SNS CRYOMODULE PERFORMANCE*

Size: px
Start display at page:

Download "SNS CRYOMODULE PERFORMANCE*"

Transcription

1 SNS CRYOMODULE PERFORMANCE* J. Preble*, I. E. Campisi, E. Daly, G. K. Davis, J. R. Delayen, M. Drury, C. Grenoble, J. Hogan, L. King, P. Kneisel, J. Mammosser, T. Powers, M. Stirbet, H. Wang, T. Whitlatch, M. Wiseman. Thomas Jefferson National Accelerator Facility Newport News, Va, 2366, USA Abstract Thomas Jefferson National Accelerating Facility, Jefferson Lab, is producing 24 Superconducting Radio Frequency (SRF) cryomodules for the Spallation Neutron Source (SNS) cold linac. This includes one medium-β (.61) prototype, 11 medium-β production, and 12 high beta (.81) production cryomodules. After testing [1], the medium-β prototype cryomodule was shipped to Oak Ridge National Laboratory (ORNL) and acceptance check out has been completed. All production orders for cavities and cryomodule components are being received at this time and the medium-β cryomodule production run has started. Each of the medium-β cryomodules is scheduled to undergo complete operational performance testing at Jefferson Laboratory before shipment to ORNL. The performance results of cryomodules to date will be discussed. INTRODUCTION Jefferson Lab has started production of the 24 Superconducting Radio Frequency (SRF) cryomodules for the Spallation Neutron Source that is being built at ORNL. To date three cryomodules have been completed and two more are in various stages of completion. Production schedule includes completion and testing of one medium beta cryomodule approximately every three weeks. Testing plans for subassemblies and completed assemblies are in place to support this schedule. The testing program is intended to support design, acceptance, and operational characterization of the cryomodules. Critical cryomodule components are tested at subassembly levels prior to cryomodule integration. Testing of the completed cryomodules follows. Currently, three cryomodules have been completed. One of these has completed integrated testing in the Jefferson Lab Cryomodule Test Facility (CMTF), and the second is being tested. SUB-ASSEMBLIES The cost of, and time required for, disassembly and rework of a completed cryomodule is prohibitive and therefore critical sub-assemblies must be qualified prior to integration into higher-level assemblies. Additionally, lifetime testing is required for some components to ensure they will continue to be operational over the 4-year life required for SNS accelerator systems. Included in these two categories are the Fundamental Power Couplers (FPC), cavity frequency tuners for lifetime requirements, and the SRF cavities themselves. Fundamental Power Couplers SNS cavities use a coaxial coupler design for 48 kw average power and driven by a 55 kw klystron with 1.3 ms pulses at 6 Hz[2]. All FPC s are processed on one of two warm test stands [3]. Processing includes a 24- hour vacuum bake resulting in vacuum levels ~ 5 E- mbar followed by RF processing to 1 MW traveling wave and 2.4 MW standing wave power levels [4]. To date 21 FPC s have been processed to levels required for SNS operations with no difficulties Cavity Frequency Tuners The SNS tuner design has been adapted from a Saclay design for the TESLA cavities. For SNS application the requirements are listed in table 1. To achieve these requirements a piezo element has been incorporated into the dead leg and provides the required fine-tuning adjustment. The tuner assembly is shown in figure 1 with the drive train on the top left and the piezo element on the bottom right. Figure 1. SNS Cavity Tuner Assembly IEEE 457

2 Prototype tuners were fabricated and tested in the Vertical Test Area (VTA) where both prolonged test cycles and rapid turn around are possible. A complete tuner assembly was mounted to a mechanical spring representative of a cavity load at maximum tuning force. This assembly is place in an evacuated can to model the cryomodule insulating vacuum where the tuner operates. A linear position monitor was mounted on the tuner assembly and used to measure tuner travel during operation. Initial testing of the tuner included cycling over small ranges equivalent to 4 khz and 16 khz. Initially the tuner performed as expected but at the end of the first extended period of operation there was an increase in required torque from the motor to drive the tuner. This was thought to be a sign of wear on the lead screw. The tuner was then operated through its entire range of motion, equivalent to ~4 khz, and the required motor torque returned to its initial value. Subsequent testing has included a full stroke cycle after each 6 months of equivalent life and the problem has not returned. A total of 3 years of equivalent life has been accumulated. Mechanical Piezo Travel (mm) Freq. Range (khz) 2 2 Freq. Resolution (Hz) 6 NA Load (N) Table 1. SNS Tuner Requirements Cavities All cavities undergo a final assembly and testing at Jefferson Lab that includes warm tuning, installation into helium vessels, and qualification in the VTA prior to being assembled into a cavity string and then into a cryomodule. Warm tuning is performed at several stages of the assembly with a final check of the field flatness after the helium vessel installation process. The SNS requirement for cavity field flatness is <8%. A typical measurement is shown in figure 2 and the measurements to date are shown in figure E+2 MB-18 % Welded (Horizontal on Weld Cart) CW FREQ = MHZ PULL DIR. FPC To FP MARCH 28,23 % deviation Avg.=5.1% Stddev.=2.9% SNS Cavity Field Flatness MB1 MB2 MB3 MB4 MB5 MB6 MB7 MB8 MB9 MB MB11 MB12 MB13 MB14 MB15 MB16 MB17 MB18 HB1 Figure 3. Field Flatness Measurements to Date During VTA cold testing the cavities are qualified at 2 K. To date 16 cavities have been qualified which includes the measurement of cavity Q, figure 4, onset of field emission (FE) and the maximum E acc and is interpreted as???. Eacc limitations include cavity quench, field emission, and RF power limitations. Eacc Limit Q at MV/m FE Onset 15 MV/m MV/m Table 2. Average Values from VTA Testing For cavities that have passed qualification testing, average values for limiting E acc, Q at nominal operating gradient, and onset of field emission, as evidenced by the start of measurable radiation, are listed in table 2. VTA testing is also monitored for trends as a feedback into the production process and process charts are maintained. Process charts are shown in figure 5 and MBspec HBspec MB1F MB2B MB3A MB4F mb5 MB6 mb7a MB8 mb9a mb11 mb12 MB14 MB16B MB E E E E E Eacc Figure 4. Q vs E acc for SNS Medium Beta Cavities -1.79E E+2-1.8E+2.E+ 5.E+ 1.E+1 1.5E+1 2.E+1 2.5E+1 Figure 2. Typical Field Flatness Measurement 458

