1 EXHIBIT B TO AGREEMENT BETWEEN PENSACOLA HABITAT FOR HUMANITY AND SUBCONTRACTOR Scope of Work Vinyl Siding Labor Division 190 General Requirements 1. All Work shall be performed in accordance with manufacturer s printed installation instructions and all local, state, and federal laws and regulations. 2. The Work shall conform to all Codes in effect in the jurisdiction where the work is performed. 3. To promote safety, the jobsite must be kept clean and free of debris at all times. All trash, discarded packaging, boxes, bags, spoils of demolition, damaged and/or waste building materials, and other forms of debris shall be disposed of properly and legally. This subcontractor may use the on site debris container if one is provided by Habitat for Humanity. We encourage recycling and ask you to participate as much as possible on this job. 4. Purchase Orders will be issued for this division of work and the amount of compensation for the Work will be listed on the Purchase Order. 5. Additional work shall not be performed without the written approval of the Construction Director. This approval will be in the form of a Variance Purchase Order. If extra work is performed without prior approval, no payment will be made and if required, the extra work will be removed by and at the expense of this Sub contractor. 6. Pensacola Habitat for Humanity is a tax exempt entity. You will be instructed by our Accounting Department how to handle sales tax. 7. This Sub contractor shall furnish all Labor, Materials, Equipment, and Supplies necessary to complete the Work, unless directed otherwise by statement below. 8. Progress payments for partial completion of the Work will be made on the Friday following the Friday that invoices are received by our Accounting Department. 9. Final Payment will be made after all work of this Scope is complete. a. Payment to the Vinyl Installation Subcontractor is based on per square of siding, per linear foot of soffit, per square foot of porch ceiling, and per pair of shutters. Special Requirements 1. Pensacola Habitat for Humanity will furnish all vinyl siding materials for installation by this Subcontractor. 2. The siding is a double 4 or 5 lap The panels are 12 feet long and trim also is 12 long. 3. Siding Installation a. Install J channel around sides and tops of windows and doors making certain that the channel is laying flat against the wall and is straight. The corners where J channel meets will be mitered by cutting the end of the horizontal piece at a 45 degree angle and notching it to fit snugly against the vertical piece. Window sill extensions and header extensions on windows and doors should be cut so that J

2 channel can be installed flush with the casings. Channel should be nailed in the factory slots every 12 inches. Do not nail tight. The bottom piece to be installed on all windows is to be seal trim provided. When window and / or door facings are to be covered with coil stock, this will be done before installing the J channel and must have a return onto the moisture barrier. This return edge needs to be sealed with peel and seal, protecto tape, or other approved tape. b. Install the finish trim at the top and under all windows, inside the J channel, nailing the slots every 12 inches. It may be necessary to fur out under the window to maintain proper slope of the panel. PHFH will provide seal trim for use under windows. c. Install outside corner post on all outside corners, making certain that the corner is plumb and that it is not twisted. The corner will be placed in position allowing 1/4" clearance at the top. Nail at top of the upper slot. The corner should be nailed in the center of the slots. The corner will extend no more than 1/4" below the bottom of the siding. The corners may be extended further down until the siding is run and then cut off flush with the bottom of the siding. d. If the wall height requires the use of more than one corner, the shorter piece will be used at the bottom and will be lapped under the top piece. Both top and bottom of the corner post must be capped, if exposed. e. Inside corners may be run by using one piece of j channel to conceal ends of siding on back wall and to hold ends of siding on side walls. (rather than use two pieces of j) When this is done a flashing must be done using the coil stock in the corner. f. To establish the starting point for siding installation, locate the lowest corner of the house. Measure down from the eave and/or windows to a point approximately 1 " above the bottom of the existing siding, then measure an equal distance down to the next corner on that wall. This ensures that the siding appears level with the windows and/or eaves, regardless of any actual settling of the house. Stretch a chalk line between these two points, checking to be sure that the line is taut and straight before popping a line. Repeat this process all around the house, making necessary adjustments until all lines meet at every corner. In case of extreme settling, splitting the difference will be necessary to achieve proper alignment around the house. g. It is extremely important that the starter strip be straight and line up at all corners. Nail starter strip in center of nailing slots 8 to 10" maximum spacing. The starter strip must not start closer than ¾ from an outside corner. Keep ends of successive starter strips at least 1/4" apart to allow for expansion. h. Be careful, to ensure that no plumbing pipes are damaged by errant nailing. i. When cutting vinyl siding with a power saw, use a fine tooth blade mounted in the reverse position or the saw can be pulled backwards. Care should be taken when using a power saw to cut steel siding, use of snips or a sliding "chopper" are recommended. j. Allow for expansion and contraction using 1/4" gap in all corner posts and channels. In extremely cold weather the expansion gap will need to be 3/8". Overlap panels a minimum of 1" as allowed by the factory pre notched ends. Stagger end laps at least 30" apart so that one is not directly above the other, unless separated by three courses of siding. Always overlap joints away from entrances and from the point of the greatest traffic. Check every 3rd course for proper alignment. Areas 12' and less will never have splices, and pieces less than 3' shall never be used as starters or finishers. Expose only the manufactured edge of the panels.

