASTRA WINDOWS RECOMMENDATIONS FOR COMMON INSTALLATION OF ALL REPLACEMENT WINDOWS. Installer: DO NOT DISCARD Please leave the Installation Guide
More informationMetal & Vinyl, Flush Mount and Recessed Fin Windows Recommended Installation Instructions
PO Box 480 Ph: 417-235-7821 Monett, MO 65708 Fax: 417-737-7140 Metal & Vinyl, Flush Mount and Recessed Fin Windows Recommended Installation Instructions These installation instructions are recommendations
More informationInstallation Guidelines for all Quaker products with nail fins New Construction nail fin installation with a Zip sheathing system.
www.quakerwindows.com www.quakercommercialwindows.com PO Box 128 504 Highway 63 South Freeburg, MO 65035 800-347-0438 573-469-4151 (fax) Installation Guidelines for all Quaker products with nail fins New
More informationNorwood Windows Permaglass Fiberglass Products Installation Instruction
Norwood Windows Permaglass Fiberglass Products Installation Instruction Care and storage of fiberglass windows: Fiberglass products purchased from Norwood Windows must be stored in a dry sheltered area
More informationINSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACIÓN FOR CLAD SLIDING PATIO DOOR PUERTA CORREDERA PARA PATIO
2008 Pella Corporation Part Number: 801W0103 INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACIÓN FOR CLAD SLIDING PATIO DOOR PUERTA CORREDERA PARA PATIO Corner Fin Corner Door Top Nailing Fin Side
More informationHow To Install Windows: Nail-Fin Application
How To Install Windows: Nail-Fin Application Required Tools & Materials: Materials: 1 3/4" galvanized roofing nails. Nails must penetrate at least 1" into framing For mulled and/or DP50 or above units:
More informationDOOR INSTALLATION GUIDE WOOD FRAMING New Construction
DOOR INSTALLATION GUIDE WOOD FRAMING New Construction IMPORTANT NOTICES AND INFORMATION Read these instructions in their entirety prior to installing doors. Any local building code requirements supersede
More informationINTERIOR. Checkrail. Flashing tape
Pella Corporation 2007 Part Number: 808F0100 INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION FOR PELLA PRECISION FIT DOUBLE-HUNG VENT WINDOW PARA LA VENTANA DE GUILLOTINA CON HOJA PRACTICABLE PRECISION
More informationInstallation Guide for E-Series/Eagle Ascent 2 or 4 Panel Gliding (Sliding) Patio Doors
Installation Guide for E-Series/Eagle Ascent 2 or 4 Panel Gliding (Sliding) Patio Doors Thank you for choosing Andersen. Instructions are for typical, new wood-framed wall construction with weather protection
More informationVINYL WINDOWS (new construction or replacement) page 2. VINYL PATIO DOORS pages WOOD CLAD WINDOWS (new construction).page 5 WOOD CLAD WINDOWS
RECOMMENDED INSTALLATION INSTRUCTIONS Please choose the appropriate instructions for the product(s) you are using. Read the instructions thoroughly before beginning the installation process. All instructions
More informationSliding Glass Door Assembly and Installation Guide
Sliding Glass Door Assembly and Installation Guide Index Door System Components and Hardware The following components are needed to complete the installation of your Sliding Patio Door unit. Check all
More informationSteel Reinforced Joining Thank you for choosing Andersen. Please leave this guide with building owner.
Steel Reinforced Joining (Horizontal/Vertical) for Andersen 400 Series Woodwright & Tilt-Wash Double-Hung, Picture, and Transom Windows and 400 Series Double-Hung Half Circle and Flexiframe Specialty Windows
More informationVinyl Windows and Doors Manufactured by VPI Quality Windows
Vinyl Windows and Doors Manufactured by VPI Quality Windows Part Number: 511_Installation ENDURANCE CASEMENT\AWNING\PW INSTALLATION INSTRUCTIONS Installation Instructions for Typical Construction These
More informationInstallation of Fiberglass Windows
Installation of Fiberglass Windows Before you begin please read and understand these installation instructions. The following installation instructions are recommended by Norwood and failure to follow
More informationInstallation Guide for Andersen 400 Series Gliding Windows
for Andersen 400 Series Gliding Windows Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance are essential if the benefits of your
More informationINSTALLATION INSTRUCTIONS FOR FORGENT SLIDING PATIO DOORS RECOMMENDATIONS FOR COMMON INSTALLATION OF SLIDING PATIO DOORS.