3 SNS Vetrical Test Results - Emax 2 15 UCL=16. Avg=12. LCL=8. 5 date Emax1 Figure 5. Cavity E acc Limit Process Chart SNS Vertical Test Results- Field Emission Onset 15 5 FEonset1 UCL=12.5 Avg=8.6 LCL=4.7 date Figure 6. Cavity FE Onset Process Chart Figure 7. Cryomodule Cooldown accomplished with the 1 MW RF source using 1.3 ms pulses at 6 Hz while maintain the coupler vacuum below -7 mbar. RF power is increased to kw on all cavities with a typical process shown if figure 8. After initial conditioning the FPC s demonstrate a memory of the conditioning and do not require reconditioning during turn on after days of non-operation although some minor exceptions have been observed. INTEGRATED CRYOMODULE PERFORMANCE During integrated cryomodule testing systems are in their final configuration and operated at 2 K using low power RF, a 2 kw CW RF source and 1 MW pulsed RF source. Testing of the first three or four cryomodules will include a larger set of tests to include design and operational characterization that will be eliminated on subsequent tests where acceptance testing is the goal. Additional tests will be required as issues of interest are identified throughout production. Cryogenics The SNS cryomodule incorporates a final counter-flow heat exchanger into the cryostat utilizing the subatmospheric return helium gas to cool the primary supply process stream before the J-T valve [5] and uses a bypass to circumvent this during cooldown. A typical cooldown is shown in figure 7. The cavities are cooled at a rate of ~2 K/Hr with the entire process taking ~8 hours from opening the J-T valve to the start of liquid collection. Heat loads for the primary and shield circuits, 12 ± 3 and 13 ± watts respectively, are measured several days after cooldown to ensure all components are in thermal equilibrium. Fundamental Power Coupler After cooldown of the cryomodule the FPC s for all cavities require RF conditioning. Conditioning is Figure 8. FPC Processing with Time in Hours Cavity Frequency Tuner Eight tuners have been tested after integration into cryomodule including three in the medium-β prototype and five in the first production cryomodule. During the testing of the prototype cryomodule the tuners performed as expected with the mechanical and piezo tuners providing in excess of 4 khz and 3 khz tuning range respectively. The mechanical tuner performance over an abbreviated range and the piezo tuner resolution measurement are shown in Figures 9 and. The piezo tuner was not part of the initial design and was included to allow for compensation for Lorentz force detuning during pulsed operations. 459

4 Change in Frequency (Hz) Cavity Position #2: Hysteresis Loop with 5 step increments (2 microsteps/step) Increasing Frequency Decreasing Frequency # Microsteps Figure 9. Mechanical Tuner After initial fabrication and test of the prototype tuners a production run for the medium and high beta cryomodules followed. Identical components were procured and integrated into the production cryomodules without subassembly testing. During the testing of M1, the first medium-β production cryomodule, all tuners worked after cooldown but two mechanical tuners, position #1 and #2, started to operate position #2 and #3 operated intermittently. Cavity position #1 has operated continuously since replacement. Investigation into the source of the tuner problems is underway. The suspect components are in the drive assembly and include the cold stepper motor, harmonic drive, lead screw, and lead screw nut. We are presently working with the designers and vendors to identify failure modes and solutions. Cavity Performance During testing in the CMTF cavity performance is characterized including Q and FE as a function of E acc, maximum E acc, Q ext of FPC s, HOM damping, HOM probe rejection of fundamental power, and identification of cavity mechanical modes using Lorentz force and the piezo tuner as drivers. The cavities have all performed above specification for Q, Figure 11, and maximum E acc. Maximum gradient for all cavities has been in the range of 15-2 MV/m with the onset of FE above MV/m for ½ of the cavities and no measurable radiation for the other ½ of the cavities at maximum gradient. 11 MBspec HBspec MB1F CM Cavity 2 MB2B CM Cavity 1 MB6 CM Cavity 3 Piezo Tuner Minimum Resolution Test, Cavity MHz,.3Vpp PZT Drive M:\asd\asddata\CMTF\M1\Cav 1 Piezo Tuner\Results\Cav 1 PZT resolution.xls.6 Cavity Delta Freq (Hz).4.2 Figure. Piezo Tuner Resolution, ~ 1Hz intermittently after a period of several days with no operation. The third tuner, position #3, continued to perform as expected. The two problematic tuner drive assemblies were removed and replaced with assemblies that had been qualified in the VTA using the life cycle test fixture. Qualification included operations over the full range of motion as well as periods of cold soaking to approximate conditions observed in the M1 cryomodule. After a second cool down and test cycle two tuners, Time (sec) Eacc Figure 11. Cavity Q in Final Assembly Considerable attention has been focused on the mechanical modes of the cavities and the dynamic Lorentz force detuning of the cavities as there is a concern regarding control of the RF during pulsed operations [6]. Dynamic Lorentz force detuning is measured by the cavity frequency shift during a RF pulse while operating at the SNS design of a 6% duty factor at 6 Hz and operating gradient of.1 MV/m. The measured frequency shift of ~3 Hz is below the requirement of 47 Hz. The frequency shift resulting from background microphonics noise is also measured. Measurements of the first mode and amplitude for M1 are included in Table 3. These levels are well within requirements for SNS. RMS Background, Hz st Mechanical Mode Table 3. M1 Microphonics Amplitude and 1 st modes Measurements of the mechanical modes are done both by sweeping the modulation frequency of an amplitude modulated cavity gradient and piezo excitation voltage. 46