3 k. Sill Trim material will be supplied to secure the top row of siding when it has to be cut down from a full piece. A snap punch tool must be used to properly prepare the cut piece of siding to fit correctly into the seal trim. 4. Fascia a. All coil work to be done on job site shall be carefully considered and planned before any coil is cut to eliminate excess scrap and ensure maximum utilization of coil. b. The exact dimensions of each level of the fascia will be measured carefully before the coil stock is bent to ensure proper and snug fitting. Since the dimensions may vary, measurements should be checked before each piece of fascia is bent. All fascia shall have a 1 " return under the fascia board to ensure uniformity. This needs to be hemmed to prevent corrosion to exposed woods. c. Fascia will be nailed to the bottom of the fascia board. The only face nailing that may have to be done is at the joints where two pieces of fascia overlap. If face nailing is necessary to keep the joint closed, pre drill holes before nailing and nail through only one piece of fascia. Extra care must be taken not to over drive the nail or let the hammer head contact the aluminum fascia. If soffit is attached to the bottom of the fascia board, the fascia will be nailed in the v grooves of the soffit. d. Matching color trim nails will be used to nail fascia. It may be necessary to use touch up paint on the heads of the nails. e. At outside or inside corners of fascia, notch the underside return back 1 from the end of the first piece of fascia. Bend the 1 tabs to fit around the corners. Cut the second piece to line up exactly with the corner of the fascia board, cutting the underside boards at 45 degree angles to create a neat mitered appearance. f. When gable boxes exist, extend the gable fascia panel through the gable box and cut the end to align with the fascia seam. Covered lower portion of box with coil stock and extend the coil underneath the fascia panel to prevent water infiltration. g. Fascia pieces shall be cut by scoring the back side on the coil stock with a utility knife and bending the coil at the point of scoring until it breaks. A square shall be used to ensure that the ends are square and straight. Never use snips to make long cuts in coil stock. Small cuts of 1 " or 2" may only be made with snips. h. Overlap of fascia on gable rake boards will always be open toward the bottom to avoid water running behind the fascia. When turning corners with fascia, extend the first piece around corner 2" or 3" then start new fascia at corner. i. Always plan fascia installation so that no piece of fascia is ever less than 5 feet long. (Unless of course, the total length of the area to be covered is less than 5 feet long.) Divide the length of fascia into equal lengths, using the longest possible piece that will fit into the break. j. In cases where fascia boards are warped or bowed, overlaps will need to be planned carefully to align with the points of greatest warping or bowing. If warping of bowed wood member cannot be wrapped in a professional workmanship matter contact or notify Crew Leader. Never force the aluminum fascia to conform to the unusual contours, as it will cause crimps or waves in the aluminum. k. Soffit, fascia and trim will be cleaned as described in the siding installation section. l. Keep hands as clean as possible during application. To clean smudges, use a soft cloth or damp sponge dipped in a mild detergent solution. Thoroughly clean the siding as it is installed and check at the end of the job that all dirt and finger smudges are removed. m. Critical points to always remember: i. Nail panels in center of slots

4 7. Trim ii. Minimize face nailing of siding or fascia (Face Nailing may be necessary to insure wind resistance) iii. Do not nail tight, let panel hang iv. Use of staples on soffit is allowed. Use of staples for siding is not recommended but will be allowed if proper staples and installation techniques are followed. v. Leave 1/4" clearance to all openings and stops for expansion and contraction vi. Leave 3/8" to 1/2" clearance in extremely cold temperatures. vii. Do not pull horizontal panels up too tight viii. Lap panels on half of factory pre notched end, use of factory ends is always recommended over job site fabrication of ends. ix. Overlap panels away from points of heaviest traffic x. Check for width of top panel before starting bottom row xi. Make sure that top panel is properly crimped every 12 and is securely installed in the sill trim piece. xii. Never use any siding that is less than 30" long unless it is being installed inside a smaller opening. a. When covering freeze boards, windows and door facings, etc. with coil stock, face nailing shall be avoided whenever possible. The nailing will always be done with color matched trim nails nailed into the edges of the covered boards or into a nailing fin which can be covered by siding or soffit. If face nailing is necessary, pre drill holes before nailing. All pressure treated material must first be covered with poly or house wrap to protect the coil stock from corrosion caused by the chemicals used to treat the wood. The poly material recommended is the 12 wide black poly on the jobs for moisture barrier. b. The recommended way to wrap brick stop is to fold the coil stock over the top and bottom ends like wrapping a present. This prevents the ends of the board being exposed. c. The exact dimensions of the board to be covered will be measured carefully before the coil stock is bent to ensure proper and snug fittings. d. If the frieze board exceeds 7" width, it will be covered by soffit material run vertically. Soffit material v grooves must be aligned with that of the soffit, frieze board that is 7" or less will be covered with coil stock. e. When fitting panels over windows make sure that there are no laps. Cut the section out for an accurate fit. Furring out over the window may be required to maintain proper alignment. 8. Soffit a. Soffit panels shall be locked securely together but never pulled too tight. If the overhang exceeds 18" with vinyl soffit or 36" with aluminum soffit, the panels will be nailed in the center to avoid sagging. b. When inside or outside corners of the overhang have equal width overhangs on both sides, the soffit will be mitered at 45 degree angles. Use T bar, or two pieces of J channel used back to back, to receive the panels. The panels will be cut so that the v grooves line up at the miter. c. When inside or outside corners of the overhang do not have equal width overhangs on both sides, the soffit will be mitered at 90 degree angles. Use T bar, or two pieces of J channel used back to back, running parallel to the widest side.

5 d. Where J channel is to be extended to the fascia at corners, it will be necessary to notch the nailing flange so as not to cause the soffit to hang down lower at that point. e. The J channel does not need to be nailed to the fascia because the joining soffits will hold it in place. It is used at corners simply to finish the soffit edges neatly, not to hold the soffit in place. f. When siding and soffit are to be installed on the same job, the soffit must be installed first to establish where the top finish course on the siding will be. 9. General a. A full 12' piece of siding will expand up to 1/2" during the hot periods, allow for both expansion and contraction. b. The framers are to install house wrap to completely cover any OSB sheathing. If there is any damage evident, to this moisture barrier, the Crew Leader must be notified to get the Framing Subcontractor to repair it. It must be repaired prior to siding installation. c. The framers are to seal the windows with peal and seal tape placing the top piece on last and the bottom piece first. d. Care should be used when caulking, do not smooth caulking with dirty fingers, it will turn the caulking black. e. All shutters require shall be installed to manufactures specifications with the fasteners provided. f. L bends or metal caps should be used to cover exposed plywood edge or as brick caps. Caulking should not be used in areas greater than 1/8". g. Flashing utilizing coil stock is to be provided at all hose bibs to prevent water from getting to the OSB sheathing. Run coil from above hose bib all the way to bottom of OSB in 12 width. Cut carefully for hose bib and caulk if permanent hose handle is installed. h. J channel requires a full 1 overlap when necessary to join two pieces. The bottom piece will require modification to allow for expansion. See installation guide for details. I Install electrical Mount Master boxes where marked. J Note all aluminum scrape is to be saved for PHFH recycling. 10. Vinyl Siding Contractors Specific Responsibilities a. Return trips; The Subcontractor shall return to each house as scheduled to: i. Complete any punch out item or correct any inspection deficiency. ii Correct any items noted in Walk thru process with Crew leader or Homeowner. iii Complete any required warranty work. Subcontractor is responsible for the Warranty. for a period one year from date of closing. iv) To handle any warranty requests from the Crew Leader as result of workmanship. b. Warranty procedures requires emergency response within 24 hours but must be immediate during business hours. Normal Warranty requests are to be handled by contacting the homeowner within 7 days of being notified by PHFH Warranty Department, and then complete the assigned work order no later than 21days from notification. Subcontractor must get work order signed by the homeowner at the time the warranty work is accepted as being complete. c. All cost associated with maintaining the Warranty shall be borne by the subcontractor. PHFH will not pay any costs associated with Warranty work. d. To supply all tools and equipment necessary to install vinyl, soffit and coil stock as necessary to properly complete the job. e. All scrap and trash shall be picked up and placed in approved trash container.