INSTALLATION INSTRUCTIONS FOR FORGENT SLIDING PATIO DOORS RECOMMENDATIONS FOR COMMON INSTALLATION OF SLIDING PATIO DOORS. Installer: DO NOT DISCARD Please leave the Installation Guide with the home owner
More informationInstallation Guide for Andersen Architectural Clad Awning Windows
Guide for Andersen Architectural Clad Awning Windows Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance are essential if the
More information8/7/ HP SWING DOOR INSTALLATION INSTRUCTIONS
8/7/17 1200 HP SWING DOOR INSTALLATION INSTRUCTIONS Installation Instructions for Typical Construction These instructions were developed and tested for use with typical construction in a wall system designed
More informationInstallation Guide for Andersen Architectural Clad Inswing Entry and Patio Doors
Installation Guide for Andersen Architectural Clad Inswing Entry and Patio Doors Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance
More informationKinro Metal, Vinyl, Flush Mount and Recessed Fin Windows OEM INSTALLATION MANUAL
Kinro Metal, Vinyl, Flush Mount and Recessed Fin Windows OEM INSTALLATION MANUAL TABLE OF CONTENTS Introduction 2 Safety Requirements 2 Fasteners 3 Preparation 3 Rough Opening Preparation 3 Resources Required
More informationInstallation Recommendations for Finless Frame Doors
Installation Recommendations for Finless Frame Doors These installation recommendations are made available by MI Windows and Doors, LLC (MI) to assist with the integration of finless or flange sliding
More informationPre-Hung Hinged Entrance Door Installation Instructions
Pre-Hung Hinged Entrance Door Installation Instructions Structure With Weather Resistant Barrier Applied Before Door Installation IMPORTANT: Please read before you begin installation. Table of Contents
More informationINSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION PELLA PRECISION FIT AND RENOVATION POCKET REPLACEMENT DOUBLE-HUNG VENT WINDOW
2011 Pella Corporation INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION PELLA PRECISION FIT AND RENOVATION POCKET REPLACEMENT DOUBLE-HUNG VENT WINDOW Part Number: 808F0105 Important! The Pella Replacement
More informationInstallation Guide for Andersen Architectural Clad Hinged Windows
Guide for Andersen Architectural Clad Hinged Windows Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance are essential if the
More informationPicture Window Rough Opening Installation with Sheathing Intact with Brickmould Tools: (Not supplied by manufacturer) Fig. 0-1
Picture Window Rough Opening Installation with Sheathing Intact with Brickmould Tools: (Not supplied by manufacturer) Tape Measure Drill Level Putty Knife Square Foam Gun Utility Knife Caulk Gun Hammer
More informationINSTALLATION INSTRUCTIONS for Wood Bay or Bow Windows with Nailing Fin or Exterior Trim (JII032)
for Wood Bay or Bow Windows with Nailing Fin or Exterior Trim (JII0) Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for wood and clad wood bay
More informationInStallatIon InStruCtIonS for vinyl 2-lIte PatIo door assembled
InStallatIon InStruCtIonS for vinyl -lite PatIo door assembled tools & materials you Will need: Measuring Tape Pencil Shims Square Hammer or Mallet Level Drill & Drill bits: 6", 8", 5 6", 7 6" Utility
More informationINSTALLATION INSTRUCTIONS - INSTRUCCIONES PARA LA INSTALACIÓN CLAD WINDOWS WITH FLUSH FLANGE
2012 Pella Corporation Part Number: 81CP0101 INSTALLATION INSTRUCTIONS - INSTRUCCIONES PARA LA INSTALACIÓN CLAD WINDOWS WITH FLUSH FLANGE Lea las instrucciones en español en el reverso Installation Instructions
More informationVISTALUXE CASEMENT, AWNING, & PICTURE WINDOW
VCSMT VISTALUXE CASEMENT, AWNING, & PICTURE WINDOW INSTALLATION INSTRUCTIONS READ THESE INSTRUCTIONS COMPLETELY BEFORE ATTEMPTING ANY INSTALLATION Kolbe & Kolbe Millwork, Co., Inc. 1323 S. 11th Ave. -
More informationAssembled Patio Door Installation Guide 2-Panel Patio Door with Non-Welded Frame
Assembled Patio Door Installation Guide 2-Panel Patio Door with Non-Welded Frame americancraftsmanwindows.com American Craftsman and all other marks where denoted are trademarks of Andersen Corporation
More informationSteel Reinforced Joining Guide (Horizontal / Vertical)
(Horizontal / Vertical) for Andersen Patio Door and/or Elliptical Top Window Combinations Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation
More information(773) INSTALLATION INSTRUCTIONS for Vinyl Windows with Integral Nailing Fin (JII001) IMPORTANT INFORMATION & GL OSSARY ROUGH OPENINGS
Thank you for selecting C l i m a t e G u a r d products. Attached are our recommended installation instructions for Vinyl windows with an integral (2400-02) will not affect application of the ClimateGuard
More informationSash may be heavy. Use a reasonable number of people with sufficient strength to lift, carry, remove and install. Tape broken glass with duct tape bef
Improper re-glazing product (s) can affect the performance under stress and may contribute to property damage or injury in high wind conditions. The installer should not proceed with re-glazing if these
More informationChapter 9. Windows and Exterior Doors
Chapter 9. Windows and Exterior Doors 9.1 INSTALLING WINDOWS 9.2 INSTALLING EXTERIOR HOUSE DOORS 9.3 INSTALLING SHED DOOR 9.4 INSTALLING EGRESS COMPONENTS Tools needed by volunteers: Hammer Nail apron
More informationwindow installation Guide wood FRaMinG New Construction
window installation Guide wood FRaMinG New Construction IMPORTANT NOTICES AND INFORMATION Read these instructions in their entirety prior to installing windows. Any local building code requirements supersede
More informationINSTALLATION INSTRUCTIONS for Vinyl Windows with Integral Nailing Fin (JII001)
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for Vinyl windows with an integral nailing fin. While the use of these installation instructions
More informationWINDOW REPLACEMENT INSTRUCTIONS FOR SINGLE-HUNG, DOUBLE-HUNG, CASEMENT, AWNING INTO EXISTING CASEMENT FRAME USING FRAME SCREWS
2009 Pella Corporation Part Number: 80YV0102 WINDOW REPLACEMENT INSTRUCTIONS FOR SINGLE-HUNG, DOUBLE-HUNG,, AWNING INTO EXISTING FRAME USING FRAME SCREWS These instructions were tested and developed for
More information