5 The transfer functions for these are shown in Figures 12 and 13 where the x-axis shows the frequency of the driving term and the y-axis is the cavity response amplitude. Figure 12. Gradient Modulated Mechanical Mode Mapping Cavity Detuning, Response Ratio (db) Cavity Detuning, Response Ratio (db) Cavity Position 1, Lorentz Transfer Function (85. MHz) M:\asd\asddata\CMTF\M1\Cav 1 Lorentz Mech Modes\Results\TRAC1.xls AM Drive Frequency (Hz) Cavity Position 1, Piezo Transfer Function (85. MHz) M:\asd\asddata\CMTF\M1\Cav 1 Piezo Mech Modes\Results\TRAC1.xls Piezo Drive Frequency (Hz) Figure 13. Piezo Modulated Mechanical Mode Mapping HOM damping is measured for all significant modes as well as the rejection of the fundamental frequency by the pickup probe. HOM mode filters achieve Q s below 4 for all critical modes, meeting the SNS requirements. Initial Q specification for the HOM filter fundamental notch filter was 12 but has been reduced to 3x and measured values range from ~5x to ~5x Relative Phase (deg) Relative Phase (deg) as required to support operations at SNS. There are problems with the mechanical tuners resulting in intermittent operation. The suspect components are in the drive train that can be replaced with little effort. Replacement of the tuner drive assemblies is planned after rework and qualification of assemblies has been completed. REFERENCES [1]S. Smee, H. Wang, M. Stirbet, T. Powers, M. Drury, J.R. Delayen, E. Daly, G. Ciovati, C.E. Reece, P. Kneisel, K. Davis, K. Wilson, J. Preble, J. Mammosser, Isidoro Campisi, Results of the Cryogenic Testing of the SNS Prototype Cryomodule 22 Linear Accelerator Conference [2]K.M. Wilson, Isidoro Campisi, Peter Kneisel, William Schneider, Edward Daly, Mircea Stirbet, The Fundamental Power Coupler for the Spallation Neutron Source (SNS) Superconducting Cavities, PAC 21, Jun 21, Chicago, Illinois [3]K.M. Wilson, C. Grenoble, G.K. Davis, Tom Powers, Ganapati Myneni, Mike Drury, Isidoro Campisi, Mircea Stirbet, Processing Test Stand for the Fundamental Power Couplers of the Spallation Neutron Source (SNS) Superconducting Cavities, PAC 21, Jun 21, Chicago, Illinois [4]M. Stirbet etal, Testing Procedures and Results of the Prototype Fundamental Power Coupler for the Spallation Neutron Source, PAC 21, Jun 21, Chicago, Illinois [5]E. F. Daly, V. Ganni, C. H. Rode, W. J. Schneider, K. M. Wilson and M. A. Wiseman, Spallation Neutron Source Cryomodule Heat Loads and Thermal Design, Advances in Cryogenics, Vol. 47A, p [6]J.R. Delayen, Piezolectric Tuner Compensation of Lorentz Detuning in Superconducting Cavities, These Proceedings SUMMARY The performance characterization of the SNS cryomodules has included testing of sub-assemblies for more than 4 cryomodules and 2 final assemblies, the prototype and first production medium-β cryomodule. Cavity performance has exceeded E acc and Q requirements for all qualified components and completed assemblies with no significant change in performance between VTA and cryomodule configurations. A focused testing program continues to characterize cryomodule performance for SNS operations. These tests will continue 461

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

SUPERCONDUCTING PROTOTYPE CAVITIES FOR THE SPALLATION NEUTRON SOURCE (SNS) PROJECT *

SUPERCONDUCTING PROTOTYPE CAVITIES FOR THE SPALLATION NEUTRON SOURCE (SNS) PROJECT * SUPERCONDUCTING PROTOTYPE CAVITIES FOR THE SPALLATION NEUTRON SOURCE (SNS) PROJECT * G. Ciovati, P. Kneisel, J. Brawley, R. Bundy, I. Campisi, K. Davis, K. Macha, D. Machie, J. Mammosser, S. Morgan, R.

More information

ABSTRACT 1 CEBAF UPGRADE CAVITY/CRYOMODULE

ABSTRACT 1 CEBAF UPGRADE CAVITY/CRYOMODULE Energy Content (Normalized) SC Cavity Resonance Control System for the 12 GeV Upgrade Cavity: Requirements and Performance T. Plawski, T. Allison, R. Bachimanchi, D. Hardy, C. Hovater, Thomas Jefferson

More information

R.Bachimanchi, IPAC, May 2015, Richmond, VA

R.Bachimanchi, IPAC, May 2015, Richmond, VA 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

5.5 SNS Superconducting Linac

5.5 SNS Superconducting Linac JP0150514 ICANS - XV 15 th Meeting of the International Collaboration on Advanced Neutron Sources November 6-9, 2000 Tsukuba, Japan Ronald M. Sundelin Jefferson Lab* 5.5 SNS Superconducting Linac 12000

More information

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY G. Devanz, D. Braud, M. Desmons, Y. Gasser, E. Jacques, O. Piquet, J. Plouin, J.- P. Poupeau, D. Roudier, P. Sahuquet, CEA-Saclay,

More information

RENASCENCE * PERFORMANCE AND PROBLEMS ON FIRST TEST Feedthrough leaks sub 70 K. End group quenching

RENASCENCE * PERFORMANCE AND PROBLEMS ON FIRST TEST Feedthrough leaks sub 70 K. End group quenching Proceedings of SRF27, Peking Univ., Beijing, China PERFORMANCE OF THE CEBAF PROTOTYPE CRYOMODULE RENASCENCE * C. E. Reece, E. F. Daly, G. K. Davis, M. Drury, W. R. Hicks, J. Preble, H. Wang # Jefferson

More information

Update 5/19/11. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton

Update 5/19/11. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton R100 Microphonics i Update 5/19/11 Andrew Hutton Reporting on work by Kirk Davis, Mike Drury, Leigh Harwood, John Hogan, Curt Hovater, Thomas Plawski, Mark Wiseman, etc. The Problem Vibrations of the superconducting

More information

LORENTZ FORCE DETUNING ANALYSIS OF THE SPALLATION NEUTRON SOURCE (SNS) ACCELERATING CAVITIES *

LORENTZ FORCE DETUNING ANALYSIS OF THE SPALLATION NEUTRON SOURCE (SNS) ACCELERATING CAVITIES * LORENTZ FORCE DETUNING ANALYSIS OF THE SPALLATION NEUTRON SOURCE (SNS) ACCELERATING CAVITIES * R. Mitchell, K. Matsumoto, Los Alamos National Lab, Los Alamos, NM 87545, USA G. Ciovati, K. Davis, K. Macha,

More information

R100 Microphonics. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton

R100 Microphonics. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton R100 Microphonics Andrew Hutton Reporting on work by Kirk Davis, Mike Drury, Leigh Harwood, John Hogan, Kurt Hovater, Thomas Plawski, Mark Wiseman, etc. The Problem Vibrations of the superconducting cavities

More information

Packaging of Cryogenic Components

Packaging of Cryogenic Components Packaging of Cryogenic Components William J. Schneider Senior Mechanical Engineer Emeritus November 19-23 2007 1 Packaging of Cryogenic Components Day one Introduction and Overview 2 What is important?