6 f. All unused material shall be returned to the PHFH Crew Leader. PENSACOLA HABITAT: By: Name: Hal Major Title: COO Date: SUBCONTRACTOR: By: Name: Title: Date: Rev. 02/15/2012

Installation Instructions Split Shake, Staggered Shake, Shingle, Perfection Shingle, and Shapes

Installation Instructions Split Shake, Staggered Shake, Shingle, Perfection Shingle, and Shapes Installation Instructions Split Shake, Staggered Shake, Shingle, Perfection Shingle, and Shapes General Guidelines These instructions show one type of installation and are intended for the professional

More information

INSTALLATION PROCEDURE

INSTALLATION PROCEDURE Vinyl Siding INSTALLATION PROCEDURE Tools Needed and Preparation MOST ESSENTIAL TOOLS The proper tools, materials and equipment can make the installation of Durabuilt Vinyl Siding much easier. Here are

More information

CONTENTS. Transitions Board and Batten Vertical Installation... 10,11

CONTENTS. Transitions Board and Batten Vertical Installation... 10,11 INSTALLATION MANUAL CONTENTS Important Notes... 2-4 Weather Protective Barriers... 2 Storage and Transportation... 2 Tools and Equipment... 2 Fastener Choices... 3 Wall Preparation... 3,4 Flashing... 4

More information

3.1 Continuous top and bottom lock 3.2 Engineered nailing hem 3.3 Temperature markings

3.1 Continuous top and bottom lock 3.2 Engineered nailing hem 3.3 Temperature markings AOBP recommends 2-1/2 ring shank nails be used. Installation over foam will require longer fasteners to assure a penetration of at least 3/4 into a structural member (stude or nail base). Corner accessories

More information

Chapter 11. Siding and Soffit

Chapter 11. Siding and Soffit Chapter 11. Siding and Soffit 11.1 SIDING PREP 11.2 INSTALLING HOUSE SIDING 11.3 INSTALLING SHED SIDING 11.4 INSTALLING SOFFIT 11.5 INSTALLING FASCIA 11.6 INSTALLING SHUTTERS 11.7 SITE CLEANUP Tools needed

More information

Installation Manual SOLID CORE SIDING

Installation Manual SOLID CORE SIDING Installation Manual SOLID CORE SIDING SOLID CORE SIDING Installation Information contained in this manual can be viewed in video form at: www.youtube.com/epbc CONTENTS Important Notes...2-4 Weather Protective

More information

Aluminum Siding System

Aluminum Siding System Aluminum Siding System Do It Yourself Installation Guide For New Construction and Remodeling The Sell-Even Aluminum Siding System is manufactured to professional tolerences, yet it s designed to be fast

More information

Shapes Siding. Perfection Shingles. Chalk Line

Shapes Siding. Perfection Shingles. Chalk Line Snap a Chalk Line Shapes Siding Perfection Shingles Chalk Line To establish a straight reference line to guide the positioning of the starter strip and the first course of siding, snap a chalk line. starter

More information

14.0 SIDING AND SOFFITS SECTION

14.0 SIDING AND SOFFITS SECTION 14.0 SIDING AND SOFFITS SECTION 1. Introduction At the present time, Habitat homes in St. Louis are being sided in vinyl. This is to keep the price down, and to provide the homeowner with a relatively

More information

Installation Guidelines

Installation Guidelines Installation Guidelines Tando Building Products provides these instructions as general guidelines only. Tando Building Products neither installs exterior cladding nor has any control over any installation.

More information

Gambrel Barn with Overhang Manual

Gambrel Barn with Overhang Manual Tools Needed: -Cordless Drill (12V or higher) -#2 Square Drive Bit -Hammer -6 Step Ladder -Tape Measure -Square utility knife w/ blade & hook blade -Speed Square Little Cottage Co. PO Box 455 Berlin, OH

More information

Effective February, 2015

Effective February, 2015 Effective February, 2015 Table of Contents Ensuring System Performance 1 Components 2 Frequently Asked Questions 3 List of Tools 3 Before you Begin Preparation 3 Quality Tips 4 Cold Weather Tips 4 Cleaning

More information

SIDING-MASTER VINYL SIDING ATTACHMENT & ALIGNMENT SYSTEM & OVERHANG ATTACHMENT & ALIGNMENT SYSTEM INSTALLATION INSTRUCTIONS

SIDING-MASTER VINYL SIDING ATTACHMENT & ALIGNMENT SYSTEM & OVERHANG ATTACHMENT & ALIGNMENT SYSTEM INSTALLATION INSTRUCTIONS Patent Pending SIDING-MASTER & OVERHANG ATTACHMENT & ALIGNMENT SYSTEM INSTALLATION INSTRUCTIONS Overview... SIDING-MASTER Strip Diagram... How to cut strips for length... Accessory Diagrams... How to (and

More information

Standard Practice for Installation of Rigid Poly(Vinyl Chloride) (PVC) Siding and Soffit 1

Standard Practice for Installation of Rigid Poly(Vinyl Chloride) (PVC) Siding and Soffit 1 Designation: D 4756 03 An American National Standard Standard Practice for Installation of Rigid Poly(Vinyl Chloride) (PVC) Siding and Soffit 1 This standard is issued under the fixed designation D 4756;

More information

Installation Guide - Evolution Series Wood Siding

Installation Guide - Evolution Series Wood Siding Installation Guide - Evolution Series Wood Siding The following instructions pertain to the installation of Fraser Wood Siding Evolution Series on a typical wood frame construction allowing for nail penetration