More information

Tuning systems for superconducting cavities at Saclay

Tuning systems for superconducting cavities at Saclay Tuning systems for superconducting cavities at Saclay 1 MACSE: 1990: tuner in LHe bath at 1.8K TTF: 1995 tuner at 1.8K in the insulating vacuum SOLEIL: 1999 tuner at 4 K in the insulating vacuum Super-3HC:

More information

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS J. Teichert, A. Büchner, H. Büttig, F. Gabriel, P. Michel, K. Möller, U. Lehnert, Ch. Schneider, J. Stephan, A.

More information

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY Abstract HIGH POWER COUPLER FOR THE TESLA TEST FACILITY W.-D. Moeller * for the TESLA Collaboration, Deutsches Elektronen-Synchrotron DESY, D-22603 Hamburg, Germany The TeV Energy Superconducting Linear

More information

Status of superconducting module development suitable for cw operation: ELBE cryostats

Status of superconducting module development suitable for cw operation: ELBE cryostats Status of superconducting module development suitable for cw operation: ELBE cryostats, A. Büchner, H. Büttig, F. Gabriel, P. Michel, K. Möller, U. Lehnert, Ch. Schneider, J. Stephan, A. Winter Forschungszentrum

More information

Coupler Electromagnetic Design

Coupler Electromagnetic Design Coupler Electromagnetic Design HPC Workshop, TJNAF October 30 November 1, 2002 Yoon Kang Spallation Neutron Source Oak Ridge National Laboratory Contents Fundamental Power Coupler Design Consideration

More information

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT G. Olry, J-L. Biarrotte, S. Blivet, S. Bousson, C. Commeaux, C. Joly, T. Junquera, J. Lesrel, E. Roy,

More information

To produce more powerful and high-efficiency particle accelerator, efforts have

To produce more powerful and high-efficiency particle accelerator, efforts have Measuring Unloaded Quality Factor of Superconducting RF Cryomodule Jian Cong Zeng Department of Physics and Astronomy, State University of New York at Geneseo, Geneseo, NY 14454 Elvin Harms, Jr. Accelerator

More information

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute CEBAF waveguide absorbers R. Rimmer for JLab SRF Institute Outline Original CEBAF HOM absorbers Modified CEBAF loads for FEL New materials for replacement loads High power loads for next generation FELs

More information

Frequency Tuning and RF Systems for the ATLAS Energy Upgrade. Gary P. Zinkann

Frequency Tuning and RF Systems for the ATLAS Energy Upgrade. Gary P. Zinkann Frequency Tuning and RF Systems for the ATLAS Energy Upgrade Outline Overview of the ATLAS Energy Upgrade Description of cavity Tuning method used during cavity construction Description and test results

More information

THE PROTOTYPE FUNDAMENTAL POWER COUPLER FOR THE SPALLATION NEUTRON SOURCE SUPERCONDUCTING CAVITIES: DESIGN AND INITIAL TEST RESULTS*

THE PROTOTYPE FUNDAMENTAL POWER COUPLER FOR THE SPALLATION NEUTRON SOURCE SUPERCONDUCTING CAVITIES: DESIGN AND INITIAL TEST RESULTS* THE PROTOTYPE FUNDAMENTAL POWER COUPLER FOR THE SPALLATION NEUTRON SOURCE SUPERCONDUCTING CAVITIES: DESIGN AND INITIAL TEST RESULTS* K. M. Wilson,I.E.Campisi,E.F.Daly,G.K.Davis,M.Drury,J.E.Henry,P.Kneisel,G.

More information

DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY -

DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY - DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY - F. Peauger, C. Arcambal, F. Ardellier, S. Berry, P. Bosland, A. Bouygues, E. Cenni, JP. Charrier, G. Devanz, F. Eozénou,

More information

Structures for RIA and FNAL Proton Driver

Structures for RIA and FNAL Proton Driver Structures for RIA and FNAL Proton Driver Speaker: Mike Kelly 12 th International Workshop on RF Superconductivity July 11-15, 2005 Argonne National Laboratory A Laboratory Operated by The University of

More information

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University Overview of ERL Projects: SRF Issues and Challenges Matthias Liepe Cornell University Overview of ERL projects: SRF issues and challenges Slide 1 Outline Introduction: SRF for ERLs What makes it special

More information

The European Spallation Source. Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013

The European Spallation Source. Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013 The European Spallation Source Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013 Overview The European Spallation Source (ESS) will house the most powerful proton linac ever built. The average

More information

ACHIEVEMENT OF ULTRA-HIGH QUALITY FACTOR IN PROTOTYPE CRYOMODULE FOR LCLS-II

ACHIEVEMENT OF ULTRA-HIGH QUALITY FACTOR IN PROTOTYPE CRYOMODULE FOR LCLS-II ACHIEVEMENT OF ULTRA-HIGH QUALITY FACTOR IN PROTOTYPE CRYOMODULE FOR LCLS-II G. Wu 1, A. Grassellino, E. Harms, N. Solyak, A. Romanenko, C. Ginsburg, R. Stanek Fermi National Accelerator Laboratory, Batavia,

More information

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7 Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7 Document Approval: Originator: Tor Raubenheimer, Physics Support Lead Date Approved Approver: Marc Ross, Cryogenic System Manager Approver: Jose Chan,

More information

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF Y. Yamamoto #, H. Hayano, E. Kako, T. Matsumoto, S. Michizono, T. Miura, S. Noguchi, M. Satoh, T. Shishidio, K. Watanabe, KEK, Tsukuba,

More information

Waveguide Arc Restrike Test Results Abstract Background

Waveguide Arc Restrike Test Results Abstract Background Waveguide Arc Restrike Test Results Tom Powers, Doug Curry, Kirk Davis, Larry King, and Mike Tiefenback Thomas Jefferson National Accelerator Facility (Test dates July 6, 2004 through September 2, 2004)

More information

Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala

Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala FREIA Report 2012/03 October 2012 DEPARTMENT OF PHYSICS AND ASTRONOMY UPPSALA UNIVERSITY Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala ESS TDR Contribution R. Ruber, T. Ekelöf, R.A. Yogi.

More information

PIP-II Superconducting RF Linac Status and Challenges" Leonardo Ristori! ICEC-ICMC Conference, New Delhi! 9 March 2016!!