More information

LUX INSTALLATION GUIDE. LUX Panel V Groove Installation. Installation Guide. February

LUX INSTALLATION GUIDE. LUX Panel V Groove Installation. Installation Guide. February LUX Panel V Groove Installation Installation Guide February 2017 www.luxpanel.ca LUX Panel V Groove Installation LUX panel steel cladding is designed to be installed vertically, horizontally, diagonally

More information

ASC Building Products. Table of Contents

ASC Building Products. Table of Contents Table of Contents Section Page(s) Introduction........................................1 Minimum Recommended Tools & Equipment.............2 Delivery, Handling and Storage.........................3 Safety

More information

Sun Windows General Information New Construction Hinged Door Installation Instructions

Sun Windows General Information New Construction Hinged Door Installation Instructions A G H F H H A. Apply Weather Resistive Barrier B. Apply Bottom Flashing Tape C. Install Sill Pan End Caps & Pan D. Caulk Sides & Top Nailing Surface, Set Door, Fasten E. Apply Side Flashing Tape F. Apply

More information

Installation Guidelines

Installation Guidelines Installation Guidelines Exteria Building Products provides these instructions as general guidelines only. Exteria Building Products neither installs siding nor has any control over any installation. The

More information

Installation Guidelines

Installation Guidelines Installation Guidelines Exteria Building Products provides these instructions as general guidelines only. Exteria Building Products neither installs siding nor has any control over any installation. The

More information

Roofing Training - Basics. Sandy Wesch

Roofing Training - Basics. Sandy Wesch Roofing Training - Basics Sandy Wesch Tools Hammer Measuring Tape Chalk Line & Chalk Speed Square Framing Square Utility Knife Metal Snips Extension Ladder(s) 2 Safety Any tools or material up on the roof

More information

Effective April 1, 2013

Effective April 1, 2013 Effective April 1, 2013 Table of Contents Ensuring System Performance 1 Components 2 Frequently Asked Questions 3 List of Tools 3 Before you Begin Preparation 3 Quality Tips 4 Cold Weather Tips 4 Cleaning

More information

E-Z BUILD SHED GUIDE 12' 12' 12' 16' 12' 20'

E-Z BUILD SHED GUIDE 12' 12' 12' 16' 12' 20' E-Z BUILD SHED GUIDE 12' 12' 12' 16' 12' 20' BUILD You can construct your own E-Z frame shed with the help of this step by step guide. North American softwood dimensional lumber sizes: Nominal Actual in

More information

Installation Instructions

Installation Instructions Installation Instructions ROLL VENT STANDARD / METRIC Page Installation Considerations 3 Roll Vent Standard General Installation 4 Roll Vent Metric General Installation 5 Steep Pitch Guidelines 6 Asphalt

More information

Installation Guide. Step 3. Valley Flashing. Step 7. Transition Flashings and Accessories. Step 6. Hip and Ridge Installation

Installation Guide.   Step 3. Valley Flashing. Step 7. Transition Flashings and Accessories. Step 6. Hip and Ridge Installation Step 7. Transition s and Accessories Step 3. Valley Step 6. Hip and Ridge Installation Step 2. Rake Trim Step 5. Installing the Shingles Step 1. Eave Starter Installation Step 4. Endwall s Installation

More information

Tuff-Rib Install Guide

Tuff-Rib Install Guide Install Guide bestbuymetalroof.com Page 2 of 27 Page 3 of 27 1. Page 4 2. a. Installation Guide b. Panel Squaring Pages 5, 6 Pages 7, 8 3. Pages 9, 10 4. a. Fascia (optional) b. Eave / 1.5x3.5 Angle c.

More information

COMPOSITE SIDING INSTALLATION GUIDE

COMPOSITE SIDING INSTALLATION GUIDE CENTURY HOME LIVING COMPOSITE SIDING INSTALLATION GUIDE Read all instructions prior to installing any siding product. Failure to install and finish this product in accordance with all local building codes,

More information

Dura-Lock Roof System

Dura-Lock Roof System DLR-14 Dura-Lock Roof System Assembly and Installation Instructions Read the instructions before starting the job. They explain the steps required to produce a finished product that will meet factory specifications.

More information

Sun Windows General Information New Construction Sliding Door Installation Instructions H F

Sun Windows General Information New Construction Sliding Door Installation Instructions H F A G B D C H F H E H A. Apply Weather Resistive Barrier B. Apply Bottom Flashing Tape C. Install Sill Pan End Caps & Pan D. Caulk Sides & Top Nailing Surface, Set Door, Fasten E. Apply Side Flashing Tape

More information

Chapter 23. Garage Construction

Chapter 23. Garage Construction Chapter 23. Garage Construction 23.1 ESTABLISHING CHALK LINES 23.2 MEASURING AND CUTTING WALL PLATES 23.3 MARKING WINDOW & DOOR LOCATIONS ON EXTERIOR WALL PLATES 23.4 MARKING STUDS ON EXTERIOR WALL PLATES

More information

Vinyl Siding Estimating and Installation Guide

Vinyl Siding Estimating and Installation Guide Vinyl Siding Estimating and Installation Guide Understanding the Basics Contractors and homeowners alike have depended on the low maintenance sidings from KP Building Products for the best product designs

More information

ROYAL HOW TO INSTALL VINYL SIDING

ROYAL HOW TO INSTALL VINYL SIDING ROYAL HOW TO INSTALL VINYL SIDING TM siding, SOFFIT AND ACCESSORIES Vinyl Fascia 5/8 T-Trim Matte 5/8 Inside Corner Matte 5/8 Outside Corner Post Double 5 Soffit Vented Drip Cap Finish Trim Double 4 Traditional

More information

Table of Contents. Fasteners... 4 Venting Preparation Installation with Battens - DECRA Tile & DECRA Shake 1

Table of Contents. Fasteners... 4 Venting Preparation Installation with Battens - DECRA Tile & DECRA Shake 1 Table of Contents DECRA Tile & Shake Roof Overview... 2 Introduction... 3 Safety... 3 Tools.... 3 Estimating Sheets... 4 Codes & Requirements... 4 Roof Slope... 4 Underlayment... 4 Deck Preparation....