PIP-II Superconducting RF Linac Status and Challenges Leonardo Ristori! ICEC-ICMC Conference, New Delhi! 9 March 2016!! PIP-II Superconducting RF Linac Status and Challenges" Leonardo Ristori! ICEC-ICMC Conference, New Delhi!! Outline" PIP-II Mission & Strategy! PIP-II SRF Linac Overview! Technical Risk & Mitigation! Indian

More information

High Power Couplers for TTF - FEL

High Power Couplers for TTF - FEL High Power Couplers for TTF - FEL 1. Requirements for High Power Couplers on superconducting Cavities 2. Characteristics of pulsed couplers 3. Standing wave pattern in the coaxial coupler line 4. Advantages

More information

Experience with 3.9 GHz cavity HOM couplers

Experience with 3.9 GHz cavity HOM couplers Cornell University, October 11-13, 2010 Experience with 3.9 GHz cavity HOM couplers T. Khabiboulline, N. Solyak, FNAL. 3.9 GHz cavity general parameters Third harmonic cavity (3.9GHz) was proposed to compensate

More information

ESS RF Source and Spoke Cavity Test Plan

ESS RF Source and Spoke Cavity Test Plan FREIA Report 2015/01 26 February 2015 DEPARTMENT OF PHYSICS AND ASTRONOMY UPPSALA UNIVERSITY ESS RF Source and Spoke Cavity Test Plan R. Ruber (ed.), A. Bhattacharyya, D. Dancila, T. Ekelöf, J. Eriksson,

More information

Lorentz Force Compensation of Pulsed SRF Cavities

Lorentz Force Compensation of Pulsed SRF Cavities Lorentz Force Compensation of Pulsed SRF Cavities S. N. Simrock, DESY, Hamburg, Germany Abstract Significant progress on the issues of pulsed operation of superconducting cavities at high gradients has

More information

HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK

HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK E. Kako #, H. Hayano, S. Noguchi, T. Shishido, K. Watanabe and Y. Yamamoto KEK, Tsukuba, Ibaraki, 305-0801, Japan Abstract An input coupler,

More information

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension XFEL Cryo System Possible extension 1 st stage Project X Collaboration Meeting, FNAL September 8-9, 2010 (XFEL WP10 & WP13) Outline 2 XFEL accelerator structure TESLA technology Basic cryogenic parameters

More information

Advance on High Power Couplers for SC Accelerators

Advance on High Power Couplers for SC Accelerators Advance on High Power Couplers for SC Accelerators Eiji Kako (KEK, Japan) IAS conference at Hong Kong for High Energy Physics, 2017, January 23th Eiji KAKO (KEK, Japan) IAS at Hong Kong, 2017 Jan. 23 1

More information

ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY

ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY P. A. McIntosh #, R. Bate, C. D. Beard, M. A. Cordwell, D. M. Dykes, S. M. Pattalwar and J. Strachan, STFC Daresbury Laboratory,

More information

THE CRYOGENIC SYSTEM OF TESLA

THE CRYOGENIC SYSTEM OF TESLA THE CRYOGENIC SYSTEM OF TESLA S. Wolff, DESY, Notkestr. 85, 22607 Hamburg, Germany for the TESLA collaboration Abstract TESLA, a 33 km long 500 GeV centre-of-mass energy superconducting linear collider

More information

Processing and Testing of PKU 3-1/2 Cell Cavity at JLab

Processing and Testing of PKU 3-1/2 Cell Cavity at JLab Processing and Testing of PKU 3-1/2 Cell Cavity at JLab Rongli Geng, Byron Golden August 7, 2009 Introduction The SRF group at Peking University has successfully built a 3-1/2 cell superconducting niobium

More information

LCLS-II SRF Linac Multi-lab partnership to build CW FEL based on SRF at SLAC. Marc Ross 13 January 2014

LCLS-II SRF Linac Multi-lab partnership to build CW FEL based on SRF at SLAC. Marc Ross 13 January 2014 LCLS-II SRF Linac Multi-lab partnership to build CW FEL based on SRF at SLAC Marc Ross 13 January 2014 What are the technical and practical limits for DF? 1st limit: Heat load at 2K for each cryomodule

More information

THE U. S. RIA PROJECT SRF LINAC*

THE U. S. RIA PROJECT SRF LINAC* THE U. S. RIA PROJECT SRF LINAC* K. W. Shepard, ANL, Argonne, IL 60540, USA Abstract The nuclear physics community in the U. S. has reaffirmed the rare isotope accelerator facility (RIA) as the number

More information

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY Low-Level RF S. Simrock, DESY Outline Scope of LLRF System Work Breakdown for XFEL LLRF Design for the VUV-FEL Cost, Personpower and Schedule RF Systems for XFEL RF Gun Injector 3rd harmonic cavity Main

More information

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Overview ALICE (Accelerators and Lasers In Combined Experiments)

More information

Third Harmonic Superconducting passive cavities in ELETTRA and SLS

Third Harmonic Superconducting passive cavities in ELETTRA and SLS RF superconductivity application to synchrotron radiation light sources Third Harmonic Superconducting passive cavities in ELETTRA and SLS 2 cryomodules (one per machine) with 2 Nb/Cu cavities at 1.5 GHz

More information

Digital LLRF Test on the Renascence Cryomodule

Digital LLRF Test on the Renascence Cryomodule Digital LLRF Test on the Renascence Cryomodule Trent Allison, Rama Bachimanchi, Curt Hovater, John Musson and Tomasz Plawski Introduction The Renascence cryomodule was the first opportunity for testing

More information

PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC

PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC F. Peauger, C. Arcambal, S. Berry, N. Berton, P. Bosland, E. Cenni, J.P. Charrier, G. Devanz, F. Eozenou, F. Gougnaud,

More information

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE M. Liepe, S. Belomestnykh, E. Chojnacki, Z. Conway, V. Medjidzade, H. Padamsee, P. Quigley, J. Sears, V. Shemelin, V. Veshcherevich,

More information

Current Industrial SRF Capabilities and Future Plans

Current Industrial SRF Capabilities and Future Plans and Future Plans Capabilities in view of Design Engineering Manufacturing Preparation Testing Assembly Taking into operation Future Plans Participate in and contribute to development issues, provide prototypes

More information

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES LARGE SCALE TESTING OF SRF CAVITIES AND MODULES Jacek Swierblewski IFJ PAN Krakow IKC for the XFEL Introduction IFJ PAN 2 Institute of Nuclear Physics (IFJ) located in Kraków, Poland was founded in 1955

More information

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium Performance of Superconducting Cavities for the European XFEL Detlef Reschke DESY for the EU-XFEL Accelerator Consortium Outline 2 European XFEL Linear Accelerator Cavity Production Vertical Acceptance

More information

Superconducting RF cavities activities for the MAX project

Superconducting RF cavities activities for the MAX project 1 Superconducting RF cavities activities for the MAX project OECD-NEA TCADS-2 Workshop Nantes, 22 May 2013 Marouan El Yakoubi, CNRS / IPNO 2 Contents 352 MHz spoke Cryomodule design 700 MHz test area 700

More information

DESIGN OPTIONS FOR CEBAF ENERGY UPGRADE

DESIGN OPTIONS FOR CEBAF ENERGY UPGRADE b JLAB-ACT-97-09 DESGN OPTONS FOR CEBAF ENERGY UPGRADE L. Phillips, J. Mammosser, and V. Nguyen;Thomas Jefferson National Accelerator Facility, 12000 Jefferson Avenue, Newport News, VA 23606 USA Abstract

More information

OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW*

OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW* Presented at the 13th International Workshop on RF Superconductivity, Beijing, China, 2007 SRF 071120-04 OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW* S. Belomestnykh #, CLASSE, Cornell

More information

S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members. Inter University Accelerator Centre New Delhi India

S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members. Inter University Accelerator Centre New Delhi India S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members Inter University Accelerator Centre New Delhi 110067 India Highlights of presentation 1. Introduction to Linear accelerator

More information

Vibration studies of a superconducting accelerating

Vibration studies of a superconducting accelerating Vibration studies of a superconducting accelerating module at room temperature and at 4.5 K Ramila Amirikas, Alessandro Bertolini, Wilhelm Bialowons Vibration studies on a Type III cryomodule at room temperature

More information

Cavity development for TESLA

Cavity development for TESLA Cavity development for TESLA Lutz.Lilje@desy.de DESY -FDET- Cavity basics History: Limitations and solutions»material inclusions»weld defects»field emission»increased surface resistance at high field Performance

More information

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University ESS RF Development at Uppsala University Roger Ruber for the FREIA team Uppsala University ESS-UU Collaboration 2009 ESS and UU start discussion on 704 MHz RF development proposal for ESS dedicated test

More information

LOW BETA CAVITY DEVELOPMENT FOR AN ATLAS INTENSITY UPGRADE

LOW BETA CAVITY DEVELOPMENT FOR AN ATLAS INTENSITY UPGRADE LOW BETA CAVITY DEVELOPMENT FOR AN ATLAS INTENSITY UPGRADE M. P. Kelly, Z. A. Conway, S. M. Gerbick, M. Kedzie, T. C. Reid, R. C. Murphy, B. Mustapha, S.H. Kim, P. N. Ostroumov, Argonne National Laboratory,

More information

Report of working group 5

Report of working group 5 Report of working group 5 Materials Cavity design Cavity Fabrication Preparatioin & Testing Power coupler HOM coupler Beam line absorber Tuner Fundamental R&D items Most important R&D items 500 GeV parameters

More information

Mircea Stirbet. RF Conditioning: Systems and Procedures. Jefferson Laboratory

Mircea Stirbet. RF Conditioning: Systems and Procedures. Jefferson Laboratory Mircea Stirbet RF Conditioning: Systems and Procedures Jefferson Laboratory General requirements for input couplers - Sustain RF power required for operation of accelerator with beam - Do not compromise

More information

Fiducialization of Superconducting Radio Frequency Cryomodules at Jefferson Lab

Fiducialization of Superconducting Radio Frequency Cryomodules at Jefferson Lab Fiducialization of Superconducting Radio Frequency Cryomodules at Jefferson Lab C. J. Curtis, J. Dahlberg, W. Oren, J. Preble, K. Tremblay. Thomas Jefferson National Accelerator Facility, Virginia, U.S.A.

More information

Fundamental mode rejection in SOLEIL dipole HOM couplers

Fundamental mode rejection in SOLEIL dipole HOM couplers Fundamental mode rejection in SOLEIL dipole HOM couplers G. Devanz, DSM/DAPNIA/SACM, CEA/Saclay, 91191 Gif-sur-Yvette 14th June 2004 1 Introduction The SOLEIL superconducting accelerating cavity is a heavily

More information

Aurélien Ponton. First Considerations for the Design of the ESS Cryo-Modules

Aurélien Ponton. First Considerations for the Design of the ESS Cryo-Modules Accelerator Division ESS AD Technical Note ESS/AD/0001 Aurélien Ponton First Considerations for the Design of the ESS Cryo-Modules 16 March 2010 First considerations for the design of the ESS cryo-modules

More information

A few results [2,3] obtained with the individual cavities inside their horizontal cryostats are summarized in Table I and a typical Q o

A few results [2,3] obtained with the individual cavities inside their horizontal cryostats are summarized in Table I and a typical Q o Particle Accelerators, 1990, Vol. 29, pp. 47-52 Reprints available directly from the publisher Photocopying permitted by license only 1990 Gordon and Breach, Science Publishers, Inc. Printed in the United

More information

RECORD QUALITY FACTOR PERFORMANCE OF THE PROTOTYPE CORNELL ERL MAIN LINAC CAVITY IN THE HORIZONTAL TEST CRYOMODULE

RECORD QUALITY FACTOR PERFORMANCE OF THE PROTOTYPE CORNELL ERL MAIN LINAC CAVITY IN THE HORIZONTAL TEST CRYOMODULE RECORD QUALITY FACTOR PERFORMANCE OF THE PROTOTYPE CORNELL ERL MAIN LINAC CAVITY IN THE HORIZONTAL TEST CRYOMODULE N. Valles, R. Eichhorn, F. Furuta, M. Ge, D. Gonnella, D.N. Hall, Y. He, V. Ho, G. Hoffstaetter,

More information

QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER*

QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER* QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER* P.N. Prakash and A.Roy Nuclear Science Centre, P.O.Box 10502, New Delhi 110 067, INDIA and K.W.Shepard Physics Division, Argonne National Laboratory,