More information

Installation Manual 0318

Installation Manual 0318 Installation Manual 0318 DOUBLE 7 CEDAR SHINGLE INSTALLATION GUIDE General Information CAUTION: REMEMBER THAT POLYMER UNDERGOES EXPANSION / CONTRACTION DUE TO VARIATIONS IN TEMPERATURE. THE FOLLOWING INSTRUCTIONS

More information

Installation Manual. Future Shingle Products

Installation Manual. Future Shingle Products Installation Manual Future Shingle Products TITLE REVISED 7/4/2011 Future Shingle Installation Manual is a component of Future Roof, Inc. and as such is intended to be used with Future Roof products only.

More information

installation guide Villa

installation guide Villa installation guide Villa Table of Contents Introduction............................. 2 Safety................................... 2 Tools.................................... 2 Codes & Requirements....................

More information

eco-shake INSTALLATION INSTRUCTION

eco-shake INSTALLATION INSTRUCTION 1 eco-shake INSTALLATION INSTRUCTION NOTE: Shuffling the eco-shakes during installation may be necessary to obtain a uniform color throughout the roof. Due to the natural wood content in the ecoshakes,

More information

INSTALLATION GIUDE.

INSTALLATION GIUDE. INSTALLATION GIUDE INTRODUCTION The instructions and drawings included here are intended only as a guide for the installation of ECO Roofing Systems Spanish and Modern profiles. The materials and methods

More information

Installation Guidelines For Quaker Window Products Aluminum flange fin sub sill & receptor system using a T mulled twin window unit.

Installation Guidelines For Quaker Window Products Aluminum flange fin sub sill & receptor system using a T mulled twin window unit. Installation Guidelines For Quaker Window Products Aluminum flange fin sub sill & receptor system using a T mulled twin window unit. Installer: Read these instructions completely before starting any installation.

More information

SECTION 4 Preparation for Horizontal Siding

SECTION 4 Preparation for Horizontal Siding SECTION 4 Preparation for Horizontal Siding Preparing Wall Surfaces Sheathings In new construction, apply sheathing first, then nail accessories over it. In home improvement projects, you can apply sheathing

More information

Vinyl Windows Manufactured by VPI Quality Windows

Vinyl Windows Manufactured by VPI Quality Windows Vinyl Windows Manufactured by VPI Quality Windows Part Number: 531&591 Installation 531 & 591 SERIES SLIDING AND HUNG WINDOW INSTALLATION INSTRUCTIONS Installation Instructions for Typical Construction.

More information

Installation Instructions

Installation Instructions Installation Instructions RAPID RIDGE STANDARD / 7 / METRIC Page Installation Considerations 3 Rapid Ridge Standard General Installation 4 Rapid Ridge Metric General Installation 5 Rapid Ridge 7 General

More information

STACKING MULTI-SLIDE DOOR SYSTEM INSTALLATION INSTRUCTIONS

STACKING MULTI-SLIDE DOOR SYSTEM INSTALLATION INSTRUCTIONS STACKING MULTI-SLIDE DOOR SYSTEM INSTALLATION INSTRUCTIONS 1290363 Revision 1 12/16 Page 1 Weather Shield Mfg., Inc. NOTICE CAUTION! Failure to install and maintain our product according to these instructions

More information

DESIGNER SERIES GUTTER SYSTEM INSTALLATION INSTRUCTIONS

DESIGNER SERIES GUTTER SYSTEM INSTALLATION INSTRUCTIONS DESIGNER SERIES GUTTER SYSTEM INSTALLATION INSTRUCTIONS GENERAL DESCRIPTION: The Designer Series Gutter System is a specially designed roof edge drainage product for industrial, commercial, and high end

More information

Installation Guide 2016

Installation Guide 2016 Installation Guide 2016 BUILDERS EDGE INSTALLATION GUIDE This guide will show you the products of the Builders Edge family. It provides specific installation steps and application details. Our main goal

More information

Installation Manual. Future Roof Shingle / Slate Products

Installation Manual. Future Roof Shingle / Slate Products Installation Manual Future Roof Shingle / Slate Products REVISED 14/09/2010 Future Roof Shingle Installation Manual is a component of Future Roof, Inc. and as such is intended to be used with Future Roof

More information

All Window Installation Instruction

All Window Installation Instruction 1 All Window Installation Instruction Hurd Window Installation Instructions for Nail Fin & Wood Brick Mould Units Nail Fin Windows See Pages 2-11 Wood Brick Mould Windows See Pages 2-6, 8 & 12BM - 14BM

More information

Installation Guide. Shingles. Classical. Shingles. Warning. Storage. Cutting Shingles. Touch-Up. Eastern White Cedar

Installation Guide. Shingles. Classical. Shingles. Warning. Storage. Cutting Shingles. Touch-Up. Eastern White Cedar Installation Guide Before you begin, take the time to read this entire guide to clearly understand the requirements and steps to follow for proper installation. The Fastening Make shingle fastening simpler

More information

Pocket Door Installation Instructions

Pocket Door Installation Instructions Installation Instructions Before getting started: Read instructions thoroughly. Be sure that you have the necessary tools and materials before starting the installation. Consult your local building code

More information

Table of Contents. Roof to Head Wall w/ Side Flashing DECRA Shake XD Roof Overview Roof Penetration - Pipes & Vents...

Table of Contents. Roof to Head Wall w/ Side Flashing DECRA Shake XD Roof Overview Roof Penetration - Pipes & Vents... Table of Contents DECRA Shake XD Roof Overview.... 2 DECRA Shingle XD Roof Overview.... 3 Introduction... 4 Safety... 4 Tools.... 4 Estimating Sheet... 4 Codes & Requirements... 4 Roof Slope... 4 Underlayment...

More information

Adorn Mortarless Stone Veneer Installation Natural Concrete Products

Adorn Mortarless Stone Veneer Installation Natural Concrete Products Adorn Mortarless Stone Veneer Installation Adorn Mortarless Stone Veneer can be used on new or existing construction. Adorn is nailed or screwed onto the wall; therefore no brick ledge is required. Adorn

More information

Ulltraclad Aluminium Cladding. Contents. 1.0 General Information Design Information Installation Information 7. 4.

Ulltraclad Aluminium Cladding. Contents. 1.0 General Information Design Information Installation Information 7. 4. Ulltraclad Aluminium Cladding Contents 1.0 General Information 2 2.0 Design Information 4 3.0 Installation Information 7 4.0 Maintenance 10 5.0 Health & Safety 10 1 1.0 General Information 1.1 Introduction

More information

INSTALLATION INSTRUCTIONS IMPERVIA SLIDING PATIO DOOR WITH FINS

INSTALLATION INSTRUCTIONS IMPERVIA SLIDING PATIO DOOR WITH FINS 2008 Pella Corporation Part Number: 803V0101 INSTALLATION INSTRUCTIONS IMPERVIA SLIDING PATIO DOOR WITH FINS Installation Instructions for Typical Wood Frame Construction. These instructions were developed

More information

Metal & Vinyl, Flush Mount and Recessed Fin Windows Recommended Installation Instructions

Metal & Vinyl, Flush Mount and Recessed Fin Windows Recommended Installation Instructions PO Box 480 Ph: 417-235-7821 Monett, MO 65708 Fax: 417-737-7140 Metal & Vinyl, Flush Mount and Recessed Fin Windows Recommended Installation Instructions These installation instructions are recommendations

More information

Cape Cod Manual. Little Cottage Co. PO Box 455 Berlin, OH Little Cottage Co.

Cape Cod Manual. Little Cottage Co. PO Box 455 Berlin, OH Little Cottage Co. Tools Needed: -Cordless Drill (12v or higher) -#2 Square drive bit -Hammer -6 Step Ladder -Tape Measure -Square utility knife with blade & hook blade -Speed Square Little Cottage Co. PO Box 455 Berlin,

More information

Siding Components. Installation Guide

Siding Components. Installation Guide Siding Components Installation Guide 2016 MID-AMERICA SIDING COMPONENTS INSTALLATION GUIDE This guide will show you the products of the Mid-America Siding Components family. It provides specific installation

More information

Vinyl Siding. Estimating and Installation Guide. Vinyl Siding

Vinyl Siding. Estimating and Installation Guide. Vinyl Siding Vinyl Siding Estimating and Installation Guide Vinyl Siding General estimating tips Estimating for siding Most homes surface areas are made up of a series of rectangles or triangles. When estimating vinyl

More information

Chapter 9. Windows and Exterior Doors

Chapter 9. Windows and Exterior Doors Chapter 9. Windows and Exterior Doors 9.1 INSTALLING WINDOWS 9.2 INSTALLING EXTERIOR HOUSE DOORS 9.3 INSTALLING SHED DOOR 9.4 INSTALLING EGRESS COMPONENTS Tools needed by volunteers: Hammer Nail apron

More information

VINYL WINDOWS (new construction or replacement) page 2. VINYL PATIO DOORS pages WOOD CLAD WINDOWS (new construction).page 5 WOOD CLAD WINDOWS

VINYL WINDOWS (new construction or replacement) page 2. VINYL PATIO DOORS pages WOOD CLAD WINDOWS (new construction).page 5 WOOD CLAD WINDOWS RECOMMENDED INSTALLATION INSTRUCTIONS Please choose the appropriate instructions for the product(s) you are using. Read the instructions thoroughly before beginning the installation process. All instructions

More information

Step 1: Planning the project

Step 1: Planning the project Step 1: Planning the project 1 of 1 Completed gutter Evaluate and plan the project Professionally installed continuous gutters using strip miters or the box style corners, remember to add 5 for each outside

More information

VINYL REPLACEMENT WINDOW INSTALLATION STANDARDS

VINYL REPLACEMENT WINDOW INSTALLATION STANDARDS VINYL REPLACEMENT WINDOW INSTALLATION STANDARDS BEFORE you start to remove the existing windows Place clean drop cloths in all work areas. Re-measure the opening to ensure the new window will fit. Remove

More information

A REFERENCE GUIDE OF TYPICAL RAINSCREEN WALL AND WINDOW DETAILS

A REFERENCE GUIDE OF TYPICAL RAINSCREEN WALL AND WINDOW DETAILS WARRANTY PROVIDER ACCEPTED A REFERENCE GUIDE OF TYPICAL RAINSCREEN WALL AND WINDOW DETAILS Per: 2006 B.C.B.C. Part 9 DISCLAIMER THE INFORMATION CONTAINED IN THIS DOCUMENT REPRESENTS CURRENT WOOD FRAME

More information

Trim (Aluminum Substrate)

Trim (Aluminum Substrate) CEILING SYSTEMS Between us, ideas become reality Trim (Aluminum Substrate) GENERAL Description WoodWorks Trim (aluminum substrate) is a unique system designed for use with Tegular, Vector, Linear and Channeled

More information

INSTALLATION INSTRUCTIONS - INSTRUCCIONES DE INSTALACION FOR HURRICANESHIELD IMPACT-RESISTANT DOUBLE-HUNG, SINGLE-HUNG AND SIMULATED-HUNG

INSTALLATION INSTRUCTIONS - INSTRUCCIONES DE INSTALACION FOR HURRICANESHIELD IMPACT-RESISTANT DOUBLE-HUNG, SINGLE-HUNG AND SIMULATED-HUNG 2008 Pella Corporation Part Number: 80ED0101 INSTALLATION INSTRUCTIONS - INSTRUCCIONES DE INSTALACION FOR HURRICANESHIELD IMPACT-RESISTANT DOUBLE-HUNG, SINGLE-HUNG AND SIMULATED-HUNG Instrucciones en español

More information

Tools required by installer: Materials required by installer:

Tools required by installer: Materials required by installer: Installation Guidelines For Quaker Window Products Vinyl product line (Single Hung, Double Hung, Sliding Window, Fixed Window, Casement, Awning, and Hopper) Installer: Read these instructions completely

More information

Chapter 17 - Porch Trim

Chapter 17 - Porch Trim Chapter 17 - Porch Trim Contents Chapter 17 - Porch Trim... 17-1 Timing & Prerequisites... 17-2 Trim on Porch Beams (Volunteer)... 17-4 Smart Trim on the Bottom of the Beam... 17-4 Smart Trim on the Inside

More information

INOVO 2-LITE SLIDING PATIO DOOR

INOVO 2-LITE SLIDING PATIO DOOR INOVO 2-LITE SLIDING PATIO DOOR ASSEMBLY AND INSTALLATION INSTRUCTIONS IMPORTANT: READ THE INSTRUCTIONS AND FAMILIARIZE YOURSELF WITH THE DOOR PARTS AND PIECES BEFORE BEGINNING ASSEMBLY AND INSTALLATION.