More information

PERFORMANCE OF THE TUNER MECHANISM FOR SSR1 RESONATORS DURING FULLY INTEGRETED TESTS AT FERMILAB

PERFORMANCE OF THE TUNER MECHANISM FOR SSR1 RESONATORS DURING FULLY INTEGRETED TESTS AT FERMILAB PERFORMANCE OF THE TUNER MECHANISM FOR SSR1 RESONATORS DURING FULLY INTEGRETED TESTS AT FERMILAB D. Passarelli, J.P. Holzbauer, L. Ristori, FNAL, Batavia, IL 651, USA Abstract In the framework of the Proton

More information

PI piezo Life Time Test Report. A. Bosotti, R. Paparella, F. Puricelli

PI piezo Life Time Test Report. A. Bosotti, R. Paparella, F. Puricelli PI piezo Life Time Test Report A. Bosotti, R. Paparella, F. Puricelli 1. Introduction...3 1.1. Vacuum...4 1.2. Temperature...4 1.3. Preload...4 1.4. Driving signal...4 2. General features and conceptual

More information

Progresses on China ADS Superconducting Cavities

Progresses on China ADS Superconducting Cavities Progresses on China ADS Superconducting Cavities Peng Sha IHEP, CAS 2013/06/12 1 Outline 1. Introduction 2. Spoke012 cavity 3. Spoke021 cavity 4. Spoke040 cavity 5. 650MHz β=0.82 5-cell cavity 6. High

More information

INTRODUCTION. METHODS Cavity Preparation and Cryomodule Assembly

INTRODUCTION. METHODS Cavity Preparation and Cryomodule Assembly RECORD QUALITY FACTOR PERFORMANCE OF THE PROTOTYPE CORNELL ERL MAIN LINAC CAVITY IN THE HORIZONTAL TEST CRYOMODULE N. Valles, R. Eichhorn, F. Furuta, M. Gi, D. Gonnella, Y. He, V. Ho, G. Hoffstaetter,

More information

Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS

Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS Patricia DUCHESNE, Guillaume OLRY Sylvain BRAULT, Sébastien BOUSSON, Patxi DUTHIL, Denis REYNET Institut de Physique Nucléaire d Orsay SRF

More information

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF Project X Cavity RF and mechanical design T. Khabiboulline, FNAL/TD/SRF TTC meeting on CW-SRF, 2013 Project X Cavity RF and mechanical design T 1 High ß Low ß 0.5 HWR SSR1 SSR2 0 1 10 100 1 10 3 1 10 4

More information

SUPERCONDUCTING CAVITIES AND CRYOMODULES FOR PROTON AND DEUTERON LINACS

SUPERCONDUCTING CAVITIES AND CRYOMODULES FOR PROTON AND DEUTERON LINACS Proceedings of LINAC2014, Geneva, Switzerland THIOA04 SUPERCONDUCTING CAVITIES AND CRYOMODULES FOR PROTON AND DEUTERON LINACS G. Devanz, CEA-Irfu CEA-Saclay, Gif-sur-Yvette 91191, France Abstract We review

More information

TESLA RF POWER COUPLERS DEVELOPMENT AT DESY.

TESLA RF POWER COUPLERS DEVELOPMENT AT DESY. TESLA RF POWER COUPLERS DEVELOPMENT AT DESY. Dwersteg B., Kostin D., Lalayan M., Martens C., Möller W.-D., DESY, D-22603 Hamburg, Germany. Abstract Different RF power couplers for the TESLA Test Facility

More information

Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay. Abstract

Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay. Abstract SRF Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay Abstract This report presents the piezo tuner developed at Saclay in the framework of CARE/SRF.

More information

Cavity Field Control - RF Field Controller. LLRF Lecture Part3.3 S. Simrock, Z. Geng DESY, Hamburg, Germany

Cavity Field Control - RF Field Controller. LLRF Lecture Part3.3 S. Simrock, Z. Geng DESY, Hamburg, Germany Cavity Field Control - RF Field Controller LLRF Lecture Part3.3 S. Simrock, Z. Geng DESY, Hamburg, Germany Content Introduction to the controller Control scheme selection In-phase and Quadrature (I/Q)

More information

Completion of the first SSR1 cavity for PXIE

Completion of the first SSR1 cavity for PXIE 2013 North American Particle Accelerator Conference Pasadena, CA Completion of the first SSR1 cavity for PXIE Design, Manufacturing and Qualification Leonardo Ristori on behalf of the Fermilab SRF Development

More information

DEVELOPMENTS AND TESTS OF A 700 MH z CRYOMODULE FOR THE SUPERCONDUCTING PROTON LINAC OF MYRRHA*

DEVELOPMENTS AND TESTS OF A 700 MH z CRYOMODULE FOR THE SUPERCONDUCTING PROTON LINAC OF MYRRHA* DEVELOPMENTS AND TESTS OF A 700 MH z CRYOMODULE FOR THE SUPERCONDUCTING PROTON LINAC OF MYRRHA* F. Bouly #, CERN, Geneva R. Paparella ##, A. Bosotti, P. Pierini,INFN/LASA, Segrate (MI) M. El Yakoubi ###,

More information

RF power tests of LEP2 main couplers on a single cell superconducting cavity

RF power tests of LEP2 main couplers on a single cell superconducting cavity RF power tests of LEP2 main couplers on a single cell superconducting cavity H.P. Kindermann, M. Stirbet* CERN, CH-1211 Geneva 23, Switzerland Abstract To determine the power capability of the input couplers

More information

Evaluation of HOM Coupler Probe Heating by HFSS Simulation

Evaluation of HOM Coupler Probe Heating by HFSS Simulation G. Wu, H. Wang, R. A. Rimmer, C. E. Reece Abstract: Three different tip geometries in a HOM coupler on a CEBAF Upgrade Low Loss cavity have been evaluated by HFSS simulation to understand the tip surface

More information

Review of New Shapes for Higher Gradients

Review of New Shapes for Higher Gradients Review of New Shapes for Higher Gradients Rong-Li Geng LEPP, Cornell University Rong-Li Geng SRF2005, July 10-15, 2005 1 1 TeV 800GeV 500GeV ILC(TESLA type) energy reach Rapid advances in single-cell cavities

More information

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM FOR THE EUROPEAN XFEL Julien Branlard, for the LLRF team TALK OVERVIEW 2 Introduction Brief reminder about the XFEL LLRF system Commissioning goals

More information

Superstructures; First Cold Test and Future Applications

Superstructures; First Cold Test and Future Applications Superstructures; First Cold Test and Future Applications DESY: C. Albrecht, V. Ayvazyan, R. Bandelmann, T. Büttner, P. Castro, S. Choroba, J. Eschke, B. Faatz, A. Gössel, K. Honkavaara, B. Horst, J. Iversen,