More information

INSTALLATION, STORAGE AND WALL CONSTRUCTION DETAILS

INSTALLATION, STORAGE AND WALL CONSTRUCTION DETAILS www.capecodsiding.com INSTALLATION, STORAGE AND WALL CONSTRUCTION DETAILS IMPORTANT READ THE FOLLOWING INSTRUCTIONS CAREFULLY BEFORE INSTALLING YOUR WOOD SIDING. FAILURE TO STRICTLY FOLLOW THESE INSTALLATION,

More information

Steel Siding Installation Instructions

Steel Siding Installation Instructions Steel Siding Installation Instructions Why Rollex Steel Siding? Proven Performance that lasts beautifully Steel siding is one of the most durable siding options on the market. Designed to withstand the

More information

SmartVent Eave Edge Installation Instructions

SmartVent Eave Edge Installation Instructions SmartVent Eave Edge Installation Instructions STEP 1: Cut a slit 1 wide (or a series of 1 ¾ holes at 3 on center) into the roof decking 6 to 7 up from the drip edge. SmartVent is rated 9NFA. Ensure drip

More information

RIDGEMASTER PLUS CAUTION INSTALLATION INSTRUCTIONS ALWAYS WEAR SAFETY GLASSES TOOLS NEEDED GENERAL GUIDELINES FOR RIDGEMASTER PLUS AND HIPMASTER

RIDGEMASTER PLUS CAUTION INSTALLATION INSTRUCTIONS ALWAYS WEAR SAFETY GLASSES TOOLS NEEDED GENERAL GUIDELINES FOR RIDGEMASTER PLUS AND HIPMASTER INSTALLATION INSTRUCTIONS RIDGEMASTER PLUS CAUTION Before beginning installation read all general guidelines, special notes and installation steps thoroughly and be sure to check and follow all your local

More information

How to install soffit VENTILATION. How to begin

How to install soffit VENTILATION. How to begin How to Install Quality Edge TruVent How to begin is the name given materials used to enclose the underside of eaves and porch ceilings. The installation of soffit will determine the positioning of the

More information

Fold-A-Way Patio Door ASSEMBLY & INSTALLATION GUIDE

Fold-A-Way Patio Door ASSEMBLY & INSTALLATION GUIDE Fold-A-Way Patio Door ASSEMBLY & INSTALLATION GUIDE This instruction guide provides the minimum recommended procedures to correctly prepare the rough opening, install a fold-a-way patio door unit and apply

More information

INSTALLATION INSTRUCTIONS FRAMELESS CONTINUOUS HINGE SHOWER ENCLOSURE QCI5233

INSTALLATION INSTRUCTIONS FRAMELESS CONTINUOUS HINGE SHOWER ENCLOSURE QCI5233 INSTALLATION INSTRUCTIONS FRAMELESS CONTINUOUS HINGE SHOWER ENCLOSURE QCI5233 QCI5233 Rev 0 Page 1 Certified 06/20/2016 INSTALLATION NOTES: Unpack your unit carefully and inspect for freight damage. Lay

More information

Slate Shingle Specifications

Slate Shingle Specifications Slate Shingle Specifications California Slate is a proud member of the Slate Roofing Contractors Association of North America, Inc. (SRCA) which publishes Section 07310 Slate Shingles setting forth architectural

More information

SHADOWBOX INSTALLATION FOR: Standard 6 H x 8 W Shadowbox Fence 5 x 5 Routed Posts Dog Ear or Straight-Edge Pickets 1.75 x 3.5 Rail

SHADOWBOX INSTALLATION FOR: Standard 6 H x 8 W Shadowbox Fence 5 x 5 Routed Posts Dog Ear or Straight-Edge Pickets 1.75 x 3.5 Rail SHADOWBOX INSTALLATION FOR: Standard 6 H x 8 W Shadowbox Fence 5 x 5 Routed Posts Dog Ear or Straight-Edge Pickets 1.75 x 3.5 Rail Storage and Handling Fence Preparation and Layout Locate and Set Posts

More information

How to Install Guide Prepare, Install & Care for your New Vinyl Siding

How to Install Guide Prepare, Install & Care for your New Vinyl Siding How to Install Guide Prepare, Install & Care for your New Vinyl Siding Guide for Traditional and Insulated Siding Installation 1 Table of Contents How to Measure 3 Basic Installation Guides 4 Basic Installation

More information

Shed Assembly Instructions

Shed Assembly Instructions Shed Kit Contents The shed kit includes all the parts needed to assemble your shed except for tools and fasteners such as screws and nails. The various pieces are pre-cut and many are marked to indicate

More information

INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS

INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS 2012 Pella Corporation Part Number: 80WH0101 INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS Installation Instructions for Typical Wood Frame Construction.

More information

Chapter 9. Windows and Exterior Doors

Chapter 9. Windows and Exterior Doors Chapter 9. Windows and Exterior Doors 9.1 INSTALLING WINDOWS 9.2 INSTALLING EXTERIOR HOUSE DOORS 9.3 INSTALLING SHED DOOR 9.4 INSTALLING BASEMENT EGRESS COMPONENTS Tools needed by volunteers: Hammer Nail

More information

Gambrel Barn Construction Manual 8x8 through 16x24 Units

Gambrel Barn Construction Manual 8x8 through 16x24 Units Gambrel Barn Construction Manual 8x8 through 16x24 Units Tools Needed: Cordless drill (12V or higher) #2 square drive bit Hammer 6 step ladder Tape measure Square utility knife w/ blade & hook blade Little

More information

Installation Manual. For Gerard Shingle Products

Installation Manual. For Gerard Shingle Products Installation Manual For Gerard Shingle Products Gerard Shingle Installation Manual is a component of Gerard roofing products and as such is intended to be used with Gerard products only. All information

More information

INSTALLATION GUIDE LEARN MORE AT DECRA.COM

INSTALLATION GUIDE LEARN MORE AT DECRA.COM Villa Tile INSTALLATION GUIDE LEARN MORE AT DECRA.COM Table of Contents DECRA Villa Tile Roof Overview... 2 Introduction... 3 Safety... 3 Tools.... 3 Estimating Sheet... 3 Codes & Requirements... 3 Roof

More information

Installation Instructions

Installation Instructions www.marlite.com Effective Date 03/01/2018 ARTIZAN FRP, SYMMETRIX FRP, ENVUE FRP, STANDARD FRP Installation Instructions Statements expressed in this technical bulletin are recommendations for the application

More information

Installation Guidelines For ALUMINUM M-SERIES 3 PANEL SLIDING DOOR

Installation Guidelines For ALUMINUM M-SERIES 3 PANEL SLIDING DOOR www.quakerwindows.comv www.quakercommercialwindows.com PO Box 128 504 Highway 63 South Freeburg, MO 65035 800-347-0438 573-469-4151 (fax) Installation Guidelines For ALUMINUM M-SERIES 3 PANEL SLIDING DOOR

More information

UNIT No FRAMELESS PIVOT SHOWER DOOR

UNIT No FRAMELESS PIVOT SHOWER DOOR INSTALLATION INSTRUCTIONS UNIT No. 3600 FRAMELESS PIVOT SHOWER DOOR NEED INSTALLATION HELP? Call 1-800-45-BASCO (452-2726) Monday - Friday 8:00 A.M. - 4:30 P.M. Eastern Time QCI0020 Rev. 3 Page 1 of 8

More information

WEEK 4 COMPLETE SIDING & EXTERIOR PAINTING

WEEK 4 COMPLETE SIDING & EXTERIOR PAINTING WEEK 4 COMPLETE SIDING & EXTERIOR PAINTING INSTALL DRY WALL CLIPS (STAFF) Safety Briefing Complete siding Caulk exterior plumbing & electrical boxes First Coat Exterior Second Coat Exterior Install siding

More information

REGAL. Installation Manual

REGAL. Installation Manual REGAL Installation Manual General Information The details shown on the following pages are suggestions or guidelines for installing the Regal system. The installation details shown here are proven methods

More information

Installation Guide. Capped Cellular PVC Fencing. Table of Contents. Storage and Handling Tools Needed Fence Layout and Locating Posts

Installation Guide. Capped Cellular PVC Fencing. Table of Contents. Storage and Handling Tools Needed Fence Layout and Locating Posts Capped Cellular PVC Fencing Installation Guide Table of Contents Storage and Handling Tools Needed Fence Layout and Locating Posts Installation instructions 4 x 4 Over Sleeve Post - 3.5 Rail Privacy Shadowbox

More information

4. Partially open the operating panel and tilt the top toward the interior of the door (Figure 4). Lift the panel off the sill and set it aside.

4. Partially open the operating panel and tilt the top toward the interior of the door (Figure 4). Lift the panel off the sill and set it aside. Effective Date: 10/1/2017 Tools Needed Kit Contents Hardware Kit Safety Glasses Cordless drill Phillips screw bit Two-step drill bit (3/8-1/8 ) utility knife Interior Mullion Exterior Mullion Cover clamps

More information

Installation Instructions Lineals around Windows & Doors

Installation Instructions Lineals around Windows & Doors Installation Instructions Lineals around Windows & Doors These instructions describe and illustrate the steps involved in installing CertainTeed siding and trim. Their purpose is to provide detailed information

More information

Panel Installation Instructions

Panel Installation Instructions EXTREMELY IMPORTANT INFORMATION PLEASE READ ENTIRE PACKET! Warranty Is Void If Panels Not Installed According to Instructions 1. WARNINGS & SPECIAL NOTES 1.1 Keep panels 24 from Heaters and shield Radiant

More information

Sliding Glass Door Assembly and Installation Guide

Sliding Glass Door Assembly and Installation Guide Sliding Glass Door Assembly and Installation Guide Index Door System Components and Hardware The following components are needed to complete the installation of your Sliding Patio Door unit. Check all

More information

Best Materials LLC distributes backer rod, caulking and sealants for all types of EIFS joints and penetration sealing applications.

Best Materials LLC distributes backer rod, caulking and sealants for all types of EIFS joints and penetration sealing applications. Best Materials LLC distributes backer rod, caulking and sealants for all types of EIFS joints and penetration sealing applications. EXTERIOR INSULATION & FINISH SYSTEM CONSTRUCTION Data Published Courtesy

More information

Inspire Aledora Slate Application Guidelines

Inspire Aledora Slate Application Guidelines July 2014 Inspire Aledora Slate Application Guidelines Only Basic Roofing Tools Required Hand fastened or fastened with a pneumatic nail gun Utility knife or a standard circular saw Tape measure, pry bar,

More information

ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION

ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION 1. Scope 4. Underlayment 2. 1.1 This roofing application standard has been developed to provide a responsive

More information

ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION

ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION 1. Scope 4. Underlayment 2. 1.1 This roofing application standard has been developed to provide a responsive

More information

1/4 FRAMELESS DOOR WITH INLINE PANEL 1413A-1713A-1813A

1/4 FRAMELESS DOOR WITH INLINE PANEL 1413A-1713A-1813A 1/4 FRAMELESS DOOR WITH INLINE PANEL 1413A-1713A-1813A F AB GLASS AND MIRROR www.fabglassandmirror.com Call: +1 888-474-2221 Fax: (614)-334-4919 Office Timing: 8:30-18:00 EST info@fabglassandmirror.com

More information

Series Sloped glazed Curtain wall. Installation Instructions

Series Sloped glazed Curtain wall. Installation Instructions Series 5600 Sloped glazed Curtain wall Installation Instructions Part NO. Y308 February 2013 SECTION TABLE OF CONTENTS PAGE I. General Notes & Guidelines. 3-4 II. Gutter and Mullion Assembly.. 5 III. End

More information

ULTRA WINDOW & DOOR EXPANDERS AND RECEIVERS INSTALLATION INSTRUCTIONS

ULTRA WINDOW & DOOR EXPANDERS AND RECEIVERS INSTALLATION INSTRUCTIONS ULTRA WINDOW & DOOR S AND RECEIVERS INSTALLATION INSTRUCTIONS! CAUTION: *REMEMBER SAFETY FIRST* Proper Eye and! Hearing Protection must always be worn during installation of all window and door products.

More information