More information

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ERL 09 8 th 12 th June 2009 ALICE Accelerators and Lasers In Combined Experiments Brief Description ALICE Superconducting

More information

SUPERCONDUCTING RESONATORS DEVELOPMENT FOR THE FRIB AND ReA LINACS AT MSU: RECENT ACHIEVEMENTS AND FUTURE GOALS

SUPERCONDUCTING RESONATORS DEVELOPMENT FOR THE FRIB AND ReA LINACS AT MSU: RECENT ACHIEVEMENTS AND FUTURE GOALS SUPERCONDUCTING RESONATORS DEVELOPMENT FOR THE FRIB AND ReA LINACS AT MSU: RECENT ACHIEVEMENTS AND FUTURE GOALS A. Facco #+, E. Bernard, J. Binkowski, J. Crisp, C. Compton, L. Dubbs, K. Elliott, L. Harle,

More information

3.9 GHz work at Fermilab

3.9 GHz work at Fermilab 3.9 GHz work at Fermilab + CKM 13-cell cavity Engineering and designing W.-D. Moeller Desy, MHF-sl Protocol of the meeting about 3 rd harmonic cavities during the TESLA collaboration meeting at DESY on

More information

CURRENT INDUSTRIAL SRF CAPABILITIES AND FUTURE PLANS

CURRENT INDUSTRIAL SRF CAPABILITIES AND FUTURE PLANS CURRENT INDUSTRIAL SRF CAPABILITIES AND FUTURE PLANS Hanspeter Vogel ACCEL Instruments GmbH Friedrich Ebert Strasse 1, 51429 Bergisch Gladbach, Germany Corresponding author: Hanspeter Vogel ACCEL Instruments

More information

Thermionic Bunched Electron Sources for High-Energy Electron Cooling

Thermionic Bunched Electron Sources for High-Energy Electron Cooling Thermionic Bunched Electron Sources for High-Energy Electron Cooling Vadim Jabotinski 1, Yaroslav Derbenev 2, and Philippe Piot 3 1 Institute for Physics and Technology (Alexandria, VA) 2 Thomas Jefferson

More information

KEK ERL CRYOMODULE DEVELOPMENT

KEK ERL CRYOMODULE DEVELOPMENT KEK ERL CRYOMODULE DEVELOPMENT H. Sakai*, T. Furuya, E. Kako, S. Noguchi, M. Sato, S. Sakanaka, T. Shishido, T. Takahashi, K. Umemori, K. Watanabe and Y. Yamamoto KEK, 1-1, Oho, Tsukuba, Ibaraki, 305-0801,

More information

LLRF Plans for SMTF. Ruben Carcagno (Fermilab) Nigel Lockyer (University of Pennsylvania) Thanks to DESY, PISA, KEK, Fermilab, SLAC Colleagues

LLRF Plans for SMTF. Ruben Carcagno (Fermilab) Nigel Lockyer (University of Pennsylvania) Thanks to DESY, PISA, KEK, Fermilab, SLAC Colleagues LLRF Plans for SMTF Ruben Carcagno (Fermilab) Nigel Lockyer (University of Pennsylvania) Thanks to DESY, PISA, KEK, Fermilab, SLAC Colleagues Outline Near-term (< 1.5 years) SMTF LLRF plan Long-term (>

More information

Impact of remanent magnetic field on the heat load of original CEBAF cryomodule

Impact of remanent magnetic field on the heat load of original CEBAF cryomodule Impact of remanent magnetic field on the heat load of original CEBAF cryomodule Gianluigi Ciovati, Guangfeng Cheng, Michael Drury, John Fischer, and Rongli Geng 1 Abstract The heat load of the original

More information

Work Package Status Report

Work Package Status Report Work Package Status Report Date: August 2018 Work Package: WP5 Elliptical cavities and cryomodules Author: Pierre Bosland, Roger Ruber, Daniele Sertore, Mike Ellis, Christine Darve 1. Accomplishments by

More information

Engineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team

Engineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team Engineering Challenges and Solutions for MeRHIC Andrew Burrill for the MeRHIC Team Key Components Photoinjector Design Photocathodes & Drive Laser Linac Cavities 703.75 MHz 5 cell cavities 3 rd Harmonic

More information

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE S. M. Pattalwar, R. Bate, G. Cox, P.A. McIntosh and A. Oates, STFC, Daresbury Laboratory, Warrington, UK Abstract ALICE is a prototype

More information

THE MULTIPACTING STUDY OF NIOBIUM SPUTTERED HIGH-BETA QUARTER-WAVE RESONATORS FOR HIE-ISOLDE

THE MULTIPACTING STUDY OF NIOBIUM SPUTTERED HIGH-BETA QUARTER-WAVE RESONATORS FOR HIE-ISOLDE THE MULTIPACTING STUDY OF NIOBIUM SPUTTERED HIGH-BETA QUARTER-WAVE RESONATORS FOR HIE-ISOLDE P. Zhang and W. Venturini Delsolaro CERN, Geneva, Switzerland Abstract Superconducting Quarter-Wave Resonators

More information

Third Harmonic Cavity Status

Third Harmonic Cavity Status Third Harmonic Cavity Status General parameters Cavity design Main coupler calculation HOM analysis and HOM coupler design Lorentz Forces and Stress analysis Summary General parameters Third harmonic cavity

More information

2008 JINST 3 S The RF systems and beam feedback. Chapter Introduction

2008 JINST 3 S The RF systems and beam feedback. Chapter Introduction Chapter 4 The RF systems and beam feedback 4.1 Introduction The injected beam will be captured, accelerated and stored using a 400 MHz superconducting cavity system, and the longitudinal injection errors

More information

DESIGN STUDY OF A 176 MHZ SRF HALF WAVE RESONATOR FOR THE SPIRAL-2 PROJECT

DESIGN STUDY OF A 176 MHZ SRF HALF WAVE RESONATOR FOR THE SPIRAL-2 PROJECT DESIGN STUDY OF A 176 MHZ SRF HALF WAVE RESONATOR FOR THE SPIRAL-2 PROJECT J-L. Biarrotte*, S. Blivet, S. Bousson, T. Junquera, G. Olry, H. Saugnac CNRS / IN2P3 / IPN Orsay, France Abstract In November

More information